You are on page 1of 34

7-1

Section 7. Terms of Reference


for Engineering Design and Procurement Support
for Dhaka Metro Line 5 (South) Project

I. Project Background

1. General background. An efficient transportation system with good inter and intra city
linkages is essential to ensure Dhaka’s position as a functional city with population of more
than 15.9 million. Present transport system in the city is chaotic in terms of traffic congestion,
pollution, accident, inefficient travel time. A huge number of modes of motorized and non-
motorized traffic are observed everywhere on roads. The number of automobiles has steadily
increased for the last decades. The city needs to provide efficient public transport infrastructure
to address the growing population, vehicles and economic activities.

2. Mass Rapid Transit (MRT) network in Dhaka has been proposed as critical measures to
mitigate the serious traffic congestion and improve economic efficiency in the area. Strategic
Transport Plan (STP) was formulated by the Dhaka Transport Coordination Board (DTCB)
under the technical assistance by the World Bank in 2005; STP emphasized necessity of a
modern, clean, efficient system which will create a high level of service covering the whole
metropolitan area and reaching out to the new communities in an integrated manner. Based on
the STP study, Japan International Cooperation Agency (JICA) conducted Dhaka Urban
Transport Network Development Project (DHUTS) in 2010 and the Revised Strategic Transport
Plan (RSTP) in 2015. The concept of urban transport development under RSTP is to set up
satellite regional centers to reduce the population density in central business district (CBD) and
to connect CBD with the satellite cities by MRT and/or Bus Rapid Transit (BRT). RSTP
proposed 5 MRT lines and 2 BRT lines as shown below. RSTP was approved as an official
transport plan in August 2016 by Ministry of Road Transport and Bridges. In line with RSTP,
JICA has conducted preparatory studies (feasibility studies [FS]) for three MRT lines in Dhaka:
MRT Line 1, Line 5 (North) and Line 6. JICA is currently supporting construction of Line 6,
and engineering designs for Line 1 and Line 5 (North) through ODA loans.

[MRT MAP from RSTP]

3. Dhaka Metro Line 5 (South). Meanwhile, the Asian Development Bank (ADB)
approved the Project Preparatory Technical Assistance (PPTA) for Dhaka Metro Project in
December 2015 to assess the RSTP and prepare a priority metro project for investment by ADB.
While waiting for the Government’s endorsement of the PPTA, JICA started in June 2016 a
feasibility study for Line 1 and Line 5 (North). Given the emerging development, the scope,
schedule and implementation of the PPTA needed to be adjusted; the Government requested
ADB to conduct a pre-feasibility study on Line 5 (South), which is the remaining part of Line
5 not covered by the JICA study, for preparation for ADB’s Project Readiness Financing (PRF)
and future investment project.

4. Under the PPTA, a consulting team was recruited to conduct a pre-FS for Dhaka Metro
Project of Line 5 (South) (the Project) in May 2018. The objectives of the study are to formulate
a proper project that is feasible in view of technical, economic, financial, social, and
environment aspects. The study covers (i) confirmation of priority of the proposed Line 5
(South) among the other MRT lines; and (ii) preparation for pre-FS including demand forecast,
operational parameters, preliminary engineering and cost estimates, economic and financial
evaluation, and safeguards consideration.

5. The total length of the Project is about 17.4 km between Gabtoli station and Dasherkandi
station with an underground section of about 12.8 km and an elevated section of about 4.6 km
with 12 underground and 4 elevated stations; a depot accommodating rolling stocks and
operational facilities for Line 5 (South) is planned near the east end of the Project at
Dasherkandi station area. Line 5 (South) will be connected with Line 5 (North) at Gabtoli
station, both of which will serve as east-west corridors and make it possible to transfer with
north-south running MRTs/BRTs at several stations. Through-services between the two lines
of North and South of Line 5 may be considered for the extension section of Line 5 (North).
There will be 15 stations (including future stations at the east end but excluding Gabtoli station)
to be constructed under the Project, 11 of which will be underground stations. Two stations at
the most east side will not be operated in the beginning for the current undeveloped surrounding
areas. About 9 km of future extension to the east to Borpa is planned but is not included in the
scope of the Project.

[Line 5 (South) Map from PPTA]

6. Dhaka Mass Transit Company Limited (DMTCL) under Ministry of Road Transport
and Bridges will be the executing agency of the Project. DMTCL will engage an eligible
consulting firm or a joint venture of consulting firms (Consultant) to conduct consulting
services for Engineering Design of the Project to implement the Project on a basis of “detailed
design and execution” for civil works and “design, supply, and installation (DSI)” for rolling
stocks, and electrical and mechanical system. The service also includes necessary bidding
document preparation and assistance in tender procedures. The Engineering Design services
will be financed by ADB through its loan of “Project Readiness Financing (PRF) for Dhaka
Metro Line 5 (South) Project”.

7. The procurement of all packages including consulting services is to be approved by


applying Paragraph 11. (3) of Public Procurement Rules 2008; thus, procurement will be
approved by DMTCL Board. DMTCL shall not obtain any of the approval of the government’s
Purchase Committee, and the endorsement of the respective ministry pertaining to any
procurement of goods and services or employment of consultants.
II. Objectives of the Consulting Services

8. The objectives of the consulting services are

1) to prepare detailed feasibility study with Engineering Design Framework (EDF) by (i)
reviewing the pre-FS of the Project including the proposed technical and operational
parameters and design standards and further reviewing the alignment; (ii) making
supplementary surveys such as topographic and geotechnical; (iii) conducting required
social and environmental surveys in accordance with ADB Safeguard Policy Statement
(SPS) (2009); (iv) develop conceptual design; (v) review cost estimates and relevant
project evaluation, and (vi) develop EDF with design parameters to satisfy requirements
for the project.

2) to develop Engineering Design packages based on the EDF that will meet all
requirements by DMTCL for the Project functions, performance, quality, and cost
control. Detailed engineering design shall be developed for civil works of elevated,
underground, stations, and depot; meanwhile, basic design shall be developed for the
other components of equipment such as rolling stock, signaling and communication,
and power supply.

3) to provide procurement support including (i) preparation for bidding documents of the
Engineering Design packages for (i) for civil works based on ADB’s standard bidding
document (SBD) for works, and (ii) DSI for rolling stocks and system contracts based
on ADB’s SBD for design, supply, and installation, by providing high-quality basic
design, technical standards, specifications, and particular conditions of contracts; and
(ii) assistance in advertising, issuing bidding documents, responding to queries,
receiving and evaluating bids, and other procurement-related activities.

4) to review management, operational and maintenance requirements for the Project, and
prepare institutional arrangement and countermeasures required for efficient operation
of the Project.
III. Outline Scope of the Consulting Services

9. The assignment of the consulting services shall cover the following key areas.

1) to review the pre-FS of the Project (Line 5 [South]) including further reviewing the
alignment;

2) to review transport development plan of other MRTs, particularly MRT Line 5 (North);

3) to assess the results of existing surveys and carry out supplementary surveys including
topographic, geotechnical, hydrologic, utility, material availability and traffic;

4) to review and revise traffic demand forecast;

5) to review and finalize technical and operational parameters and design standards;

6) to finalize alignment and location of the stations and depot;

7) to conduct land acquisition and resettlement assessment and prepare land acquisition
plan (LAP) and resettlement plan (RP) for the entire project including depot in
accordance with ADB SPS;

8) to conduct social impact assessment (SIA) including poverty, gender, and universal
design elements;

9) to conduct environment impact assessment (EIA) in accordance with ADB SPS;

10) to assess climate change risk and vulnerabilities of the Project;

11) to assess labor requirements and occupational safety and health risks;
1.
12) to prepare detailed feasibility study with Engineering Design Framework;

13) to prepare infrastructure/utilities relocation plan;

14) to prepare soil management plan;

15) to prepare traffic management plan;

16) to prepare project cost estimate and financing plan;

17) to conduct economic and financial evaluation of the Project;

18) to prepare project implementation plan, including overall implementation schedule


with due consideration of coordination and interface activities among components;
19) to review and identify optimal high technology and/or construction methodology, if
any, to be incorporated into the project design in terms of sustainable and quality
infrastructure development;

20) to develop engineering design packages for

a) stations, offices, operations control center (OCC), depot, bridges, overpasses,


underground and elevated structures with due consideration of integration with
other MRTs and traffic modalities;
b) tracks alignment, stations and stabling yard;
c) power supply;
d) electrical and mechanical systems including escalators/elevators;
e) signal, communication, operations control and IT systems;
f) rolling stock, rails and equipment;
g) platform screen doors, automated ticketing and fare collection system and
SCADA
h) fire prevention system, ventilation system of the tunnel and stations, air condition
facilities for stations, and required safety facilities;
i) water supply, drainage, and sewage systems;
j) inter-modal facilities

