You are on page 1of 10

Document Title: P&ID, GAS FUEL SYSTEM

Project Doc. 4000046273-PGCA-EA-C01- Revision: C1


Number: 001
Vendor Doc. 6074-C01-001 Vendor B
Number: Rev.:
Facility Identifier: PGCA
Discipline: EL Document PID
Type:

Submitted For: Vendor Name:


Review X Approval Info. Certified SIEMENS

Review does not constitute acceptance of design


details, calculations, test methods or materials
developed or selected by vendor nor does it relieve
vendor from full compliance with contractual or other Package Description:
obligations. Gas Turbine Generator Package

A. Approved
(Submit final document in MDR/IOM
only)
P.O. No:
Manufacture may proceed
4000046273
B. Approved with comments
(Revise and resubmit document)
Manufacture may proceed once Model/Serial No.:
comments are incorporated SGT-300-1S
C. Rejected
(Resubmit)
Manufacture may not proceed
VDRL Prime Code:
I. For Information Only
C01
(Submit final document in MDR/IOM
only) Tag No.:
Name: Xavier Grostabussiat PGCA-EZ-8110A
PGCA-EZ-8110B
Signature:
PGCA-EZ-8110C
Date: 23 Sep 2019

PEGAGA DEVELOPMENT
PROJECT
Comment Response Sheet

Company : MDC Oil & Gas (SK320) Ltd CRS for Doc.: 6074-C01-001, Rev A

Project Title : Provision Of Engineering, Procurement, Construction, Installation Doc. Title : P&ID, GAS FUEL SYSTEM
And Commissioning (EPCIC) for the Pegaga Development
Project Doc. No. : 4000046273-PGCA-EA-C01-001 Rev: 5.2

PO No. : 4000046273

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

1 1 All comments related to relocation of the off- It has been informed that relocation is not possible HH 02/04/19 C
skid block & vent valve assembly upstream of at the customer kick-off because vent valve vents 05/09/19
the filter. the gas, back flow will damage the filter element.
please inform how do we depressurise the SIE: The assumption here is that the filter vessel,
flow meter and off-skid block and bleed valves will
section between XV-30 and HV-31 be installed in close proximity therefore the amount
of volume downstream of the filter is very limited
compared to the volume upstream of the filter
(platform fuel gas supply system). Backflow will be
limited and depressurization slower when compared
to XV30/XV31. The volume upstream of XV30
should also rarely have to be vented unless
maintenance needs to be done as XV30 (off-skid
block valve) is already provided to isolate the fuel
gas supply to the package.
2 1 Please define note B All general note shall be referred by Legend, HH 02/04/19 C
Siemens doc# 6074-C01-000.

Unrestricted

Page 1 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

3 1 XV30/XV31 to be controlled by SIS. Dual coil Off-skid block & bleed valves must remain in HH 02/04/19 C
solenoid. Siemens control. Gas is automatically vented by
Siemens for safety reasons (e.g. a fire or gas
detected). For normal stops, an adjustable timer will
be started and after it runs out, the off-skid block
valve will be closed then the vent valve opened to
vent the line (timer can be set between 0 and 4h).
Solenoids do not have dual coils.
6 1 Query: There will be an SDV located upstream There is no provision for venting upstream lines on HH 02/04/19 C
of the filter assembly. With closure of this SDV our equipment. This will have to be done by 05/09/19
and valve XV30, is there a way to depressurize Contractor.
section between these two valves? SIE: please refer to answer #1.
If we are depressurising this section than it will
be backflow which will damage the filter
element as per your response on Item no.1
Please advise proper way of depressurising
this section.
7 1 VENDOR TO ADVISE HAZOP REQUIREMENT Please refer to information sent by email on HH 02/04/19 C
FOR THIS P&ID, IF VENDOR ALREADY February 3rd.
PERFORMED HAZOP FOR THIS SYSTEM,
PLEASE SHARE WITH CONTRACTOR FOR
REFERENCE
8 1 Siemens to provide specific details for the There is a no straight length requirement on the HH 02/04/19 C
installation of the flowmeter such as: mass flowmeter as Coriolis. Siemens will furnish
a. straight length requirement complete assembly of flowmeter and flow direction
b. flow direction (vertical flow up, or horizontal) will be shown on the body. O&M will be provided.

