Professional Documents
Culture Documents
I. Project Background
1. General background. An efficient transportation system with good inter and intra city
linkages is essential to ensure Dhaka’s position as a functional city with population of more
than 15.9 million. Present transport system in the city is chaotic in terms of traffic congestion,
pollution, accident, inefficient travel time. A huge number of modes of motorized and non-
motorized traffic are observed everywhere on roads. The number of automobiles has steadily
increased for the last decades. The city needs to provide efficient public transport infrastructure
to address the growing population, vehicles and economic activities.
2. Mass Rapid Transit (MRT) network in Dhaka has been proposed as critical measures to
mitigate the serious traffic congestion and improve economic efficiency in the area. Strategic
Transport Plan (STP) was formulated by the Dhaka Transport Coordination Board (DTCB)
under the technical assistance by the World Bank in 2005; STP emphasized necessity of a
modern, clean, efficient system which will create a high level of service covering the whole
metropolitan area and reaching out to the new communities in an integrated manner. Based on
the STP study, Japan International Cooperation Agency (JICA) conducted Dhaka Urban
Transport Network Development Project (DHUTS) in 2010 and the Revised Strategic Transport
Plan (RSTP) in 2015. The concept of urban transport development under RSTP is to set up
satellite regional centers to reduce the population density in central business district (CBD) and
to connect CBD with the satellite cities by MRT and/or Bus Rapid Transit (BRT). RSTP
proposed 5 MRT lines and 2 BRT lines as shown below. RSTP was approved as an official
transport plan in August 2016 by Ministry of Road Transport and Bridges. In line with RSTP,
JICA has conducted preparatory studies (feasibility studies [FS]) for three MRT lines in Dhaka:
MRT Line 1, Line 5 (North) and Line 6. JICA is currently supporting construction of Line 6,
and engineering designs for Line 1 and Line 5 (North) through ODA loans.
3. Dhaka Metro Line 5 (South). Meanwhile, the Asian Development Bank (ADB)
approved the Project Preparatory Technical Assistance (PPTA) for Dhaka Metro Project in
December 2015 to assess the RSTP and prepare a priority metro project for investment by ADB.
While waiting for the Government’s endorsement of the PPTA, JICA started in June 2016 a
feasibility study for Line 1 and Line 5 (North). Given the emerging development, the scope,
schedule and implementation of the PPTA needed to be adjusted; the Government requested
ADB to conduct a pre-feasibility study on Line 5 (South), which is the remaining part of Line
5 not covered by the JICA study, for preparation for ADB’s Project Readiness Financing (PRF)
and future investment project.
4. Under the PPTA, a consulting team was recruited to conduct a pre-FS for Dhaka Metro
Project of Line 5 (South) (the Project) in May 2018. The objectives of the study are to formulate
a proper project that is feasible in view of technical, economic, financial, social, and
environment aspects. The study covers (i) confirmation of priority of the proposed Line 5
(South) among the other MRT lines; and (ii) preparation for pre-FS including demand forecast,
operational parameters, preliminary engineering and cost estimates, economic and financial
evaluation, and safeguards consideration.
5. The total length of the Project is about 17.4 km between Gabtoli station and Dasherkandi
station with an underground section of about 12.8 km and an elevated section of about 4.6 km
with 12 underground and 4 elevated stations; a depot accommodating rolling stocks and
operational facilities for Line 5 (South) is planned near the east end of the Project at
Dasherkandi station area. Line 5 (South) will be connected with Line 5 (North) at Gabtoli
station, both of which will serve as east-west corridors and make it possible to transfer with
north-south running MRTs/BRTs at several stations. Through-services between the two lines
of North and South of Line 5 may be considered for the extension section of Line 5 (North).
There will be 15 stations (including future stations at the east end but excluding Gabtoli station)
to be constructed under the Project, 11 of which will be underground stations. Two stations at
the most east side will not be operated in the beginning for the current undeveloped surrounding
areas. About 9 km of future extension to the east to Borpa is planned but is not included in the
scope of the Project.
