Professional Documents
Culture Documents
According to
According to clause According to clause 14.7
Contactor submit to
14.5 Consultant QS clause 14.6. b Employer pay
Consultant QS
issue Interim Payment Employer pay Contractor with
Application of Interim
Certificate Contractor financing charge
payment Certificate
according clause 14.3
>14 Days
IPA ≤14 Days
≤ 21 Days
payment
s
Consultant QS verify
Final the statement, If need ≤14 Days ≤56 Days
Payment Contractor QS submit
further information
Contactor submit to
Contactor submit to Consultant QS Employer pay
Consultant QS draft
Consultant QS submit issue Final Contractor
final statement
Final Statement Payment according to
payment according
according clause 14.10 Certificate clause 14.6 .c
clause 14.10
and discharge according according to
to clause 14.11 clause 14.12
Advance payment procedure
1 4
3
2
Contractor QS
prepare IPA
Consultant QS after
receiving IPA within
21days issue Interim
payment certificate if
Consultant QS check and correct no issues are
IPA. Clause 14.5 encountered. Clause
14.5
`
Delay payment procedure.
If Dispute resolved