9 1 Valve tag number assignment to be checked with Only Siemens tags are provided on our HH 02/04/19 C
Instrument i.e. for SDV, BDV, etc. The client documentation. Option for Customer tagging was 05/14/19
instrument tag number shall follow project not selected as part of this PO.
requirement, refer to comment in PID part list,
4000046273-PGCA-EA-C01-014
10 1 P&ID Note 6, TBA: Please advise ASAP This valve is controlled by Siemens, no action HH 02/04/19 O
required by Contractor. It will be updated at the next
revision.

Unrestricted

Page 2 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

11 1 2. PROVIDE ACRONYM Please refer to legend (6074-C01-001) HH 02/04/19 C

12 2 Please advise tie-ins number – XF194 It will be updated at the next revision HH 02/04/19 C

13 2 Move inside since it is under Siemens scope. Scope Customer scope is identified by the following HH 02/04/19 C
of supply and installation of the pressure gauge symbol. This pressure gauge is already shown as in
shall be by Siemens. Please provide note indicating Siemens scope.
this.

14 2 Please provide piping class and tie-ins schedule Please refer to Siemens doc# 6074-C04-001. HH 02/04/19 C

REVISION A - 5.2

15 1 PLS STATE REF CLIENT P&ID NOS FOR Please mark-up the references you wish to use and XG 05/09/19 C
CLARITY we will include them.

16 1 Information on material of construction is missing? Material of Construction is not shown on our P&IDs. XG 05/09/19 C
Fuel gas system is made of 316SS.

17 1 SIE to confirm any warranty issue for termination SS The filter will catch the contaminants generated by XG 05/09/19 C
MATERIAL TO CUSTOMER CS material. the upstream carbon steel piping. That piping should
rarely be vented therefore contaminants should be
limited. The filter element will need to be changed
more often.
18 1 What is Note B ? cannot find in this FG p&id sheets Note B is a general note that is shown on the legend XG 05/09/19 C
P&ID (6074-C01-000).

Unrestricted

Page 3 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

19 1 IA supply by client direct to individual user? PID Yes. XG 05/09/19 C


PGCA-PR-PID-1-126/127/128 indicate a single tie-
in point to skid only.
20 1 Vent to Flare Vent is to atmosphere, volume is limited to 2” pipe XG 05/09/19 C
between the block valve and the skid as previously
discussed.
21 1 Confirm meter by client? Flow meter by Siemens. XG 05/09/19 C

22 1 What is type of this flowmeter? Please indicate Coriolis flow meter. XG 05/09/19 C
clearly

23 1 Please advise maximum allowable pressure drop 10 psid (0.7 bard) XG 05/09/19 C
across

24 1 What is pressure drop across this flow element. 3 psid (0.2 bard) XG 05/09/19 C

25 1 Commissioning strainer and PG provided off skid. Since Sapura controls this scope, it should be XG 05/09/19 C
Please update this drawing shown on Sapura’s P&IDs

26 1 SIE shall supply these piping. The presentation GA is correct, there is no piping. This P&ID XG 05/09/19 C
doesn't look right since it didn't appear/show in the represents the block and bleed valve set-up and is
GA off skid block & Bleed Valve functionally correct.
27 1 WHAT ASTM SPEC OF THIS SS ? PLS STATE Will show 316SS at next revision. XG 05/09/19 C
FOR CLARITY PURPOSES.

28 1 NACE compliance SS to be met for in-skid piping Already confirmed. XG 05/09/19 C

29 1 It's not clear whether this means just off-skid HT, or All off-skid piping/equipment. Will clarify at next XG 05/09/19 C
all HT. Pls specify positively in this drawing. revision.

Unrestricted

Page 4 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

30 1 Is this line for blowdown of the GTG during This is for blow-down off the fuel gas supply to the XG 05/09/19 C
USD/PSD/ESD? skid in case of fire or gas confirmed inside of the
enclosure.
31 1 WHY CAN'T SIEMENS SUPPLY HEAT TRACING All the off-skid components are small and shipped XG 05/09/19 C
AS PART OF PERFORMANCE WARRANTY separately for installation in the supply line by
FROM SIEMEN'S FOR ENTIRE SKID PACKAGE. Contractor. It will be more efficient to have one
combined heat tracing installation for these
components rather than 4 separate heat tracing
systems (one for each component + one for piping)
32 1 General comments to all P&IDs; 1. This is not provided as part of our P&IDs. XG 05/09/19 C
1. To provide equipment data table/information
which includes design & operating conditions 2. Tie-in Schedule shows tie-in size, rating and
(temp/Press), capacity, flowrate, filter specification, material.
duty, etc.
2. Piping size, material and spec to be
shown
33 1 TYPICAL COMMENT : TO INCLUDE PEGAGA Please clarify what ICPP is. XG 05/09/19 C
ICPP IN DRW TITLE BLOCK.

