Wisdom on Maintenance
Troubleshooting is no longer an effective strategy.
When people become really good at fixing failures,
then something is definitely wrong with your
maintenance organization. Because they are doing
it much too often, but when we expect a different
result from the same things that they are doing, it’s
not possible.
The 8 Pillars of Total Productive Maintenance
Preparedness

Only 3 out of 8 Pillars are partly prepared


Planned Maintenance Pillar

Preventive Maintenance

The practice of conducting


routine inspections, tests, and
servicing so that impending
troubles can be detected and
reduced or eliminated.

Predictive Maintenance

The practice of conducting


diagnostic tests and inspections
during normal equipment
operations in order to detect
incipient weaknesses or
impending failures.
Overhead Line
Interruptions
2016 - 2019
Program Creation
DND RELIABILITY PLAN Hypothesis
A focus group discussion must
be done and generate a list of
hypothesis of the causes of the Data Validation and
problem. Then an interview,
survey and inquiry to other Identification of Variables
Engineering Department will For better analysis of the
Problem Identification then be conducted on their problems, Variables and
Unscheduled interruption has insights of the problem. nuisance in the records and
not been improving for the last timestamp must be identified
4 years even if we have done using statistical tools.
too much reliability project
instill.

1 2 3 4 5 6
Research Study Examine Current Experimental
Framework Approach Sampling and
GOAL Looking at methodology by An inquiry will also be done on Assessment
SAIDI = 75 min way of elimination. All how and what action they have Feeders will be tested
SAIFI = 1 hypothesis will be tested taken to eliminate the cause of and assessed using the
and possibly interview to the problem. methodology stated in
the crew who responded . the research study
On-line test equipment is framework.
necessary in this type of Recommendation can
framework. also be stated in this
stage.
Reliability Program 1

Heavy Rain Broken Primary Vegetation


Mitigation Line Mitigation Mitigation
Increased Air Gap Prevented Corrosion
16Structures 36Structures
Corrected Insulation Increased Surge Covered Distribution
Compromised Capacity Line
21Structures 25Kilometers 0Kilometers

- This Program will be completed in 7-8 gang-years


- An estimated Annual CAPEX of PHP 30-40Million
- Once completed will improve SAIFI by 16% and SAIDI by 58%
- Program started on January 15, 2020
Reliability Program 2

Animal Intrusion
Mitigation
Exclusion
0Structures
Increased Ground
Clearance
3Structures

- This Program will be completed in 4 gang-years


- An estimated Annual CAPEX of PHP 10-15Million
- Once completed will improve SAIFI by 8% and SAIDI by 6%
- Program started on February 1, 2020
Reliability Program 3

Program III
1) Physical Post Fault
Investigation

This Program will answer the causes of


“No Fault Found” reports.