Professional Documents
Culture Documents
Fabrication Inspection Procedure
Fabrication Inspection Procedure
GEM/XXX.XXX-PROC-XX Rev. 0
CONTENTS
SECTION NO TITLE
1.0 SCOPE
1.0 SCOPE
Fabrication & Inspection Procedure Page 2
MECHANICAL PLANT
GEM/XXX.XXX-PROC-XX Rev. 0
This procedure details the requirements for the welding and inspection in the shop
fabrication of Piping and Pressure Vessel.
The following standards and code shall be considered part of this procedure :
Each fabrication technique shall be in accordance with accepted current good engineering
practice and shall be in accordance with requirements of all applicable specifications.
Material shall be kept free from dirt , grease and other foreign matter, and shall be
protected from corrosion. Fabrication shall take place at shop location to the greatest
extent possible.
All Code welding shall be in accordance with ASME Section IX and related
Construction Code and specification and to qualified welding procedures. Unless
otherwise specified, all welds shall be full penetration welds except where noted on
drawings.
All welds shall be continuous. Butt welds between materials of different thickness shall be
tapered by grinding the thicker parent material at a taper of 1 in 3 and not by the
use of additional weld outside the width of the joint. When the different of thickness
is less than 3/8” (10mm) the transition may be formed by adding addition weld metal
and MT upon adequate surface dressing of the weld.
Welding shall be done by Shielded Metal Arc Welding (SMAW), Submerged Arc Welding
(SAW) & Gas Tungsten Arc Welding (GTAW).
Weaving shall be limited to a maximum of 2.5 times core wire diameter or 12.7 mm,
whichever is the smaller.
GEM/XXX.XXX-PROC-XX Rev. 0
Welding machines shall have adequate controls for making the current
adjustments as necessary for all welding requirements. Sufficient meters, portable or
permanent, shall be provided to calibrate machines and to regulate voltage and
amperage on a regular basis.
4.3 WORKMANSHIP
Shearing, flame cutting, beveling and chipping shall be done carefully and accurately
with an automated or mechanically guided tool, where possible. Any beveled edge
that has been damaged shall be restored prior to welding. The cutting line shall be
marinated to allow the back dressing of 0.5 mm (minimum).
Beveled edge of carbon steel material to be stored for more that two weeks may
be protected by a lead free primer coat, such as deoxialuminate of about 10 m.
Surfaces of metal to be welded and 2 inches to either side of the weld, shall be
free of fins, tears, cracks, mill scale, slag, rust, oil, paint, and other defects or
contaminants which might adversely affect the quality or strength of the weld.
Run On - Run Off tabs , used in welding of longitudinal seams and plate splices,
shall be of the same thickness, specification , grade and edge preparation as the
plate being welded. Tabs shall be of a minimum length of 200 with a width of
150 to permit complete freezing of the puddle on the tab before extinguishing the
arc. Material for the Run On - Run Off tabs shall be furnished from original.
The welding shall proceed in a manner that minimizes residual stresses or
distortions.
GEM/XXX.XXX-PROC-XX Rev. 0
The welding arc shall only be struck within the weld preparation or onto already
deposited weld metal. Should arc strikes occur outside the joint, they shall be
removed, flushed and NDE by MT or PT.
It is advisable to use “Striking plate “.
When more than one weld pass is deposited on a joint , each pass shall be
thoroughly cleaned by wire brushing and chipping before the next pass is
applied.
Weld shall not be quenched or unnaturally cooled and shall be protected from
rapid cooling caused by rain, wind, or inclement weather. Suitable wind breaks /
shields shall be provided during high wind velocity exceed 10 mph.
Completed welds shall be clearly marked with welders stamp every 3 ft. to allow
proper documentation of weld or recorded in welding map.
When required, stiffeners shall be fitted accurately, neatly, and tightly to transmit
bearing loads. Stiffener end shall be or ground smooth to conform to the
geometry of the stiffener member to assure 100 percent fusion in the root of the
weld.
