Professional Documents
Culture Documents
Environmental
Assessment/Analysis
Reports ___ ___
Report E0051
Public Disclosure Authorized
Ghana -
Thermal Power --
Project.
Public Disclosure Authorized
EA Category A
Environmenta Assessment.
L1~of
4
Public Disclosure Authorized
August 1993
August 1993
The plant will initiallyuse light crude oil, or distillateoil with the possibilityof
later conversionto naturalgas shoulda supply becomeavailable.The plant
requiresa 3.0 m conduitfor once through coolingwater, drawing 5.7 m3 /s
from the sea.
In general the analysis indicates that the plant will have modest, but
mitigatable,environmentalimpacts. The key potentialissuesinclude:
i
the effectof the cooling wateron marinelife and the consequenteffects
on the thrivingfishing industryof Aboadzeand neighboringvi!lages
the effectsthat the loss of site land (some35 - 40 ha) will have on nearby
familieswho currentlypracticepredominantlysubsistencelevelagriculture
on that site
air qualityimpacts
..
lands are farmedby tenants. Commercialfarmerspay for the use of the
land with a shareof theircrops grown,whilesubsistencefarmersmakea
nominal contribution to the land owner. The concern is that any
compensationwill be paid to the land ownersand not to the tenantwho
may find it difficultto find an alternatefarm site. It is importantthat this
issue be addressed in the compensationstructure and it may be
appropriateto provideassistanceto tenantsin locatingotherlands. The
developmentplan for the projectincludespreservation2of the beachridge
coconut palm plantings.
Air Quality
The majorair qualityconcernof the projectis relatedto NOxemissions.
Sourceemissionstandardsare measuredin nanogramsperjoule and the
World Bank guideline for NOx is 130. The plant could generate
approximatelythreetimes that levelwithout controlmechanisms. Water
injectiontechnologyused to lower NOxemissionswill be installedon the
combustionturbineburners,however,dueto limitedfreshwateravailability
on site,may be delayedby up to 12 monthsfrom the start-upof the first
CTG. To provide,a sufficientand reliablesourceof waterfor this control,
a desalinationplant is providedin the plantdesign. Assumingno delays
in contractawardor schedule,thewatersupplyfrom the desalinationplant
will be availableshortly after the start-upof the second CTG, thereby
ensuring thatemissionlevelsarebelowapplicablestandardsfor operations
beyondthis point.
iii
requirementsand help determineif the predictionsand mitigationsgivenhere
are correct.
iv
Table of Contents
Ust of Talies
Ust of Figures
1Introductlon ..................................... 1 -1
Bibliography
Number Title
4.3 PopulationStatistics
C~~~~~~~~~~~~~~~Cu
VOL7AWR.ERAu1u...0
1AXOE IOIEO4 _, LI'
." I
STUDYARE An
1-5
TheEIBhasrequestedelaboration of theenvironmental
impactof the project,particularly
withrespectto theeffectsofwarmwaterdischargesandfuelspillageonaquaticlife. The
impactof noiseon thecommunity of Aboodzeandthepotentialto reduceNOxemissions
to lowerlevelswith newtechnologyas it becomesavailable.
develDpment. The Action Plan has been approved by the Ghana Environmental
ProtectionAgency and these principles have been followed here.
Tables 2.1 and 2.2 provide ambient air and water quality emission guidelines for the
World Bank,US and Canada,whileTable 2.3 provides hourlyair emissionguidelinesfor
a thermal power plant operatingwithin those different jurisdictions. Discussionshave
been undertakenbetweenGhana's EnvironmentalProtectionCounciland VRAregarding
air emissionstandardsduring the past3 years. Initially,it was proposedthat the thermal
plant be located inland from the coast and air emissionswere consideredmost critical
and criteriawere developed (see Table 2.1). The preferred site for the plant has now
been identified as a coastallocation. Although Ghana has some proposed guidelines
for freshwaterqualitythey have no establishedwaterqualitycriteriafor marinesituations.
In discussionwith the EnvironmentalProtectionCouncil(1993),they have proposedthat
discharges of warm water into the sea, not exceed 33°C with a temperaturerise of not
more than 50 C at the beach or landfall,and that the dischargesmust be controlledsuch
that they do not have any adverseeffects.
RegulatingAgency
(RevisedEPC, Aug. 1990)
Canadian
World United Acceptance
Parameter Bank States Llmits Ghana
1 SulphurDioxide(SO2 )
- Ambient Concentrations
- annualarithmeticmean (ug/m3 ) 100 80 30-60
- maximum24-h concentration(ug/m3 ) 500 365' 150-300 200
2 NitrousOxide (expressedas NO2)
- AmbientConcentrations NO2
- annual arithmeticmean (pg/m3) 100 100 0-100
-
3)
average24-h concentration(pg/rn 0-200 320
3 Carbon Monoxide(CO)
- Ambient Concentrations
- averageconcentrationover 8-h period (mg/m3 ) 10 6-15
averageconcentrationover 1-yr period (mg/m ) 351 15-35 10
4 SuspendedParticulateMatter
- Ambient Concentrations
3) 100 50 60-70
- annualgeometric mean (ug/mr
- average24-h concentration(pg/rn3 ) 500 150 0-120 260
5 Opacity = <20% <20%
._________________ RegulatingAgency
Suspendedsolids30-d 2S
average(mg/L) 30
Phenols(ug/I) 20
Dissolvedoil and 15 15 5
grease(mg/L) No visiblesheen
Phosphorus(mg/I) I
Temperature state not to alterambientlemperatureby SeeSection2.2 in text
regulated > 1__C2
Effluentemissionsfromfederalfacilities.
2 At edge of mixingzone.
Table 2.3
RegulatingAgency
Parameter World United
Bank States Cana
da
1 Sulphurdioxide
- tonnesper day 1002 500
- maximumallowablegroundlevelIncrement 3), 1-yraverage.
to ambient(pg/m 10 - 50 340 3
- hourlymean rate of discharge(ng/J)' 258
2 Nitrousoxidehourlymeanrateof discharge(rng/J)
- liquidfossilfuel 130 130 129
- gaseousfossilfuel 86 86 86
3 Suspendedparticulatematterhourlymeanrateof discharge(ng/J) 43 43
4 Opacity 20% 20%
1ng/J
- nanograms
(10wf
g)fJoule.
2 Mostto leastrestrictive
condition
(seep 435WorldBankEnvironmental
Guidelines).
Forunitsemitting
lessthan2580ng/Jol heatinput.
2-7
TakoradiThermalPlant - PredictedEmissions
(300 MW CombinedCycle Plant)
Applicable
2
EmtsslonTo Parameter Predicltion Standard Exceedance
Air Sulphurdioxide(SO 2 )
* maximumstackconcentrations (mg/m3)l 63.5
5
- annualmeanconcentralions at plumeimpact(ug/m3) 12.3 Amb + 50 No
* emissionrate- hourly(ng/J) 927
* daily(/d) 5.5 100 No
Nitrousoxides
* maximumstackconcentralion(mg/m3) 297.5
- annualmeanconcentrations at plumeimpactf(glm)
- uncontrolled 57.4 100 No
* controlled 8.0 100 No
* hourlyemissionrate(ng/J)
- uncontrolled 447 130 Yes
- controlled 77.9 130 No
- daily emissiontate (td)
- uncontrolled 27.2
* controlled 4.7
Carbonmonoxide
* maximumstackconcentration(mg/m3) 7.2
- maximum0.5 h conceniration
al plumeimpact ug/m) 5.1
over 8 h period(mg/m)
* averageambientconcentration 10 No
* averageambientconcentrationover 1 h period(mg/r) .004 35 No
Suspendedpaniculatematter
* maximumstackconcentration(mg/rn) 3.3
* maximum0.5 h concentrationat plumeimpact ug/Im3) 2.4
- averageannualgeometricaverage(rg/m3) 0.7 100 No
- average24 h concentration(ug/m3) 0.8 500 No
- meanhourlyrateof discharge(ngfJ) 4.9 43 No
Table 2.4
TakoradiThermalPlant - PredictedEmissions- 2
(300MWCombinedCyclePlant)
I I 2
I ~~~~~~~~~~~~~~~~~~~Applilable
EmluslonTo Parameter Predictlon Slandard Exceedanee
Coolingwaler
t-emperature(C) - Tmax- at discharge 42 33 - 36 Yes
- at edgeol mixingzone ambient+ 0.5 33.36
-8No
Notes:
Duringcombinedcycleopetation.
2 At moststable(c), atmosphericconditions,wilh 40 m stackandat low temperalureoperalion(i.e.,worstcase).
3 NVS= no visiblesheen.
4 Worstcasescenario,12'C at 11.3m3/s and 0.1 m/s ambientlongshorecurrent.
S Not to exceed100ug/m3
^ NO,controlwilh walerinjection
'* Worstcasescenario,uncontrolledoperation.
3 Description of the Proposed Project
3 Description of the Proposed Project
The proposed TakoradiThermal Plant consists of a 300-MW oil-fired combined cycle
thermal generatingplant. I Is to be located just west of the village of Aboadze on the
Gulf of Guinea, approximately15 km northeast of the city of Sekondi-Takoradi. The
purpose of the plant is to furnishpeaking powerto the nationalgrid and to providebase
load capacity in timesof low water levelswhen hydroelectricgenerationis affected. The
plant will be built for a 20-yr life. Constructionis anticipatedto begin in 1994, and the
first unit would be operalionalby February1996 (theschedulefor consiructionis outlined
in Figure 3.1).
Combined cycle plants offer operationalflexibility,in that one, two or three unit operation
can be providedto meet demand. Combustionturbinescan be brought into servicevery
quickly (<1 h from start to full output), while total operationalcapacity can be achieved
within 12 - 48 h, depending on the degree and length of the previous shutdown.
3-2
- 161-kVswitchyard
- two 2-circuit, 161-kV transmissionlines from the site to the nationalgrid at Inchaban
- use of light crude oil as the principalfuel supply for powergenerationwith the option
of convertingto natural gas it a suitablesourcewas to become available. Operation
also possible on distillateoil
- a fuel oil tank farm having enoughcapacity for a minimum60-d supply; proposedto
have three tanks of 36 000 m3 each (224 000 bbls)
- the cooling water intake and dischargewill both be located on the sea bottom, in a
water depth not less than 7.5 m. at lowest astronomicaltide level (Figure3.5).
- the intake will be fitted with a cap and bellmouthto preventvortex formationand
reduce entrainment of marine organisms,while the discharge will be fitted with
appropriatestructuresto facilitatehydrodynamicmixingof the thermalplume. Intake
velocitywill be no morethan 0.5 m/s,while dischargeexitvelocitywill be a minimum
of 2.0 m/s
Contract TK-1
Award Combustion Turbine
Plant ........ I....*. ..... ........ ..... I. ................ ......................... ....... .......
*........*........ ------- ...
TK2SemSteam.........
TurineAu.lIaie
Tr*2A xlare ....... .................. . .....................................................................................
....
Design, Etc.
Mobilization
' DesignTK-1........1........... m.I........... m.......................-........
... ..-..... .......... .... ........ ...
aMobilization
Personnel TK-1
&Equipment
At Sheo TK-2........2.............-.. ........ ................ ................-........ . ......... ... ....... ........... . .....
.
&Generator
Turbine & Installation
Manufacture
Turbine)
-Unit2(Combustion ..................... .. ..... .. ....... ..
............. ...........
Turbine)
- Unit3 (Steam ............. I...........................................................
Recovery
*Heat Generators
Steam 1&2
forUnits ........ ............... ...... ............. -........................
&Civil
Development
Siteaccess, Works
Clearing,
* SiteServices, Site,Offices
Town ......... -....... n...... ....... ..-....................... .. . ....-....-.... ................ I .......
*AccessRoad
(InchabantoAboadze)/1Landscaplng
.......................... 01-1,,11 ................................
*Intake SiteSelection
andOutfall Study m..............-.
............-.............. m....... ......-...... . .. .......- ..... .... I..........
*Intake Construction
andOutfall ........... .............-.... ....... .....-.. m....... m.... ........ ........ ................. .......
*Fuel Tanks
Storage Systems
&Treatment ........ ....... ................ ..................... .............. ........... ..... .......
*Desalination Plant
andDemineralization ... ... I. . ................ ....... ................-.-.........................
-....... -.. ................
Buildings...........
'Ancillary n s......... ........ ........ ....... m...... m. .................. -.. .... ......... ..... ........
' Completion
Housing Units &Guest
Houses.*... . ....... ....... ....... .. .............................. ........................ ....... ....... ....... .......
TransmissionLine,
Switchyard &Instrumentation
*TransmissionLine- TieInatInchaban .......... ..... ....... . ........................ ....... ....... ....... .......
Switchyard
'Transformer, &PlantControl.m....... ........ ........ ..-.................. m.... ........ ....-...................- .......
FuelSystem
'SiteSelect
ionStudy ......-......................... .... ......................... ................ .............. .........
SPMandOilPipeline.......-.................................- ....... ..-....
33ntPatUnLnl........tPlanto..............nL.....in........I........e.......................... ............... .............. *.... .......
.... …a.
Fg.3.1
VoltaRiverAuthority
Thermal
Takoradi Plan
Scherf""' ..4k-f
Construction
VOLTA RIVER AUTiYORiY
TAXOII TiOEPUAL P
_____________________________ GENERAL OF CC PIANTI
SCHEMATIC
jIgr S1N3NOdPlOO INYd- -
I.. llJAJWOHIAVb3AIU
V11OA |< _)l........................._.
ihWAN
J 10
I $ .M
[11-S.gF gA I~~~~
|e~~~~~~~~Pd"
AboadzeShe
LowestWater Level0.0
Ez 4.5m l
} j 1 ~~~~~~~~~~~~~~~~~~
Pad
0 )s X ci1* 0.25%Slope/.,1.,.;
Fig.3.4
Volta River Authority
ThermalPlantSitingStudy
Typical Arrangementof CoolingWaterTunnellntaki nllIl
~~~~~~~~~~~~~~~-7~~~~~~~~~~~~~~~~~~~~~~~~~S
v- ~~~~~~~~~~~~~~~VOLTA
RIVER AUTHORITYrl--j
_~ INTAKE DISCHARGE A KDRAM
LOCATIONSPLANT
INiU
INTAKE DISCHARGEAND 5PM LOCATIONS
3-13
maximum additional water flow through the cooling water circuit, associated with
desalinationplant operation,estimatedat less than 0.05 m3 /s
- the project to be contracted on a turnkey basis, and will consist ol four major
contract, relating to CTGs, STU,transmissionand housing.
4 Description of the
Existing Environment
I'
4 Description of the Existing Environment
The area encompassed by the environmentalstudy is shown In Figure 1.1. The
proposedTakoradiThermalPlantwill be located on the southwestcoast of Ghana in the
WesternRegionin the Districtof ShamaAhanta East. The proposedsite for the plant is
approximately15 km northeastof the city of Sekondi-Takoradi,Immediatelyto the west
of the village of Aboadze. The sitewill coveran area of approximately1 km2. Presently,
the site is connected by a gravel road to the main Takoradi-CapeCoast Highway at
Inchaban. The transmissionline from the plantwill run parallelto, and north of, this road.