21) to prepare construction, management, and operation and maintenance (O&M)


manuals;

22) to assist DMTCL in preparing relevant project documents required for the government
approval;

23) to provide assistance in preparation for bid documents;

a) optimal procurement packaging with or without prequalification;


b) optimal procurement methods in consideration of (i) technical compatibility, and
(ii) requirements of ADB’s procurement policy and regulations;
c) cost estimate for each procurement packages;
d) evaluation and qualification criteria for each procurement package;
e) employer’s requirements for each procurement package, including design
instructions, specifications, output standards, and drawings;
f) forms of contract for each procurement package including particular conditions of
contracts based on (i) ADB’s SDB for works and (ii) ADB’s SBD for design,
supply, and installation for rolling stocks and systems with necessary
modifications for the Project and ADB standard bidding document language;
g) prepare bidding documents in accordance with ADB’s procurement policy and
regulations;

24) to assist DMTCL in advertising, issuing bidding documents, responding to queries,


receiving and evaluating bids, and other procurement-related activities;
25) to review management, operational and maintenance requirements for the Project, and
prepare institutional arrangement and countermeasures required for efficient operation
of the Project;

26) to provide necessary trainings to DMTCL;

27) to support DMTCL in its project publicity campaign; and

28) to prepare required reports to be submitted to DMTCL.


IV. Implementation Schedule

10. The consulting services will be carried out in three (3) phases for a total duration of 36
months: phase 1 of development of detailed feasibility study with Engineering Design
Framework (EDF) for 9 months; phase 2 of preparation of Engineering Design packages for 15
months (including 3 months for bidding document preparation); and phase 3 of assistance of
the procurement process for 12 months. Detailed tasks and required deliverables are described
in chapter V. below.
V. Detailed Tasks

A. Phase 1: Detailed Feasibility Study with Engineering Design Framework (9


months)

11. Task 1: Technical Feasibility Assessment. The Consultant shall conduct detailed
technical feasibility assessment based on the pre-feasibility study including further reviewing
the alignment. The detailed technical feasibility assessment includes (i) review of the pre-
feasibility study including demand forecast and operational plan, (ii) surveys of topographic,
geologic, hydrologic, project right-of-way, and utilities, (iii) design standards and design
framework (please see Task 2), (iv) conceptual design, (v) update of cost estimates, and (vi)
project evaluation including economic and financial analysis. The Consultant, in cooperation
with Client, shall make the best use of outputs of (i) the preparatory survey and (ii) detailed
design/ basic design for Line 5 (South), particularly for rolling stocks and systems to secure
compatibility of the components and avoid redundant assignments, but also efficiency and
economy in conducting the assessment. Detailed tasks are:

1) Collect and review all available relevant studies, reports, materials, documents,
and information including findings from the Pre-feasibility study for Line 5
(South), preparatory surveys on Line 1, 5 (North), and 6 supported by JICA, and
ongoing detailed design works for Line 1 and Line 6.
2) Collect all necessary information of existing, ongoing and future planned
development works of government and private sector in and around the project
site and consult all relevant agencies/stakeholders. Take all findings into
consideration in the study. Support the client in carrying out continuous
coordination and consultations with all relevant stakeholders.
3) Assess and review detailed traffic forecasts of RSTP and the pre-feasibility
study, and revise and/or update, if necessary, the demand forecast of the
project along the route of the phase 1 section proposed in the pre-feasibility
study.
4) Conduct traffic survey of (i) traffic volume and speed surveys, and (ii) interview
survey along the proposed route to supplement data for the demand forecast
as well as to develop a traffic management plan.
5) Review the operation plan proposed in the pre-feasibility study, and finalize it to
be used for the basis for design parameters of the project. This will include
headway, commercial speed, the number of rolling stocks, and metro system
requirements, which meet demands of the project.
6) Carry out detailed topography, geology, hydrology, utility, material availability
and infrastructure surveys to develop the basic engineering design and to
provide full information to bidders. Details of the required surveys are shown in
Annex 1.
7) Finalize detailed horizontal and vertical alignment, station location, depot
location, and layouts duly considering the topography, geology, hydrology, land
formation, commercial aspects, economical and safeguard considerations,
existing infrastructures of the area, ongoing and future development plan and
schemes of both the government and private sectors in the area. Finalize
'Construction Right of Way‘(CROW) in the final alignment including land
required temporary for metro construction and access to the site, camp-sites or
quarries etc. Scale of alignment design drawings shall be or more detailed as
appropriate at selected critical locations.
8) By reviewing the pre-feasibility study, calculate the power demand for the trains
based on traffic forecast and proposed operation program considering also
degraded operation and emergency operation and power demand in case of
partial failures of the power supply system; define feeding points and capacity
of the substations; develop emergency power supply; develop a layout of
feeding lines from the national grid that minimizes the risk of total power failure
in case of planned blockage.
9) Examine the proposed signaling and interlocking system, telecommunication
system and train control system in the pre-feasibility study. The train control
system shall also include facilities for passenger information system, public
address system, on-board communication, CCTV and safety and security
monitoring. The Consultant shall fully consider compatibility of the system in
Line 5 (North).
10) Examine requirements of rolling stocks proposed in the pre-feasibility study.
The consultant shall fully consider possible direct-service to Line 5 (North) from
Line 5 (South) and efficient operation and maintenance required for both Line 5
(North) and (South).
11) Finalize detailed scope of work, technical aspects and design parameter of all
components/projects in consultation with DMTCL. Develop design standards
for all relevant track components, tunnels, bridges, stations, signaling and
telecom (Including Train Control Center), rolling stock and workshops. Please
also refer to Task 2.
12) Design facilities for multimodal connectivity of the project with other public and
individual modes of transport, particularly with other MRT and BRT lines.
13) Transit-oriented-development (TOD) shall be examined in close consultation
with relevant stakeholders to increase ridership and/or revenue of the MRT line.
Recommend feasibility and practical measures under the TOD concept which
could be implemented for Line 5 (south). In relation thereof, recommend areas
for commercial development and its cost sharing structure in the stations such
as advertising and for supporting establishments such as coffee shops, kiosks,
food stores, restaurants, bookshops, convenience stores etc. depending on the
size and category of stations and the commercial functions available in the
station environment.
14) Review practices of occupational safety and standards and prepare safety code
for the project.
15) Prepare traffic management plan with possible options during the construction
period to choose the best options that will have the least impact on the traffic
flow in Dhaka. These will include (i) sidewalk closures, (ii) street lane closures,
(iii) rerouting plan, and (iv) optimal construction measures.
16) The study should also include conceptual engineering design and layout plan
for all necessary railway tracks, rolling stocks, stations, depot, signaling and
telecom, tunnels, bridges, other structure, functional buildings, other facilities
such as automated ticketing and fare collection system, and platform screen
doors.
17) Prepare cost estimates for proposed project, showing foreign and local
currencies, and tax and duty elements, etc. This cost estimate is calculated with
the unit price based on the quantity indicated in the design documents prepared
in the technical feasibility.
18) Review and update the overall schedule and implementation plan of the project
based on the design documents, required construction measures, required
coordination and interface among components, and technical options reviewed
and examined in the technical feasibility.
19) Assess operation and maintenance personnel and other resources/facilities
requirements for operation and maintenance works. Prepare capacity building
plan, propose training facilities (e.g. training center/simulator) and program in
due consideration of other capacity building and training program provided by
other development partners.
20) Prepare an economic analysis of the project in accordance with ADB’s
guidelines for the economic analysis of projects. The analysis should include
distributional analysis with target units/groups of distributional analysis
determined through consultation with the experts for Poverty and Social
Assessment to a necessary extent. Also calculate financial internal rate of
return (FIRR) based on the fare to be adopted for metro system in Dhaka.
21) Critically assess possibility of Public-Private Partnership in terms of risk sharing,
financial viability, and institutional arrangement.
22) Estimate the required budget for appropriate operational and maintenance of
the project. Assess the financial sustainability.
23) Develop a monitoring and evaluation framework in accordance with ADB’s
Guidelines for Preparing a Design and Monitoring Framework.
24) Finalize procurement packages and frame suitable investment projects
covering all the components mentioned. Consultants should propose optimal
procurement methods, particularly for components of signaling communication,
and rolling stock, satisfying (i) technical compatibility requirements and (ii)
ADB’s procurement policy and regulations. Consultant may suggest inclusion
of additional component which might be essential to achieve the full benefit of
all the components.
25) Prepare detailed Feasibility study report which will contain main report with
detailed scope of work, all technical aspects, drawings/layouts, cost estimate
and Resettlement Plan (RP), Land Acquisition Plan (LAP), Environment
Management Plan (EMP), Operational plan, various survey reports and other
required documents.
12. Task 2: Design Standards and Framework Design. The Consultant shall establish
design standards and technical requirements for civil works, rolling stocks and equipment of
the project. The Consultant shall comply with the following:

1) The design standards shall comply with existing and on-going laws and
regulations of Bangladesh such as Metrorail Act and Metrorail rules, and in
accordance with Technical Standards of Metro Rail in Bangladesh or other
applicable standards adopted in metro lines in Dhaka.
2) The design standards for the project, in particular, rolling stocks and signaling
system, shall be consistent with those of Line 5 (North) for possible direct-
service and efficient operation and maintenance.
3) The design standards shall cover all technical areas of the project.
4) The design standards shall support the general design objectives of a highly
reliable, efficient, economical, productive, safe, comfortable, productive,
environmentally friendly, and reasonably advanced.
5) The design standards shall fit with the local environment conditions and comply
with the relevant Bangladesh and international environment protection
standards.

