You are on page 1of 63

Project

Management &
Finance
Lecture 6 – ‘Time
Management (CO1,
PO12)

Ir. Victor Nageshwar. A

Lecturer @ TARUC
Project Management & Finance
Lecture 6 (Week 8) Time Management’

Schedule
Management
Project Management & Finance
Lecture 6 (Week 8) Time Management’

– Lecture 6: Project Schedule Management


– This lecture covers following sub topics:
– Time Planning – The Process
– Gantt Charts
– Estimating
– Activity – on – Arrow (A-o-A) diagrams and Critical Path analysis (CPA)
– Activity-on-Node (A-o-N) diagrams
– Scheduling
– Fast Track projects
– Relevant areas of the bodies of knowledge
– Summary
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Schedule Management


– At the end of Lesson 6, students are expected to
• By the time you have completed this chapter, you should be able to:
• Demonstrate basic tools for the modelling of time, cost and quality requirements of
projects
• Carry out basic calculations on a project plan,
• Make this plans amenable to optimization ( improvement and risk avoidance)
• Undertake a first attempt at recourse allocation
• Identify benefits and pitfalls of fast-track projects
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Time Management


– Project Time Management includes the processes
required to manage timely completion of the project
Project Management & Finance
Lecture 6 (Week 8) Time Management’

– Lecture 6: Project Schedule Management


– Introduction
– This section is concerned with developing detailed time plans and the techniques that
follows are of increasing complexity.
– However, despite the diversity of the project being considered, one area of commonality
between project managers is the use of various graphical techniques to:
– allow the construction of a comprehensive but comprehensible picture of the project
activities:
– Communicate this with others.
– The preference for graphical techniques is more than “a picture telling a thousand words”
– The whole revision –refinement process is built around people being able to understand
what is going on.
– This is known as visibility, and is an essential feature of both the plan and the process. One
of the most commonly used techniques is the bar chart or “Gantt chart”.
Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Time Management


– Plan Schedule Management
– Is a process of establishing the policies, procedures and
documentation for planning, developing, managing, executing
and controlling the project schedule.
– It provides guidance and direction on how the project schedule
will be manage throughout the project
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Time Management


– The requirements for Plan Schedule Management
– Project Management Plan
– Project Charter
– Organization Process Assets
– Methodology
– Expert Judgement
– Analytical Techniques.
– The outcomes of Plan Schedule Management
– Schedule Management Plan
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Time Management


– “Schedule Management Plan” (established the following:))
– Specification of the scheduling methodology and scheduling tools
– Level of accuracy in determining activity estimates
– Units of measured used
– Linkage to the WBS of the project
– Process used to update the status of the project
– Variance threshold for monitoring schedule performance
Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Define Activity


– Define Activities
– Define activity is a process to identify specific actions that need to
be performed to produce project deliverables
– Activities are smaller decomposed components of the project
work packages, which represent the work necessary to complete
the work package
– Work packages may be divide into activities or tasks.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Define Activity


– The requirements for Define Activity
– Scope Baseline
– Organizational Process Assets
– Enterprise Environmental Factors
– The methodology
– Decomposition Techniques
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Define Activity


– The outcome of Define Activity
– Activity List
– Activity Attributes (Which includes activity codes, predecessor
activities, successor activities, logical relationships, lead and lags,
resource requirements, imposed dates,
– Milestones list
Project Management & Finance
Lecture 6 (Week 8) Schedule Management

– Lecture 6: Define Activity


Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Sequence Activities


– Sequencing Activities are identifying and documenting
relationships among project activities.
– Uses logical relationships
– Can be performed by using manual or automated techniques or
project management software
– Portions of project schedule network
– Diagrams are called fragment network or sub-networks.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Sequence Activities Data Flow Diagram


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Precedence Diagramming Method Relationships


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Examples of Dependencies Relationships


– Finish-to-start (FS): A logical relationship in which a successor
activity cannot start until a predecessor activity has finished.
Example: The awards ceremony (successor) cannot start until the
race (predecessor) has finished.
– Finish-to-Finish (FF): A logical relationship in which a successor
activity cannot finish until a predecessor activity has finished.
Example, Writing a document (predecessor) is required to finish
before editing the document (successor( can finish.
– .
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Examples of Dependencies Relationships


