Professional Documents
Culture Documents
References
1. The PNAP in force are listed in the Appendix A of ADM-1 and there are over 300
Practice Notes in force.
2. Effect of the PNAP, see Yeung Pui Yee v BA [1989] 1 HKC 356. PNAP 125 (APP-47)
“has the effect of reminding APs …” and provides “guidelines to APs”.
5. For instance APP-16 on “Claddings” has provided tests to confirm the performance of
the claddings. Paragraph 15 indicates that “no consent for the commencement of the
stone cladding works will be given until the test reports specified in paragraphs …
have been submitted and found to be satisfactory by the Building Authority”.
6. Some of the PNAP are only served as guidelines for AP and RSE, see APP-47.
1
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam
d. The applicant sought leave to apply for judicial review against the
Tribunal’s determination on both questions. By his judgment dated
7 April 2014, Au J refused leave.
f. Court of Appeal was of the view that the issue of building works
versus plant or machinery was squarely before the Tribunal right from
day one. In particular, the Tribunal mentioned Leung Lai So v The
Building Authority, Appeal Tribunal (Buildings) Case No 44-2005,
31 October 2008, at paragraph 17, it says :-
2
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam
h. Likewise, the Tribunal summarised its reasons for concluding that (ii)
was also a building work in paragraphs 26 to 28 of its determination:
“26. This Tribunal accepts the intended use of (ii) is for loading and
unloading purpose. But this will not mean for this very factor, it will
fall outside the definition of building. 27. (ii) itself is 400,000 lb in
weight and it gives this Tribunal an expression that it is a huge and
complex structure consisting of a number of substantial size metal
elements connected, if not welded together. It is anchored and bolted to
the Building and cannot be moved around. The degree of permanence
is apparent. Further, it is supplied with electricity. The water tanks
thereon are connected to the water mains of the Building. It cannot be
moved to another location without dismantle the whole structure. No
doubt its erection and dismantling require operations normally
associated with normal building works…”
3
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam
4
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam
13. For alteration and addition works in existing buildings, see APP-117.
14. Fee are chargeable upon application for approval, see APP-55.
15. When will be the relevant law to apply? See Attorney-General v. Firebird Ltd (PCA
17/82). The Privy Council decided that on an application for approval of plans for
building works under section 14(1)(a) of the Ordinance, the law which the Authority
is obliged to apply is the law applicable on the date when the Authority considers the
plans. That applies even if the law has been changed since the date on which the plans
were submitted to the Authority for approval.
16. See also Super Mate Ltd. (HCMP 200/1994) and Re Head Step (CA 131/1995).
18. BO s14A requires the AP to lodge a supervision plan for the building works or street
works.
Originally published in 1997 and came into operation in 22nd December 1997
2nd edition came into operation on 31st December 2005
This edition came into operation on 31st December 2009
Paragraph 4.2(a): quality supervision in accordance with BO and Regulations
Paragraph 4.2(b): safety supervision to mitigate/control hazards/risk
Paragraph 4.3: management structure for site supervision
Paragraph 5.7: engineering safety supervision
Paragraph 5.8: routine safety supervision
Exceptions: see the list under paragraph 11
Draft Code of Practice for SSP (refined in November 2000) was revised to
Code of Practice for SSP came into effect on 31st December 2005. This is the
latest edition.
Scope: quality supervision and site safety supervision
Routine safety supervision: T1 to T3
5
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam
24. As to the remaining 4 elements, the CoP suggests that “The implementation of the
Safety Management Regulation will be reviewed one year after the Regulation has
come into force to decide on the appropriate time to bring the remaining 4 elements
listed in Part 3 of Schedule 4 into operation.”
This practice notes enhance the coordination of the Site Supervision Plan
System (SSPS) under the Buildings Ordinance (BO) and the Safety
6
CSE566 Statutory Framework for Construction Practice Ir Dr Eddie Lam