34 2 TP-XXX, PLS ASSIGN Only Siemens connection labels are used on our XG 05/09/19 C
P&IDs. Contractor’s tie-in points, if different, should
be referenced in Contractor’s P&IDs.
35 2 Off skid block & vent assembly We refer to these valves as “Block and Bleed” which XG 05/09/19 C
is synonymous of “Block and Vent”

36 2 Indicate interface TP no. Refer to item 33. XG 05/09/19 C


(typ)

37 2 How is it ensured by package control that adequate Fuel Gas supply temperature is controlled by XG 05/09/19 C
superheat is provided? Contractor’s fuel gas system. Fuel gas supply
How do you take care of the stagnant gas with low temperature will vary greatly over the years,
temperature during start-up? therefore monitoring is only in Contractor’s scope.
Heat tracing is provided to maintain fuel temperature
of stagnant gas.
Unrestricted

Page 5 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

38 2 To reconfirm operations of this TT in relation to This transmitter does not monitor for superheat of XG 05/09/19 C
fuel gas supply not up to the required the gas as dew point varies greatly over the 9 gas
temperature. Have requested start-up compositions provided. Piping will be maintained at
procedure from Siemens. temperature by heat tracing. For initial start-up, Fuel
gas will be blown down by Contractor upstream of
fuel gas filter.
39 2 What is executive action in case of HH and LL? Turbine will be tripped. XG 05/09/19 C

40 2 ET inside this module shall be supplied by supplier. Confirmed. XG 05/09/19 C

41 2 what is the initiator for this valves to close? Turbine trip/stop. XG 05/09/19 C

42 2 Pilot and main manifold with same piping diameter, Yes. XG 05/09/19 C
is this sufficient, pls clarify ?

43 2 Power supply to motor from which source? UCP XG 05/09/19 C

44 2 What is the function of these valves? is this for Yes. XG 05/09/19 C


controlling flow rate?

45 2 ANY INTERFACE SIGNAL TO CUSTOMER Interface signals PCS/UCP (START/STOP, ESD etc XG 05/09/19 C
SYSTEM TO BE ADDRESS VIA LEGEND AND …) are defined on the control narrative and ICSS
SYMBOLS. communication list.

Unrestricted

Page 6 of 7
Comment Response Sheet

Comm
Status
No. Page Comment Response ented Date Remarks
O/C *
by

Additional Notes (if any)

* O - Open, C - Closed

Unrestricted

Page 7 of 7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

REFERENCED NOTES:
1. IT IS THE CUSTOMER'S RESPONSIBILITY TO PROVIDE PRESSURE
RELIEF IN THE SUPPLY SYSTEM WHERE THERE IS THE POSSIBILITY
A A
SIMPLEX COALESCER FILTER ASSEMBLY THAT THIS PRESSURE COULD BE EXCEEDED.
OFF-SKID BLOCK & VENT ASSEMBLY
NOTE 8 B 2. OFF-SKID PIPING TO BE 316 STAINLESS STEEL.

PDI 3. CUSTOMER SUPPLY OFF-SKID HAND VALVE IS A SAFETY


107 REQUIREMENT FOR MANUAL ISOLATION AND MUST ALWAYS BE
FITTED.

HV680 INSTRUMENT AIR 4. N/A.


1/2" OD x 0.065" C S S SOL11
CLIENT NC NO ZS ZI H
44
B CCc2 5. N/A. B

ZS ZI B 6. CONTROL VALVE DIFFERENTIAL PRESSURE TRIP SETTING = 1.38 BAR.