Regional Topography
Generally,the areahas an irregular,hillysurface,risingin elevationfrom sea level
to 50 m inland. The shorelineshows evidenceof bothdepositionaland erosional
features. Clifis, rising 5 to 10 m in elevation,are located2.5 km east of Sekondi,
which then recede along the shoreline in an eastwardlydirection. A wave cut
platform,backed by a sandy beach/ridge,is moretypical of the area. There are
rocky headlandsat Aboadze and Aboesi with sandy bays between. The Pra
Riveris the mainwatercoursein the area and dischargesinto the sea through a
coastal lagoon just east of Shama. Immediatelyto the west of the proposed
plant site is the AnankwariRiverand its tributarieswhich flow through a verylow-
lying,wet floodplain. Generallythis river is isolatedfromthe oceanby a sand bar
that builds up across its mouth during the dry season. This riveris controlledby
a dam at Inchaban. Water is spilledfrom the reservoirdepending upon rainfall
amount, but otherwisethe flow in the lower reaches results from a few small
tributaries downstreamof the dam.
Site Topography
At the proposedpower plant site, land elevationranges between 1 and 8-10 me
with the higher ground forming a discontinuousridge on the north side of the
4-2
TransmissionLine Topography
Along the proposedtransmissionlineroute,the terrainccnsistsof a seriesof
steep-sidedhills (occupying50%to 60%of the area)and broadflat-bottomed
valleys,200to 500 m wide,whichcontaintributariesof theAnankwariRiver.
Regional Geology
Theunderlyingbedrockin thestudyareaisof Precambrian to Carboniferousage,
thebasementrocksconsistprimarilyof gneiss,granitesandschists.Throughout
mostof the region,theserocktype, are overlainby sedimentsof the Sekondi
Serieswhichare believedto be of Devonianor Carboniferousage. Theyconsist
mainly of sandstones and shale_;with occasionalconglomeratestrata.
Overburdenin the region consists of weatheredbedrockthat can reach
thicknessesof 20 m. SouthernGhanais not a highlyactive seismicarea;
however,it is a regioncapableof producingsignificantearthquakes.The area
100 - 200 km east and southeastof the site is periodiceally
seismicallyactive
(Crowe,1952). A seriesof fault lineshavebeenmappedthroughthe general
region(Figure4.2).
1 ~ ~ ~ ~ ~ ~ ~ ~ ~ 1~~~~0
I R~~~~~~
~~
335M ~ ~ ~ OKOUCOeJ / :~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~_::__________SUFCCOTR
BENCH,-0 0 ITRE
. . .. .... SE.ASONALWETAREA
~0.41~ ~
BENCH
MARK ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ N ErE
APPROXIMATE
LOWTIDELTASORIVER A ETHORETYA
~ ~ ~ ~ ~ ~ ~
SHORELINE TAOAO HELL LN
Legend
Sekondi
Series l.ch,abn
I Sekondi
Sandstone
/S6 AboaVi
Faull
Eflia
Nkwanta /S55
Beds
_ / S4
Shales
Takoradi Ab',eu
I /S3
Sandstone
-I Takoradi Incha,anFault
Elmina
Sandstone/
S2
SI
AjuaShales/ Faull
NoithBoundafy Site
Precambrian
Basement
Rock
IJ IMetamorphic
- Line
Fault
\ - .: ~~~Windy
RidgeFal
I X' > g
Kiomte
s pVlaRieAuhrt
-' If
Fig.4.2
Takoradi
Thermal
Plant
Pumpunl . =- _--~~~ TakoRegional
Plogy
4-7
Site Geology
Sedimentary rockof theAjuaShaleandElminaSandstoneunitsof the Sekondi
Seriesunderliethe projectsite. TheAjuaShalesare presentin an east-west
depressionacrossthenorthend or the site,butthereare no surfaceoutcrops.
Outcropsof Elminasandstoneoccur east of the site in Aboadze.along the
shorelineon the outer edge of the site, and along the basalridge near the
northerncontactwith theAjuaShale. Surfaceoutcropsalongthe tidalzoneof
theshorelineconsistol freshto slightlyweathered
soundrock;whereas,outcrops
exposedfurtherinlandusuallyhavea completely weatheredmantleof 0.5to 1 m
overlyingsoundbedrock.Therockweathersto a brown,hardsand,andclayto
clayey,sand.
4.1.4.2 PhysicalOceanography
SedimentTransport
Thecoastof theGulf of Guineashowsslightconcavecurvesbetweena series
of capes (Palmas,ThreePoints,St. Pauland Formosa).TheVolta and Niger
rivers,both some distanceto the east of the site, are the only large rivers
discharginginto the Gulf of Guineaand werehistoricallythe mainsourcesof
sedimentsfor formationof the shores. The coastal orientationand the
continuousactionof the oceanswellfrom the southwestresultsin sediments
being transportedawayfromthe capesand depositedon the shorebetween
them. On a smallerscale,thispatternof depositionis repeatedwithinthelarger
concavecurves,makingthe coasta seriesof beachesintersectedby rocky
promontories andsomecliffs. Thispatternis apparentin thevicinityof Aboadze
wherethe shoreconsistsprimarilyof sandybeacheswith rockyoutcrops. The
depthof the sanddepositsis not likelylargeas evidencedby the occurrence of
severalexposedrocksin the nearshorearea. In shoreof the 10 m contour,the
bottomsubstrateconsistsof sandwithrockoutcropschangingto mudandsand
in deeperwaters.
4-11
Currents
Currentsin the studyareaare generallywest to eastbeing dominatedby the
GuineaCurrentwhichis a countercurrentto thecounterclockwise circulationof
the SouthEquatorialCurrentin thesouthAtlantic.Alongthecoast,this general
west to east circulationis alteredlocallyby eddy currentsin bays, and by
dischargesfromrivers.Currentsare generallystrongestfromMayto Julywhen
speedsbetween0.5and 1 rn/sare oftenrecorded,but rarelyexceed0.25 m/s
during November to January.
Tides
ThetidalrangealongtheGhanacoastis approximately 1 m on a dailybasis,but
rangesalmost2 m annually.Thissmallrange,combinedwiththeshallowcoastal
plainsand lack of largetidal basinsmeansthat strong,tidallyinducedcurrents
are generallyabsent.
Waves
Theprevailingwindsalongthe Ghanacoastare generallynotstrongenoughto
generatesignificantwaveaction. Windgeneratedwavesrarelyexceed1 m in
heightand periodsgreaterthan3 to 4 seconds.However, the shoreis attacked
by constantswellsthat aregeneratedin the openwatersof the Gulfof Guinea
and beyond.Theseswellshavean averageinternalheightof between0.9m in
winterand 1.2m in summer.Theyoriginatefromstormsin thesouthernAtlantic
and arriveon the coastfroma relativelynarrowsoutherlysector. Theseswells
are verylongwith a periodof 12 or 13 seconds.
Temperatureand Salinity
Sea surfacetemperaturesand salinitiesalong the coastof Ghanacan vary
widely,with the oceanographicregimecharacterizedby a seasonalmajor
upwellingand a minorupwelling.Themajorupwellingoccursfor approximately
3 monthseach year, beginninglate June or earlyJuly and ending in late
Septemberor early October. This eventis defined as that periodwhen sea
surfacetemperature failsbelow25aC.Theupwellingis strongerandlastslonger
alongthewesternsectionof thecoast. Surfacetemperatures candropto as low
as 17.5'Cduringthe upwelling,whilesalinitygenerallyincreasesand dissolved
oxygendeclines.Seatemperatures tendto be lowestduringthisperiodas solar
heatingis limitedby cloudcoverandupwellings arefrequent.Salinityon average
is highestin August and lowestin late Octoberand November. Salinityis
influencedby rainsand highriverdischargeswhichdilutenear-shore watersand
upwellingthat bringsdeeper,moresalinewatersto the surface.
variesfrom10 to 50 m on
In the off-shoreregion,the depthof the thermocline
an annualbasis,with the resultthat watersin shoreof the 10-mcontour,and
c'ftenthe 20- or 30-mcontour,are isothermal.Seasurfacetemperatures are
4-13
January 25.7
February 26.8
March 26.8
April 27.3
May 27.1
June 26.0
July 23.1
August 21.1
September 21.3
October 24.9
NDvember 27.0
December 26.5
Reference:Olori- Adu,ND
4-15
- intertidalzone
- strandzone
- evergreen shrubzone.
Intertidal Zone
Theintertidalzoneis the presentbeachzoneand has littleplantlife exceptfor
well-attachedmarinealgaeandmicroscopic organisms.(Thiszonewasincluded
in the terrestrialvegetationalzoning although,it is also part of the marine
environment.)
Strand Zone
Thestrandzonecan be dividedinto the pioneerzone,whereplantcoveris low
andgrowingconditionsdifficult,andthemainstrandzonewheretherearemore
stable communities.The pioneerzone is characterizedby rhizomatousor
stolonilerousspecieswiththeirunderground spreadingrootsystemsstabilizing
the shiftingsubstrate(e.g., Canavaliarosea,SDorobolusvirpineusSisaland
Sanseveria).
Themainstrandzonehasa highergroundcover,bettersoiltexture,andhigher
organicmatter. Thereis a greatervarietyof plantsand not all are adaptedto
salineconditions.CommongrassesareAndroDopon qavanusandHeteroDopon
contortus.Thiszoneis oftenthesite of copra(coconutpalms)plantations.
EvergreenShrub Zone
Landward, thestrandzonegraduallymergesintotheevergreen
shrubzone. The
shrubsmay be dwarfedand shapedby the prevailingwinds. The common
species include Eugenia coronalus.Chrvsobalanusorbicularis.Thesoesia
poDulnea,andPhoenixreclinala.
In Ghana,immediatecoastalzonevegetationis broadlymappedas'strandand
mangrove'(Dicksonand Benneh,1988). On a broad scale, the regional
vegetation
patternof theareainlandof Sekondi-Takoradi
andextendingeastjust
beyondShamaBay (encompassing the projectarea),is dry semi-deciduous.
Coastalzone vegetationis shown in FigureBi. Appendix B. Mangrove
communitiesmaydevelop,especiallywithinthe coastallagoons.and locally,
theseare mainlyfound to thewest of CapeThreePointsand eastof Shama.
Mangroveare,however.prevalentalongthe banksof the PraRiver.extending
upstreamasfarasthemainhighwaybridge.No mangrovearepresentalongthe
southernedgeof the site.
4.2.2 Wildlife
Table 4.2
Waders, Terns and Herons Found
Along the Ghanaian Coastline
A - Waderm
Percentof Eastern
Atlantic Flyway
Species Fopulation
(%)
CurlewSandpiper Calidristerruqinea 2 -3
UttleStint C. minuta 2-3
Sanderling C. alba 2-4
Knot C. canutus 1
SpottedRedshank Trinaaervthroous 17 - 38
Greenshank T. nebularia 8 - 16
RingedPlover Charadrius hiaticula 2-3
GreyPlover Pluvialissquatarola 1- 2
Black-winged Stilt Himantopus himantovis 2 - 10
Avocet Recurvirostraavosetta 1-6
Black-tailed
Godwil Limosalimosa 1-2
Bar-tailedGodwit L. laDponica I
WVhimbrel NumeniusphaeoDus 1
Tumstone Arenariainterwres 1
B - Terns and Heron/Egrets
MaximumNumber
Species Observed
CommonTern Sternahirundo 17 200
BlackTern Clidoniasniara 12 000
SandwichTern S. sandvicensis 6 100
RoyalTern S. maxima 3 300
UttleTern S. albiJrons 1 000
UttleEgret Eqrettaaarzetta 12 200
WesternReefEgret E. aularis 2 000
GreyHeron Ardeacineria 1 500
C - The Importanceof CoastalAreas In
the Western Region for Sea- and Shorebirds
Total Numberof Estimated Bird
Slte SpeciesRecorded Population
RiverHwinestuary 341 3000
Sekondiharbour * 10 100
Aboadzibeach 7 1500
Aboesibeach 6 1000
1ncludesone threatenedspecies,Sternadouqalli(Roseate
Tern).
4-19
vicinityofAboadzeandAboesibeacharealsopresentedInTable42, andcompared
to thoserecordedIn the HwinRiverestuaryand Sekondiharbour(Ntiamoa-Baldu,
1993).
musselPernaperna, thelimpetsPatellasaliana,Fissurella
coarctataandF.nabecula
and carnivoroussnailsof the genusThais.Wherewaveactionis considerable,the
large barnacle,BalanustinfinnabulumIs also present,as Is the crab GraDsus
araDsus.
Rocky,off-shorereelsand shoalsareoftenwellcolonizedbyvariousred,blue-green
and solitaryalgae species,providinghabitat and feeding grounds for various
invertebrateand fish species. Off-shorereefsand cobblebanks,especiallythose
nearTema,are quite unstablebeing subjectto surfacemovementand cobble
tumblingdue to tide and wave-induced surgeaction,whichis especiallyprevalent
duringtherainyseason(May/June).Thisresultsin theremovalof muchof thea!gal
growth, and a correspondingreductionin benthic populations. It has been
suggestedthat theseseasonaldisturbances preventthe obtainmentof trueclimax
communitiesand helps to maintainthe presenthigh level of speciesdiversity.
Commoninhabitantsincludethe bivalve,CreDidula porcellana and thefishspecies
Abudeldutsaxatilis(terrestrialdamselfish), Acanthurusmonroviae(Surgeonfish),
Ophioblenniusatlanticus,Steqastesimbricatusand Pseudoscarus hoefleri(large
parrotfish)(Johnand Lawson,1991).
Generally, major pelagic stocks off shore of the project area include Sardinella
species (flat and round sardines) (Figure4.3), anchovy, and tuna species, while
demersalspecies Includemembersof the sparidaelamily(sea breams,pandorasand
dentexs)with red pandora (Paqellusbellottic)being the most abundant.
To the east of the site, from Aboadze Point through ShamaBay to the east side of
the Pra Riverestuary,significantfisheryresourcesexist. Shrimp,lobsterand cassava
fish are majorlocal resourcesin ShamaBay,utilizingthe bay and/or Pra Riverestuary
as spawning/nurseryor foragingzones. Otherspecies noted to occur near-shorein
the area between Aboadze Point and Fort Shama include barracuda, snapper,
grouper and thread fin, while pelagic or semi-pela-ic species such as long-finned
herring,ribbonfish,shad, burrito.anchovy,and cuttlefishare presentfurtherof f-shore
to the 2Dto 30 m depth zone. The catchesand presumablyabundanceof cassava
fish, long-finned herringand burrito,arehighest in the 26 to 290C temperaturerange.
while the abundance of shrimpand cuttlefishare also highest during the periods of
high water temperature. Other species noted to breed in or around the Pra River
estuaryinclude long-finned herring,ribbonfishand cuttlefish.
4-22
Population
The populationof theWesternRegionwas 1.1millionIn 1984,with 15%of the
peoplelivingIn theSekondi-TakoradiLocalAuthority.Presently,
ShamaAhanta
EastDistrictcoversapproximately 2
350km , andhasa populationof 340000or
20%of the total populationof the WesternRegion.
GUs1 Guneda C 5.
It<m~~~~~~~~~CrGUI1~~~~~~~~~ 46X
CapeApa~~~~~~~~~~~~~~~~~~~~~~Fg .
3W 2Pr
sedW 0h 1E
Legiend
_- Coastwardus
Migration.
January
andEndofJune
~Mveniant
.->Eastwards Durnng
dieFishing
Season
_~ Seaward,
M Oclober-March
Plradont
Rel.:From
Ansa-Emmim,
1976in Agyeporig
atal, 1990) VoIlaRiver
Auihority I
TakoradiThermalPlant xD[ T
Distribution
of RoundSardinellain the Gulfof Guinea IIJ
ng _
Prqm*d
Tlwmall v / 0_
CapeC. -.