6. Dhaka Mass Transit Company Limited (DMTCL) under Ministry of Road Transport
and Bridges will be the executing agency of the Project. DMTCL will engage an eligible
consulting firm or a joint venture of consulting firms (Consultant) to conduct consulting
services for Engineering Design of the Project to implement the Project on a basis of “detailed
design and execution” for civil works and “design, supply, and installation (DSI)” for rolling
stocks, and electrical and mechanical system. The service also includes necessary bidding
document preparation and assistance in tender procedures. The Engineering Design services
will be financed by ADB through its loan of “Project Readiness Financing (PRF) for Dhaka
Metro Line 5 (South) Project”.
1) to prepare detailed feasibility study with Engineering Design Framework (EDF) by (i)
reviewing the pre-FS of the Project including the proposed technical and operational
parameters and design standards and further reviewing the alignment; (ii) making
supplementary surveys such as topographic and geotechnical; (iii) conducting required
social and environmental surveys in accordance with ADB Safeguard Policy Statement
(SPS) (2009); (iv) develop conceptual design; (v) review cost estimates and relevant
project evaluation, and (vi) develop EDF with design parameters to satisfy requirements
for the project.
2) to develop Engineering Design packages based on the EDF that will meet all
requirements by DMTCL for the Project functions, performance, quality, and cost
control. Detailed engineering design shall be developed for civil works of elevated,
underground, stations, and depot; meanwhile, basic design shall be developed for the
other components of equipment such as rolling stock, signaling and communication,
and power supply.
3) to provide procurement support including (i) preparation for bidding documents of the
Engineering Design packages for (i) for civil works based on ADB’s standard bidding
document (SBD) for works, and (ii) DSI for rolling stocks and system contracts based
on ADB’s SBD for design, supply, and installation, by providing high-quality basic
design, technical standards, specifications, and particular conditions of contracts; and
(ii) assistance in advertising, issuing bidding documents, responding to queries,
receiving and evaluating bids, and other procurement-related activities.
4) to review management, operational and maintenance requirements for the Project, and
prepare institutional arrangement and countermeasures required for efficient operation
of the Project.
III. Outline Scope of the Consulting Services
9. The assignment of the consulting services shall cover the following key areas.
1) to review the pre-FS of the Project (Line 5 [South]) including further reviewing the
alignment;
2) to review transport development plan of other MRTs, particularly MRT Line 5 (North);
3) to assess the results of existing surveys and carry out supplementary surveys including
topographic, geotechnical, hydrologic, utility, material availability and traffic;
5) to review and finalize technical and operational parameters and design standards;
7) to conduct land acquisition and resettlement assessment and prepare land acquisition
plan (LAP) and resettlement plan (RP) for the entire project including depot in
accordance with ADB SPS;
8) to conduct social impact assessment (SIA) including poverty, gender, and universal
design elements;
11) to assess labor requirements and occupational safety and health risks;
1.
12) to prepare detailed feasibility study with Engineering Design Framework;
22) to assist DMTCL in preparing relevant project documents required for the government
approval;
10. The consulting services will be carried out in three (3) phases for a total duration of 36
months: phase 1 of development of detailed feasibility study with Engineering Design
Framework (EDF) for 9 months; phase 2 of preparation of Engineering Design packages for 15
months (including 3 months for bidding document preparation); and phase 3 of assistance of
the procurement process for 12 months. Detailed tasks and required deliverables are described
in chapter V. below.