– Start-to-Start (SS): A logical relationship in which a successor
activity cannot start until a predecessor activity has started.
Example: Level concrete (successor) cannot begin until pour
foundation (predecessor) begins.
– Start -to-Finish (SF): A logical relationship in which a successor
activity cannot finish until a predecessor activity cannot A logical
relationship in which a successor activity has started. Example:
The first security guard shift (successor) cannot finish until the
secondary security guard shift (predecessor). Begin.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Precedence Diagramming Method


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Dependence Determination


– Mandatory or Hard Logic
– Inherent in nature of work being done or required by contract.
– Discretionary (preferred) or Soft logic
– Determined by project team and may be changed
– External Dependency
– Based on needs of parties outside the project.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Lead sand Lags in project schedule


– Leads indicates that an activity can start before predecessor
activity is completed
– E.g. Coding may start five days before design is finished
– Lags is the inserted waiting time between activities:
– E.g. Waiting for three days after pouring concrete before
constructing the frame..
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Milestone


• Significant events within the project schedule
• They are NOT work activities
• Part if the project management Plan
• Added to project scope statement and WBS discretionary
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Network Diagram


– Any schematic display of logical relationships among the project
schedule activities
Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimate Activity Resource


– Estimates the type and quantities of materials, People,
equipment or supplies required to perform each activity.
– Closely coordinated with the estimated Cost process
– Performed in parallel with estimation cost,
– Estimation can be done as follows:
– Top down method
– Bottom – Up method,
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimate Activity Resource


– The requirements for Estimate Activity Resource are
– Activity List and activity attributes
– Enterprise Environment Factors
– Organizational Process Assets
– The methodology
– Alternatives Analysis
– Bottom up estimation
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimate Activity Resource


– The outcome of Estimate Activity Resource
– Activity Resource Requirements
– Resource Breakdown structure
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: The methodology of Estimates Activity Durations


– Expert Judgement
– Guided by historical information, this techniques may be used to
provide duration estimates from prior similar projects.
– Analogous estimating
– Uses historical data from similar activity or project
– Parametric estimating
– Algorithm is used to calculate cost or duration based on historical data
– Three Point Estimating
– Considers estimation uncertainty and risk
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Important Formulae:


– Expected Activity Duration
– (P+4M+O)/6 for Beta Distribution
– Activity Standard Deviation
– ((P-O) / 6] *2
– Activity Variance
– [(P-O) / 6
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Work Breakdown Structure


Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimate Activity Durations


– Process of approximating the number of work periods
needed to complete individual activities with estimated
resources.
– It is progressively elaborated with duration estimates
becoming progressively more accurate
– May use analogous or historical estimations
– May include reserve analysis
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimate Activity Durations


– Estimates can be:
– Pessimistic
– Most Likely
– Optimistic
– Called the “three point average”
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Estimation
– WBS work packages provides the basis for making estimates on
– Resources required
– Time required
– Cost involved
– The outcome form the estimates are
– Leads to quality of the project
– Ensures project continuity
– Provides input to the project plan
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Examples of Estimating techniques


– Three Point estimates
– Et = O + 4ML + P
6
– Where
– Et = Estimated Time
– ML = Most likely estimates
– P = Pessimistic estimates
– O = Optimistic estimates
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Exercise on Standard Deviation and Estimates


Activity P ML O Expected Activity Activity Standard Activity Range of
Duration Deviation Variance Estimates
A 47 27 14

B 89 60 41

C 48 44 39

D 42 37 29

Overall
project
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Exercise on Standard Deviation and Estimates


Activity P ML O Expected Activity Activity Standard Activity Range of
Duration Deviation Variance Estimates
A 47 27 14 28.167 5.500 30.250 22.667 to
33.667
B 89 60 41 61.667 8.000 64.000 53.667 to
69.667
C 48 44 39 43.833 1.500 2.250 42.333 to
45.333
D 42 37 29 36.500 2.167 4.696 34.333 to
38.667
Overall 170.167 10.060 101.196 160.107 to
project 180.060
Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule


– The process of analyzing activity sequences, durations, resource
requirements and schedule constrains to create the project
schedule
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Project Schedule Network Diagram


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Critical Path Method Diagram


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Types of Floats


– Free float or free slacks
– The amount of time that a schedule activity can be delayed without delaying the
early start date of any successor or violating a schedule constraint.
– Total float or total Slack
– The amount of time that a schedule activity can be delayed without delaying the
project finish date or violating a schedule constraint.
– Total float for a path
– Difference between the length of the critical path and the length of the path in
question
– Project float
– Total time the project can be delayed without affecting the externally imposed
project completion.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Schedule Compression


Techniques
– Crashing
– A technique used to shorten the schedule duration for the least
incremental cost by adding resources
– Fast Tracking
– A techniques in which activities or phases normally done in sequence
are performed in parallel for at least a portion of their duration.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Fast Tracking.


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Diagrams used to depict


project schedule
– Project Schedule Network Diagrams
– Shows project activities, network logic and critical path activities
– Bar Charts
– Shave time on the X axis and bars showing the activities.
– Miles Stone Charts
– Have time on the x axis and show milestone. (That have a Zero
duration).
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Precedence Diagraming


Method
– Method used in critical Path Methodology (CPM) for constructing a
project schedule network diagram that uses boxes or rectangles,
relationships that exist between them.
– Activities on the critical path
will have ZERO FLOAT.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Precedence Diagraming


Method
– Critical Path method calculates the theoretical early start and
finish dates and late start and finish dates for all schedule
activities
– To do this we first do a forward pass followed by a backward pass
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Precedence Diagraming


Method
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Graphical Evaluation and


Review Technique (GERT)
– Modification of the network diagramming method
– Computer simulation technique
– Allows loops between activities
– E.g. Design a component and then test it.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Transforming a WBS into a Network


Diagram (Work Packages: Replace a legacy core switch with a mobile
switch )
Activities Durations Predecessor
a. Determine system requirements 10 -
b. Design system layout 15 a
c. Obtain new lines 20 a
d. Obtain permits 32 b
e. Order / Receive parts 35 b
f. Install mobile soft switches 5 d, e
g. Test new system 2 C, f
h. Deactivate legacy core switch 1 g
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Forward Path Diagram


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Backward Path Diagram


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Determining Float


Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Develop Schedule – Reverse Analysis


Project Management & Finance
Lecture 6 (Week 8) Time Management’

Project Lifecycle Process


phase
Planning Plan Schedule management
Planning Define Activities
Planning Sequence Activities
Planning Estimate Activity Resources
Planning Estimate Activity Durations
Monitor and Develop and Control Schedule
Control
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Control Schedule


– The process of monitoring the status of the project to update
progress and manage changes to the schedule baseline.
– Involves taking corrective and preventive actions to keep schedule
on track
– The main output of the control schedule process is work
performance measurements.
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Control Schedule – Activities involved


– Re-estimating the remaining components of the project
– Conducting performance reviews
– Adjusting future parts of the projects
– Measuring variance against planned schedule
– Leveling resources
– Undertaking “What If….” analysis
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Control Schedule – Project Schedule


– Results pf previous planning process and the schedule network
analysis
– Output of develop schedule process
– Formats of project schedule
– Network Diagram
– Milestone Chart
– Bar Chart
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Control Schedule – Project Schedule


– Results pf previous planning process and the schedule network
analysis
– Output of develop schedule process
– Formats of project schedule
– Network Diagram
– Milestone Chart
– Bar Chart
Project Management & Finance
Lecture 6 (Week 8) Time Management

– Lecture 6: Control Schedule – Activities involved


• Re estimating the remaining components of the project
• Conducting performance reviews
• Adjusting future parts of the project
• Measuring variance against planned schedule
• Leveling resources
• Undertake (What If…..” analysis

You might also like