13. The Consultant shall develop framework design for the project and for each package
design to be carried out in Phase 2. The Consultant shall perform framework design in
accordance with requirements described in Annex 2.

14. Task 3: Poverty and Social Assessment. The Consultant shall conduct poverty and
social assessment of the project. Details are:
1) Conduct 20% poverty and social assessment taking into account
socioeconomic and poverty status of the project area of influence. The baseline
socio-economic survey (SES) is to be designed to capture information on the
Project Affected Persons (PAPs), their resources, employment, and
vulnerability. The survey data will lead to the development of management
information system (MIS) that will help consultation process and assist in
planning and implementation.
2) Identify all potential project stakeholders and elaborate what their stakes are in
the proposed project.
3) Conduct a benchmark video recording of the physical situation of the dwellings
and belongings as well as community assets before the commencement of SES
conducted.
4) Identify safeguards and non-safeguards social issues relevant to the project’s
objectives, scope and operational characteristics, and specify verifiable social
development outcomes of the project.
5) Identify and estimate the likely socioeconomic and poverty reduction impacts of
the project.
6) Assess local demand for the proposed investments, employment opportunities,
child labor, HIV/AIDS and human trafficking, affordability, gender and other
social risks that would result from the project and include measures to mitigate
social impacts, if any. This will be in accordance with ADB's Safeguard Policy
Statement (2009), and ADB’s Handbook on Social Analysis (2012). Prepare the
Poverty and Social Analysis for the proposed project.
7) Propose design features and measures for inclusion in the follow-on
investments (including the need for any technical assistance) to address
gender, labor, HIV, trafficking, and other social parameters identified in the
analysis above. Special attention to be paid to the gender to mainstream the
concept into project and its design.
8) Conduct stakeholder consultation with key stakeholder groups in terms of social
and economic characteristics (gender, ethnic and indigenous minorities;
socioeconomic vulnerability, etc.) who would be directly and indirectly affected
by the project’s objectives and scope, design alternatives, likely positive and
negative impacts, possible measures to mitigate adverse impacts and other
information that would be of use to the stakeholders. Consultant shall keep the
records of such stakeholder consultations.
9) With the participation of stakeholders, identify and analyze the reasons behind
the vulnerability of at-risk groups, including their exposure to risks. Suggest
participatory development strategies for key stakeholders to apply when
designing and implementing the project.
10) Collect sex-disaggregated data during poverty and social assessment for all
applicable indicators. Focus on how women may have different use or needs
when traveling by rail, and on issues of safe transport. Prepare project specific
'Gender Action Plan' (GAP) for gender development in and around the project
location of all the projects. Identify project design elements (policy or
implementation) in which women can participate in and thus benefit from the
project. The GAP shall be prepared, in consultation with the EA/IA, with a
proposed timeline reflecting the annual activities and deliverables.
11) Prepare Summary Poverty Reduction and Social Strategy (SPRSS) in
accordance with ADB’s format.

15. Task 4: Land Acquisition and Resettlement Planning and Indigenous Peoples. The
Consultant shall conduct required land acquisition and resettlement planning and indigenous
peoples assessment and due diligence in accordance with ADB’s Safeguard Policy Statement
2009 (SPS). Details are:

1) For each project, carry out a screening of involuntary resettlement and


indigenous peoples’ impact in accordance with the Government’s policies and
regulations, and ADB’s Safeguard Policy Statement 2009 (SPS). Identify
whether the project is likely to lead to private land acquisition, thus, impact on
non-titleholders. The screening exercise will also include a due diligence of past
social impacts, viz., if land acquisition has been accomplished in anticipation of
the ADB project. The screening shall likewise flag any land acquisition or
ownership issues that that may be directly or indirectly related to the proposed
project, as reputational risks may be present.
2) Identify whether the project will be located in, or pass through, areas of
significant indigenous people’s settlements, and if this is the case propose how
to specifically include indigenous peoples in project planning and
implementation in accordance with ADB’s Safeguard Policy Statement 2009
(SPS). If relevant, make an overview of population characteristics in the project
area and anticipate project impacts.
3) Prepare and complete the checklist for involuntary resettlement and indigenous
people screening.
4) Since this is ADB’s first project with DMTCL, experience of recent and ongoing
resettlement activities financed by ADB and similar multilateral development
agencies in Bangladesh should be reviewed. After review, draft a resettlement
frameworks (RF) as necessary that meets the Government and ADB policy
compliance standards. The RF should define categories for impact, eligibility of
affected people for compensation and provide an entitlement matrix covering
compensation and other assistance for all types of impacts. The RF should
provide the methodology for the calculation of compensations based on
replacement cost to fully replace the asset. The entitlement matrix should focus
on assistance provided to non-titleholders in the urban context.
5) Should impacts on indigenous peoples be identified during the screening
process, even if indicative, prepare an Indigenous Peoples Planning Framework
(IPPF) as necessary.
6) Both the RF and IPPF should be based on a consultative process with the
executing agency and ADB and draw from broad-level consultations with the
communities likely to be affected by the subprojects.
7) Prepare relevant chapters and appendixes of the feasibility study report on
resettlement and indigenous peoples planning. The appendixes should include
the screening checklist for each subproject; one Resettlement Framework as
necessary; one Indigenous Peoples Framework as necessary (if impacts on
indigenous peoples are identified during the screening exercise).
8) Prepare a resettlement plan (RP) for each proposed subproject, and if impacts on
indigenous peoples are identified, an indigenous peoples plan (IPP) in
compliance with the Government’s policies and regulations and ADB's
Safeguard Policy Statement 2009 (SPS).
9) Based on the design, determine the legal status of private land within the Right
of Way (RoW), verify application of customary and traditional laws governing
land tenure, usufruct rights, and leasehold. Verify legal boundaries of the RoW
with the relevant ministry.
10) Based on the design, conduct census survey of all affected people (APs) and an
Inventory of Lost Assets.
11) Conduct a socioeconomic assessment of all APs residing/using the corridor of
impact to collect data on family composition, details on age and sex of all the
household members, income levels and occupational pattern, vulnerability
status, legal ownership status of land (private, traditional and customary rights,
lease), asset occupancy status and skills possessed.
12) Assess whether the compensation standards for all types of assets, crops, and
trees are based on replacement cost and describe in detail the valuation
methodology used. Undertake market surveys to compute replacement value of
land. Mouza index will be considered in conjunction with the full replacement
cost principles as described in ADB’s SPS; the national standard will be
compared and contrasted with ADB involuntary resettlement policy principles
and requirements, and if there is gap between the two, a suitable gap-filling
strategy should shall be proposed.
13) Undertake market survey to assess the rental market in nearby areas to ensure
security of tenure for non-titleholders.
14) Prepare a comprehensive income and livelihood restoration program, supported
by adequate budget, to help APs improve, or at least restore, their incomes and
livelihoods. Identify specific measures for the affected poor, ethnic minorities,
or other vulnerable households.
15) Conduct in-depth consultations with the APs, ensuring the involvement of
women in the process. Consultations should take the form of public meetings,
focus group discussions and one-on-one interviews. Ensure that the consultation
process is well documented and demonstrate how the concerns of the affected
persons are included to the design of the RP.
16) Identify livelihood impacts that emanate from land acquisition and resettlement
and propose mitigating measures after due consideration of consultations with
affected people.
17) Establish a cut-off date for eligibility criteria for the project, including for non-
title holders and ensure and document that it has been publicly disseminated.
18) Prepare overall budget for compensation, resettlement and rehabilitation
assistance.
19) Based on the draft R&R entitlements prepare an appropriate action plan for
additional support required for the vulnerable
20) Organize workshops on draft R&R policy to receive feedback from identified
stakeholders, including implementing agency, line agencies (specifically
revenue, forest, tribal welfare, etc.), NGO and others.
21) Assist the DMTCL to develop a computerized database management system for
recording APs and lost assets. The system should reflect the present impact on
APs and accordingly the entitlements for APs are planned. The system should
be in place from the beginning of the resettlement survey. Also, develop
cadastral mapping of affected plots for construction of new alignments using
inventory map developed under the feasibility study.
22) Assess the capacity of the Government in implementing the proposed RP and
IPP, and recommend improvements and actions required.
23) If impacts on Indigenous Peoples are identified, prepare an Indigenous Peoples'
Development Plan to minimize adverse impacts on tribal communities and to
enhance their access to project benefits on par with others.
24) Prepare relevant chapters and appendixes of the detailed design report on
resettlement and indigenous peoples planning. The appendixes should include
the RP for each project where resettlement impacts have been identified; IPP for
each project, where impacts on indigenous people have been identified.
25) Should the EA/IA decide to immediately implement the approved (with
concurrence from ADB) resettlement plan, the external monitoring need to be
institutionalized and the external monitoring agent need to be in place.
26) In the ensuing project loan, a social compliance audit shall be undertaken to
identify any past or present concerns related to the impacts of land acquisition
and resettlement and to determine whether actions were in accordance with
applicable social safeguards requirements, including ADB SPS.
27) Provide skills transfer with respect to resettlement and land acquisition, through
workshops, seminars, and on the job trainings to DMTCL staff and district
officials.