Excess root opening at welds my be repaired by depositing weld metal from one
side only , by applying weld buildup to their side of the joint (i.e. through
member). The maximum weld buttering deposit thickness shall be limited to 3/8
inch (10 mm) total for any weld joint. The corrected root opening shall be capable
of closure with a single pass of an approved electrode weaving techniques shall
not employed to close excessively wide root openings.
GEM/XXX.XXX-PROC-XX Rev. 0
In the event that joint fit-up tolerances for production welds exceed permitted
values, buildup of the joint surfaces via weld buttering is permissible, using a
qualified, approved, weld buttering procedure (see Sect. IX for qualification of
Buttering / Built-up and Construction Code).
The Production Dept. shall repair the defect in accordance with the approved
welding specification and Company’s Standard Operating Procedure No. QP-02-05
(STANDARD PROCEDURE WELDING DEFECTS REPAIR).
The Production Dept. shall notify QC Inspector and Client about any repair welds
performed to correct weld defects, weld bevel imperfection and/or base material
defects or imperfections. The repair of defects in weld deposits or base metal shall
GEM/XXX.XXX-PROC-XX Rev. 0
be approved by QC and Client prior to executing the repair and Client shall have
right to witness such repair.
Removal of the defect may be by any method which produces a clean surface for
the installation of the repair weld deposit. Details of all defects and their
subsequent repair shall be documented, for insertion in the inspection reports.
Cracks, plus approximately 2 (two) inches (50 mm) of sound metal at each end,
shall be removed (by grinding) to sound metal. Dye penetrant test or magnetic
particle examination of the excavated and ground cavity, prior to welding, is
required to verify complete removal of the crack. The entire weld joint shall be
removed if, in the opinion of QC Inspector or Client, the vessel part can not be
properly inspected or repaired or if the weld is rejected.
For detail refer to Standard Operating Procedure No. QP-02-05 (STANDARD
PROCEDURE WELDING DEFECTS REPAIR).
5.1 GENERAL
The Client reserves the right to request testing of any welding samples at any
time as necessary to maintain verification of the quality of welding work.
5.2.1 GENERAL
This section defines the minimum technical requirements for the inspection of
the Piping & Pressure Vessel structural.
The QC. Dept. Shall inspect and documented all work during
fabrication and assembly through the utilization of qualified quality control
inspectors and NDE personnel’s
The Q.C. Dept. shall provide Client access to fabrication facility at all
times of work at any stage and to reject any part not complying with this
specification.
GEM/XXX.XXX-PROC-XX Rev. 0
Welds in High Strength Material (50 ksi yield and above), due to the
possibility of delayed hydrogen cracking, shall be Non Destructive
Examination no less than 48 hours after welding.
Visual Inspection
Visual Inspection of the stages listed 5.2.2, shall include, but not limited to
the following :
- Each weld appearance shall be in accordance with the requirement of
the related Code Construction.
- Each weld surface profile shall be in accordance with Section 4.5
- Each weld attaching internal ring stiffeners
- Other welds in addition to the above, as specified by QC. Inspector or Client
Fabrication & Inspection Procedure Page 8
MECHANICAL PLANT
GEM/XXX.XXX-PROC-XX Rev. 0
Radiographic Examination
Film exposure techniques and processing shall provide a film free from
defects, which will show a 1.8% X-Ray and 2% Gamma Ray sensitivity
based on the nominal wall thickness.
All films shall be identified by job number, weld number, thickness, diameter
and welder stamp as a minimum to allow full traceability. Film shall be
held for storage in a film safe box. as part of inspection records, and retain
for at least for 5 (five) years.
Ultrasonic Examination
GEM/XXX.XXX-PROC-XX Rev. 0
QC. Inspector and ASNT/NDT Level III reserves the right to test the shop
sub-contractor ultrasonic examination procedure, to ensure that the procedure
meets the Code’s requirement. If the shop sub-contractor procedure proves
inadequate, QC / ASNT/NDT Level III reserves the right to change the
procedure to one that gives required weld flaw sensitivity.
Attachment 1
Acceptable and Unacceptable Weld Profiles
GEM/XXX.XXX-PROC-XX Rev. 0