V. Detailed Tasks
11. Task 1: Technical Feasibility Assessment. The Consultant shall conduct detailed
technical feasibility assessment based on the pre-feasibility study including further reviewing
the alignment. The detailed technical feasibility assessment includes (i) review of the pre-
feasibility study including demand forecast and operational plan, (ii) surveys of topographic,
geologic, hydrologic, project right-of-way, and utilities, (iii) design standards and design
framework (please see Task 2), (iv) conceptual design, (v) update of cost estimates, and (vi)
project evaluation including economic and financial analysis. The Consultant, in cooperation
with Client, shall make the best use of outputs of (i) the preparatory survey and (ii) detailed
design/ basic design for Line 5 (South), particularly for rolling stocks and systems to secure
compatibility of the components and avoid redundant assignments, but also efficiency and
economy in conducting the assessment. Detailed tasks are:
1) Collect and review all available relevant studies, reports, materials, documents,
and information including findings from the Pre-feasibility study for Line 5
(South), preparatory surveys on Line 1, 5 (North), and 6 supported by JICA, and
ongoing detailed design works for Line 1 and Line 6.
2) Collect all necessary information of existing, ongoing and future planned
development works of government and private sector in and around the project
site and consult all relevant agencies/stakeholders. Take all findings into
consideration in the study. Support the client in carrying out continuous
coordination and consultations with all relevant stakeholders.
3) Assess and review detailed traffic forecasts of RSTP and the pre-feasibility
study, and revise and/or update, if necessary, the demand forecast of the
project along the route of the phase 1 section proposed in the pre-feasibility
study.
4) Conduct traffic survey of (i) traffic volume and speed surveys, and (ii) interview
survey along the proposed route to supplement data for the demand forecast
as well as to develop a traffic management plan.
5) Review the operation plan proposed in the pre-feasibility study, and finalize it to
be used for the basis for design parameters of the project. This will include
headway, commercial speed, the number of rolling stocks, and metro system
requirements, which meet demands of the project.
6) Carry out detailed topography, geology, hydrology, utility, material availability
and infrastructure surveys to develop the basic engineering design and to
provide full information to bidders. Details of the required surveys are shown in
Annex 1.
7) Finalize detailed horizontal and vertical alignment, station location, depot
location, and layouts duly considering the topography, geology, hydrology, land
formation, commercial aspects, economical and safeguard considerations,
existing infrastructures of the area, ongoing and future development plan and
schemes of both the government and private sectors in the area. Finalize
'Construction Right of Way‘(CROW) in the final alignment including land
required temporary for metro construction and access to the site, camp-sites or
quarries etc. Scale of alignment design drawings shall be or more detailed as
appropriate at selected critical locations.
8) By reviewing the pre-feasibility study, calculate the power demand for the trains
based on traffic forecast and proposed operation program considering also
degraded operation and emergency operation and power demand in case of
partial failures of the power supply system; define feeding points and capacity
of the substations; develop emergency power supply; develop a layout of
feeding lines from the national grid that minimizes the risk of total power failure
in case of planned blockage.
9) Examine the proposed signaling and interlocking system, telecommunication
system and train control system in the pre-feasibility study. The train control
system shall also include facilities for passenger information system, public
address system, on-board communication, CCTV and safety and security
monitoring. The Consultant shall fully consider compatibility of the system in
Line 5 (North).
10) Examine requirements of rolling stocks proposed in the pre-feasibility study.
The consultant shall fully consider possible direct-service to Line 5 (North) from
Line 5 (South) and efficient operation and maintenance required for both Line 5
(North) and (South).
11) Finalize detailed scope of work, technical aspects and design parameter of all
components/projects in consultation with DMTCL. Develop design standards
for all relevant track components, tunnels, bridges, stations, signaling and
telecom (Including Train Control Center), rolling stock and workshops. Please
also refer to Task 2.
12) Design facilities for multimodal connectivity of the project with other public and
individual modes of transport, particularly with other MRT and BRT lines.
13) Transit-oriented-development (TOD) shall be examined in close consultation
with relevant stakeholders to increase ridership and/or revenue of the MRT line.