16. Task 5: Environmental Assessment. The Consultant shall conduct environmental


assessment; details are as follows.

1) Carry out an environmental assessment of the project in accordance with ADB's


Safeguard Policy Statement 2009 (SPS), and the Government’s environmental
regulations and policies. Study area must include the appropriate corridor of
impact for the entire alignment of Line 5 (south) including associate facilities
such as the depot, stations, etc.
2) Classify the project in accordance with the environmental impact assessment
requirements under Bangladesh Environment Conservation Act and ADB’s
screening checklist for environmental categorization according to the SPS.
3) Depending on the classifications, prepare EIA and TOR as per relevant
guidelines of DOE and ADB. In preparing the EIA, a minimum of the following
areas and issues must be covered:
a) Adequate baseline data representing the environmental conditions of the
project site must be collected on physical (air, noise and vibration,
surface and ground water, soil), ecological (flora, fauna, protected areas)
and socio-economic (physical cultural resources, heritage sites, etc.)
environmental components
b) Potential impacts on biodiversity including modified, natural, critical
habitat (as defined in the SPS) and protected areas and necessary
measures to minimize, mitigate, and offset impacts. If the project area
has any critical or natural habitat or any critically endangered/locally
protected species, detailed background information on such areas and
species must be provided and the significance of impact clearly defined.
Where necessary, mitigation may include physical measures such as
design and construction of wildlife overpass or underpass, linkage of rail
signaling systems to detection of wildlife on the rail corridor,
implementation of biodiversity conservation activities and other
innovative measures. Overall, there should be no net loss of biodiversity
as a result of the project.
c) Impacts related to tunneling and earthmoving, and proposed soil
management plan, including dumping sites or activities for utilization of
excess spoils in coordination with design engineers and based on
information from geological and topographical survey.
d) Potential waste issues including hazardous materials and wastes and
appropriate measures for their disposal, treatment, and other forms of
management.
e) Potential impacts on ambient air and water quality, noise and vibration
levels, and soil characteristics, including recommendations for suitable
mitigation measures. Impacts must be compared with the national
standards and World Bank Environmental Health and Safety (WB-EHS)
standards
f) Detailed privacy, noise and vibration study including
projections/modelling during metro operations as deemed necessary,
g) Quantification of greenhouse gas (GHG) emissions expected from the
construction activities under the project and GHG emissions and
reductions during operation of the railway lines and improved systems.
If the gross operation related GHG emissions exceed 100,000 tons per
annum, provide recommendations for suitable mitigation and/or offset
measures.
h) Assess labor requirement and propose labor management strategies or
mitigation measures.
i) Occupational Health Safety issues and measures for the construction
workers as well as the local communities in and around the project site
following the WB-EHS guidelines.
j) Potential impacts on physical and cultural resources including sensitive
receptors (temples, schools, hospitals, etc.) and measures to avoid,
minimize, or mitigate impacts. This must include modelling of air
pollution, noise and vibration levels during operation stage at various
distances from the edge of the rail ROW with clear identification of
sensitive receptors, including vibration-sensitive equipment, that will be
impacted due to air pollution, noise and vibration levels being higher
than baseline levels or higher than the national or WB-EHS standards.
For such receptors, clear mitigation measures must be provided.
k) Public consultations with affected people in the project area including
men, women, vulnerable or indigenous groups with clear documentation
on dates of meeting, issues discussed, and total number of male and
female participants. Consultations must also be carried out with relevant
government agencies (e.g. Forest Department, Agriculture Department,
etc.) and relevant environmental NGOs if any.
l) Grievance Redress Mechanism to address concerns and grievances of the
APs in the course of the project cycle.
m) Cumulative and induced impact assessment with recommendations for
mitigation measures to be implemented within the project, where
feasible and for implementation by other agencies responsible for other
projects.
n) Alternative analysis including the no project option (required only for
EIA under the ADB SPS).
o) Assessment of the institutional set up and capacity of the EA for meeting
environment safeguard requirements of the government as well as ADB.
Institutional and capacity needs, if any must be identified and planned
for with adequate budge provisions.
4) Prepare the EIA report to fulfill the requirements of the government and ADB.
5) Prepare an Environmental Management Plan (EMP) and Environmental
Monitoring Plan (EMOP) to implement and monitor the mitigation measures
with clear information on costs, time frame, responsible agencies, monitoring
methods and monitoring indicators and targets.
6) Incorporate into the EIA report including EMPs/APs, feedback from all relevant
stakeholders including the EA, ADB, and others. Prepare the Environment
Assessment and Review Framework (EARF), if necessary.
7) During the feasibility study stage, the outputs will be the complete EIA report
and EARF, as necessary fulfilling requirements of both the government and the
ADB SPS, including as many site-specific details as possible. For aspects of the
project with different requirements between the government and ADB SPS, one
report will be prepared to fulfill requirements of both agencies to the extent
possible.
8) The EIA prepared during the feasibility study stage must provide clear
recommendations for follow-up activities required during the detailed design
stage. Recommendations may include but not be limited to: (a) updating the
EMP to provide more site specific details or other updates; (b) providing more
detailed or updated information and analysis on location, expected impact and
mitigation measures on sensitive receptors; (c) updating the number of trees
required for removal; (d) conducting air and noise impact modelling; and (e)
other updates in the reports based on design updates. The output of the detailed
design stage will be the final EIA report and EARF, as necessary, fulfilling
requirements of both the government and the ADB SPS.

Task 6: Climate Risk and Vulnerability Assessment. The Consultant shall conduct a
general climate risk assessment of Dhaka to understand the key risks and ongoing climate
resilience initiatives. Based on the background information on Dhaka, the Consultant shall
conduct an in-depth climate risk assessment for the proposed alignment and sites of associated
structures of Line 5 (South). Specific tasks include:

1) Conduct literature reviews to: i) collect data and information on projected


climate changes in Dhaka area; ii) to understand if there are any ongoing climate
resilience initiatives being undertaken in the project area; iii) to understand
current practices and lessons learnt on climate change adaptation measures in
cities around the world, Asia and Bangladesh; iv) to understand the typical
adaptation measures being taken for similar projects within urban settings
2) Collect primary and secondary climate data (rainfall, temperature, highest flood
level (HFL) etc.) as necessary for identifying climate risks in Dhaka and
Bangladesh as a whole and in the proposed alignment and sites of the associated
structures in Dhaka in particular
3) Based on the findings of the literature review and data collected (as stated in
tasks 1 and 2 above) identify the key climate risks in Dhaka and make general
recommendations for adaptation based on ongoing best practices in the world,
Asia, and Bangladesh
4) Also identify key climate risks in the project alignment and locations of
associated structures
5) Review project design documents of Line 5 (South) to understand the project
scope
6) Based on the type of climate risks identified in Dhaka, conduct further in-depth
studies as necessary such as: hydrological analysis and modelling; statistical
analysis, GIS based analysis and consultation with relevant local authorities such
as the meteorology center and communities etc.
7) Where relevant, review hydrological studies carried out by the engineering team
and provide inputs to integrate future climate data into the study
8) In consultation with the design engineers, identify and incorporate climate
adaptation measures or design modifications to mitigate the key climate risks
identified. Where feasible, identify innovative measures or best practices being
applied successfully in similar projects and/or other countries
9) The adaptation measures for Line 5 (South) must be consistent with other climate
resilience measures, if any, that are being taken in the city
10) Estimate the incremental costs of adaptation measures or design modifications
in relation to the total project costs
11) Prepare a report on the climate risk assessment and adaptation measures
incorporated in the project design.