Oruniis or th RoundSardniela
KnownSpawnhig/Feedfng
. AurEla)/ ~
{~~~~~~~~~~~~~~ ~~Sarrnela
4'30' _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4. 30
0 go 2
N~~~~~~~~~~~~~~~~~~MKA
d~~~~~~~Pooe
TM
X~~~~~~~~~~~~~~~~~k
7J IK
A
X~~~~~~~~~~~~~~~~~~~~~~~~-1o
a o-m
V~~~~~~~~~~~~~~~~~ak R h '_O
AOWO ~~~~~~~~~~~~~~~~
limiti
FQA
EXISTING.J ;.X *i. ~
BOUN:R
: ACQUISITION : . : *WAMP :OLY : :D :A : 5. D MA
~~
-~ ,... -.. CESSA PLANTATiO
. . . ... * . MJTt
K U. SCRUBAND WAL
.
33500 ,1.. . . . MANGO.CLL%.. ,l ThE
S ORPLAWAIN
j : - . : . - : * : - :I AT -W N :D : ::::1-JNEg--
. . . . . . . . . W-
Ea;..............
;'!.'jkf::r!...
R....- :::!...,... .'
P4~~~~~~~~~~~~~~~~~~.
.a~~~~~~~~~~~~~~~~~~~ -o -a -0 - ~~~~~~~~~
4- N
OOE
LANDUSE AT PROPOSAE
.APPROXIMATE ASITE
OFI
Xl
II X II . SLEGEND
- COCONuT
PLANTh4
370X 37000
/ ROADWAY
J v 1 .@,@,','l - SEASONAL
SWAMP
& CRASS
/ ZJ vC 1 ( > IlRlilililililillrill~~~~~~~~~-
CESSIPU:I
- iseNtMg
FARM
>- PLOIS
- PoPULATEID
AREA AAE
- WESTERNCLAYPRODUCTS
Co. LD
36000 :,k Is 36= ~~~~~~~~~~~~~~~~~~~
PERUMENDT TO)%7ISIT AND
COSRUCTION
CAMPSfTE
INCKAGN 7 CIrM
34000_ > k 4Y
OQ
33WO _
oRJ_~~ ~ ~ ~
~
RfVER ~ VLA
TAKPAO TNIMTALPLAND
UiPfhi
APPROXIMATE
LANDUSE ALONGPROPOSED
TRANSMISSION LUU
UNE STUDYCORRIDOR
Table 4.3
Population Statistics
Demographics
In the entireWestemRegion 1 therewas a slightly highermale popuilatUon
to
female(50.6%comparedto 49.4%)In 1984.Forthe studyarea,however,it was
onlyin Takoradithat malesoutnumberedfemales(Table4.3). Also,45%of the
totalWesternRegionpopulationwasunderthe age of 15 in 1984and lessthan
10% were in the 'over 50' age category In the Shama Local Authority
approximately40%of thehouseholds consistedo' morethan 4 peoplewnth2r7
having6 or moremembers.Thispatternwas alsosimilarfor the urbanareaof
Sekondi-Takoradi.
4.3.5 Infrastructure
proposed plant site. At present,this planning area Is only In the proposal stage.
Thereare no planning schemesdrawnup for the Aboadze/Aboesiand Shamaareas.
The area located immediatelyoff shore from the proposed powe plant site is not
used as a shipping route or anchorage into Sekondi or Takoradi harbour. The
Sekondi-Takoradimetropolitanarea has an airport.
The site for the proposed plant is presentlyconnectedto the mainroad at Inchaban
by a Class 3, half-tarred,half-gravelledroad. A 150-mmwaterlinefrom the Ghanaian
Waterand SewageCorporationwater treatmentplant at Inchabanprovides potable
waterto Aboadzeand Aboesi. Thewaterlineis located besidethe Aboadze-inchaban
road. The water supply has been described as erratic, at times (VRA, 1993).
Aboadze is supplied with electricity. Aboadze has a police station, headed by an
Inspectorof Police. The crime rateis low, consistingof petty assavlltsand arguments
among the residents,especiallyduring the bumper fishing seasons.
There are no waste disposal sites near the proposed site and both domestic refuse
and human excretaare dischargeddirectlyinto the sea.
4.3.6 Education
In the 1984 census for the WesternRegiDnit was determinedthat 62% of the total
populationhad attendedor were presentlyattendingschool,consistingof 73% males
snd 51% females. Almost 70% of those that attended completedmiddle school.
4-32
In the ratio of two thirds to a third In favour of the former. The grantor provAdesonly
the land, whilst the granteeprovideslabour and capilal for the farm operations.
By the State Lands Act, Act 125, 1962, the central government or delegated
authorities, wield sweeping powers with regard to compulsory acquisition
(expropriation)and compensationof land holdings for purposesIn the Interestof the
generalpublic. Paymentof promptand lair compensationfor thoseaffected by such
acquisitlonsIs guaranteedby the constitution. Under the Volta River Development
Act (amended),the AuthorityIs empowered to acquire land compulsorilyfor their
operations, using the State Lands Act. The land for the project will therefore be
acquired under this legislationin view of the secured title It aflords requisitioners.
Recognizing that the land for the project falls under stool land, not all the
compensationwill enureto the benefitof the Aboadze stool. The greaterpercentage
of the compensationwAIIgo to the wider community, including the Metropolitan
Assembly.
The status of the land and its ownershipwas reaffirmedby the ParamountChief of
ShamaTraditional- the oflicial land holder. With respect to the proposed site, he
mentionedthe Abradzefamilyof Dwomoand Aboadze as the bona-fideland owners.
ElderKwesi Egyiris the head of the familyand other membersare ElderEssounWui
and Mr. J. K. Arthur,secretaryto the family. At an earliermeetingwith the Chief and
people of Abradze, (AppendixD) the Chief (chief fisherman) pronounced the
Aboadze family with Elder Kwesi Egyir as the head of the land owners. Any
compensationpaymentsor proceedsfrom the land would have to be made to this
family.
Land litigation is not a common occurrence in the area, as all the people are
informed of who to deal with in land transactions
The regional area exhibits a range of land uses from intense urbanization in the
Sekondi-Takoradiarea to well established plantations of coconut and oil palm, to
areas of nativeforests and savannasfurther to the north. Within the ShamaAhanta
East District, about 45% of the land area is suitable for agricultural production
(17 700 ha), with approximately 30% of that area (=6000 ha) currently under
cultivation. The remainder is native forest, swamp/wetlandand areas of urban
4-36
development.TimberextractionIs an Importantcommercialactivityfurthernorth in
the region.
4.3.9 Fisheries
The coastalfisheryis exploitedby four fleets: the artisanalor canoe fleet,the semi-
industrialfleet, the industrialfleet,and the tuna fleet. The artisanalfisheryin Ghana
consisted of approximatelyBOO canoes in 1986 (Mensah and Koranteng,1988).
Severalfishing gears are utilized by the artisanalfishery including beach seine, set
net, hook and line, drift gill net, 'ali', 'poli'. and 'watsa'. The canoe fisheryis limited
to the coastalzone.
The semi-industrial(in shore) fleet consistsof locally built trawlersand purse seiners
of varying lengths between 8.2 and 37 m. These boats generally operate in the
coastal zone. There were approximately250 vessels in the semi-industrialfleet
between 1980 and 1986 (Mensahand Koranteng,1988).
The tuna fisheryis operated by both artisanaland tuna fleets, the latter consistingof
32 vesselsin 1986 (Mensahand Koranteng,1988). The canoe fleetutilizes hookand
line and drift gill nets to catch tuna while the tuna fleet uses largelypoleand line and
to a lesserextentpurse seinesto exploittuna. The canoefishery is limitedto the in-
shore coastal zone while the tuna fleet operatesfrom the coast to the equator.
4-40
During the period 1981 to 1986, the industrialfleets landed from 34 000 to 57 000
tonnes of fish inc;uding the followingmain species:
- Sardinella SardinellaSPD.
- SkipjackTuna KatsuwonusDelamys(Unn.)
Yellowfin Tuna Thunnus albacares(Bonn.)
Sea Breams Sparidae
Burrito/BigeyeGrunt Brachydeuterusauritus
Cuttlefish Seia SPD.
The most productivefishing occurs during the major upwellingin July to September
and to a lesser extent during the minor upwellingin January and February. During
the upwellings, pelagic species such as the sardinellasmove in shore to spawn.
Withintheprojectarea,recordso1landings(byspecies)areavailablefor theShama
AhantaEastDistrict,as well as for the threefishingvillages(Shama,Aboesiand
Aboadze)closestto theproposedsite. Thisinlormation is summarizedIn Table4.4
and presentedin its entiretyin AppendixB. The artisanalfisheriesIn Shama,
AboadzeandAboesicontributebetween25 and50%of the District'slandings.The
district'slandingin turn representapproximately
10%of the nationaltotal landed.
WithinShamaBay,differentfishingtechniquesareemployedto capturethevarious
specieswithinspecificpartsof the bay. Eastof the PraRiverestuary,the sand
bear:h and smooth bottom lend themselvesfor beach seining,with activities
extendingoutwardto the 12 m depth. Mainspeciescaughtincludeshrimp,cassava
fish, ribbonfish,meagrefish and shad(Ethmalosa
sp.).
Landings by Community
- Shama nlal 1960 2895 2003 2600
- Aboesi n/a 1280 1960 1945 2156
- Aboadze n/a 965 1770 1490 1893
1 NotNaivbl
4-44
4.3.10 Employment/Manufacturing
4.3.10.1 Employment
4.3.10.2 Fisheries
Aboadze/AboesVShama areknownnationallyasimportantfishingareas,andassuch
attractfishermenfromotherplaces.A fishrecordingstationis currentlyoperatedby
the FisheriesDepartmentat Shama,and a similarstationoperatedat Aboadzeuntil
the mid-1980s.
Equipment Cedis
4.3.10.3 Industry
4.3.10.4 Agriculture
Intermsof agricultural
production,
the Districtranksninthof theelevendistrictsin the
Region. A comparisonof croppingarea, yield and productionof major crops
betweenthe Districtsis presentedin TableC.4,AppendixC. Landareadevotedto
peppers,tomatoand eggplantin the Districtis estimatedat 100.115 and 100ha,
respectively.Yieldsof cassava,maize,plantainand cocoyamsare low to below
4-47
- introductionof higheryielding,fastermaturing,hybridcoconutvarietieswith
bettertoleranceto wiltingdisease(leaf-hopper
transmitted)
- introduction
of higheryieldingvarietiesof maize,cassavaand othercrops
- increaseemphasisandassistancein developing
agroforestry
plotsforfuelwood
supply
establishmentof anAgricultural
SectorInvestmentProject(ASIP)to providecredit
to localcommunitiesfor eligibleprojectssuch as small-scalewaterschemes,
construction
andrehabilitationof markets,construction
andrehabilitationof rural
roads and the constructionand operationof farm and village level food
processingandstorageunits.
Nurses/
Doctors/ Paramedlcs/ Support Unskilled
Dlstrict Populatlon Den'lsts Assistants Staff Assistants
ShamaAhantaEast 340000 8 188 32 179
Table 4.6B
Shama-Ahanta
EastMetropolitan
Authority
Development
Planning
Commiltce,
1992AnnualReportRegional
Director.
Ministry
d Heath
4-52
Solidwastesarepositivelycorrelatedwithhumanpopulationdensity,withthe areas
most affectedbeingthosenearcoastalsettlements.
Accumulations of plasticsof up
to 200 g/m2 havebeenobservedin someof themostpollutedareas(Biney,1982).
4.3.12.3 Oil
5.1 ConstructiotnPhase
Site Access
The presentroad from Inchabanto Aboadzewill be upgradedto a pavedasphalt
surfaceand increasedin width from its present6 m to 7.5 m with a further1.2 m
shoulder.
Site Preparatlon
The location of the main components of the proposed plant are shown in
Figure 3.3. The majorityof the plant will be on the higherwestern ridge but some
infilling and levellingwill be required. The final site elevationwill be 3.5 m. A
total area of 115 ha will be used for both plant and town site.
Transmission
line _
preparalion - _
Sile
dewatering . ._ .
Borrowdevelopmenl _ _ _ __.
Aggregatesources = =_=_=_=
Batchplant . . _ __=
Excavated
materiala S S
disposal . _
Inlakeandoultfall
consiructin
Pipeline
constructlon . . . . .
Deliveryof r,aleilalsa
Oredgirhand disposal _ _
ofmalerialat sea _ ____ _
Worklorce . . . . .
WastedisposalsHe . . . .
5-3
Borrow Areas
Themajorityof fill for sitelevellingduringtheinitialphaseof thedevelopment will
be providedfrom a combinationof the redistributionof on-sitematerial(hills,
knolls) and the import or aggregatefor lay-down areas, backfill around
foundations.etc. It is. however,possiblethat a smallamountof fill will be
requiredto completesitelevellingandlandscaping.A smallborrowareaclose
to the site,pDssiblyalongthetransmission line,will be used,if required.
Aggregate Sources
Therearesevenbedrockquarrieswithin9 - 14 kmof thesitewhichwouldmost
that new
likelybe usedfor aggregatesourcing(Figure4.5). It is not anticipated
quarrieswouldbe openedup. Approximately 3
200000 m of aggregatewill be
requiredfor concrete, asphalt,fill and lay-downareas.
the site and used for ground levelling/preparationneeds if the plant were
expanded In the future or used for berm materialaround the site, If required.
Pipeline Construction
A 16- to 20-in. (40-50cm) pipelinewill connect the SPM lor the oil tankersto the
fuel oil storagetanks on site. The underseaportion of the pipelinewill be laid on
the sea bed and anchoredto preventmovementdue to the currentswell or wave
action. The pipeline will be buried from an off shore location beginning at a
minimum depth of 3 m below low-waterlevel to the plant fence line. It may be
necessaryto excavaterock by drilling and blasting to bury the pipeline.
Delivery of Materials
Materialswill be delivered to the site by truck using the access road.
The followingprovides an estimateof the traffic movementto and from the site.
Transports,materialdelivery 3fwk
Work Force
Approximately400 local workerswill be required during the construction phase.
The followingis the breakdownof the work force:
Type Total
Electricians 60
EquipmentOperators 18
Labourers 100
Drivers 15
Iron workers 24
Carpenters 6
Millwrights 6
Boilermarkers 20
Plumbers 5
Welders/pipefitters 130
Masons 16
Total 400
It is assumed that the majority of the work force can be met from the local
Sekondi-Takoradiarea (exceptfor the supervisorystaff). Buseswill be provided
for the local work force for transportationto the site. Housingin the form of both
dormitoriesand single dwellingunits will be required for expatriatesand special
trades only. Initialaccommodationwill be arrangedmainlyin Sekondi-Takoradi
and the workerswill be bussed to.the site, until the construction housing has
been developed.
5-6
Paints and solvents may possiblybe stored on site and disposed of in the oil
sludge incinerator. Any materialsthat can be reused/recycledshould be reused
or disposed of in accordancewith VRA procedure.