Recommend feasibility and practical measures under the TOD concept which
could be implemented for Line 5 (south). In relation thereof, recommend areas
for commercial development and its cost sharing structure in the stations such
as advertising and for supporting establishments such as coffee shops, kiosks,
food stores, restaurants, bookshops, convenience stores etc. depending on the
size and category of stations and the commercial functions available in the
station environment.
14) Review practices of occupational safety and standards and prepare safety code
for the project.
15) Prepare traffic management plan with possible options during the construction
period to choose the best options that will have the least impact on the traffic
flow in Dhaka. These will include (i) sidewalk closures, (ii) street lane closures,
(iii) rerouting plan, and (iv) optimal construction measures.
16) The study should also include conceptual engineering design and layout plan
for all necessary railway tracks, rolling stocks, stations, depot, signaling and
telecom, tunnels, bridges, other structure, functional buildings, other facilities
such as automated ticketing and fare collection system, and platform screen
doors.
17) Prepare cost estimates for proposed project, showing foreign and local
currencies, and tax and duty elements, etc. This cost estimate is calculated with
the unit price based on the quantity indicated in the design documents prepared
in the technical feasibility.
18) Review and update the overall schedule and implementation plan of the project
based on the design documents, required construction measures, required
coordination and interface among components, and technical options reviewed
and examined in the technical feasibility.
19) Assess operation and maintenance personnel and other resources/facilities
requirements for operation and maintenance works. Prepare capacity building
plan, propose training facilities (e.g. training center/simulator) and program in
due consideration of other capacity building and training program provided by
other development partners.
20) Prepare an economic analysis of the project in accordance with ADB’s
guidelines for the economic analysis of projects. The analysis should include
distributional analysis with target units/groups of distributional analysis
determined through consultation with the experts for Poverty and Social
Assessment to a necessary extent. Also calculate financial internal rate of
return (FIRR) based on the fare to be adopted for metro system in Dhaka.
21) Critically assess possibility of Public-Private Partnership in terms of risk sharing,
financial viability, and institutional arrangement.
22) Estimate the required budget for appropriate operational and maintenance of
the project. Assess the financial sustainability.
23) Develop a monitoring and evaluation framework in accordance with ADB’s
Guidelines for Preparing a Design and Monitoring Framework.
24) Finalize procurement packages and frame suitable investment projects
covering all the components mentioned. Consultants should propose optimal
procurement methods, particularly for components of signaling communication,
and rolling stock, satisfying (i) technical compatibility requirements and (ii)
ADB’s procurement policy and regulations. Consultant may suggest inclusion
of additional component which might be essential to achieve the full benefit of
all the components.
25) Prepare detailed Feasibility study report which will contain main report with
detailed scope of work, all technical aspects, drawings/layouts, cost estimate
and Resettlement Plan (RP), Land Acquisition Plan (LAP), Environment
Management Plan (EMP), Operational plan, various survey reports and other
required documents.
12. Task 2: Design Standards and Framework Design. The Consultant shall establish
design standards and technical requirements for civil works, rolling stocks and equipment of
the project. The Consultant shall comply with the following:
1) The design standards shall comply with existing and on-going laws and
regulations of Bangladesh such as Metrorail Act and Metrorail rules, and in
accordance with Technical Standards of Metro Rail in Bangladesh or other
applicable standards adopted in metro lines in Dhaka.
2) The design standards for the project, in particular, rolling stocks and signaling
system, shall be consistent with those of Line 5 (North) for possible direct-
service and efficient operation and maintenance.
3) The design standards shall cover all technical areas of the project.
4) The design standards shall support the general design objectives of a highly
reliable, efficient, economical, productive, safe, comfortable, productive,
environmentally friendly, and reasonably advanced.
5) The design standards shall fit with the local environment conditions and comply
with the relevant Bangladesh and international environment protection
standards.
13. The Consultant shall develop framework design for the project and for each package
design to be carried out in Phase 2. The Consultant shall perform framework design in
accordance with requirements described in Annex 2.