11 L
PDI GAS FUEL XF193 LL
H C S S C C S 7. TAPPING POINT ON XF94 TO BE USED FOR FORWARD AND REVERSE
VENT TO ATMOSPHERE PURGE OF THE SYSTEM PRIOR TO MAINTENANCE.
NOTE B
BYc BXc BZc XV31 NOTE 11
PDT FO 8. OFF-SKID BLOCK AND BLEED VALVE IS AN INTEGRATED ASSEMBLY.
B OFF-PACKAGE FUEL GAS BLOCK VALVE AND ALL ASSOCIATED
C 140 UPSTREAM PIPING MUST BE INSTALLED OUTSIDE OF THE GAS C
B TURBINE PLANE OF ROTATION.
HV672
9. FLOW TRANSMITTERS TO BE INSTALLED AWAY FROM SOURCES OF
VIBRATION AND NOISE. ARRANGEMENT SHOWN IS A TYPICAL
SIMPLIFIED SCHEME RECOMMENDED FOR MAINTENANCE. HAND
VALVES CUSTOMER SUPPLY.
XX5
2" NPS SCH 10s 10. PRIMARY BLOCK VALVE, SECONDARY BLOCK VALVE, AND VENT
D VALVE ARE CONNECTED VIA A MANIFOLD BLOCK WHICH CONTAINS D
A 9.5 MM DIAMETER VENT LINE RESTRICTOR.

B 11. ALL OFF-SKID HEAT TRACING (UPSTREAM OF CONNECTION Dc)


XF97
2" NPS SCH 10s

IS TO BE PROVIDED BY CONTRACTOR.

E C S S SOL12 HH E
HV673

FI NC NO ZS ZI H
NO

12
CCc1

FT ZS ZI
FG L GAS FUEL
1 45
GAS FUEL 18 LL TO GAS FUEL MODULE
C S S C C S S C C S S C 00001
CLIENT 2" NPS SCH 10s 2" NPS SCH 10s
/2.F2
F HV31 AUAc AUBc HV678 FOc NOTE 9 FPc HV679 CAc XV30 CBc F
HV674

NOTE 1, 2 NO NO FC
NC

NOTE 11
NOTE 3

HH 2" NPS SCH 10s


LI H
HV677
NC
B LD
G 103 G
HV115

H H

J J

HYDROCARBON
CONDENSATE
C S FO109
TO DRAIN 3/4" OD x 0.065"
NOTE B UNSPECIFIED TOLORANCES B 08-20-2019 VANL E HUANG B ELKINS INITIAL RELEASE
AUCc US AND EU EXPORT CONTROLS
TECHNOLOGY CLASSIFICATION: ECCN: EAR99 AL: N X > 1000mm ± 1.5mm REV SHEET COORD. DATE DRAWN CHECKED APPROVED DESCRIPTION OF CHANGE
US-CONTENT: YES X ≤ 1000mm ± 1.0mm
.X ± 0.5mm SOURCE DOC: HHCT480001 WITH REVISION: C
THIS DOCUMENT IS SUBJECT TO NATIONAL EXPORT CONTROL REGULATIONS. .XX ± 0.25mm DATE NAME SCALE: NONE
.IF US-CONTENT IS MARKED " YES " THEN US RE-EXPORT REGULATIONS APPLY. ANGLE ± 0.5°
DIVERSION CONTRARY TO THOSE REGULATIONS IS PROHIBITED. IN CASE FINISH (Ra) 3.2µm DRAWN 11-19-2018 VANL TITLE:
K OF DOUBT, THE EXPORT COMPLIANCE DEPARTMENT MUST BE CONTACTED.
UNLESS OTHERWISE SPECIFIED:
DO NOT SCALE DRAWING
DIMENSIONS ARE IN MILLIMETERS
CHECKED

APPROVED
11-19-2018

11-19-2018
X GROS

H HWANG
Gas Fuel System
DIMENSIONS IN [ ] ARE INCHES
COPYRIGHTED AS AN UNPUBLISHED WORK. ALL RIGHTS RESERVED. THIS BREAK ALL SHARP CORNERS
WORK CONTAINS THE CONFIDENTIAL AND PROPRIETARY INFORMATION OF REMOVE ALL BURRS
SIZE DOCUMENT - NUMBER REV LANGUAGE SHEET
SIEMENS. NEITHER THIS DOCUMENT NOR ANY INFORMATION DISCLOSED
HEREIN SHALL BE REPRODUCED IN ANY FORM, USED, OR DISCLOSED TO THIRD ANGLE PROJECTION
10730 Telge Rd.
OTHERS FOR ANY PURPOSE INCLUDING MANUFACTURING WITHOUT THE
EXPRESS WRITTEN PERMISSION OF SIEMENS. Houston, Texas 77095 USA
(281) 856-4400
D 6074 - C01-001 B en 1/2
1 2 3 4 5 6 7 8 9 10 11 Protection class: 02 Restricted Copyright (C) Siemens Energy, Inc 2018 All Rights Reserved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