Parameter Value
pH 7.6
Colour 6 Hazen
Nitrite nil
5-7
Air Quality
The major effectson air qualityduring the constructionphase will be an increase
in total suspended particulate matter during site clearing and constructon of
access roads. Traffic speeds should be reducedto minimizedust, and approved
dust suppressantsshould be applied as required. Dust suppressantsshould not
include oil. All trucks carryingfine materialshould be covered. Wheretopsoil is
to be stockpiled for a long period of time, it should be covered or seeded to
preventwind erosion.
Poor air quality can result from diesel-powered machinery and vehicles.
Constructionequipmentmust be wellmaintainedto minimizeexcessivegaseous
emissions.
Batch plant operations can produce high dust levels. Dust collectors may be
requiredto preventhigh dust emissions.Otherwise,water spraysystemsmaybe
appropriate.
When working underground during the construction of the intake and ouffall
tunnels, there is a possibilitythat gassescan be encounteredwhich could either
5-8
- 5.5 m3/min at the face of the tunnel for each man underground plus
2 m3 /min/brakehorsepowerfor all diesel units operatingin the underground
operations.
Noiseand Vibration
Excessive noiselevelscan occurfromthe operationof constructionequipment,
the concreteand asphaltbatch plants,and blasting. Thereis presentlyno
Informationon noise levels In the area, hence backgrounddata Is being
obtained. Generally, It is recommended thatnoiselevelsat theperimeterof the
site should not exceed55 dBA(WorldBank Guideline,1988). Duringsome
construction(i.e..clearingoperationsusinglargeequipment), closeto the site
boundariesand along thetransmission line, It will not be possibleto meetthis
guideline.However,to causethe leastdisruptionto theadjacentcommunityof
Aboadze,Itis recommended thatconstruction workthatproducesnuisancelevel
noisebe minimizedduringthenightor an locallyrecognizeddaysof rests.All
equipmentshouldbe well maintained and particularly noisysystemsshouldbe
screenedor muffled.Allworkersshouldbe providedwith,andtrainedin theuse,
of hearingprotectionwhenworkingnearnoisyequipment.
and sediment settling ponds) must be used where necessary,before the water
discharges into the existingnatural watercoursesto preventany increasein erosion
and sediment loading to the watercourse.
An increase in the total suspended solids in the surface water could result from
erosionof soil stockpiles. Measuresmust be takento minimizesoil erosion,Including
seeding any topsoil that Is to be stockpiled for a considerableperiod of time; straw
berms/silt fences, etc, should be used as temporarycontrol measures.
To prevent the leakage of oil/fuel from tanks into the ground and ultimatelyinto the
watercourses.all storagefacilities,eventemporaryfacilities,mustbe in a bermedarea
with an impermeableliner and of a capacitygreaterthan that of the tank. There must
be a means to remove rainwaterfrom the bermed area and the water treated (oil
removed) before discharge.
5-11
Runofffromthebatchplantsiteaswellas runofffromtheconstructionlay-downarea
mustpassthroughthe settlingbasinbeforebeingdischargedto a watercourse.
At the town site location,where feasible, any coconut and oil palms should be
retained. Duringconstruction,the trees, should be fencedoff to preventdamage
from equipment.
Aggregate Resources
It is planned to use aggregatefrom existingquarries. It would appear that there
are sufficientsupplies to meetthe project's needswithout depleting the reserves
to the detrimentof the local community. When actual aggregate requirements
are known,furtherinvestigationsof the aggregatesourcesshould be undertaken.
If negativeeffects are forecast,then alternatesourcing should be examined.
Off site sourcesof fill maybe required. Beforeany borrow areasare openedup,
the necessaryapprovalsfrom the appropriatelandownersmust be obtained. All
sites must be graded and revegetatedwhen constructionis finished.
Fisheries
In water constructionactivitiesfor the intake and outfall portals, the oil pipeline,
and the SPM buoy will interferewith fishing activitiesin their immediatevicinity.
To minimizethe impact,constructionshould not occurduring the time of greatest
fishing activitywhich coincideswith the upwellingperiods. These are the times
when in-shore fish numbers are highest, i.e., July to September (see
Section5.12.4).
Coastal Navigation
Marineconstructionactivitiescould interferewith coastalnavigation. An barges.
buoys. etc.must be clearlymarkedand illuminatedat night. Notificationmust be
given to the naval authoritiesat Sekondiand the TakoradiHarbourMaster prior
to commencementof any in-waterconstructionactMties,and conflicts with the
approachto Sekondi Harbourmust be avoided.
Transportation
Delivery of construction materials and the main plant components will put
considerable pressure on the existing Inchaban-Aboadzeroad. The main
mitigationis to upgrade the existingroad so that it is able to handle the increase
in traffic. It is recommendedthat the road improvementscontinue past the plant
and into the village of Aboadze. Thiswill be a benefitto the Aboadze community
in the long term as it will improvethe access into the area.
5-13
Land Use
The effects of constructionactivitieson land usewill be most markedat the plant
site-itself. All land will be clearedand, therefore,all the small farm plots will be
destroyed as will the tree crops on the two knolls. The only mitigationpossible
will be to compensatethe owners and land users. Negotiationswith the owners
and land userswill be required to establish reasonablecompensation.
It is recommendedthat the plant be located away from the sand ridge adjacent
to the beachwhere coconut palms havebeen planted. Coconutsprovide a high
and dependable source of income for the local population. Their root systems
also stabilize the beach ridge protecting the land behind from erosion and
inundation. The beach ridge reduces erosionaleffects and should be flagged
and/or fenced and all construction equipment must be kept out of this area.
Plant property has been purposelyset back 150 m from the beach to protect
coconut plantation. The central section of the beach strand, where sand was
excavatedin the past, should be infilledwith excess clean fill and replantedwith
coconut palm.
5-15
PermanentTownsNte
Thepermanent townsitewouldbeestablished to houseconstructionsupervisors,
and later,operationsstaff. Generally,the townsitewoulddependon Sekondi-
Takoradifor health,educationand othersocialfacilities.However,provisionwill
be retainedwithinthe townsitelayoutfor the additionalof someof the above
mentionedfacilities,if Sekondi-Takoradiservicesare unavailable
or insufficient.
7.5 down 27
facilitiesfor
In additionto the mainfeaturesof the planttherewill be maintenance
servicingvehicles,and plantmechanical and electricalequipment. Housingwill be
provided for the permanentsupervisoryoperating staff. This will include
approximately 75 housesandguesthousescapableof accommodating 12 people.
Townsiteserviceswill be providedas notedin Section5.1.2.5.
Air Quallty
Themajorityof air emissionswill resultfromboth the burningof fuelfor power
generation,while intermittentemissionswill originate from the waste oil
incinerator.The plantwill operatewith light crudeoil as the principalenergy
sourcewith provisionto alsousedistillatefueloil. Futureoperations
maybewith
naturalgas if a dependablesupplybecomesavailable.
CHARACTERIlSTIC OF WHOLECRUDE
CRUDE BonnyLight BraceR"e Escrave Forcadd Mahlb 0O0-OST Paanca ua Nigera Sar an Wend
COUNTRY OFORIGIN Ngeria Niaeria NigerIa Nigoria Yemcn Nigera Angb Ngeria Algerba
YEAROFASSAWATA BANKNO. 1073 4014411502 87115 118 401677 1095 4711221592 471830 19O 401741U
t90o 471714 1001 49178691075 4014218
PROPERTIES (BUREAUOFMINESCASS1FICATION)
rav1ty.API 34.50 l40.10 3520 30.50 -in11
42.10 -943-8 30 3- .40 44
Specific GrvIly 0.8524 0.8240 0.0488 0.8731 0.e11e 0 7938 0.8304 0.1621 0.3026
FBP
OIstillation. C F C F C F C F C F C F C F C F C F
IBP N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A I /A N/A WA WA WA N/A
S% VolRecovred 23 74 la 58 60 140 41 105 15 69 17 63 40 121 51 124 27 so
l0 101 213 71 160 67 189 111 232 62 144 46 11e at 173 77 171 10 139
20 151 303 107 224 132 270 177 350 97 206 01 195 123 263 123 253 - 209
30 202 396 146 299 lei 357 117 441 123 263 113 236 178 352 170 338 133 271
40 246 474 192 373 222 431 Z62 604 164 328 144 291 225 637 219 427 166 331
S0 2bJ 536 242 468 2le 502 294 661 207 405 176 353 272 522 266 S10 206 403
60 316 696 261 537 305 51 332 629 255 491 235 455 322 612 307 S5S 264 489
Tag.C
FleshPoint. -16 -.I N/A N/A N/A -15 -10 WA -18
FlashPoint.Tag.F 0 0 N/A N/A N/A 0 0 N/A 0
Pour Point. Upper.C -1 -4 4 4 5 12 0 13 -54
Pour Podnt,Upper,F 30 25 40 25 23 6s 32 55 -s
Viscosity.KinemalleISC( SOF),eS 5.40 3.62 7.02 11.10 3.67 2.20 8.21 WA 2.78
Viscosity,Kinemtlic 40C (104F).cS 3.52 2.23 3.50 5.13 2.16 1.44 3.20 3.08 1.82
Viscosity 500(122F).cS
Kinematic 3.03 1.00 2.89 2.46 1.32 1.25 2.67 WA 1.57
CarbonResidue.% Wt(CCR) 1 0.7 1.25 1.2 0.91 0.14 0.75 1 0.79
AnilinePoint. C 6s 6S N/A N/A N/A e5 N/A WA e6
Aniline Point, F 149.2 143.5 N/A 0.18 N/A 143.3 N/A NWA i15
Sullur. WI 0.122 0.093 0.14 N/A 0.09 0.042 0.12 0.12 0.145
'Hydrogen Sulfide, ppm 0 0 10 0.31 N/A 0 WA WA 0
NeutralizationNO, Total Acid (D0643 0.13 0.15 N/A N/A 0.17 0.15 0.06 0.30 O.os
Water and Sediment.% Vd. N/A N/A N/A N/A N/A N/A N/A WIA N/A
*Salt contont.Ibe/10009 1 4.2 36 N/A N/A 1.6 20 N/A a
Reld VaporPreurtc. lbs. 5.3 7.3 1.6 N/A N/A N/A N/A 5.2 6.4
Nitrogen.Tdal, ppm 000 490 N/A N/A 700 170 00 6093 310
Nickel,ppm 2.7 1.7 3.6 4.6 1.1 0.5 0.2 6 0.15
Vanadium,ppm 0.3 0.4 0.3 0.3 0.27 0.05 0.1 0.2 0.25
Copper.ppm 0.55 1.2 N/A N/A N/A 0.0o N/A WA 0.05
Carbon% wt. 67.39 37.11 N/A N/A N/A 33.36 N/A NWA 14.37
Hydrogen,% wt. 13.23 13.63 N/A N/A N/A 13.2 N/A WA 13.26
Carbon/HydrogenRatlo 6.61 6.39 N/A N/A N/A 6.32 WA N/A o0.
*U.O.P. characterizatlonFactor *K 11.6 11.S N/A N/A N/A 11.0 WA NWA I 1.0
Mercury,ppb N/A N/A N/A N/A N/A N/A N/A WA WA
1LIghtHydroeaubon analysis Wt l Vol % Wt % Vd % Wt % Wt
Vol St Vol % Wt % Vo % Wt W Vol WVA % Vd % Wt % Vd 6Wt 6 Vd
Ethaneand lighter 0.03 0.03 0.06 0.12 0.04 0.6 0.11 0.24 0 0 0.00 0.01 0.00 0.02 0.02 0.06 0 0
Propane 0.3 0.60 0.55 0.39 0.26 0.43 0.28 0.43 0.23 0.36 0.44 0.09 0.25 0.44 0.3 0.49 0.36 0 56
iSO-Butane 0.31 0.67 0.64 0.04 0.22 0.33 0.31 0.43 0.41 0.59 0.U3 1.25 0.22 0.33 0.2e 0.41 0.30 0.43
N-Butans 0.62 0.90 1.30 1.34 0.53 0.S6 0.S3 0.70 2.11 2.03 2.04 2.77 0.03 1.33 0.37 1.25 1.79 2.46
C4 and lighter 1.27 1.06 2.56 3.81 1.1 1.60 1.23 1.00 2.75 3.33 3.83 6.73 1.44 2.13 1.47 2.21 2.46 3.46
ISO-Pentans 0.71 0.07 1.42 1.U6 0.66 0.30 0.63 0.23 1.37 1.73 2.40 3.OS 0.34 1.12 0.34 1.13 1.36 1.75
N-Pentans 0.66 0.30 1.30 1.70 o.6s 0.87 0.52 0.71 1.72 2.21 2.31 2.91 1.26 1.67 0.02 1.22 2.61 3.41
TotalCS 1.37 1.30 2.72 3.58 1.31 1.67 1.16 1.60 3.00 3.00 4.72 5.96 2.11 2.70 1.70 2.36 4 04 5.16
CS and llghter 2.64 3.83 5.20 7.30 2.41 3.46 2.31 3.50 5.e4 7.38 6.10 10.7 3.56 4.03 3.23 4.57 e6.s0 363
-may ob Iniluenced by mannerow amp ng nd sampls hmnnl -Einimngd
Table 5.3
ASTM Test
Property Limits Method.
Flash Point Greater than 38C D93
Pour Point D97
KinematicsViscosity Not greaterthan 4.1 cSt (60 US) at D445/D
40°C
Thermal Stability Not to exceed Class 2 classification D1661
Specific Gravity Not greaterthan 0.88 D1298
Water and Sediment Not greaterthan 0.05% by volume D1796
Sulphur Not greaterthan 0.2%
Ash Not greater than 0.01% by weight D482
Trace Elements Sodiumplus potassium--notgreater
than 0.5 ppm by weight
morethan 0.5ppm by
Vanadium--not
weight
Site Condiions
FuelType Oil Oil Oil lI Oil Oil
AmbientTeerapoaure,
O(F 60 86(30) 86 (30)
Fuel HeatingValue,
BTUABLHV 18450 18450
ReativeHumidity 6o 60
BarometricPresure, PSLA 14.696 14,696
InletPressureLos,
In-water 42 4.2
ExhaustPressureLoss.
In-water 10.6 11.2
injectionFluid None None Water Steam Water Waler Water
GeneratorPowerFactor 0.95 0.85
GeneratorHydrogen
PSIA 30 30
CombustionTurbinePetlorman-e
Net Pwr OutplutKW 121110 140570 131470
Heat Rate.BTUJKW.H LHV 10190 9980 11110
ExhaustFlow. LB/HR 3263 3521011 3470052
ExhaustTemperature,IF 1004 1032 1030
Fuel Flow. Lb/Hr 76030 79160
InjectionRate.Lb/Hr 140650 87070
AuxilaryLoad. KW 550 700
InletAir Flow. Lb/Hr 3276533 3276821
Heat hnput.MMBTLHr(LHV) 1402.754 1460.502
InjectionRatio.LBLB 1.85 1.1
ExhaustGas Composnion
(by PCT Vo):
Oxygen 13.9 1227 1229
Carbon Dioxide 4.17 4.42 4.71
Water 5.48 12.70 10.73
Nitrogen 75.56 69.72 71.37
Argon 0.85 0.88 0.90
Ernsions
NO.. PPMVD
@15%02 & ISO 160 241 42 42 42 S6ppm 42 ppm
NO.. Lb/Hr 827.9 1247 220 229
CO.PPMVD 10 50 90
CO.LblHr 30 158 284
S02, PPMVD - 11 12
S02. Lb/Hr 78 82
H2S04 Mist,Lb/Hr - 12A 12.9
UHC.PPMVD 7 10 20
UHC,Lb/Hr 13 18 36
Table 5.4
VOC,PPMVD 10 5
VOC,Lb/Hr 18 9
TSP& PM-10,Lb/Hr
(exclH25(4) 14 50.8 51.6
Opacity% 20 20
NOTES:
1. Net poweroutputIs powerat the generatortermial minusthe auxiliaryloads.
2. Thu fueloNcompositionis 86.425%C, 13.5%H. 0.5%S. 0.01%Asb and is mumed to contain cO.015% FBN
3. Pat loads are achievedby modulatingIGVsandwe basedon percentol unrestrictedCT. output.
4. Thegross powerlimitIs 169000KW.
5-21
Sulphurdioxidehasbeendirectlylinkedto acidrain,whichhasbeenresponsible
for alteration of certain aquatic ecosystems,damage to vegetation,and
deteriorationot buildingmaterials.Sulphurdioxideis alsodetrimentalto health,
as It is knownto aggravateasthma,lung and heartdisease.
