You are on page 1of 17

Secant

Pile Wall Design and Analysis example


 
 

Secant Pile Wall Design & Analysis example 
 
DeepXcav software program (Version 2011) 

(ParatiePlus within Italy) 

Document Version 1.0 

Issued: 13‐January‐2012 

Deep Excavation LLC 

www.deepexcavation.com 
 

Created by Deep Excavation LLC, Astoria, New York Page 1


 
Secant Pile Wall Design and Analysis example
 
A. Problem description 

We are going to design a 12 m excavation between two secant pile walls. The distance between the two 
walls is 8 m. There wall depth will be 16 m. 

The minimum required dewatering level is ‐1 m below maximum excavation level. 

In this model we will use strut supports, Metric Pipes with Diameter = 0.6 m. 

Concrete cube strength: 40 N/mm2, so we will use concrete C 32/40. 

 Figure 1 presents the construction site and Figure 2 presents the Design Section AA, which is marked in 
Figure 1 and will be analyzed.  Tables 1 and 2 present the soil properties and the wall properties 
respectively. 

Figure 1: Site plan and Design Section AA. 

Created by Deep Excavation LLC, Astoria, New York Page 2


 
Secant Pile Wall Design and Analysis example
 

Figure 2: Design Section AA. 

Table 1: Soil parameters. 

Design parameter 
Soil 
φ’  C’  γ  γ  KX   KY   ELOAD  ERELOAD 
Layer 
(deg)  (kPa)  (kN/m3) (kN/m3) (m/s)  (m/s)  (kN/m2)  (kN/m2) 
MDS  34  0  19  19  1.15 E‐5  1.15 E‐5  30000  90000 
VDS  41  0  19.5  19.5  1.15 E‐5  1.15 E‐5  60000  180000 
 

Table 2: Wall parameters. 

Pile diameter (D)  0.6 m 
Pile spacing  0.6 m 
Pile length  16 m 
Concrete  C 32/40 
Steel  S 500 
Rebars  D25 
Number of rebars per pile  10 
Shear reinforcement  Spiral Reinf 
D10 
Shear reinforcement spacing  250 mm 
 

Created by Deep Excavation LLC, Astoria, New York Page 3


 
Secant Pile Wall Design and Analysis example
 
B. Modeling in DeepXcav 

Now  we  will  present  how  this  model  can  be  designed  using  DeepXcav.  In  DeepXcav  we  can  add 
construction stages by pressing the Add Stage button in the Model tab. 

Stage 0: 

 First, we modify our soil layers. In the General tab of DeepXcav we press the button   (Figure 3). 
In  the  dialog  that  appears  we  choose  to  change  the  general  elevation  to  the  elevation  7.2  m,  and  to 
apply this change to all boreholes (Figure 4). Next, we press the button   in the model tab in 
order  to  add  a  second  wall  to  the  model  (Figure  5).  We  right  click  on  each  wall  and  we  choose  to 
Deactivate it for this stage. 

Figure 3: The General tab of DeepXcav and the Move model Elevations button. 

Figure 4: The Move Elevations dialog. 

Created by Deep Excavation LLC, Astoria, New York Page 4


 
Secant Pile Wall Design and Analysis example
 

Figure 5: The two walls, deactivated in Stage 0. 

Next, we will apply the soil properties. To do so, we go to the Model tab of DeepXcav and we press the 
button   in order to modify our stratigraphy. When we do so, the Edit Borings and Soils 
dialog appears (Figure 6). Here we choose to add a new soil with the top elevation of 0. We press the 
Edit  button  next  to  each  soil  layer  in  order  to  edit  the  layer  properties.  Then  the  Edit  soil  data  dialog 
appears (Figures 7 and 8). 

Figure 6: The Soil Layers dialog. 

Created by Deep Excavation LLC, Astoria, New York Page 5


 
Secant Pile Wall Design and Analysis example
 

Figure 7: The Edit soil data dialog. 

Figure 8: Soil model and Loading – Reloading Elasticity parameters. 

Created by Deep Excavation LLC, Astoria, New York Page 6


 
Secant Pile Wall Design and Analysis example
 
Next, we edit the wall properties. We double click on each wall and we apply the changes (Figure 9). To 
edit the wall section properties, we press the Edit Section button. In the dialog that appears, we choose 
to use secant pile walls and we apply our preferences (Figures 10 and 11). 

Figure 9: The Edit wall data dialog. 

Figure 10: The Edit wall section properties dialog. 

Created by Deep Excavation LLC, Astoria, New York Page 7


 
Secant Pile Wall Design and Analysis example
 

Figure 11: The concrete and rebar properties. 

Stage 1: 

In  this  stage  we  will  modify  the  soil  inclinations  in  order  to  design  our  model.  To  create  the  bench 
surfaces, we right click on our model, first on the left side of the left wall and next on the right side of 
the  right  wall,  and  we  choose  to  “Set  left  bench  surface”  and  “Set  right  bench  surface”  respectively 
(Figure 12). Then the Modify surface section dialog appears, and we apply our preferences (Figure 13). 

Figure 12: The available surface options. 