B. Phase 2: Engineering Design Package (15 months including 3 months for bidding
document preparation)

17. The Consultant shall further refine the outputs of Phase 1 within the boundaries of the
principles and standards, and carry out Engineering Design packages for all components for
Line 5 (South) based on the technical framework established in Phase 1. Phase 2 shall be
completed within 15 months after the commencement of services for Phase 2. Specific
requirements are as follows.

1) Adjustment and Expansion of Phase 1 Output


The Consultant shall update and work on more details of Phase 1 output which will be used
for Engineering Design package design in Phase 2. The Consultant shall:
a) define the Line 5 (South) alignment in more detail and submit an
alignment plan with drawings in 1/500 scale for Line 5 (South) layout,
1/200 for horizontal sections, 1/100 scale vertical sections and 1/100 or
1/50 scale typical section;
b) develop design guidelines, technical instructions, drawings, functional
requirements for each package design, construction and technical
guidance to contractors so that they can perform detailed engineering for
Line 5 (South);
c) develop plans and designs for Line 5 (South) auxiliary facilities
including car parks, passenger pathways and other commercial
buildings/facilities to the stations of Line 5 (South);
d) develop preliminary civil and structural design drawings of main
structures based on codes and standards established in Phase 1 and
refined in Phase 2 in consultation with the relevant agencies on space
requirements, land availability, architecture, power consumption,
geotechnical conditions, construction methods, project scheduling and
cost management; design all key structural elements and define structural
design parameters and loading standards; space and loading requirement
for power supply and other E&M equipment also need to be considered;
e) develop in detail the implementation plan for existing infrastructure/
utilities relocation;
f) develop construction methods according to the site conditions (geology,
hydrogeology, environment, adjacent structures and accessibility) taking
into consideration of new/ advanced technology, code of practice, safety,
impact on adjacent structures, roads, traffic and environment, noise and
vibration;
g) further refine, update the traffic detour plan for Line 5 (South)
construction period;
h) finalize EIA and develop detailed requirements for environmental
protection;
i) update and finalize RP in accordance with final alignment. the
engineering design, and the agreed resettlement framework, including
entitlement matrix and compensation plan in coordination with various
agencies in preparing the procedures for timely land acquisition (not only
for construction site but also for depot and construction yard);
j) assist land acquisition and compensation activities being undertaken by
DMTCL and/or competent authorities and report the results in monthly
progress report (throughout phase 2 and 3);
k) assist DMTCL to implement the measures identified in the RP
(throughout phase 2 and 3);
l) finalize poverty and social assessment with GAP and implementation
arrangement with cost estimate with due consideration of requirement
for universal/ gender design features of Line 5 (South) required by
social/gender analysis to ensure that the engineering design for Line 5
(South) will provide an accessible, convenient and safe public transport
for users of all walks of lives;
m) develop requirements for labor safety and detoured traffic safety during
Project construction, Line 5 (South) employee and passenger safety
during operations and maintenance of Line 5 (South);
n) refine and update Project implementation schedule and key milestones
with more details and a Gantt-chart;
o) identify volume of equipment and materials to be used for construction
of Project;
p) refine and update total investment cost estimate and identify total cost
for each package with breakdowns for the main items of each package;
q) develop the requirements for inspection, testing and performance
standards for all systems/subsystems/components of the Project; and
r) develop Engineering Design packages with clear and sufficient detail for
preparing the bidding documents and well-defined design principles for
the contractors to develop the final design and construction drawings and
in case needed, make justified adjustments in the final designs within the
defined design principles due to any new discovery by the contractor in
their construction surveys. At this stage, the Consultant will also
define typical equipment drawings and detailed technical standards. The
Consultant shall carefully review all aspects of the design and of all
interfaces between subsystems to ensure the quality of Line 5 (South)
and its longest life-cycle and lowest maintenance cost. All design
packages shall be subject to approval by the Client;
s) Produce drawings in accordance with requirements in Annex 3;
t) propose the optimal combination of components into packages that is
technically and economically most suitable for engineering design,
procurement and construction.

2) Rolling Stock
In designing rolling stock, the Consultant shall consider, but not limited, to the following
factors:
a) Technical requirements for vehicle gauging, vehicle weight, track-train
interface, couplers, braking systems, sanding systems, reliability,
availability and maintainability, Safety (RAMS) – RAMS data must be
analyzed to ensure optimal performance of the whole Line 5 (South) and
minimize total cost during the life of Line 5 (South) operations.
b) Possible direct-service operation from Line 5 (South) to Line 5 (North).
c) Performance requirement including aerodynamic performance,
propulsion performance (acceleration, traction, braking, maximum
speed, design speed), energy efficiency and ride quality.
d) Environmental requirement for minimizing the environmental impact of
rolling stock.
e) Passenger comfort and security requirements with special attention to the
design door locking/ door releasing functions, emergency breaking,
alarms and passenger help phones, evacuation mode (front evacuation
door or side), universal design features and platform screen doors (PSD)
following international best practices.
f) Driving cab and control system requirements.

3) Track and Rail System


The Consultant shall:
a) develop rail system design (including the crossover and turn outs) for the
whole of Line 5 (South); perform track alignment design based on the
parametric design produced in Phase 1 covering main alignment
(elevated, ground and underground sections), sections to depot and
stabling yard and to workshop and with due consideration of passenger
safety and comfort ability, maximum loading, corrosion risks,
construction and operations and maintenance cost, environmental impact
and noise (rolling stock noise, aerodynamic noise, equipment noise,
noise radiated by infrastructure vibrations) and vibration control; The
Consultant shall take full consideration of local climate conditions such
as temperature (concrete creep & shrinkage, steel relaxation) and ground
and rain water;
b) produce drawings for horizontal and vertical alignment including:
i) cross section drawings showing dynamic envelop and vehicle
clearance;
ii) drawings of typical cross sections in straight and curved
alignments for at-grade, aerial and underground sections
specifying different track laying principles for running line,
workshop and stabling yard;
iii) drawings demonstrate railway switches for mainline, the
connection between mainline and Stabling Yard, and
Stabling Yard area;
c) design the rail system using ballast less tracks for each particular section
(switches and crossing);
d) prepare drawings of typical cross section with corresponding description
and justifications of the characteristics of track components (rail,
fasteners, sleepers, ballasts, expansion joints and switches and
crossings); and
e) prepare guidelines for the installation of the tracks taking consideration
of various methods including traditional method (rails delivery along
site, fastenings & base plate assembly, rails welding, positioning on jigs,
shuttering, fine adjustment, concrete pouring, welds, definitive
fastening), use of rail beam (prefabricated element composed of rail
embedded in concrete beam), use of slip form technologies to construct
a continuous slab track, embedded slab track system with special
replaceable rail; select the best method to ensure maximum reliability
and safety and least cost for construction, operation and maintenance.

4) Stations
The Consultant shall perform design for all stations including underground and elevated stations
and in particular, interchange stations connecting the elevated station of Line 1 and Line 6. The
Consultant shall produce structural, architectural and electrical and mechanical drawings and
3D models for each station. Building Information Modeling (BIM), from open data format,
should be utilized for 3D design drawings together with time and cost aspects to examine
collision detection and engineering analysis. Specific requirements for design drawings are in
Annex 3. In designing the stations, the Consultant shall consider the following key factors:
a) Safety and security (free and safe movement of people);
b) Traffic, road and pedestrian requirements;
c) Urban utilities;
d) Structural requirements;
e) Inclusiveness and accessibility (passenger forecasts and entrance location
requirements, adequate capacity for movement of people);
f) Interchange stations, intermodal exchange and way-finding (minimum
distance of walking to and from the platform and between platforms for
transfer between lines, clear signs for transfers and exits);
g) Interfaces with existing, proposed and potential future projects;
h) Environmental considerations;
i) Weather conditions including cyclone and possible flood;
j) Constructability and disruption due to construction;
k) Flexibility in design to allow stations to respond to site specific
requirements;
l) Future expansion;
m) Specific criteria to be applied in the development of station designs are as
follows:
i) Dimension of the station platforms and other spaces must satisfy the
passenger flow based on careful analysis of traffic survey and
passenger demand forecast;
ii) Passengers safety and convenience:
− minimum walking distance to and from the platform and
between platforms for transfer between lines;
− adequate capacity for passenger movements;
− clear signage on train routes, transfers and exists;
− safety and security, including a high level of protection against
accidents, crime and terror;
− Accessibility of women, children and handicapped persons
(disabled and elderlies);
iii) Platform Screen Doors (PSD): design principles for signaling/PSD
interface to ensure PSD open only when train is present and correctly
positioned, rolling stock door/PSD synchronization and positioning;
degraded mode operation (train evacuation, train in wrong position,
door locked, power outage), operations and maintenance (O&M
principles to be included in the Preliminary Operation and Safety
plan); requirement for driver access to cabin; definition of PSD /
platform nose and other infrastructure interface, specific design
criteria for civil engineering and alignment, tolerances for PSD
positioning; special gauge and clearance requirement to limit
infringement in the structure gauge while reducing the gap between
doors and trains where someone could be trapped; principles to
prevent someone to have hand or clothes trapped and train starting,
(object detection principles), grounding and bounding requirement;
iv) Emergency evacuation from public areas and non-public areas;
v) Space requirements for electrical, mechanical and equipment;
vi) Space requirement for operational purposes and passenger services;
vii) Fire prevention and control;
viii) Building materials and finishes (fire and smoke retardant,
waterproof, durable, cost effective for maintenance,
constructability); and
ix) Access control and anti-intrusion and other necessary components.