14. Task 3: Poverty and Social Assessment. The Consultant shall conduct poverty and
social assessment of the project. Details are:
1) Conduct 20% poverty and social assessment taking into account
socioeconomic and poverty status of the project area of influence. The baseline
socio-economic survey (SES) is to be designed to capture information on the
Project Affected Persons (PAPs), their resources, employment, and
vulnerability. The survey data will lead to the development of management
information system (MIS) that will help consultation process and assist in
planning and implementation.
2) Identify all potential project stakeholders and elaborate what their stakes are in
the proposed project.
3) Conduct a benchmark video recording of the physical situation of the dwellings
and belongings as well as community assets before the commencement of SES
conducted.
4) Identify safeguards and non-safeguards social issues relevant to the project’s
objectives, scope and operational characteristics, and specify verifiable social
development outcomes of the project.
5) Identify and estimate the likely socioeconomic and poverty reduction impacts of
the project.
6) Assess local demand for the proposed investments, employment opportunities,
child labor, HIV/AIDS and human trafficking, affordability, gender and other
social risks that would result from the project and include measures to mitigate
social impacts, if any. This will be in accordance with ADB's Safeguard Policy
Statement (2009), and ADB’s Handbook on Social Analysis (2012). Prepare the
Poverty and Social Analysis for the proposed project.
7) Propose design features and measures for inclusion in the follow-on
investments (including the need for any technical assistance) to address
gender, labor, HIV, trafficking, and other social parameters identified in the
analysis above. Special attention to be paid to the gender to mainstream the
concept into project and its design.
8) Conduct stakeholder consultation with key stakeholder groups in terms of social
and economic characteristics (gender, ethnic and indigenous minorities;
socioeconomic vulnerability, etc.) who would be directly and indirectly affected
by the project’s objectives and scope, design alternatives, likely positive and
negative impacts, possible measures to mitigate adverse impacts and other
information that would be of use to the stakeholders. Consultant shall keep the
records of such stakeholder consultations.
9) With the participation of stakeholders, identify and analyze the reasons behind
the vulnerability of at-risk groups, including their exposure to risks. Suggest
participatory development strategies for key stakeholders to apply when
designing and implementing the project.
10) Collect sex-disaggregated data during poverty and social assessment for all
applicable indicators. Focus on how women may have different use or needs
when traveling by rail, and on issues of safe transport. Prepare project specific
'Gender Action Plan' (GAP) for gender development in and around the project
location of all the projects. Identify project design elements (policy or
implementation) in which women can participate in and thus benefit from the
project. The GAP shall be prepared, in consultation with the EA/IA, with a
proposed timeline reflecting the annual activities and deliverables.
11) Prepare Summary Poverty Reduction and Social Strategy (SPRSS) in
accordance with ADB’s format.
15. Task 4: Land Acquisition and Resettlement Planning and Indigenous Peoples. The
Consultant shall conduct required land acquisition and resettlement planning and indigenous
peoples assessment and due diligence in accordance with ADB’s Safeguard Policy Statement
2009 (SPS). Details are:
Task 6: Climate Risk and Vulnerability Assessment. The Consultant shall conduct a
general climate risk assessment of Dhaka to understand the key risks and ongoing climate
resilience initiatives. Based on the background information on Dhaka, the Consultant shall
conduct an in-depth climate risk assessment for the proposed alignment and sites of associated
structures of Line 5 (South). Specific tasks include:
B. Phase 2: Engineering Design Package (15 months including 3 months for bidding
document preparation)
17. The Consultant shall further refine the outputs of Phase 1 within the boundaries of the
principles and standards, and carry out Engineering Design packages for all components for
Line 5 (South) based on the technical framework established in Phase 1. Phase 2 shall be
completed within 15 months after the commencement of services for Phase 2. Specific
requirements are as follows.
