Professional Documents
Culture Documents
SECTION-8
SPECIAL CONDITIONS OF CONTRACT (SCC)
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-2
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-3
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-4
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-5
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-6
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-7
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-8
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-9
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-10
26. 34:- Professional Add GCC sub clause 34 with the following:
Indemnity
Insurance (PII)
1. AOA (any one accident) limit equal to total contract
value with AOY (any one year) with unlimited
occurrence in the PII policy, the deductible amount
shall be 5% of claim amount or as per requirement of
statutory regulations.
2. The insurance policy shall include a cross liability
clause such that the insurance shall apply to the
Consultant and the Employer as separate insureds.
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-11
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-12
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-13
33. 60.2 Payment for The Consultant shall be entitled to have included in any
Claims Interim Payment Certificate such amount for any claim as
the Engineer considers due, after taking approval from the
Employer. If the particulars supplied are insufficient to
substantiate the whole of the claim, the Consultant shall be
entitled to payment for such part of the claim as has been
substantiated.
34. 60.3 No legal Any and all Disputes shall be settled in accordance with the
action till Dispute provisions of Clause 60. No action at law concerning or
Settlement arising out of any Dispute shall be commenced unless and
Procedure is until all applicable Dispute resolution procedures set out in
exhausted. Clause 60 shall have been finally exhausted in relation to
that Dispute or any Dispute out of which that Dispute shall
have arisen with which it may be or may have been
connected.
35. 60.4 Notice of For the purpose of Sub-Clause 60.5, a Dispute shall be
Dispute deemed to arise when one party serves on the other party a
notice in writing (hereinafter called a "Notice of Dispute")
stating the nature of the Dispute provided that no such
notice shall be served later than 28 days after the date of
issue of Performance Certificate by the Engineer.
36. 60.5 Two Stages Disputes shall be settled through two stages:
for Dispute a) Conciliation procedures as established by “The
Resolution Arbitration and Conciliation Act-1996” & amended by
the Arbitration & Conciliation (Amendment) Act,
2015 and any statutory modification or re-enactment
thereof and in accordance with this Clause. In the
event this procedure fails to resolve the Dispute then;
b) Arbitration procedures undertaken as provided by
“The Arbitration and Conciliation Act -1996” &
amended by the Arbitration & Conciliation
(Amendment) Act, 2015 and any statutory
modification or re-enactment thereof. and in
accordance with this Clause.
37. 60.6 Conciliation Within 60 days of receipt of Notice of Dispute, either party
shall refer the matter in dispute to conciliation.
Conciliation proceedings shall be initiated within 30 days
of one party inviting the other in writing to Conciliation.
Conciliation shall commence when the other party accepts
in writing this invitation. If the invitation is not accepted
then Conciliation shall not take place. If the party
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-14
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-15
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-16
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-17
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-18
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-19
50. 60.9.10 The award of the sole Arbitrator or the award by majority
of three Arbitrators, as the case may be, shall be binding
on all parties. Any ruling on award shall be made by a
majority of members of Tribunal. In the absence of such a
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-20
53. 60.10 Interest on Where the arbitral award is for the payment of money, no
Arbitration Award interest shall be payable on whole or any part of the
money for any period, till the date on which the award is
made.
54. 60.11 Cost of The fees and other charges of the Arbitrators shall be as
Arbitration per the scales fixed by the Employer from time to time
irrespective of the fact whether the Arbitrator(s) is / are
appointed by the Employer or by the court of law unless
specifically directed by Hon’ble Court otherwise on the
matter, and shall be shared equally by the Employer and
the Consultant. However, the expenses incurred by each
party in connection with the preparation, presentation
will be borne by itself.
55. 60.12 Jurisdiction Where recourse to a court is to be made in respect of any
of Courts matter, the court at Delhi/ New Delhi shall have the
exclusive jurisdiction to try all disputes between the
parties.
56. 60.13 Suspension (i) The ongoing work of the project shall in no case be
of Work on interrupted or stopped in view of making reference for
Account of conciliation/arbitration or its commencement.
Arbitration (ii) The obligations of the Employer, Engineer and the
Consultant shall not be altered by reasons of arbitration
being conducted during the progress of the Works.
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-21
Appendix-I
Key Dates
The *Cluster wise key dates are defined for the major critical tasks to be carried out by
Consultant based on the Stage Payments for each item of payment Schedule (APPENDIX-
II) of SCC (Section-8) of the bid document, as approved and accepted by NCRTC.
Detailed Work plan is to be submitted by the Consultant to the Employer within a week of
the Effective Date. (with schedule for meetings, review, approval and submission)
The Consultant shall deliver the “Deliverables”, as mentioned in the table below, during
this Consultancy. Each Deliverable shall include drawing (CAD and GIS files, PDF, hard
copies on suitable scale), report, presentations, photographs & 3D views, GIS model as
mentioned in the format column below. The deliverables shall be so drafted that they
could be given to the prospective Developer Entity / concerned agencies for guidance in
preparation of TOD schemes, area improvement projects and carrying out various
development activities.
(Inception Report
will layout the § Presentation to
detailed Development Authority
methodology, and Transit Agency
Combined submission Yes, as per Sub-
1. Inception work plan, § 2 printed copies for all 4 Clusters clause 48 of
Stage logistics, etc. and of Report + Presentation D+2 weeks GCC/SCC
how the § 2 digital copies
consultant of Report + Presentation
proposes to carry - in CD/DVD/USB
out the tasks laid
out along with
the deliverables
within the
stipulated
timelines)
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-22
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-23
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-24
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-25
1. Total time of the completion of the consultancy work is 42 weeks (294 days)
excluding the time of the final approval from the State Government
2. The Employer shall endeavour to provide approval / comments to the Consultant’s
submissions for each of the milestones at the earliest and not exceeding 10 days
from the date of the submission provided the submission by the Consultant is
complete in all respects.