Created by Deep Excavation LLC, Astoria, New York Page 8


 
Secant Pile Wall Design and Analysis example
 

Figure 13: The modify surface section dialog. 

Next, in the Model tab we choose to excavate between the 2 walls to the Elevation 4 m (Figure 14) and 
by right clicking on each wall we choose to activate it. Figure 15 presents the model of this stage. 

Figure 14: Model tab: Excavate between the two walls to Elevation 4 m. 

Created by Deep Excavation LLC, Astoria, New York Page 9


 
Secant Pile Wall Design and Analysis example
 

Figure 15: Model, Stage 1. 

Stages 2 to 8: 

In these stages we excavate and apply the strut supports step by step. To excavate, we change the Layer 
elevation between the 2 walls (Figure 14). We are careful to keep the water table at least 1 m below the 
excavation. Table 3 presents the soil and water table elevation in each construction stage. 

Table 3: Soil and Water table elevations. 

Stage  Soil Elevation (m)  Water table elevation (m) 


Stage 2  3.4  1 
Stage 4  ‐1.1  ‐2.1 
Stage 6  ‐4.6  ‐5.6 
Stage 8  ‐8  ‐9 
 

In the stage that follows each excavation, we add a strut support to the model. To do so, we click on the 

button   in the toolbar on the left side of the screen, and then we click first on the left and next on 
the right wall. In the dialog that appears we can define the strut properties (Figure 16). Table 4 presents 
the strut and excavation levels when each strut is first installed. 

Table 4: Soil and Water table elevations. 

Stage  Soil Elevation (m) 
Stage 3  3.7 
Stage 5  ‐0.8 
Stage 7  ‐4.3 
 

Created by Deep Excavation LLC, Astoria, New York Page 10


 
Secant Pile Wall Design and Analysis example
 

Figure 16: Edit Strut properties dialog. 

In Stage 3 we add a surface load on the left wall of 15 kPa. To do so, we click on the tool button   on 
the left vertical tool bar. Then we click on the left point and next to the surface point next to the wall. 
When we do so, the dialog on Figure 16B appears. Here we select the "Treat as surface load option" and 
change the vertical surcharge intensity to 15kPa on both point 1 (left) and point 2 (right). 

Created by Deep Excavation LLC, Astoria, New York Page 11


 
Secant Pile Wall Design and Analysis example
 

Figure 16B: Surcharge dialog 

In the Analysis tab of DeepXcav we apply our analysis options (Figure 17). 

 We choose to use the Beam on Elastoplastic Foundations Analysis Mode (non‐linear) 
 We choose to apply wall friction as a percentage of soil friction on both walls (66%) 

Figure 17: Analysis options. 

Finally, we go to the Design tab of DeepXcav and we apply a Wall Safety Factor of 1.5 (Figure 18). 

Created by Deep Excavation LLC, Astoria, New York Page 12


 
Secant Pile Wall Design and Analysis example
 

Figure 18: Wall Safety Factor. 

Stage 9: 

We add this last stage to the model in order to change the water behavior to a full flownet for this stage 
(in all other stages we will keep a Simplified flow). In the Analysis tab, we choose to use a flownet and to 
apply this change only to the current Stage (Figure 19).  

Figure 19: Flownet. 

Created by Deep Excavation LLC, Astoria, New York Page 13


 
Secant Pile Wall Design and Analysis example
 
C. Results 

After  we  perform  the  calculations  we  can  see  the  results  in  the  results  tab  of  DeepXcav.  We  can  see 
various results for each construction stage: 

 Wall moments 

    

Figure 20: Wall moment diagrams for stage 8 and 9 respectively (red line is wall capacity). 

 Wall shear forces 

    

Figure 21: Wall shear diagrams for stage 8 and 9 respectively (dark red line is wall shear capacity). 

 
 
 
 

Created by Deep Excavation LLC, Astoria, New York Page 14


 
Secant Pile Wall Design and Analysis example
 
 Wall displacements 

    

Figure 22: Wall displacements for stage 8 and 9 respectively. 

 Effective vertical stresses 

    

Figure 23: Effective vertical stress for stage 7 and 8 respectively. 

Created by Deep Excavation LLC, Astoria, New York Page 15


 
Secant Pile Wall Design and Analysis example
 
 Water Pressure shadings (Stage 9 – Flownet analysis) 

Figure 24: Water pressure shadings. 

 Embedment Safety Factors 

Figure 25: Embedment safety factors. 

From the results above, we come to the following conclusions: 

a.  The  shear  capacity  of  the  wall  is  not  enough  for  this  model,  so  we  suggest  reducing  the  shear 
reinforcement spacing. 

b. The wall embedment is not enough, so we should increase the pile length. 

c. We should increase the dewatering depth beneath the excavation surface. 

Created by Deep Excavation LLC, Astoria, New York Page 16


 
Secant Pile Wall Design and Analysis example
 
We will perform the following actions and recalculate the model: 

 We will increase the wall depth to 22 m. 
 We will decrease the shear reinforcement spacing to 125 mm and shear reinforcement diameter 
to D12. 
 We will set the dewatering level to the elevation ‐10 m for the stages 8 and 9. 

Created by Deep Excavation LLC, Astoria, New York Page 17


 

You might also like