2) Rolling Stock
In designing rolling stock, the Consultant shall consider, but not limited, to the following
factors:
a) Technical requirements for vehicle gauging, vehicle weight, track-train
interface, couplers, braking systems, sanding systems, reliability,
availability and maintainability, Safety (RAMS) – RAMS data must be
analyzed to ensure optimal performance of the whole Line 5 (South) and
minimize total cost during the life of Line 5 (South) operations.
b) Possible direct-service operation from Line 5 (South) to Line 5 (North).
c) Performance requirement including aerodynamic performance,
propulsion performance (acceleration, traction, braking, maximum
speed, design speed), energy efficiency and ride quality.
d) Environmental requirement for minimizing the environmental impact of
rolling stock.
e) Passenger comfort and security requirements with special attention to the
design door locking/ door releasing functions, emergency breaking,
alarms and passenger help phones, evacuation mode (front evacuation
door or side), universal design features and platform screen doors (PSD)
following international best practices.
f) Driving cab and control system requirements.
4) Stations
The Consultant shall perform design for all stations including underground and elevated stations
and in particular, interchange stations connecting the elevated station of Line 1 and Line 6. The
Consultant shall produce structural, architectural and electrical and mechanical drawings and
3D models for each station. Building Information Modeling (BIM), from open data format,
should be utilized for 3D design drawings together with time and cost aspects to examine
collision detection and engineering analysis. Specific requirements for design drawings are in
Annex 3. In designing the stations, the Consultant shall consider the following key factors:
a) Safety and security (free and safe movement of people);
b) Traffic, road and pedestrian requirements;
c) Urban utilities;
d) Structural requirements;
e) Inclusiveness and accessibility (passenger forecasts and entrance location
requirements, adequate capacity for movement of people);
f) Interchange stations, intermodal exchange and way-finding (minimum
distance of walking to and from the platform and between platforms for
transfer between lines, clear signs for transfers and exits);
g) Interfaces with existing, proposed and potential future projects;
h) Environmental considerations;
i) Weather conditions including cyclone and possible flood;
j) Constructability and disruption due to construction;
k) Flexibility in design to allow stations to respond to site specific
requirements;
l) Future expansion;
m) Specific criteria to be applied in the development of station designs are as
follows:
i) Dimension of the station platforms and other spaces must satisfy the
passenger flow based on careful analysis of traffic survey and
passenger demand forecast;
ii) Passengers safety and convenience:
− minimum walking distance to and from the platform and
between platforms for transfer between lines;
− adequate capacity for passenger movements;
− clear signage on train routes, transfers and exists;
− safety and security, including a high level of protection against
accidents, crime and terror;
− Accessibility of women, children and handicapped persons
(disabled and elderlies);
iii) Platform Screen Doors (PSD): design principles for signaling/PSD
interface to ensure PSD open only when train is present and correctly
positioned, rolling stock door/PSD synchronization and positioning;
degraded mode operation (train evacuation, train in wrong position,
door locked, power outage), operations and maintenance (O&M
principles to be included in the Preliminary Operation and Safety
plan); requirement for driver access to cabin; definition of PSD /
platform nose and other infrastructure interface, specific design
criteria for civil engineering and alignment, tolerances for PSD
positioning; special gauge and clearance requirement to limit
infringement in the structure gauge while reducing the gap between
doors and trains where someone could be trapped; principles to
prevent someone to have hand or clothes trapped and train starting,
(object detection principles), grounding and bounding requirement;
iv) Emergency evacuation from public areas and non-public areas;
v) Space requirements for electrical, mechanical and equipment;
vi) Space requirement for operational purposes and passenger services;
vii) Fire prevention and control;
viii) Building materials and finishes (fire and smoke retardant,
waterproof, durable, cost effective for maintenance,
constructability); and
ix) Access control and anti-intrusion and other necessary components.
7) Viaduct
The Consultant shall design elevated structures with an aesthetic (including privacy concerns
in built up areas) and economic view and with due consideration of safety and construction
quality. The Consultant shall produce concrete and steel structure layout drawings following
the requirements in Annex 3 with descriptions on calculations and pre-stressing requirements.