3. Consultant shall obtain the in-principle approval from the concerned department
within the above mentioned time period for each stage. However, final Approval of
the reports (submitted by the consultant) by the competent authority at different
stages may take considerable time which shall not be counted in the period of days
mentioned in the above table.
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-26
Appendix- II
Payment Schedule
Stage Milestone achieved Clusters Extent of
payment/
percentage of
fee of
Lumpsum
cost quoted in
Sl. No. 1 of
BOQ.
Submission &
Approval of § Presentation to
Inception Report Development Authority
and Transit Agency
(Inception Report will
layout the detailed § 2 printed copies
1. Inception of Report + Combined
methodology, work plan, 5.0%
Stage Presentation submission for
logistics, etc. and how
the consultant proposes § 2 digital copies all 4 Clusters
to carry out the tasks laid of Report +
out along with the Presentation - in
deliverables within the CD/DVD/USB
stipulated timelines)
§ Presentation to
Development Authority
and Transit Agency
§ 6 printed copies
Submission &
of the Base Map for
Approval of Report
TOD Zones (in
on Existing Studies
appropriate scale)
2. Surveys and Data
and § 2 printed copies Combined
of Report and maps (in 5.0%
Studies (Detailing all surveys, submission for
Stage studies and analysis appropriate scale) +
Presentation all 4 Clusters
conducted under Task 1,
findings and § 2 digital copies
observations thereof) of Report and Base
map, other maps (in
AutoCAD and GIS
format) + Presentation
– in CD/DVD/USB
§ Presentation to
Development Authority
Submission & and Transit Agency
Approval of Report § 2 printed copies
on Demand of Report and maps (in
Assessment, appropriate scale) +
3. Demand Visioning and Presentation Combined
Assessme Strategy § 2 digital copies
nt and submission for 6.0%
of Report and maps (in
Visioning (Detailing all studies, AutoCAD and GIS all 4 Clusters
Stage assessments, workshops format) + Presentation
and analysis conducted, – in CD/DVD/USB
including vision,
estimations and
proposals under Task 2)
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-27
§ Presentation to
Development Authority
and Transit Agency
§ 8 printed copies 3.0%
of Draft Land Use Plan Cluster 1
Submission & and other key
Approval of Draft Circulation and
Land Use Plan and Infrastructure
Zonal Development Proposals maps
Plan Report; Draft (convertible scale
Byelaws and printed in A0 sheets) +
other relevant maps (in
Development Control
Norms for TOD appropriate scale) + All
Reports including Draft
Zones
5. Draft Byelaws and
Zonal (Draft Land Use Plans, Development Control 4.0%
Cluster 2
Norms for TOD +
Developm other Maps and Plans,
ent Plans Draft Zonal Presentation
Stage-I Development Plan § 8 Digital copies
Report, Report on of Draft Land Use Plan
Byelaws and and other key
Development Control Circulation and
Norms for TOD Zones as Infrastructure
required under Task 4, Proposals maps (in
for approval of Transit AutoCAD and GIS
Agency, Development format) + other relevant
Authority and public maps (in AutoCAD and
Cluster 3 8.0%
consultations thereafter) GIS format) + All
Reports including Draft
Byelaws and
Development Control
Norms for TOD +
Presentation – in
CD/DVD/USB
Cluster 4 8.0%
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-28
Cluster 1 3.0%
§ Presentation to
Development Authority
and Transit Agency
Submission & § 8 printed copies
Approval of Draft of Draft Land Use Plan
Land Use Plan and and other key
Circulation and
Zonal Development
Plan Report; Draft Infrastructure
Byelaws and Proposals maps
(convertible scale
Development Control
Norms for TOD printed in A0 sheets) + 4.0%
Cluster 2
Zones other relevant maps (in
appropriate scale) + All
(Draft Land Use Plans, Reports including Draft
Byelaws and
6. Draft other Maps and Plans,
Zonal Draft Zonal Development Control
Developm Development Plan Norms for TOD +
Presentation
ent Plans Report, Report on
Stage-II Byelaws and § 4 Digital copies
Development Control of Draft Land Use Plan
Norms for TOD Zones and other key
incorporating relevant Circulation and
suggestions, objections Infrastructure
Cluster 3 8.0%
and feedback received Proposals maps (in
from general public, AutoCAD and GIS
approval by Transit format) + other relevant
Agency, Development maps (in AutoCAD and
Authority and onward GIS format) + All
submission to State Reports including Draft
Government) Byelaws and
Development Control
Norms for TOD +
Presentation – in
CD/DVD/USB
Cluster 4 8.0%
DM/GC/COR-OF/216 NCRTC
Section 8 - Special Conditions of Contract 8-29
Note:
1. Payment for S. No. 1 to 6 above shall be released by 70% on submission of documents
as per checklist specified in the table (deliverables and format) and rest 30% payment
shall be released on approval from NCRTC and MDA upon issuance of Milestone
Completion Certificate (MCC) by the Engineer-in-charge
2. Payment for S. No. 7 shall be released once the Zonal Development Plan document(s)
are approved by the State Government, under provisions of the Uttar Pradesh
Planning & Development Act 1973.
DM/GC/COR-OF/216 NCRTC