* Based
onfuel contining0.2%sulphur.
- annualmean 10.0pg/M3
- 0.5peak 3
34.4,ug/m
- 1 h average 28.3pg/M3
5-33
- 24 h average 11.6pg/mr3
Thus the desalinationplant should be placed on the critical path within the STG
contract,as it hasa significantimpact on the plant's abilityto producepowerand
meet emission standards. Groundwaterfrom a series of boreholesmay be able
5-35
Subsequent groundlevelconcentrations
havealsobeenmodelled, undervarious
stackheights(40,80 and 120m). for bothstabilityclassesin orderto evaluate
potentialnegativeimpacts. Model runs are summarizedIn Table 5.6 and
presentedin moredetailin AppendixE (SectionE2.2).
Other Emisslons
GuidelinesfortheTakoradiThermalPlanthavenotbeensetfor particulate matter
or opacity.Theseemissions shouldfollowthesamelimitsasset for Canadaand
the UnitedStates. Particulate
emissions,however,are normally nota factorIn
an oil-firedplant.
Veryhighnoiselevels(possibly120dBA)can be generatedfromthecombustion
turbines.Theseunitswillbe placedin acousticalenclosuressuchthatthenoise
levelwill not exceed85 dBAat 1 m from the enclosures.All workersin the
vicinityof this equipmentmustbe trainedin the use of and mustuse hearing
protectiveequipment.
Structures,
foundedon rock,shouldbe designedfor a seismicfactor(Z) of 0.25In
accordance withthe 1991UnilormBuildingCode.Theoil pipelineandcoolingwater
Intakeanddischargestructuresshouldalso be designedto meetthis seismicrisk.
(a) Oil
Potentialsourcesof oil spilledinto themarineenvironment
fromoil usageat
theTakoradiThermalPlantmayarisedue to threemainactivities:shipping,
unloadingand transferto shore,and storageon shore.
To assistIntheassessment
of impactsassociated withreleases,thepotential
movementof off shoreand coastaloil spillswereevaluated.Accordingto
proceduresIn the GhanaNationalOilSpillContingencyPlan,the rateand
directionof movementof a spill Is a vector (V,) that can be estimated
throughvectoradditionusingthewatercurrentspeedvector(Va)and the
windspeedvector(Vw)multipliedby a correctionfactorof 0.035.
P
IAbdn.enl50 *7 1 < ,,a. . I
S\kandiV de Aurila / WS E
VI t m *Ia2Jm
1 Um " aPUM
l d is Kft
FishincUS Knound
foar Sardinelm"
nlnglFeedilganroundSPforMtauSRound
4 30' (Sa~~~~~~~~~~~~~~~~~~~Kow
roiel unts)
fo te oud arinl0
h _ ___ _ _ _ _ , : ~~~~~~~~~~~~~~~~~~~~~~
olind d
Mveme0Sih"nl
0 10 20
Roe:FWuhersResearch
Infoematlon
Rspen VollaRiverAsghlwt
CompleteOilSpillReport
FormandNotrfySecretary
for FuelandPower
NotifyIndustrial
Usersof SeaWater
(Sat andPetrolieumIndusiries)
AssessSituation
by Obtaining
Detailed
fromCompetent
Information Observes
NotifyNeighbouring Countriel
if SpillPosesa Treat
ActionNecessary?l
Is Response
Response
Activate Team,
StaffSecretariats
NotifyGovernment F StandDownand
Surveillance
Maintain
Request as Deemed
Assistance Appropriate
fromSourcesOutside
theCountry
ActivateFinance
& Economic
Secretariatsfor
ProperAccounting of SpillActivities
andDocumentation
OSCAssumes OverallFieldResponsibility
for allOpeiations
Including
AssistancefromSources
Outside Ghana
Fig.5.2
Volta River Authority
Ref:Ghana 0i SpinContrigency
National Plan TakoradiThermalPlant IPUW
I
Contingency Plan IWO11
_
.3 0
~~~~~~~~~~~~~~~~~~~~~~~~~
-*x
ml..-e
V 'v...
- a.~~5
VOLTARWER mootHqI
Ia X,.
M4a X
-12 ~~~~~~~~~~~~~~~~~~~~~w*~W9.
re S
VOLTARwVR AF4OMTf
Ingestion
I of water solublecompoundsby fish and other organisms.
whichmaybe acutelyor chronicallytoxic
- deoxygenation
of water throughthe biologicaland chemicaloxygen
demandassociatedwith the weathering
of oil
Giventhepossibility
thata spillmayoccur,a goodunderstanding of present
fisheries'r.,omemust be obtained,so that in the event that a spill does
occur,therewould be a basis upon which to developa compensation
package.
- intake of water
- dischargeof heated water
- chronicoracutedischargesof toxicsubstances.
5-51
Intake of Water
At full capacity,theproposedfacilitywill utilize5.7m3fs of coolingwater.
In additionto the waterdrawnfrom the sea,largequantitiesof marine
organismswill alsobe drawnIntothe generatingfacilitywith the water.
Planktonicorganisms(phytoplankton, zooplankton), macroinvertebrates
andthe larvalstagesof fishand shellfishwillbe entrainedIn thecooling
waterflowand passedthroughthestation.Mortalityto theseorganisms
willoccurdue to mechanical effects(pressurechangesor abrasion)or
due to the effectsof a temperatureIncreaseas the organismsare
passedthroughthe condensercoolingsystem. Althougheachfacility
hasitsownuniquecharacteristics thatcontributeto entrainment mortality,
it is generallyassumedthata newfacilitywillinflict100%mortality,until
provenotherwise.
Dischargeof Heated-Water
Ascoastalwatersin tropicalareasare generallyverywarm,manyspecies
of marineorganismsare living at the upper end of their thermal
tolerance.Additionalheatdueto the dischargeof heatedeffluentscan
increasetemperaturesbeyondthermallethallimits of some species.
Fishes,being mobile can normallydetect and avoid heatedareas.
However,non-mobilespecies,such as clamsand seagrasses,cannot.
Hence,sensitivespecieswill either move out of, disappearfrom, the
heatedarea.
The other dischargeto the cooling water circuit will be from the
desalinationplant. Thiscouldamountto up to 750m3/d (<0.01m3/s).
whichis a smallamount,comparedto predictedcoolingwaterdischarge.
5-60
Criteria
The effluentsfrom the differentwaste treatmentsystems shall meet the
lollowvngcriteria prior to discharge':
- pH 6.50 to 9.0
- iron s 1.00 mg/L
- chromiumhexavelant s0.05 mg/L
- chromiumtotal s0.50 mg/L
- copper s Q.50 mg/L
- nickel s 0.50 mg/L
- zinc s 0.50 mglL
- total suspended solids (TSS) s25.00 mg/L
- oil and grease s 5.00 mglL
- total residual chlorine (TRC) 0.20 mg/L
- biochemicaloxygen demand (BODO) s20.00 mg/L
Runoff from the site may discharge contaminantsinto the feeder stream to the
AnankwariRiverand increasethe rate of discharge. As discussedin the construction
phase, a site drainage plan will be developed. Site runoff will first be collected in
Relerence
Environmental
Codesd Pracdce
forSteam
Electrical
Power
Generation.
Environment
Canada,
1986
5-62
5.2.2.5 SocloculturalConcerns
Revised
August24. 1993.
6-2
an adequate supply of cooling water, Ihe site is generally flat and accessible and It
requires no resettlementof the local population.
An SPM at this depth will also accommodatevessels of less capacity and draft,
increasingthe flexibilityof supply options. Smaller tankerscould provide full capacity
deliveries,whereaslarger tankerswould dischargeonly a portion of their total capacity.
August24,1993.
Revised
7 Mitigation Plan
Ii;
7 Mitigation Plan
TheTakoradiThermalPlantwillhaveoverallpositivebenefitsto thecountryas a whole.
Locelly,thecitizensof Aboadzewillhaveimprovedaccessto thelargertowns,andsome
new employmentopportunities will be available,especiallyfor skilledtradesmenfrom
Sekondi-Takoradi, andlabourersfromthelocalarea.Thereare,however,somenegative
impactspredicted,but with carefulmitigation,thesecan be minimized.Thissection
discussesthe mitigativerequirements of the projectand providesa preliminarycost
estimatefor thosemeasures.
- air emissions
- effects to marine environment
- social requirements.
Construction Phase
Potential Effects and Proposed Mitigation
Site Clearing, Grading, Lossof agriculturallands Compensate for crop boss. Ens;re coconutplantationalongcoastalstripis not affected. MIll previous
Railsinglo General sandextractionateain the beachridge, replantwithhybridcoconut. Fenceof this areaso no access
Elevatlonof 3.5 m providedfromsite. Preservealloil and coconutpalmselsewhere wherevetleasible. 1fpossible
providealternativelandarrangements to thosewho lostlanddue to projectsiting.
Lossof trees Minimizeall treecutting. No treesto be cul that do not interferevith the worksandthoseretained
fencedto preventconstructionequipmentdamage.Oflerany useablewood for fuelpurposesto local
population.Beforecuttingtrees,shouldevaluatewhethertheycan be movedandusedfor aesthetic
screeningalongplant perimeter.Replantwithfruit andshadeIfees.
with naturaldrainage
Inteilerence Unavoidableto changedrainage. Finalgradeto facfliatedrainageandavoidfloodingand ponding.
of site Sitedrainageplanlo be developedthat ensuresminimalsoil erosion,excludeshazardsto personsor
duringstormflaro. Watercolkcted by site drainswill be
damageto propertyand land particularly
dischargedthroughsump/settlingbasinto teducevelocityand sedimentload,into watercourse to west
of site.
with buriedservices
Interference No buriedservicesat the site; no mitigationrequired.
7
;Activity i; Predlited Effecs* Mitigatlon Plan
Interference
to local population SomeInconvenience
Is unavoidable,roadto remainopenduringconstruction.Obtainpermissionfrom
duringconstructionof road GhanaHighwayAuthorityto upgraderoad.
Interference
with naturaldrainage Culvertslo be designedto accommodate
flood flowor permittoppingof road- flood watersarenot to
be backedup by road.
Interference
with buriedservices All servicesare to be located,if necessary,movedandtheir continuedoperationensured.
Soiland watercontamination
from Everyprecautionto be takento preventspills. Fueltanksto be enclsed in animpermeableberm.the
spills holdingcapacityof whichmustexceedthe volumeof the largesttank. Thebermedareamusthavea
sumppump or methodof watet removal.Watermustfirst haveanyoil remorved belorebeing
dischargedoff site. Spillandemeigencyresponseplanto be developedand in placepriorto
commencement ot consiruction.
9 Aggregate Sources Pressureon existingresources No new pitswill needto be opened;existingquarrieswill be used. Studyto detetmined existing
quariieshavesufficientreserves
to meetfequirements andnot to depletereserves to detrimentof local
community.If negativeimpact,alternatesourcingto be examined.
10 Batch Plant/ Noise,dust concerns,runoff Runofffromplantto go throughsettlingbasins;noisemustbe controledso thati does not exceed55
Concrelb and problems, dBA at boundaryof works. Dustbags to be installedif necessary.
Asphalt
11 Construction Work Influxof workersIromother areas Influxof workersnot anticipatedto exceed100andtheywil be housedin the Sekondi-Takoradi
aea.
Force hopingto findemploymenl, Employees to be bussedfromresidencesto site.
producingsquattersin
neighbouringarea.
Pressuresput on local social Projectto provideown first aid clinic. Majoritycf the work forcewil be derivedfromlcal communriies,
structures- schools,health andwill liveat homethereforepressureIrornin-moversshouldbe mrinimal.
services,housing.etc
12 Delivery
of MeatIals Increasedtrafficflow on Aboadze- Upgradeof roadto be designedto lake existingand increasedtrafficflowexpectedto be a positive
Inchabanroadcausingdisruption effectto localpopulation.Dustfromtiuck movementeliminaledby useof tarredroad. Trucksshould
to use by local community be tarpedwhen catryingload. Sometemporarydisruptionwil occurwhenlargecomponentsare
I I delivered.Speedscontrolledto reducepotentialfor pedestrianandvehicleaccidents.
Table 7.1
Construction Phase
PotentialEffectsand ProposedMitigation- 4
13 Waste DiOposal
* SolidWaste Sourceof pollutionand health An engineeredlandfillsite to be developedawayfromlw coastalweas (possiblyuse borrowpit area).
concerns only nonbiodegradable materiallo be landrined.Recycleand reuseas muchas possible. Ste should
not be closeto residences.To minimizeodouranddiseasethe ste shouldbe coveredregulalyby
inertfill. No contaminated runoffto groundor surfacewatercoursesto be allowed.
* LiquidWaste Contamination
of surfaceand Sewagetreatmentfacilityto be a priorityitemin constructionschedule.No dkectdischargeof iqidd
groundwater wastewill be allowed.
Interference
to fishermen Construction
shouldbe scheduledto avoidthe upwellingperiod.
Interference
to coastalnavigation All barges,buoys,etc, to be clearlymarkedandilluminatedat night. Notification
of andpermission
Iromnavaland port authoritiesin Sekondifor marinework.
- RockExcavation Sedimentreleasefromexcavation Intakeandoutfallmustbeconstructedby tunnellingratherthanopencutexcavion to minimize
sedimentreleaseandelfectto fisheries.
Excessive
dust andnoiselevels Dustand noiselevelsat plantperimeterto be monitored.Dustcollectorsand noiseshieldingto be
fromventilationexhaustsystem usedif required.
15 Site RehabIlIatllon Poorimplementationcouldresult Topsoilspreadout, gradedand seeded. Treeplantingto screenshe. Any borrowareas/disposal
areas
In erosionandaesthetically gradedendrevegetaledto preventlong-termerosion.Accessroadgradingandseedingas required.
displeasingsite Generalgood housekeeping to be maintainedthroughconstruction
phase.
Settlingbasinsprovidemosquito Basinsmustbe decommissioned
follwing construction.
breedinggrounds
Table7.2
OperationPhase
PredictedEffectsand ProposedMitigation
I Burning Fuel Burningof oil for CTU increases Air emissionsto be strictlymonitored.Emissionsnot to exceedWorldBankguidelines.Ii
theemissionof S02,NO, CO, levelsare higherplant operationsadjustedto meetemissionrequirements.Ambient
and particulalematterwhichcan conditionsaroundthe plantare lo be monitoredandtheymustmeetthe conditionsgiver.
adverselyaffecthealth,vegetation, in Table2.1. Choiceof luel to minimizethe emissionof noxiousgases. Alternativefuels
buildings,etc. withhighersulphurcontentsnot to be used. Oil burnerslo befitledwithwaterinjectionto
controlNO1 emissions.