Reinforcement drawings or detailed structural steel drawings are also required.
8) Signal System
To the greatest extent possible, the signal system shall be proven systems which utilize state
of the art standard equipment and components providing the highest levels of reliability,
maintainability and safety. In designing the signaling system, the Consultant shall meet the
general requirements for designing the system adopted in Line 5 (North). The system will
apply communication-based train control (CBTC) technology and include automatic train
protection (ATP), automatic train operation (ATO), automatic train supervision (ATS),
automatic Train Control (ATC), and computerized interlocking systems (CIS). The signaling
system must be a “fail-safe” system. In addition to the general requirements in Annex 2, The
Consultant will perform the following tasks but not limited to:
a) defining engineering conditions (including requirements for RAMS,
electromagnetic compatibility etc.);
b) designing data transmission system for signaling system;
c) defining functional requirements of the system and subsystems (such as
ATP, ATO, Wayside signal);
d) defining performance requirement of the system and subsystem (such as
stopping accuracy, minimum dwell time);
e) defining system requirements (in accordance with international standards;
f) defining interface Requirements (rolling stock interface, track work
interface, traction power system interface, communications interface);
g) determining features of control system;
h) defining signaling equipment specifications (running and dwell time,
maximum speed; maximum number of simultaneously operating trains and
other key parameters);
i) conducting a multi-criteria analysis (transmission system, degrees of
automation, speed limits, impact on operation, investment and operation
costs) and comparison of systems and alternatives (from conventional relay
interlocking to the latest computerized interlocking, CBTC, and fully
unmanned solutions) to identify the state-of art technology that will be most
suitable and economical for Line 5 (South) with safety as the first priority in
mind;
j) developing detailed design for each subsystem and assembling all
specification requirements (design criteria and functional performance
criteria) of the entire system with due consideration of first cost and life-
cycle cost as well as compatibility with other traffic signal systems and
requirements of grade crossing protection for at grade system;
k) designing the train control systems in accordance with the driverless
operational requirements, the ATP, ATC and ATO and in compliance with
international standards; and
l) identifying wayside equipment.
9) Communication System
The Consultant shall design a highly reliable and efficient communication system for Line 5
(South) using a multiservice telecommunication network comprising a radio communication
network and a fixed telecommunication network integrated with mobile telecommunications.
RAMS should be fully considered. The communication system using a master clock system
and the networks shall be linked together and monitored by the OCC. An agreement of radio
frequency for Line 5 (South) will be made with the concerned authorities of Government of
Bangladesh. The system should provide real-time train traffic information, rolling stock alters,
direct telephone, on-board communication system, passenger information (visual and audio),
CCTV etc. for the OCC. The Consultant shall consider the following factors in designing the
communication system:
a) Radio Communication Network - Radio will be used for mobile transmission
of data, video and voice between OCC, trains, track, stations and stabling
yard. The Consultant will propose applicable technical solutions including
digital trunked radio network technologies. The Consultant shall select and
design the radio network configuration for outdoor and indoor coverage.
This system can also provide real-time arrival time to passenger through
information panels. These panels can be linked to the central system by radio
communication or fixed communication network.
b) Fixed Telecommunication Network–A fixed telecommunication network
will be installed along Line 5 (South) using fiber optic cable or similar
technology to allow fast and reliable data transmission between OCC and
equipment along the line. A switch module will be installed at each station
connecting telephones, video cameras, audio announcement system,
passenger information panels, ticket distributor, power and signaling system,
access control and intrusion prevention system. The Consultant shall
consider adequate allowance in system capacity for future expansion. In
designing the system, the Consultant shall give due consideration to
electromagnetic compatibility.