5) Depot and Stabling Yard


The Consultant shall develop depot and stabling yard design, including:
a) Suitable construction method;
b) Access from the main line to depot and stabling yard
c) Depot structure, layout, facilities, and construction plan, including, but not
limited to, test track, bogie equipment plant, and vehicle paint coating plant;
d) Stabling yard equipment and special tools, including, but not limited to,
fixed installation factory and track maintenance equipment, welding
equipment and NDE inspection equipment, shunting vehicle, rail grinding
vehicle, track inspection vehicle, track cleaning vehicle, and train rescue
vehicle;
e) Stabling yard operation principle, Stabling Yard train travel description;
f) Stabling yard system design (fixed and dynamic: Signaling, Power
distribution, traction power supply, stingers or other system for train power
supply during cleaning and maintenance);
g) Stabling yard grounding principles, stray current protection, lighting
protection principles;
h) Stabling yard service vehicle circulation;
i) Stabling yard buildings (limited to Metro related operation and maintenance
buildings, OCC);
j) Stabling yard user circulations (roads, access, fencing, gates control, closed-
circuit television (CCTV), tools and spare part delivery, train delivery
principle –If in Stabling Yard); and
k) Maintenance and special tools functions, performance requirements and
preliminary locations (washing machine, wheel lathe, lifting machine).

6) Underground Section and Tunnels


The Consultant shall design and propose construction methods for the underground sections
and tunnels based on geological data, groundwater data and topographical data to ensure the
structures to be able to withstand the pressure of soil and groundwater. The Consultant shall
perform the following tasks:
a) Calculation and design of the tunnel structure;
b) Calculation and design of the statics loads;
c) Geotechnical design;
d) Designing layout solutions for tunnel construction;
e) Calculation of the geometric dimensions of the boreholes and shaft at
beginning and the end of TBM and the end of the excavation section;
f) Assessment of the tunnel construction impact on the surrounding
infrastructure, utilities, objects, buildings, vibration-sensitive equipment;
g) Producing drawings, in accordance with requirements in Annex 3, showing:
i) tunnel, including rails, drainage systems, emergency exit;
ii) neighboring infrastructure, utilities, buildings;
iii) integration interface between structures and systems;
iv) connection tunnel between two main tunnels;
v) dewatering pumps; and
vi) Geometric dimensions and structure of the start point, finish
point of TBM and tunnel.

7) Viaduct
The Consultant shall design elevated structures with an aesthetic (including privacy concerns
in built up areas) and economic view and with due consideration of safety and construction
quality. The Consultant shall produce concrete and steel structure layout drawings following
the requirements in Annex 3 with descriptions on calculations and pre-stressing requirements.
Reinforcement drawings or detailed structural steel drawings are also required.

8) Signal System
To the greatest extent possible, the signal system shall be proven systems which utilize state
of the art standard equipment and components providing the highest levels of reliability,
maintainability and safety. In designing the signaling system, the Consultant shall meet the
general requirements for designing the system adopted in Line 5 (North). The system will
apply communication-based train control (CBTC) technology and include automatic train
protection (ATP), automatic train operation (ATO), automatic train supervision (ATS),
automatic Train Control (ATC), and computerized interlocking systems (CIS). The signaling
system must be a “fail-safe” system. In addition to the general requirements in Annex 2, The
Consultant will perform the following tasks but not limited to:
a) defining engineering conditions (including requirements for RAMS,
electromagnetic compatibility etc.);
b) designing data transmission system for signaling system;
c) defining functional requirements of the system and subsystems (such as
ATP, ATO, Wayside signal);
d) defining performance requirement of the system and subsystem (such as
stopping accuracy, minimum dwell time);
e) defining system requirements (in accordance with international standards;
f) defining interface Requirements (rolling stock interface, track work
interface, traction power system interface, communications interface);
g) determining features of control system;
h) defining signaling equipment specifications (running and dwell time,
maximum speed; maximum number of simultaneously operating trains and
other key parameters);
i) conducting a multi-criteria analysis (transmission system, degrees of
automation, speed limits, impact on operation, investment and operation
costs) and comparison of systems and alternatives (from conventional relay
interlocking to the latest computerized interlocking, CBTC, and fully
unmanned solutions) to identify the state-of art technology that will be most
suitable and economical for Line 5 (South) with safety as the first priority in
mind;
j) developing detailed design for each subsystem and assembling all
specification requirements (design criteria and functional performance
criteria) of the entire system with due consideration of first cost and life-
cycle cost as well as compatibility with other traffic signal systems and
requirements of grade crossing protection for at grade system;
k) designing the train control systems in accordance with the driverless
operational requirements, the ATP, ATC and ATO and in compliance with
international standards; and
l) identifying wayside equipment.

9) Communication System
The Consultant shall design a highly reliable and efficient communication system for Line 5
(South) using a multiservice telecommunication network comprising a radio communication
network and a fixed telecommunication network integrated with mobile telecommunications.
RAMS should be fully considered. The communication system using a master clock system
and the networks shall be linked together and monitored by the OCC. An agreement of radio
frequency for Line 5 (South) will be made with the concerned authorities of Government of
Bangladesh. The system should provide real-time train traffic information, rolling stock alters,
direct telephone, on-board communication system, passenger information (visual and audio),
CCTV etc. for the OCC. The Consultant shall consider the following factors in designing the
communication system:
a) Radio Communication Network - Radio will be used for mobile transmission
of data, video and voice between OCC, trains, track, stations and stabling
yard. The Consultant will propose applicable technical solutions including
digital trunked radio network technologies. The Consultant shall select and
design the radio network configuration for outdoor and indoor coverage.
This system can also provide real-time arrival time to passenger through
information panels. These panels can be linked to the central system by radio
communication or fixed communication network.
b) Fixed Telecommunication Network–A fixed telecommunication network
will be installed along Line 5 (South) using fiber optic cable or similar
technology to allow fast and reliable data transmission between OCC and
equipment along the line. A switch module will be installed at each station
connecting telephones, video cameras, audio announcement system,
passenger information panels, ticket distributor, power and signaling system,
access control and intrusion prevention system. The Consultant shall
consider adequate allowance in system capacity for future expansion. In
designing the system, the Consultant shall give due consideration to
electromagnetic compatibility.

10) Operation Control Center (OCC)


The Consultant shall design the OCC with due consideration of ensuring efficiency, safety
and security of daily operations of the trains, stations and related facilities of Line 5 (South).
The consultant will identify the nature of OCC, either it would be separate for MRT Line-5
(South) or will be integrated with MRT Line-5 (North) and MRT Line-6. As the OCC for MRT
Line 5 (North) and MRT Line-6 will be located at Uttara and Hemayatpur respectively hence,
Line 5 (South) could be managed from the same OCC. Based on this assessment the consultant
will design separate OCC or will design integration required for the central OCC.

11) Power Supply


The Consultant shall review the proposed power supply system in the pre-FS. In designing
power supply for Line 5 (South), the Consultant shall follow the principles of value
engineering, and international practice in similar urban railway designs; the Consultant shall
also comply with the existing and applicable laws and regulations of Bangladesh, and
consider requirements of RAMS. The power supply for Line 5 (South) will be from two
independent power supply sources as mentioned in Phase 1. The power supply design shall
cover but not limited to:
a) High Voltage (HV), Medium Voltage (MV) and Low Voltage (LV)
distribution systems based on the plan and initial design developed and
approved by the Client in Phase 1;
b) Proposal of configuration and equipment for connecting with electricity
network from PGCB;
c) System and interface of traction power source (including overhead catenary
system);
d) Protection and insulators systems;
e) Voltage drop, overvoltage, overload, short circuit etc.;
f) Transformer and electrical at stations, OCC, stabling yard and auxiliary
systems;
g) SCADA system for power supply systems;
h) Lightning arrester and electrical system at right of ways;
i) Electrical cable systems;
j) Issues related to power supply on right of way such as lighting and other
facilities for maintenance;
k) Schedule;
l) Drawings; electricity diagram; layout etc.; and
m) Hazard and risk management.