Excessive
noisefromstack Silencersto be placedon stackssuchthal noiselevelsbeyondthe plant fm6nce
line do
emissions not exceed55 dBA.
Excessive
noisefromair intake Fanslo be surroundedby acousticalbarriersas necessary
suchthat noiselevelsbeyond
fans the plant'sfencelinedoesnot exceed55 dBA.
- Delivery Possibletankeraccidentloilspill Onlya - 7 delivetiesof oil peryearto the site. Verysmallincreasein riskof accidentthan
on routeto site presentlyin Gulf of Guinea
* Unloadingof oil at Oil spill duringdisconnect Oil deliveryshouldbe dedicatedto onefirmor onetanker--their contractshouldbe
SPM conditionalon the safedeliveryof oil andno spillageis to occurduringthe drsconnect.
10 Aesthetic
* Intrusionof plant Aesthetically
displeasing Somedisruptionto viewunavoidable.Plantset backfromcoasl with coconutplantation
appearance,disturbanceto to act as screen. Areabermedand treesplantedto furtherreducevisibleintrusioninto
potentialtouristappealof landscape.
coastline
7-9
Location of Intake
Theintakemustbe locatedupstreamof the RaoniandSherbiobanksandinsidethe
10-mcontour. Theintakewill be fittedwith a velocitycap,and raisedoff the sea
bed. Buoys shall be placed to indicatethe locationof the intake. Detailed
preconstruction marineinvestigations
willbe requiredto selectanintakelocationthat
does not inflict undueimpacts.Thesestudieswill includephysicaland biological
components.
7-10
The outtall shall extenda minimumof 1500m from shore. Cost of the outfall
constructionis approximatelyUS$14.5M, whichincludesprovisionof the nozzle.
Thefield investigationsrequiredto selectan appropriatedischargelocationwill be
undertakenat the sametimeas the intakesite selectionstudies.
- sorbents/dispersants
tocollect/disperse
oiloutsideboomenclosure
to acceptable
levels.
- theprocedures fornotifyingthespillresponsecoordinator
and teammembers
of
oil spillsand release
- recordkeepingand reportingrequirements
The oil spill responseand contingencyplan developedby VRA for the Initial
responsesshoulddescribehowthatplanIs to be Integrated intotheGhanaNOSCP.
To facilitatethis Integration,
theproceduresInVRAresponseplanand the NOSCP
should,to the extentpossible,be consistent. In the NOSCP,spill containment
followedby the recoveryand removalof the materialis the preferredapproach.
NOSCPsuggests,however,thatthe useof chemicaldispersants maybe necessary
In some situations. Chemicaldispersantshavethe potentialto spreadthe toxic
componentsol oilwhilehelpingto break-upa spill Thisdispersalmayincreasethe
potentialfor thebiologicalexposureto thetoxiccomponentsof oil. Therefore,VRA
shouldminimizethe use of chemicaldispersantsin spill responses.The NOSCP
recommends the use uf natural,locally-occurring
materialsas adsorbents.to the
greatestextentpossible. TheVRAplan should seek to implementthis NOSCP
recommendation.
WasteTreatmentSystems
Initially,all wastewaterwillbe dischargedthroughonepipeintoa feederstreamof
the AnankwariRiverjust westof the proposedsite. The effluentat the point of
dischargewill be monitoredon a continuousbasis. All waterwill be treatedpriorto
dischargeso thatit meetstherequirements asoutlinedin Section5.2.2.3.Oncethe
coolingwatersystemis in operation, wastewaterwili be directedthroughthe ouffall
pipe. Effluentmonitoringwillstill be undertaken.
7-14
Loss of Land
The land ownershipand land tenuresystemin Ghanais such that the persons
activelyfarmingthe landat thepresenttimeare not the ownersandwill receiveno
or verylittlecompensationfor their loss.otherthan the valueof the currentyear's
crop.
Loss of Fisheries
As yet, this isan unknownfactor. it is not anticipatedthat therewill be a major
changein thefishery. However,monitoringis required(seeSection9). If catches
in the immediate fishingareasdecrease,butthereis no similartrendalongthe rest
of the coast,thenthe fishermenshouldbe compensated for theirlossof catch,if the
loss is attributedto the project.
Influx of Non-LocalWorkers
It is expectedthat most of the constructionwork force will be from the Sekondi-
Takoradiarea,whiletheremainder willbe fromotherpartsof Ghana.Mostof the in-
moverswill residein Sekondi-Takoradi, althoughsome maytake up residencein
Aboadzeor Aboesi. It is not anticipatedthat in-moverswill put excessivepressure
on the existingsocialservices. The supervisory staff will not be localand will be
housedin a newtownsite.A schoolandclinicwill be providedif SekondiVTakoradi
servicesareinsufficient.
- air emissions
7-15
It is recommended
that a p.ovisionalsumbe set asidefor the first 3 yearsof operation
to addresspotentialcommunityimpacts. After this time, the situationshould be
reassessedandan actionplandevelopedas requiredfor futureoperations.
A detailedenvironmental
management
and trainingprogramme
mustbe developed.
GeneralInformation
General understandingof concept of sustainabilityand reasonsfor sound
environmental
management.
Understanding
of potentialenvironmental
impactsthatcan be expectedfromthetwo
mainphasesof the powerplantdevelopment
- construction
- operation.
Reasonsfor mitigationmeasuresproposed.
Establishingchainof responsibility
and decision-making.
8-2
Specific Training
Air-and water-quality
monitoring
Procedures
for off loadingoil,specifically
to eliminatespillageduringplantoperation.
Healthandsafetyrequirements.
Noisemonitoring.
Goodhousekeeping.
A tentativelistof procedures
Is providedbelow.
Healthand SafetyProcedures
- administrationand organization
- project emergencypractices
- tunnel rescue
- work over or near water
- first aid and medical services
- control measures
- safety officer
- site security
- safety tagging and lock out
- trainingand orientation
- accidentinvestigation,
reportingand recordkeeping
- workplacehazardousmaterialinformationsystem(WHMIS)
- specific safety requirements
- confined space entry
undergroundworkings
- blasting operations
- employer safetyprogramme
- project healthand safety committees
- use of personal protectiveequipment
- personal decontaminationpractices.
EnvironmentalProcedures
- noise and vibration plan
- contacting outside agencies
- handling,storage,and disposalof fuelsandhazardousmaterials
- site aestheticsand restoration
- site drainage,dewatering.erosionandsedimentcontrol
- blasting procedures
- waste managementplan
- dust control
- spill responseplan
- water monitoring
- air monitoring
8-4
- communityrelations
- environmentalinspection
- oil handling plan.
9 Monitoring Plan
9 Monitoring Plan
9.1 Preconstruction
9.1.1 Air
- one control site, upwind and to the west of the project area
- one located near the village of Aboadze
- one furtherdownwindof the projectarea (eastnortheast)In the vicinityof Aboesi.
9.1.2 Noise
- at the settlementon the beach ridge just beyondthe SW corner of the project
site area.
At each location,noise will be monitoredfor 8 hours, once during the day and once
during the night and this will be repeatedthree times prior to construction.
9-3
The off-shore temperatureregime will be measuredat the same t,rne that current
measurementsare taken.
Diving,netting,orothermeansof samplecollectionwillbeemployed(asapproptiate)
to collectsubtidalsamples.
9.1.3.3 Oil
9.1.5 SocioculturalEnvironment
9.1.5.1 Fisheries
9.2 ConstructionMonitoring
The followingparameters
are to be monitoredduringtheconstructionperiod.
9.2.1 Air
Inorderto meetthespecifications
forfreshwaterdischargefromconstruction settling
basinsto thefeederstreamof theAnankwari River,it is necessarythatthe discharge
is monitoredon a weeklybasisfor the parameters identifiedon page5-31.
9.3 Operations
Thefollowingparameters areto be monitoredduringtheoperational phaseof theproject.
As the constructionandoperationof the plantis phasedto takeplaceovera numberof
years,operationalmonitoringprogrammes havebeendesignedto monitorvariouskey
events.
9.7
9.3.1 Air
In addition,thefluegas characteristics
of eachCTGwillbe determinedon a regular
basis over a period of 1 yearalter commencement of operationto ensurethat
emissionperformance criteriaaremet.
9.3.2 Noise
9.3.3 Agriculture
Theoperationalmonitoring
programme is designedto assessthe impactsof station
operationon themarineenvironment.Theprogrammes are phasedto evaluatethe
stagesof implementation
and thefinalinstalledcapacityof theplant.
9.3.4.1 PhysicalParameters
Thermalplumedelineationstudiesarerequiredfor normalonesteamunitoperation.
It is recommendedthat dyes or droguesbe employedto definethe extentand
9-8
A specificstudyshouldbe undertakendownstream
of the diffuserto delineatethe
area impactedby the plume. This study could be undertakenby diving,
supplemented with intensivesampling.
9.3.4.3 Oil
9.3.5 SocioculturalEnvironment
9.3.5.1 Fisheries
If complaintsare receivedfromlocalfishermenregardingdecreasingcatchesafter
the station is in operation.a surveysimilarto that outlinedin Section9.1.4.1is
recommended.
9.3.5.2 Agriculture
Thefollowingliststhecontactsmadewithgovernment
agenciesand thepublic.Minutes
of thesemeetingsare providedin AppendixD.
10.1 InteragencyContacts
10.1.1 CentralGovernment
Contacts
Ministryof EnvironmentEnvironmental
Protection
Council
- Mr. J. K. Dansoand Mr. D. S. Amialo,June22. 1993
(NationalOil SpillContingencyPlan,1985)
- Mr. D. S. Amlalo,EPC,June 21, 1993. Mr. Amlalowas involvedwith the
preparationof the existingplan:updateforthcomingin nearfuture.
Departmentof GameandWildlife
- Mr. N. K. Ankudey,June 22, 199
FisheriesDepartment
- Mr. M. Mensah. Director- June 25, 1993
- Ms. E.Annang,June21, 1993,DeputyDirectory.
(Researchand UtilizationBranch)
- Mr. K. E. Koranteng,FisheriesResearchOfficer - June 21, 1993
10.1.2 WesternRegion
RegionalEconomicand PlanningGroup(Sekondi-Takoradi)
- Mr. A. Arthur, Planner,June 23, 1993
10-2
RegionalAgricultureOffice(Sekondi-Takoradi)
- Mr. E. D. Arkhurst,Director,June23 and24, 1993
- Mr.J. Osel,RegionalDeputyExtensionOfficer,June23, 1993
* Mr.V. Agadjie,AgriculturalDevelopment Officer,June23, 1993
- Mr. l. Longdon,AgriculturalExtension Agent.June24, 1993
Services
RegionalFisheriesOfficer(Sekondi-Takoradi)
- Mr. A. Addo. June 22, 1993
RegionalHealthOlfice(Sekondi-Takoradi)
- June23. 1993
- Dr. E. Hanson. Director
ShamaAhantaDistrictFisheriesOfficers
- Mr. Opoku,DistrictFisheryOfficer.June23, 1993
- Mr. Asselua.Recorder.Shama,June 23,1993
TouristBoard
- Mr. Oppong,RegionalManager.June24. 1993
Instituteof AquaticBiology
- Dr. C. Biney - June 22,1993
Universityof Ghana
- Dr. Yaa Ntiamoa-Baidu.June 24. 1993
- Mr. C. Gordon
Universityof CapeCoast
- Dr. John Blay. Jr. - June 24, 1993
VRA held a meetingwith the Chief (Landowners) and the people of Aboadzeon
January29, 1993. Minutesof that meetngareincludedin AppendixD. TheChiefand
his eldersindicatedthat therewas a lot of speculationas to what the landwas to be
usedforand howthelocalinhabitants wouldbe affected.Theywantfaircompensation
paidpromptlyfor any landexpropriated.
10-3
- KVIP(place of convenience)
- cold storage
- clinic
- post oflice
- resurfacingthe road
- constructionof a communitycentre.
Ongoing discussions between VRA and the Chief of Shama (the Paramount Chief
responsible for Aboadze) and the local families, are planned to solicit views for the
mitigation plan.
There are no NGOs currentlyoperatingin the Aboadze area. The Regional Directorof
HealthServices(WesternRegion)explainedthat both WorldVisionand CAREare present
in the region. World Vision has provided administrativesupport throughout the region
but, in particular,in the northernpart of the Region. They have helped to develop cold
storagefacilitiesand obtain vehiclesfor outreachservices. CAREhas undertakensome
preliminaryinvestigationsand studies. They are interestedin providing support at the
District level. One further NGO. Adventist DevelopmentRehabilitationAgency (ADRA)
was reported to also be presentin the Region.
11 Conclusionsand Recommendations
11 Conclusionsand Recommendations
11.1 Conclusions
The TakoradiThermalPlant will have overall benefits to the country. It will provide the
powerto meet Ghana's energyneeds in the nearfuture. Locally,citizensof Aboadzewill
haveImprovedaccessto the larger towns,and some new employmentopportunitieswill
be available,especiallyfor skilled tradesmenin the Sekondi-Takoradiarea.
1he power plant is to be prefabricated,and will thereforeminimize the need for a large
constructionlabourforce and extensiveconstructionfacilities. Generally,on site activities
will be directed to site preparation, plant assembly, and installation of utilities and
services. The plant will use equipment designed with availableproven technologyand
as such, will reduce many of the potentialimpacts on the environment. Provisionof a
desalinationplant will ensure that there is sufficient water for control of NOx emissions
and also provide a reliable fresh water supply for other operational requirements. By
carefulsite selectionof certainfeatures(i.e.,the locationsof the cooling waterintakeand
outfall and the SPM)it will be possible to furtherminimizeimpacts. At this time,there is
a lack of baselinedata to finalizethe environmentalinput into this site selectionprocess,
hence an extensivemonitoring plan has been outlined to gather the requiredbaseline
data, as well as fulfil long-termmonitoringneeds. The plan also indicatesthe appropriate
time frame during which this monitoringmust be undertaken.
- air emissions
- loss of agricultural land at the proposed power plant location and along the
transmissioncorridor
newtownsitefor up to R5permanentfamilies.
11.2 Recommendations
The programme
wouldincorporate
- threeinterimreports
- on completionbf construction
- oneyearafterthefirst unit comeson line
- oneyearafterall units areoperational
11.2.2 CommunityImpactAgreement
and Local Citizens'Committee
DesalinatlonPlant
The desalinationplant is the major,and most expensive,mitigationmeasure
proposed.Theplantis requiredto ensurethatthereis sufficientwaterfor control
of NOxemissionsto the atmosphere.Withoutcontrol,NO. emissionscould
exceedtheWorldBank'scriteriaby morethanthreefold.
reliablewater supply of lls own. Thus, it will not impose undue pressureon the
potable waler supply to the existing local communities,although the connection
will be maintainedto the municipal supply. It reduces water chlorination and
demineralizationsystem requirements,although some additional storage and
handling of chemicalsmay be associated with the systems.
Land Loss
The land at the proposedsite and along some of the transmissioncorridor Is
farmed mainly for subsistence requirements. It would be prelerable If
replacementland could be located for these farmersratherthan a one-timecash
payment. VRA should contact other landowners/titleholders in the immediate
area and ensure that replacementland is available.
