1. Calculation of Net Power Generated from SSPL 4.5 MW WHRB CPP Project Plant:
To achieve the above we follow the steps below (as per instrumentation plan given in the
schematic diagram enclosed):
Calculation of Net Power generation from the Project activity i.e. SSPL 4.5 MW WHRB CPP
PROJECT PLANT.
Note : (1) Steam enthalpy Ent in K Cal/Kg is arrived by using thermodynamic steam tables, based
on the pressure and temperature readings.
(2) The temperature and pressure of steam generated by boilers and consumed by TG sets
will practically remain same, hence the above monitoring can also be carried out on
quantitative percentage contribution of steam by WHRB.