19) Cost Estimate, and economic/financial analysis updates for the Project
At the end of Phase 2 and based on the design packages completed during Phase 2, the
Consultant shall update the cost estimate for the procurement and construction of the entire
Line 5 (South) initially done at Phase 1 based on the design packages completed during Phase
2. The Consultant shall prepare an updated fund allocation for each package. The cost
estimate should indicate the amount for each package and breakdowns into key components
of each package. The economic and financial analysis carried out in Phase 1 needs to be
updated based on the revised cost estimates and implementation schedule.
18. The Consultant shall assist DMTCL for both prequalification and bidding in advertising,
pre-bid (pre-PQ) meetings, clarifications and addendum issuance, technical and financial
evaluation in accordance with evaluation and qualification criteria set forth in prequalification
and bidding documents, preparation for relevant evaluation reports, and contract negotiation for
each bid package.
D. Other Assignments
19. The Consultant shall hold workshops inviting relevant government stakeholders and
development partners in the course of detailed feasibility study preparation.
20. The Consultant shall assist DMTCL in preparation for Development Project Proposal
(DPP) after finalizing the detailed feasibility study.
21. The Consultant shall conduct overseas training for DMTCL and/or other relevant
government officials.
22. The Consultant shall prepare animation in 3D to illustrate the project including train
operations and passenger flow.
V. Team Composition and Qualification Requirements
23. The Consultant shall provide key personnel with an estimated total of 494 person
months of inputs of which 290 person months are from international experts and 204 person
months from national experts. Total person months required as inputs are estimated at 1,564 of
which 566 person months are international and 998 person months are national. In addition,
459 person months supporting staff are estimated to be required. The Consultant shall note that
the distribution of the total person months among the positions is indicative. However, the
Consultant should not revise the key expert positions. An indicative composition of the
Consultant task teams is suggested in Table 1-1 and 1-2 below; The Consultant may also adjust
and rename the task teams when such adjustment is fully justified in the best interest of the
Project.
Surveys • Assess and identify the need for surveys required for 13 23
B engineering design tasks
• Conduct the identified required surveys
• Conduct experiments, analyze survey results, and
prepare reports
C Traffic management/ • Conduct surveys, collect and analyze data to develop 12 18
utility relocation traffic management plan and utility relocation plan
• Develop location specific traffic management plan for
station construction areas, and elevated and cut-and-
cover sections
• Design utility infrastructure system layout at station
areas, and elevated and cut-and-cover sections
D Tunnel design • Review pre-FS document and evaluate survey results 63 108
• Develop tunnel design package for Metro Line 5
(South)
• Propose optimal construction methods for Metro Line
5 (South)
• Conduct structural calculations and submit relevant
reports
E Underground station • Review pre-FS document and evaluate survey results 78 123
design • Develop underground station design package for
Metro Line 5 (South)
• Develop construction method
• Design stairs, walkways, lift, escalators, ventilation, air-
conditioning, exits, and other facilities for underground
stations
• Conduct structural calculations and submit relevant
reports
F Depot design • Review pre-FS document and evaluate survey results 73 78
• Develop depot and stabling yard design package for
Metro Line 5 (South)
• Develop construction method with due attention to soil
conditions
• Design layout, buildings/ facilities, required equipment
other facilities for depot/stabling yard
• Conduct structural calculations and submit relevant
reports
Task Team Responsibility Int’l National
person person
months months
G Elevated section design • Review pre-FS document and evaluate survey results 39 51
• Develop elevated section design package for Metro
Line 5 (South)
• Develop construction method
• Design stairs, walkways, lift, escalators, ventilation, air-
conditioning, exits, and other facilities for underground
stations
• Conduct structural calculations and submit relevant
reports
H Architect design • Review pre-FS document and evaluate survey results 29 57
• Develop architectural design package for all stations,
depot, offices, and other structures for Metro Line 5
(South)
I Power supply system • Review pre-FS document 23 37
• Develop power supply system design package for
Metro Line 5 (South) including traction, rolling stocks,
substations, ring circuit, overhead power supply
system, power system at stations and depot, cabling,
lighting protection system, lighting system, and other
systems for the project