Ol Spill Response
As there is no dedicatedoil spill responseteam or oil recoveryequipment existing
in Ghana, it is recommendedthat VRA, purchase and maintain, a tug-style oil
responsevessel. To minimizeoil spills at the SPM, especiallyat disconnect, it
is recommendedthat a dedicatedvesselor companybe usedfor all oil deliveries,
stipulatingthat their contractis dependent upon the safe deliveryof oil, and that
they will be directly liablefDr clean-up costs and environmentaldamages from
spilled oil.
Aquatic Requirements
Furthermarine investigationsare required to select appropriatelocations for he
intake and dischargeportalsand the SPM. The intakeand dischargestudies will
require a 12 month period and must be completed prior to the start of
construction of those facilities (January 1995, if both contracts awarded
simultaneously).The SPMsite selectionstudy will be of shorter duration, being
required prior to contract award in August 1994.
Fisheries
Although it is not anticipatedthat there will be a major change in the fisheries,
it is recommendedthat the fish catch be monitored. If the catch in the immediate
area decreasesbut there is no similartrend along the coast, then compensation
for catch loss may be required.
11-5
The stack height for the CTG units should not be less than 40 m to ensure that
ground level ambientair quality Is minimallyImpacted, particularlyby SO2 .
At no time should oil with greaterthan 0.2"% sulphur content be used to fire the
plant,or that the plant be operatedwithoutitsemissioncontrolequipmentfunctional.
11.2.5 Training
AcresInternational
Umited.1985.Ghana GenerationPlanningStudy. Preparedfor
the Republicof Ghana,VoltaRiverAuthority.
AfricanDevelopment
Bank.1990. EnvironmentalPolicy Paper.
Biney,C. A., 1982. Preliminary Survey of the State of Pollution of the Coastal
Environmentof Ghana. Oceanologica Acta,pp 39 - 43.
Biologyof the
onthe Reproductive
Blay,J. Jr. andK. N.Eyeson,1982.Observatlon
Ethmalosafimbriata (Bowdich),In the CoastalWatersof ape Coast,Ghana. S.
Fish Biol. pp 21:485 - 496.
Crow,A. T.. 1952.The Rocks of the SekondiSeries of the Gold Coast. GoldCoast
GeologicalSurveyBulletinNo.18.
FoodandAgricultureOrganization
of theUnitedNations,1991.AfricanFisheriesand
the Environment.RegionalOfficefor Africa,Accra.RAFRJ91/02.
GhanaNationalOil SpillContingencyPlan,(GNOSCP.
ND).no date.
Gullard,J. A. (ed), 1971. The Fish Resources of the Ocean. preparedfor FAO.
WhitefriarsPress.London.
Bibliography
-3
Ntiamoa-Baidu,
Y.,1991.SeasonalChangesInthe Importanceof CoastalWetlands
In Ghanafor Wading Birds. BiologicalConservation
57, pp 139- 158
Ofori-Adu,D. W., 1988. Ust of Fishes, Shellfishes and Other Marine Food
ResourcesIn the GhanalanCoastalWaters. MarineFisheriesResearchTechnical
PaperNo.1. FisheriesDepartment,
Tema.
Portmann.J. F., C. Biney. A. C. Ibe. and S. Zabi. 1989. State of the Marine
Environment In the West and CentralAfrican Region.UNEPRegionalSeasReports
and StudiesNo.108.
ShamaAhantaEast MetropolitanAuthorityDevelopmentPlanningCommittee,1992.
of Health,WesternRegion.
Annual ReporL RegionalDirector-Ministry
PlanningCommittee,1992.
ShamaAhantaEast MetropolitanAuthorityDevelopment
Seven-YearDevelopmentPlan, Agricuitural Component. Ministryof Agriculture,
WesternRegion.
Studyof TakoradiThermalPlantEnvirons.
VoltaRiverAuthority,1993. Socioeconomic
RealEstateDepartment.
1993.Developmentof ProgrammeStrategies
HealthAdministration,
WesternRegional
1994. Presentedat the RegionalDirectorsConference,July 1993.
Number Title
Number Title
I.Ae 4 [163 fi 34 11 4
lsnwv..... 111 inI so3 3 9S1 I3 ii 3I 1 3 4 5 lIQ Is I 2 5 3to 3 3 4 3 S S
ManL......10100 jil 23 31 21 9' 13S 4 0 59 4 3364 5921914 23 1 313 6 Ia z ou
A.I ...... 10103 2I3 33 22 9117351 10 11311I 4 I61623 is3 2 43is43133 I
XV...... lol 29 23 3! 2941 SI 336
1$0 14 415 I10a 1 5is
a 314 530396333 II
.......101323
Na 23 3v 219 so13116 111 56 451 it 1 621111
aJo 23 3344113to IOa
Il.....1014217
I
Z 23 19 9!179 ,6 U 6 3I4 i 19 to 59 a3 a 3I3S4333oI2II3t 90 3
It
S~ptn~4a....0l31 3a 2' 20 95P an 16 413 l US 6 '10 Is s 1,2 I 03 153o 43 I Is33 2
tOll 23 fl 31~~~5
2336 95 333 II II 4 3 3 4 I 30 34 23 2 3 2 3~li 29 4 S I I I 10 0 1
1I I
Not-trAb.. 303,
10113.....
1I I oU m
l3o
0
1oi 23 3 33
2 1 23 94
219 Qf 73U4 4 3 I 77
0 3130 5344561134
4 4 6 3 317 21 2I 3 0
a16 S431 3 2 I I3
2
'(I',bq
Toids.........lbcs U… ---
1i-
o3
Obuns....qiew.... I0I I IK fCP1 11 8 2 I I
Ewem.v,l un. - - - -3z -6- -
egh ~*v
*Ietnlof h4Lheel Ihuc taiidmpuvaiuus. *13tmr.
3gaq
91l= o3am to h p1. ILw,i uided wtvmeitwet. eAlsobwrvanuem.
NJK ftwhdrA
.ini 1...
Table A1.2
23 ir 24 ijU!,I I :9
31.* 3 i . ti a
u 01I 515 ,
0.0OS) . 9) 3
tx . U(2 u:
- - 09
E -'
Table A1.3
Jan Fab Mar Apr May Jun Jul Aug Sep Oct Nov Deo Y"r
PrevailingWind Direction
SW SW SW SW S S SW SW SW SW S S 1961 90
S SW SW SW SW SW SW SW SW SW S S 1989
SW SW Sw SW SW s SW SW SW SW SW Sw 1990
SW SW SW SW SW S SW SW SW SW S S 1991
SW SW SW SW S SW SW SW SW SW S S 1992
S SW SW SW SW SW 1993
AverageMaximumTemperature('C)
30.8 31.3 31.5 31.3 30.6 28.9 27.9 26.4 27.9 29.1 30.4 30.6 1961 90
31.0 32.3 32.1 31.7 312 29.4 28.9 27.9 28.3 29.5 31.8 31.4 1989
31.3 31.8 32.5 31.8 31.3 29.8 27.6 27.4 28.6 30.0 31.1 31.0 1990
31.6 31.6 31.9 30.8 30.8 30.1 28.5 27.2 28.5 28.6 30.1 30.7 1991
31.4 32.4 31.7 31.8 30.7 28.7 27.2 27.4 27.8 29.3 30.3 31.0 1992
31.1 31.3 31.2 31.7 31.1 29.1 1993
23.6 23.2 23.5 23.8 23.5 23.1 22.4 22.0 22.2 22.5 22.8 22.5 1961-90
20.9 23.6 23.7 24.1 23.7 23.4 23.1 22.1 22.3 22.8 23.7 23.2 1989
23.2 22.8 24.9 24.2 24.0 24.0 22.2 22.0 22.9 23.2 23.5 -22.8 1990
23.3 24.0 24.3 23.6 23.8 23.9 22.5 22.2 23.1 22.3 22.9 23.1 1991
21.3 23.9 24.6 24.7 23.9 23.2 21.4 21.5 22.4 23.0 22.9 232 1992
21.7 24.0 23.4 23.9 24.5 23.5 1993
2.4 3.1 3.3 2.9 2.5 3.1 3.3 3.1 3.5 3.4 2.9 2.3 1951- s
1.9 3.5 4.5 4.1 3.5 3.3 3.5 4.4 4.3 3.9 3.0 2.2 1989
2.8 3.2 3.0 4.3 3.5 4.4 3.9 4.2 4.9 42 32 2.5 1990
al 4.1 3.9 2.7 3.3 3.9 4.2 4.3 4.0 4.0 3.1 2.1 1991
2.8 3.8 4.1 3.1 3.8 3.6 3.8 4.8 4.4 4.6 2.9 2.4 1992
2.5 4.0 3.2 3.4 2.6 32 1993
41 36 44 49 40 40 31 0 23 34 46 36 1961-93
Table A1.4
Hourly Readings
Time 1101/92 1/02/92 1/03/192 1/04/92 1/05/92 1/06/92 1/07/192
(GMT) WDf WS WD WS WO WS WO WS WD WS WD WS WD WS
(knots)
00 C 0 C 0 C 0 C 0 C 0 030 4 070 4
01 X X X X X X X X X X C 0 C 0
02 X X X X X X X X X X X X X X
03 X X X X X X X X X X X X X X
04 X X X X 340 2 X X X X X X X X
05 X X X X 360 X X X X X X X C 0
06 300 2 X X X X X X X X X X 040 2
07 C 0 X X X X X X X X X X C 0
08 340 4 X X 040 4 X X X X C 0 X X
09 320 X X X X X 360 3 X X 050 4 X X
10 X 6 X X X 11 060 5 050 10 020 8 350 6
11 X 8 170 5 060 X X 12 060 040 X 030 X
12 X 5 140 2 X X 090 X 090 12 080 X 080 8
13 300 4 X 4 090 14 X 16 080 10 090 X 090 X
14 160 5 180 6 070 12 X 12 090 X 080 12 080 12
15 190 4 160 4 X X X 10 808 X X X 090 X
16 X 6 200 4 080 8 060 4 090 X 070 X 080 8
17 X X 170 X 050 5 050 6 X 8 X 10 X 4
i8 X 4 C 0 X 8 090 2 X 5 050 X X 2
19 230 X X X X X 080 X 070 6 070 7 C 0
20 250 5 X X X X C 0 0509 080 6 X X
21 230 X X X 060 6 X X 070 10 X 7 X X
22 C 0 X X 020 4 X X 3950 2 X X X X
23 X X X X C 0 X X 050 4 X 5 X X
C Calm
Table A1.4
/F ~~~~~PERCENTAGE A
/r429SP ~SURFACE
WIND FREQUENCY N
/ Z/ ~~~~~TAKORADI %
__ _ > OF OBSERVATIONS
SCALSANDNUMBER
\ };!t5t
\ ~~~TOTAL
1tMR OF MSYWV TIONS
~~~~~~~IUIl 11\1
Fee -T Frc. * r~ T F. a r- 7
Sco% or Percentoges
* O * @12 isDt 24 to 32 n do Ad 4 SR so
*so
e G#
\< , ~~~ ~~~MAR.
TOLAL
(31AND 4R
0) 59-11 OF ORSSRVATIONS
SEP. (300) 4861-7 030 G M TT.11111W
0300Feuc
\ \\ ~JUNE
(300) 470O DEC(31 0) 74-21 /
\S on/ATn
~~~~~~~~NW*
_ _ _ MAR. (310) 59 1
a EP..c.nt 48g.,
SURFASurfaceWiQUNdCYoaiThra ln
Scat* or Powc9rotaog-
O *= *t Is Ito 2 to 1X X. s 40 4- St 14 so
Fig.Al 2
Voka RiverAuthorky
ThermalPlantm
Takoradi l
SurFaceWind Frequency, 0300 G.M.T. lW
PERCENTAGE %
/ W - ~~SURFACE
WIND FREQUENCY P \
/ / ~~~~~TAKORADI \
/ |^} ~~~~~0600
G.M.T. ^'
.CALMS
AD NUMBER
OF OSERVATIOM
/~~~~~~~~
Scale of Percentages
0 * U 11 is 10 24 to 12 16 40 44 48 St is g0
Fig. A1.3
Volta River Authority
Takoradi Thermal Plant
SurfaceWind Frequency,0600 G.M.T. H I
/ / / ~~~~SURFACE WIND FREQUENCY
/ // / /j ~~~~TAKORADI \
_5
. F. 4 F.0900
&T. U \
O _= _
5 o CALMlS AND NUBMREOF OSERVATIONS
_~~~~~~~~~cl
F at rufi g
'!<~~~~~~~~~~~s
Scaeb of Percnteg-s
aa 1ist so*2 sA i as at so so
Fi. A1.4
VoltaRiverr=lhlor
TakoradiThermalPlant
Surface Wind Frequency, 0900 G.M.T.Jn
w ~~~PERCENTAGE '
/ > t ~-
SURFACEWIND FREQUENCY e
TAKORADI
1200 GM.T.
CALMSANDNUMBER
OF OBSERVATIONS
ScleT or Pc Plentato
a a 9 12 of 20 Sr t W in
sen 4 se StM 1
o0 0
Fig.A1.5
Volta River Authority.
Takordi Thenna Plant 1
SurfaceWind Frequency,1200G.M.T.iR
/, ~~PERCENTAGE q
< > ~~SURFACE
WIND FREQUENCY %
TAKORADI
1500 GMT.
Scale or Percentages
0 o _2 so s 24 13 11 3 40 Ad as 12 so 60
Fig. A1.6
Volta River Authority
TakoradiThenmalPlant I![ I
SurfaceWind Frequency,1500G.M.T. HE
~~~~~~~.A. . j .5..0....N
/_ ~~~PERCENTAGE \
><
t} SURFACEWIND FREQUENCYX
/S ~~~~~~AT \
TAKORADI
1800 GMT,
Scale of Percentages
o 4 5 32 is t0 ad &I 32 34 4o 44 a3 s2 1t o
Fig. A1.7
VoltaRiver Authority
Takoradi Thermal Plant i
SurfaceWind Frequency,1800 G.M.T. HNlU_
N~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Z tis ~~PERCENTAGE'
/@tw ~SURFACE
WIND FREQUENCY^
F ~~~~~~AT \
TAKORADI
2100 GA.T.
Scale oe PercenLages
o 4 I2 lgo No id St 22 U do 44 3 2 4 so
A1.8
Fig.
VoftaRiver Authority
Thor=mSPlantII!