12) Water Supply, Drainage and Waste Treatment


The Consultant shall design water supply, drainage, sewage and waste treatment systems for
Line 5 (South) and develop the related technical standards, codes, identifying the size of each
component and present computer-generated graphs for typical stations. Water supply for Line
5 (South) will be connected with the main water supply of Dhaka (DWASA). The Consultant
shall specify the method of water supply (such as city water and pressure tank etc.) and calculate
the volume of water supply and water tank capacity for the design of water supply pipe system
for stations and other facilities of the metro line. The Consultant shall pay special attention to
drainage system in below grade structures. Water drainage and pumping equipment will be
located and sized based on estimates of the water inflow rates (including heavy rainfalls and
climate change projections) and the line profile. In addition, the type of pumping will be defined
(pressurized or not pressurized). Whenever practicable, sanitary and rain water drainage and
pumping will be segregated. The Consultant shall also give due consideration to wastewater
issues in the design of depot, vehicle storage yards and maintenance facilities. For each typical
facility (station, depot, etc.), the Consultant shall develop the functional requirements and
general specifications of the main equipment (dewatering pumps, decantation system, cleaning
equipment, etc.) in accordance with the drainage requirements. The drainage system will
connect to main sewer network and local drainage system.

13) Fire Protection


The Consultant shall design fire prevention and control system for Line 5 (South) in
accordance with related codes and regulations and other applicable international standards.
The Consultant shall:
a) establish standards and develop specifications for fire prevention, detection
and suppression systems;
b) determine locations of fire detection and suppression equipment and
establish management and operations rules for both normal and emergency
conditions;
c) develop standards for fire resistance materials, toxicity and smoke control,
insulation; and
d) develop guidelines for evacuation and accessibility for rescue services
during a fire emergency following international standards.

14) Lighting System


The Consultant shall design the lighting system for all Line 5 (South) structures, buildings and
facilities. The levels of illumination will be based on the recommendations of international
standard/ practices. The Consultant shall specify the lighting level, the quality, the
performances required and the spacing of conventional and emergency lighting. Luminaries
should be the standard products of reputable manufacturers and should be the best of their
respective kind. The protection class of all luminaries will be specified in accordance with the
nature of the area where they will be installed. For emergency lighting, the Consultant shall
design the emergency lighting system that can prevent panic during outage of power supply and
emergency power supply transfers. For outdoor lighting, the design shall ensure adequate
lighting level for security and safety purposes. The Consultant shall design outdoor lighting
control at main entrance with separate switching for each category of outdoor lighting system.
The design of headlight for illuminating building facades should help enhance architectural
features without undue glare effect. The color of the lamps shall be selected following
international standards.

15) Heating, Ventilation and Air Conditioning (HVAC)


The Consultant shall design HVAC with adequate detail for procurement, installation and O&M
for Line 5 (South) in accordance with the related codes and regulations and international
standards. The Consultant shall use dedicated software to perform simulations and analysis to
identify the most suitable HVAC technical solutions for Line 5 (South). In designing the
HVAC, the Consultant shall define rules, standards and solutions for both normal and
emergency conditions. The Consultant shall provide general and functional specifications of:
a) air cooling equipment with refrigeration capacity to meet required levels of
temperature and humidity;
b) ventilation equipment (fans performance curves – pressure vs. air low rate,
ventilation shafts arrangement and cross sections area, acoustic level);
c) specifications of related equipment/ facilities (including the such
considerations as placing the platform screen doors along the edge of
platforms to isolate the station airconditioned public areas from the railway);
d) air ventilation and smoke exhaust devices in underground stations and
tunnels; and
e) HVAC noise and vibration attenuation devices.

16) Escalators and Elevators


The Consultant shall perform layout design (location, space, size dimensions, and distance to
other transport modes) of escalators and elevators for all Line 5 (South) stations and buildings
based on passenger flow forecast and develop specifications and technical standards
accordingly for procurement, installation and maintenance. The design shall ensure easy access
by all users with special attention to handicapped persons and elderlies.

17) Automated Ticketing and Fare Collection (ATFC) System


The Consultant shall design an integrated and automatic ticketing and fare collection system.
In doing so, the Consultant shall analyze “Specification for public transport operators to
introduce common IC Card for fare collection including clearing house” in May 2015. The
other metro lines are developing ATFC system based on the specification. The Consultant
shall review the proposed ATFC system in the pre-FS, and finalize the system, required
equipment, and design. More specific requirements/preferences are listed in, but not limited
to, the following:
a) e-ticketing system integrated with the ticketing systems of other metro lines
and transport systems to issue universal multimodal tickets;
b) flexible payment modes using traditional cash payment (coins or bills) as
well as debit/credit cards and electronic wallet;
c) mobile validation ticket system;
d) contactless smart card/e-passes;
e) user friendly ticketing machines and ticketing offices at locations at
locations most convenient to passengers;
f) an all-in-one integrated database and management system for managing
ticket sales and producing statistical data for monitoring and management
purposes; and
g) a built-in security control mechanism and software for preventing
revenue/case loss from theft, fake or illegally hacked tickets/cards/passes.

18) Operations and Maintenance (O&M) Master Plan


The Consultant shall:
a) provide an outline and the requirement for the main contents of O&M
document for each procurement package to be submitted by the contractors;
b) define key O&M requirements such as drivers/conductors, station staff,
maintenance staff, supply of spare parts, consumables, special tool, defect
liability and warranty, O&M term and conditions for construction and
equipment procurement packages;
c) define O&M tasks and responsibility for different stages as well as the key
performance indicators and the required process in O&M;
d) based on the basic operation principles defined in the pre-FS, develop a
preliminary operations plan which will define the operation principles of the
whole Line 5 (South) (line, depot and OCC);
e) develop an operation plan describing the operation requirements for the
system, according to the traffic forecast and the line characteristics,
including:
a. operating characteristics (principles, peak hour load diagrams)
b. implementation of headway (theoretical headway in the terminal
stations, theoretical headway along the line, calculation of the
practical headway)
c. trip time duration (practical standard running, dwell times)
d. transportation offer and fleet size (fleet needed, distance run by the
vehicles)
e. turn back in the terminal stations (calculation method, computation
of the minimum theoretical headway)
f. timetable (computation of the practical headway, operation
characteristics)
g. normal operation, degraded modes, depot operation plan, and safety
of operation
f) define the organizational arrangement for the O&M, key positions, and staff
requirement;
g) prepare required operation training requirements such as driver training
simulator; and
h) calculate O&M cost and revenues from fare collection and other sources.

19) Cost Estimate, and economic/financial analysis updates for the Project
At the end of Phase 2 and based on the design packages completed during Phase 2, the
Consultant shall update the cost estimate for the procurement and construction of the entire
Line 5 (South) initially done at Phase 1 based on the design packages completed during Phase
2. The Consultant shall prepare an updated fund allocation for each package. The cost
estimate should indicate the amount for each package and breakdowns into key components
of each package. The economic and financial analysis carried out in Phase 1 needs to be
updated based on the revised cost estimates and implementation schedule.

20) Project Schedule


At the end of Phase 2 and based on the design packages completed during Phase 2, the
Consultant shall update the Project procurement and construction schedule initially proposed
at Phase 1. Special attention should be paid to coordination and interface among the
components as well as with Line 5 (North).

21) Bidding Document Preparation


In accordance with ADB’s Procurement Policy and Regulations, the Consultant shall prepare
bidding documents including prequalification documents for each package based on Standard
Procurement Document for Prequalification of Bidders, SBD for works for civil works and
ADB SBD for design, supply, and installation for the other rolling stocks, equipment, and
systems. For each procurement package, the Consultant shall define and prepare:
a) Bidding data sheet;
b) Evaluation and qualification criteria for each prequalification and bidding
package;
c) Bill of Quantities (BOQ) and other relevant forms;
d) Employer’s requirements for specifications, coordination and interface
requirements, and schedule of supply for goods contracts/works
requirements for civil works;
e) Assess security requirements in and around the sites, and incorporate
appropriate countermeasures and requirements;
f) Special provisions in the contracts (e.g., health and labor safety, environment
management, risk mitigations);
g) Type of contract (propose most suitable type of contract, based on the
technical nature of the package) including Conditions of Contract; and
h) Procurement schedule.

C. Phase 3: Bidding Process Assistance (12 months)

18. The Consultant shall assist DMTCL for both prequalification and bidding in advertising,
pre-bid (pre-PQ) meetings, clarifications and addendum issuance, technical and financial
evaluation in accordance with evaluation and qualification criteria set forth in prequalification
and bidding documents, preparation for relevant evaluation reports, and contract negotiation for
each bid package.