PI
16
A A
HV1499

GAS TURBINE SKID EDGE


B B
GAS FUEL MODULE

INSTRUMENT AIR
S SOL470 AIR DISTRIBUTION
XV616C 63
NC
C01-004 /1.F6
NO C1
C C
HH
ZS ZI H
742
1" NPS SCH 10s

ZS ZI
743 L
GAS FUEL XF194 LL
C S S C C S
VENT TO ATMOSPHERE
D NOTE B D
AEc ADc ACc XV212 FO126 3/8" OD x 0.065"
FO NOTE 10 HH
B XI H ZC
L 12
LL

S SOL5 S SOL110
XV616A XV616B MAIN GAS FUEL
NO NC NC NO
E CONTROL VALVE E
IFV
ASSEMBLY
NOTE 6
FO127 FO128
XV463 XV464

HH HH PT PT ZT PT PT
ZS ZI H ZS ZI H
2A 2B 12 181A 181B
178 207
XM26
F GAS FUEL F
ZS ZI ZS ZI
FROM OFF SKID BLOCK
NOTE 7 L L M GAS FUEL
& BLEED VALVE 5 208
LL LL TO MAIN MANIFOLD
00001 C S XF94 2
2" NPS SCH 10s 2" NPS SCH 10s 1 1/2" NPS SCH 10s
/1.F13 C01-032 /2.F2
NOTE 2 Dc XV7 XV6 XV150
TT FC FC FF

1 1/2" NPS SCH 10s


HH
G HH XI H ZC G
TI H L 13
L LL
LL

PILOT GAS FUEL


CONTROL VALVE
IFV
ASSEMBLY
NOTE 6
H H

PT PT ZT PT PT
220A 220B 103 182A 182B

XM27

M GAS FUEL
TO PILOT MANIFOLD
J 3 J
C01-032 /2.E2
XV149
FF

UNSPECIFIED TOLORANCES B 08-20-2019 VANL E HUANG B ELKINS INITIAL RELEASE


US AND EU EXPORT CONTROLS
TECHNOLOGY CLASSIFICATION: ECCN: EAR99 AL: N X > 1000mm ± 1.5mm REV SHEET COORD. DATE DRAWN CHECKED APPROVED DESCRIPTION OF CHANGE
US-CONTENT: YES X ≤ 1000mm ± 1.0mm
.X ± 0.5mm SOURCE DOC: HHCT480001 WITH REVISION: C
THIS DOCUMENT IS SUBJECT TO NATIONAL EXPORT CONTROL REGULATIONS. .XX ± 0.25mm DATE NAME SCALE: NONE
.IF US-CONTENT IS MARKED " YES " THEN US RE-EXPORT REGULATIONS APPLY. ANGLE ± 0.5°
DIVERSION CONTRARY TO THOSE REGULATIONS IS PROHIBITED. IN CASE FINISH (Ra) 3.2µm DRAWN 11-19-2018 VANL TITLE:
K OF DOUBT, THE EXPORT COMPLIANCE DEPARTMENT MUST BE CONTACTED.
UNLESS OTHERWISE SPECIFIED:
DO NOT SCALE DRAWING
DIMENSIONS ARE IN MILLIMETERS
CHECKED

APPROVED
11-19-2018

11-19-2018
X GROS

H HWANG
Gas Fuel System
DIMENSIONS IN [ ] ARE INCHES
COPYRIGHTED AS AN UNPUBLISHED WORK. ALL RIGHTS RESERVED. THIS BREAK ALL SHARP CORNERS
WORK CONTAINS THE CONFIDENTIAL AND PROPRIETARY INFORMATION OF REMOVE ALL BURRS
SIZE DOCUMENT - NUMBER REV LANGUAGE SHEET
SIEMENS. NEITHER THIS DOCUMENT NOR ANY INFORMATION DISCLOSED
HEREIN SHALL BE REPRODUCED IN ANY FORM, USED, OR DISCLOSED TO THIRD ANGLE PROJECTION
10730 Telge Rd.
OTHERS FOR ANY PURPOSE INCLUDING MANUFACTURING WITHOUT THE
EXPRESS WRITTEN PERMISSION OF SIEMENS. Houston, Texas 77095 USA
(281) 856-4400
D 6074 - C01-001 B en 2/2
1 2 3 4 5 6 7 8 9 10 11 Protection class: 02 Restricted Copyright (C) Siemens Energy, Inc 2018 All Rights Reserved

You might also like