This document outlines an environmental management action plan for a construction project. It identifies construction activities and their potential environmental impacts, as well as proposed mitigation measures and monitoring activities to address those impacts. The plan covers issues like soil erosion, water and air pollution, noise, waste management, and occupational health and safety. Mitigation strategies include using proper construction techniques, limiting work to daytime hours, maintaining equipment, controlling dust and noise, safely disposing of waste, and providing safety training and protective equipment for workers. Compliance will be monitored through observations, testing, and reviewing permits, insurance policies and other documentation. The goal is to minimize environmental disruption and risks to safety during the entire construction period.
This document outlines an environmental management action plan for a construction project. It identifies construction activities and their potential environmental impacts, as well as proposed mitigation measures and monitoring activities to address those impacts. The plan covers issues like soil erosion, water and air pollution, noise, waste management, and occupational health and safety. Mitigation strategies include using proper construction techniques, limiting work to daytime hours, maintaining equipment, controlling dust and noise, safely disposing of waste, and providing safety training and protective equipment for workers. Compliance will be monitored through observations, testing, and reviewing permits, insurance policies and other documentation. The goal is to minimize environmental disruption and risks to safety during the entire construction period.
This document outlines an environmental management action plan for a construction project. It identifies construction activities and their potential environmental impacts, as well as proposed mitigation measures and monitoring activities to address those impacts. The plan covers issues like soil erosion, water and air pollution, noise, waste management, and occupational health and safety. Mitigation strategies include using proper construction techniques, limiting work to daytime hours, maintaining equipment, controlling dust and noise, safely disposing of waste, and providing safety training and protective equipment for workers. Compliance will be monitored through observations, testing, and reviewing permits, insurance policies and other documentation. The goal is to minimize environmental disruption and risks to safety during the entire construction period.
Construction Activity Environmental Impact Mitigation Measures Monitoring Time frame
Indications Cut and fill Soil erosion Proper shoring system will be provided. Observation During the Water pollution Excavated soil will be stored properly in a way construction Sedimentation that is not going to be affected by the rain. Dust Proper drainage system will be prepared Change the surface runoff Dust emission will be reduced by spraying of the land water during machinery movement. Land Preparation Removing of vegetation CEA guidelines will be followed. Observation During the will impact on ecological Well maintained machinery will be used to construction system. reduce the noise. Noises due to machinery Conduct awareness program to increase the will influence on species knowledge of the all the worker and staff behavioral patterns. regarding the importance of the ecological system and highlight mitigation measures. Use and Noise, water and air Construction materials such as soil, sand, Observation During the transportation of pollution is possible due to quarry dust and other natural resources will be Follow road construction Natural the extraction and purchased only from permit holders (Approval signals and construction transportation of natural from the CEA and related LAs) LA materials construction materials. Materials will be covered properly to avoid guidelines Ecological system can get dust emission during transportation. Permits influenced badly. Permitted vehicles will be hired for transport Dust emission due to materials on local roads (LA approval) to make transportation of the sure carrying capacity of the road is not going materials. to exceed especially on local roads. Roads can be damaged Materials will not load up to the top level of during material the tipper to avoid accidents during transportation due to transportation due to falling. excessive loads. PPE will be used during loading and unloading. Loading and unloading of the material can induce damages on the workers. Loading and unloading may lead to dust emission and noise level increasing. Construction Activity Environmental Impact Mitigation Measures Monitoring Time frame Indications Use and Access paths can be Materials will be placed in the way that it is not Observation During the transportation of blocked due to loading and going to disturb the access path and entrances. construction Natural unloading construction materials On site house Unpleasant environment Approval will be takes from the CEA and MC to Observation During the keeping Increase of risk of getting dispose solid waste from the construction construction injuries activities to an isolated location. General cleanness and Solid waste will not burn. tidiness will be influenced. Garbage will be handed over to the MC. Garbage bins will be provided to collect plastic, polythene and organic waste separately All the construction solid waste will be removed after the construction completed. Air pollution Dust from construction Water will spray to prevent dust as much as Observation During the activities, emission from possible. Test reports construction vehicle and machines will Vehicle speed limit will be enforced to mitigate reduce the quality of the dust emission at the site. air. Proper cover will be used during transportation of materials Dust screens will be provided Noise pollution Noise can influence on All machinery and vehicles will be maintained Test reports During the occupants close to the site properly to reduce excessive noise. construction premises and also who are Construction activities will be limited to day working inside the site. time Noise level will be checked and maintained approved limits ( 75dB during day time) PPE will provide to workers in order to avoid hearing defects due to high noise. Occupational Unsafe practice may lead Insurance facility will be provided for all the Insurance During safety to unfavorable situation to occupants and other assets from all risk policy construction occupants and other factors. Observation properties by increasing First aid box and trained personal will be at the the risk of exposing to the site hazards. Construction Activity Environmental Impact Mitigation Measures Monitoring Time frame Indications Occupational Drinking water related Licensed operators will be hired. Test reports During safety issue Safety orientation meetings, toolbox meetings construction Dengue fever and other will be carried out regularly. deceases Periodic testing will be carried out to ensure Sanitary facility related the standards of the machinery issues. Insurance policy will be offered to all the occupants. Furthermore machinery, assets will be covered under an insurance policy. Potable water will be provided by the national water board for consumption. Mosquito breeding will be prevented through destroying water accumulation.