D. Other Assignments
19. The Consultant shall hold workshops inviting relevant government stakeholders and
development partners in the course of detailed feasibility study preparation.

20. The Consultant shall assist DMTCL in preparation for Development Project Proposal
(DPP) after finalizing the detailed feasibility study.

21. The Consultant shall conduct overseas training for DMTCL and/or other relevant
government officials.

22. The Consultant shall prepare animation in 3D to illustrate the project including train
operations and passenger flow.
V. Team Composition and Qualification Requirements

23. The Consultant shall provide key personnel with an estimated total of 494 person
months of inputs of which 290 person months are from international experts and 204 person
months from national experts. Total person months required as inputs are estimated at 1,564 of
which 566 person months are international and 998 person months are national. In addition,
459 person months supporting staff are estimated to be required. The Consultant shall note that
the distribution of the total person months among the positions is indicative. However, the
Consultant should not revise the key expert positions. An indicative composition of the
Consultant task teams is suggested in Table 1-1 and 1-2 below; The Consultant may also adjust
and rename the task teams when such adjustment is fully justified in the best interest of the
Project.

Table 1-1: Indicative Task Team and Responsibility

Task Team Responsibility Int’l National


person person
months months
A Team Management • Lead the Consultant team and manage the team in 78 36
terms of high quality of the team’s performance
• Prepare work plan for the entire team
• Coordinate and supervise all task teams
• Develop quality control mechanism, and enforce
quality control over all implementation process
• Take responsibility for the quality of the team’s
outputs
• Verify and sign documents produced by the team

Surveys • Assess and identify the need for surveys required for 13 23
B engineering design tasks
• Conduct the identified required surveys
• Conduct experiments, analyze survey results, and
prepare reports
C Traffic management/ • Conduct surveys, collect and analyze data to develop 12 18
utility relocation traffic management plan and utility relocation plan
• Develop location specific traffic management plan for
station construction areas, and elevated and cut-and-
cover sections
• Design utility infrastructure system layout at station
areas, and elevated and cut-and-cover sections
D Tunnel design • Review pre-FS document and evaluate survey results 63 108
• Develop tunnel design package for Metro Line 5
(South)
• Propose optimal construction methods for Metro Line
5 (South)
• Conduct structural calculations and submit relevant
reports
E Underground station • Review pre-FS document and evaluate survey results 78 123
design • Develop underground station design package for
Metro Line 5 (South)
• Develop construction method
• Design stairs, walkways, lift, escalators, ventilation, air-
conditioning, exits, and other facilities for underground
stations
• Conduct structural calculations and submit relevant
reports
F Depot design • Review pre-FS document and evaluate survey results 73 78
• Develop depot and stabling yard design package for
Metro Line 5 (South)
• Develop construction method with due attention to soil
conditions
• Design layout, buildings/ facilities, required equipment
other facilities for depot/stabling yard
• Conduct structural calculations and submit relevant
reports
Task Team Responsibility Int’l National
person person
months months
G Elevated section design • Review pre-FS document and evaluate survey results 39 51
• Develop elevated section design package for Metro
Line 5 (South)
• Develop construction method
• Design stairs, walkways, lift, escalators, ventilation, air-
conditioning, exits, and other facilities for underground
stations
• Conduct structural calculations and submit relevant
reports
H Architect design • Review pre-FS document and evaluate survey results 29 57
• Develop architectural design package for all stations,
depot, offices, and other structures for Metro Line 5
(South)
I Power supply system • Review pre-FS document 23 37
• Develop power supply system design package for
Metro Line 5 (South) including traction, rolling stocks,
substations, ring circuit, overhead power supply
system, power system at stations and depot, cabling,
lighting protection system, lighting system, and other
systems for the project

J Electrical and • Review pre-FS document 18 42


mechanical design • Review applicable standards and regulations to ensure
compliance of these standards and regulations and
compatibility with other Metro lines
• Develop mechanical and electrical design package for
Metro Line 5 (South) including stations, tunnels, depot
and facilities such as escalators, elevators, ventilation,
lighting, cooling system, power generations at the
stations
2.
K Fire safety, water supply, • Review pre-FS document 18 33
and drainage system • Review applicable standards and regulations to ensure
compliance of these standards and regulations and
compatibility with other Metro lines
• Develop fire protection, water supply, and drainage
design package for Metro Line 5 (South)

L Railway tracks design • Review pre-FS document 8 12


• Review applicable standards and regulations to ensure
compliance of these standards and regulations and
compatibility with other Metro lines
• Develop railway track design package for Metro Line 5
(South)

M Rolling stocks design • Review pre-FS document 14 6


• Review applicable standards and regulations to ensure
compliance of these standards and regulations and
compatibility with other Metro lines
• Develop rolling stock design package for Metro Line 5
(South) including equipment for trains and rolling stock,
dimensions, configuration of trains, furniture, fabricate
materials, dashboard, electricity system, cooling
system, information system, door system, bogie, case
number, motor, braking systems, wheels and shafts
etc.
Task Team Responsibility Int’l National
person person
months months
• Coordinate with the operation and maintenance team
to develop operation and maintenance manuals,
requirements, and testing parameters

N Signaling • Review pre-FS document 22 20


communication system • Review applicable standards and regulations to ensure
design/ automated compliance of these standards and regulations and
ticketing and fare compatibility with other Metro lines
collection (ATFS) and • Develop signaling communication system design for
platform screen door Metro Line 5 (South) including information systems
(PSD) under multi-service telecommunications network,
signal system, interlock system, real-time train
information, on-board communication, CCTV,
passenger information, and automatic operation mode
• Develop automated ticketing and fare collection
system with consideration of specifications of the other
metro lines
• Develop platform screed door design
O Land acquisition and • Review pre-FS document and other related reports 8 38
resettlement • Carry out impact assessment and prepare land
acquisition and resettlement plans in accordance with
ADB’s SPS
• Provide necessary capacity building on resettlement
planning
• Assist land acquisition and resettlement activities.
P Poverty and social • Review pre-FS document and other relevant reports 6 6
assessment • Carry out poverty, social, and gender assessment and
related surveys among the local communities and
potential users along Metro Line 5
• Provide inputs/recommendations on specific functions,
and related design features to be reflected to ensure
accessibility, gender mainstreaming, safety and
security of public transport system to potential users
(including women, elderly, disable or children)
• Prepare draft poverty and social assessment (including
gender action plan) and summary poverty reduction
and social strategy
Q Environment • Review pre-FS document, survey results, and other 10 28
assessment relevant reports
• Carry out necessary environment surveys
• Ensure meaningful public consultation and information
disclosure during project design and environment
impact assessment
• Conduct a climate risk and vulnerability assessment
and develop a climate risk mitigation plan
• Calculate climate risk related financing amount
• Prepare a draft Environment Impact Assessment
Report including Environment Management Plan in
accordance with ADB’s SPS
• Provide necessary capacity building on environment
safeguards
R Climate Risk and • Conduct review of all available climate-related data on 4
Vulnerability the project site and immediate locality and region;
Assessment • Identify climate risks and vulnerabilities of the project,
including associated facilities
Task Team Responsibility Int’l National
person person
months months
• Based on identified climate risks, conduct in-depth
studies as necessary (e.g. hydrological analysis and
modelling, GIS-based analysis, consultations, etc.)
• Provide mitigation measures, including design
modifications in coordination with design engineers
• Estimate the incremental costs of adaptation measures
or design modifications in relation to the total project
costs
S Economic and financial • Review pre-FS document and other related reports 6 10
analysis (including PPP) • Review the demand forecast in the pre-FS, and update
the demand based on the traffic survey by surveys task
team
• Critically examine possibility of Public-Private
Partnership to be applied to the project, in terms of risk
sharing, financial viability, and institutional
arrangement.
• Calculate economic and financial analysis in
accordance with ADB’s guidelines including
distributional analysis.
T Operation and • Review pre-FS document and other related reports 17 16
maintenance • Develop operation and maintenance system design
package for Metro Line 5 (South) including train
schedule chart, operations management organization
chart, human resource requirement and its
development plan, operational manuals, maintenance
manuals, training programs for management and
operation personnel
U Procurement technical • Provide technical data, specifications and other 16 33
support technical contents to the client
• Coordinate with other task teams to gather data and
information for bidding document preparation
• Prepare bidding document in accordance with ADB’s
standard bidding documents
• Assist the client in the tendering process, including
advertisement, pre-bid meetings, responses to
clarifications, and evaluation
V Bill of Quantity • Coordinate with procurement technical support task 11 33
team and propose procurement packages
• Prepare budget for each procurement package based
on through analysis of price information of domestic
and world markets
• Coordinate with other task teams to prepare bill of
quantity
W Design development • Coordinate with other task teams to develop required - 190
engineering drawings
TOTAL 566 998

Table 1-2: Indicative Team Composition

You might also like