Takoradi
2100G.M.T. nunw
SurfaceWindFrequency,
Appendix A
2 - Hydrologicand Water Quality Data
Table A2.1
1955 43.19 40.56 107.99 113.74 197.39 423.34 480.77 269.27 172.22 418.21 422.74 192.13 240.13
19S6 65.06 43.02 117.84 171.34 192.04 482.47 177.88 36.62 73.21 275.45 215.83 104.47 162.98
1957 27.70 10,31 21.33 63.10 101.19 419.88 718.23 227.70 266.27 485.33 409.63 266.89 251.30
1908 79.10 49.84 63.95 85.84 303.85 544.44 169.33 166053 157.92 260.63 262.31 223.17 197.24
1959 155.90 115.77 176.21 226.54 607.82 538.90 810.71 350.50 323.17 692.18 659.84 362.76 410.33
1960 71.45 48.31 78.62 241.63 142.93 338.80 337.30 182.72 146.05 510.82 407.65 118.86 216.76
196) 56.90 20.53 12.52 97.34 78.87 430.30 618.85 294.00 184.74 398.10 216.71 99.77 206.71
1982 46.76 13.14 64.66 95.98 228.65 647.15 731.89 471.28 124.64 367.83 396.53 271.25 288.30
1963 97.34 84.45 113.88 123.87 157.12 311.33 591.16 631.01 779.86 1040.22 459.64 182.81 381.06
1964 114.30 82.10 102.52 139.34 225.40 475.45 278.32 137.10 193.00 185.36 150.55 141.29 185.23
1965 W6.95 72.02 111.47 138.20 170.72 451.71 865.17 342.76 464.97 638.12 289.89 141.35 311.94
1968 88.78 51.40 60.72 143.50 145.66 359.44 684.51 424.44 314.19 475.42 355.37 163.66 272.28
1967 86.60 57.66 64.80 113.65 184.17 555.79 307.65 111.67 264.06 228.18 141.91 80.0)9 193.02
1966 00.55 31.41 55.99 95.44 160.32 539.34 1047.78 1134.27 1200.68 893.97 453.75 275.84 494.94
1969 - _ 135.77 177.49 295.33 409.74 391.31 220.82 185.30 198.19 383.83 127.64 202.04
1970 86.41 58.48 100.16 151.91 219.97 233.05 145.34 70.38 172.22 368.13 308.38 92.01 171.20
1971 63.83 37.61 68.62 49.38 45.20 229.85 235.37 232.77 204.28 285.76 130.95 109.63 141.10
1972 35.80 18.35 51.20 200.08 221.64 472.19 288.56 192.64 120.78 193.57 125.63 65.62 165.00
1973 42.34 17.53 17.67 66.44 56.27 162.22 138.54 177.06 345.99 280.03 188.67 64.43 129.77
1974 26.68 9.26 37.27 85.44 218.35 294.25 331.78 250.24 417.79 337.36 229.40 90.29 193.1B
1975 43.39 68.20 52.59 92.52 159.50 249.50 520.25 140.27 89.55 226.20 140.50 100.06 156.88
1976 30.87 28.18 52.70 65.47 156.22 415.29 192.61 86.43 57.89 127.33 212.26 62.82 125.66
1977 29.23 13.03 11.55 17.87 42.14 277.48 63.83 21.86 45.45 282.07 80.66 58.00 76.60
1978 11.81 4.96 23.58 118.86 218.78 525.28 102.38 56.98 133.90 210.28 152.17 57.16 134.68
1979 31.32 14.42 18.34 19.82 83.43 261.14 310.54 296.78 296.67 721.13 329.99 247.86 219.45
1980 _ - - - 218.63 362.11 246.16 317.53 275.64 486.86 - - 317.82
1981 - _ 130.95 165.48 270.63 336.31 391.31 322.77 347.95 379.35 333.16 183.21 286.11
1982 59.47 51.97 102.61 116.57 198.47 324.87 526.42 215.29 206.00 204.59 139.51 53.07 183.24
1983 _ - - - 106.43 293.68 188.90 67.71 107.05 168.37 87.57 72.06 136.50
1984 28.32 22.23 48.03 90.06 114.27 282.64 339.56 494.39 252.70 438.97 247.41 122.23 206.74
1985 74.43 40.33 55.78 133.47 137.38 210.31 341.09 358.65 432.31 306.37 200.64 103.99 203.73
1986 77.06 57.58 117.05 161.63 171.28 271.96 286.97 137.13 170.36 237.07 238.57 87.71 167.87
197? 50.35 25.28 63.07 138.23 129.76 172.10 223.05 381.88 662.42 763.30 298.83 136.09 251.86
1986 71.06 63.52 127.05 127.95 175.05 420.08 385.98 179.21 378.59 424.19 243.50 158.54 229.56
Average 60..1 1.71. 75.45 ,120.26,,180,37 374.19 395.98 264,20 281.47 397.21 271.63 139.61 222S3.
- no monihly reading
Table A2.2
InchabanRawWaterFlow' (1992)
Date Jan Feb March AprIl May June July Aug Sept Oct Nov Dec
1 9860 10420 7680 7040 3060 3080 3600 2480 5600 8550 9600 8800
2 8960 10200 8340 9460 3560 3060 3600 6600 3220 9700 8800 9600
3 8040 9820 7580 9120 3640 3560 4200 2840 4000 9600 9600 s8o0
4 8480 8480 8040 8720 3360 3360 4200 3000 3200 9600 7200 96o0
5 8720 10740 6020 8480 3360 3640 4800 1200 3200 9600 9200 9600
6 8340 9260 10040 7420 3080 3560 4200 3000 4000 9600 7200 8000
4 8040 8960 10080 8020 1120 3200 4200 4800 9600 - 8800 9600 96
8 8860 9260 9000 4740 3080 3660 3600 3000 9040 9600 7200 1300
9 8640 9400 9020 5900 2500 2840 4800 3000 4800 9830 4000 9800
10 8340 9600 9680 7A60 2960 2400 3000 3600 7200 9600 6200 10320
11 9020 6150 9600 7520 6240 4200 4200 72D0 9600 8600 10700
12 9680 10020 9600 7440 2780 4200 3000 1600 9600 9640 15400
13 9600 9820 8800 6840 3200 5400 4200 4800 7200 9800 16380
14 9300 8460 7700 6320 2620 5400 3200 5000 1600 7200 3200 15180
15 10420 10168 3940 6340 3220 5400 6600 8200 7200 9600 8S00 16560
16 10200 7620 8140 2020 3220 5400 4800 4400 9400 9700 g600 15400
17 10020 9760 9760 3500 4000 6000 4200 5600 9610 9600 15980
la 10168 11040 9020 6260 4200 5520 600 4200 5600 9600 960D 7600
19 11040 111oo 9560 8160 4800 7560 4200 9600 7200 9600 9040
20 11100 10540 9800 8240 3600 7520 6600 1600 8800 9600 11540
21 10800 10940 9600 5780 5000 5400 5400 9600 7200 6400 16800
22 9520 10380 9600 4800 5020 2400 6400 2400 9600 14000
23 9320 7560 9600 5420 5600 4800 6000 9600 7200 5600 11400
24 10460 7100 8860 5290 6680 3000 5400 7520 7200 8000 9600
25 11060 6900 4520 4940 7480 4200 4800 8400 8000 80W0 9600
26 10960 9300 4980 2000 5380 4800 4800 9000 8800 8800 11400
27 10200 6840 4980 480 5580 4800 7200 9600 7200 9600 9600
28 9300 5880 7900 4360 6000 4240 8800 9660 8800 9600 8800
29 8760 3200 5320 4240 7560 5400 9000 9760 9600 9600 9600
30 8640 8640 52.80 7200 4200 3600 9600 9600 8800
31 7900 7360 6960 2800 7 7200
TOTAL293748 258928 253060 181820 127040 132820 143000 86700 183600 272800 241640 347500
AVG 9475.7 8928.6 8i63.2 6060.7 4380.7 4427.3 4766.7 3923.5 6331.0 8800.0 8332.4 11209.7
1 mies perday
Cubirc
Table A2.2
InchabanRaw Water Flow' (1991) - 2
1 Cubicmetresperday
Table A2.3
RawWater Quality'at InchabanReservoirfor 1992
Number Parameter January April July Ocober
Date Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec
1989
1 21.50 18.11 16,30 13.10 12.30 12.40 22.20 22.20 22.40 22.30 22.25 20.80
2 21.80 18.10 16,20 13.00 12.20 12.90 22.50 22.20 22.40 22.30 22.0 20.75
3 21.40 18.90 16.10 13.10 12.10 12.80 22.50 22.20 22.40 22.30 22.20 20.70
4 21.30 18.80 16.00 13.00 12.10 12.60 22.50 22.30 22.40 22.30 22.20 2060
5 21.20 18.70 16,00 13.00 12.00 12.50 22.50 22.20 22.40 22.30 22.15 2050
6 21.10 18.60 15,90 13.80 11.90 12.40 22.50 22.30 22.40 22.30 22.15 20.40
7 21.00 18.50 15.80 14.00 11.80 14.60 22.50 22.30 22.40 22.20 22.10 20.30
8 21.10 18.40 15,70 14.10 11.70 14.60 22.40 2230 22.40 22.30 22.00 2020
9 21.00 18.30 15.50 14.01 11.60 16.20 22.30 22.30 22.40 22.30 22.15 20.10
10 20.90 18.20 15.40 14.00 11.50 16.20 22.20 22.30 2240 22.30 22.10' 2000
11 20.80 18.10 15.30 14.10 11.55 17.40 22.20 2230 22.40 22.30 22.05 20.15
12 20.80 18.00 15.20 14.00 11.60 19.80 22.10 22.20 22.40 22.25 22.00 20.10
13 20.80 18.05 15.10 13.90 11.60 22.80 22.10 22.15 2230 2230 21.95 20.15
14 20.70 17.90 15.00 13.80 12.40 22.80 22.10 22.20 22.30 22.20 21.90 2000
15 20.60 17.80 15.10 13.70 12.40 22.60 22.10 22.20 22.20 22.20 21.80 1990
16 20.50 17.60 15.00 13.60 12.30 22.50 22.10 22.20 22.30 22.75 21.75 19,85
17 20.40 17.50 14.90 13.50 12.30 22.50 22.10 22.10 2230 22.70 21.70 1980
18 20.20 17.40 14.80 13.40 12.20 22.40 22.10 22.10 2Z30 22.70 21.60 19.70
19 20,05 17.30 14.60 13.30 13.70 22.25 22.30 22.20 22.30 22.40 21.50 1960
20 20.15 17.20 14.50 13.20 13.60 22.40 22.30 22.20 22.40 22.30 21.45 19.50
21 20.1O 17.00 14.40 13.10 13.50 22.50 22.20 22.20 22.40 22.30 21.40 1940
22 20.00 17.10 14.30 13.00 13.40 22.40 22.20 2220 22.40 22.30 21.30 1930
23 19.90 17.00 14.20 13.10 13.30 22.70 22.20 2220 22.50 22.40 21.20 1920
24 19.80 16.85 14,10 13.00 13.20 2270 22.20 22.60 22.50 22.40 21.10 1905
25 19.70 16.70 14.00 12.90 13.10 2260 22.20 22.60 22.50 22.40 21.00 19.10
26 19.60 16.60 14.00 12.80 13.00 22.50 22.20 22.70 22.50 22.35 21.10 1900
27 19.50 16.50 13.90 12.80 13.10 22.40 22.20 22.70 22.40 22.30 21.05 18.85
28 19.40 16.40 13.70 12.70 12.90 22.30 22.20 22.70 22.40 22.30 21.00 18.75
29 19.30 13.50 12.60 12.80 22.50 22.20 22.60 22.30 22.30 2095 18.65
30 19.15 13,30 12.40 12.60 22.25 22.20 22.50 22.30 22.30 20.90 1850
31 19.00 13.20 12.50 22.20 22.40 22.30 18.40
Table A2.4
Inchaban Dam Levels (Rt)- 3
Date Jan Fab Mar Apr May Jun July Aug Sept Oct Nov Doe
1 990
1 18.30 15.80 13.375 10.70 8.00 3.80 6.70 5.70 3.40 1.70 6.18 5.68
2 18.20 15.70 13.275 10.60 8.10 6.70 5.70 3.20 1.70 6.20 5.59
3 18.10 15.60 13.150 10.50 8.00 5.60 5.60 3.00 1.66 6.20 5.59
4 18.00 15.50 13.200 10.45 7.90 6.60 5.60 3.10 1.58 6.20 5.50
5 18.10 15.40 13.100 10.30 7.90 3.60 6.50 5.50 3.00 2.58 6.15 5.49
6 18.00 15.30 13.000 10.15 7.80 6.30 5.50 2.90 1.60 6.12 5.40
7 17.90 15.20 13.050 10.00 7.70 6.10 5.50 2.90 1.62 6.11 5.40
a 17.80 15.20 12.900 10.10 7.60 3.40 6.30 5.40 2.85 1.61 6.56 5.45
9 17.70 15.10 12.775 9.95 7.50 6.50 5.30 2.80 1.50 6.00 5.50
10 17.60 15.00 12.575 9.80 7.40 6.70 5.20 1.40 5.95 ' 5.55
11 17.60 15.00 12.450 9.70 7.30 3.20 6.90 5.10 1.40 5.91 5.s5
12 17.40 15.10 12.300 9so 7.20 3.00 6.80 5.00 1.38 6.00 5.55
13 17.30 15.00 12.200 9.30 7.10 3.10 6.90 5.10 1.35 5.95 5.46
14 17.20 14.90 12.050 9.15 7.00 2.90 7.10 5.10 1.55 6.00 5.39
15 17.10 14.80 12.150 9.00 7.10 2.70 7.00 5.00 2.75 6.05 5.39
16 17.00 14.70 12.150 9.10 7.00 6.80 4.75 4.25 6.05 5.39
17 17.10 14.50 11.950 9.00 6.90 6.80 4.80 4.80 6.00 5.40
18 17.00 14.40 11.850 8.90 6.80 2.30 6.70 4.70 5.38 6.00 5.30
19 16.75 14.30 11.850 8.85 5.60 2.00 6.60 4.58 5.75 5.95 5.29
20 16.67 14.20 11.750 8.75 5.40 2.00 6.45 4.65 6.00 5.95 5.28
21 16.58 14.10 11.650 8.65 5.40 2.00 6.30 4.60 6.10 5.95 5.27
22 16.50 14.00 11.525 8.55 5.40 6.15 4.50 6.15 5.93 5.27
23 16.42 14.10 11.525 8.60 5.00 6.00 4.30 6.28 3.93 5.22
24 16.33 13.95 11.325 8.65 5.10 3.30 6.05 4.20 6.30 5.91 522
25 16.25 13.80 11.167 8.65 5.00 4.10 6.90 4.10 6.15 5.91 522
26 16.17 13.70 11.100 8.55 4.00 5.30 6.75 4.10 6.15 5.90 522
27 16.08 13.60 ¶1.000 8.50 4.60 6.10 6.60 4.00 8.15 5.80 5.22
28 16.00 13.50 11.000 8.40 4.45 6.30 6.90 4.50 6.15 5.70 522
29 16.08 11.100 825 4.30 6.80 3.90 6.18 5.60 522
30 16.00 10.900 8.10 4.00 6.60 6.70 3.80 2.65 6.18 5.70 522
31 15.75 10.800 3.90 6.80 3.60 5.10
Table A2.4
Inchaban Dam Levels (ft) - 4
Date Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec
1991
1 5.08 4.00 2.90 2.15 2.00 i8.60 22.50 22.35 22.40 22.15 22.35 21.10
2 5.04 4.00 2.85 2.15 2.00 18.72 22.55 22.35 22.40 22.10 22.30 21.00
3 5.00 4.00 2.85 2.15 2.00 19.40 22.90 22.35 22.35 22.05 22.30 21.00
4 4.97 4.00 2.5 2.10 2.00 19.40 22.90 22.40 22.35 22.00 22.30 20.95
5 4.93 4.00 2.85 2.10 2.00 19.35 22.85 22.40 22.35 22.00 22.30 20.90
6 4.90 4.00 2.85 2.10 2.00 19.36 22.90 22.45 22.35 21.95 22.30 20.80
7 4.88 4.00 2.80 2.10 2.00 19.25 23.00 22.50 22.35 21.90 22.30 20.70
8 4.88 4.00 2.80 2.10 2.00 19.20 23.50 22.45 22.35 22.25 22.25 20.60
9 4.86 3.11 2.80 2.10 2.00 19.15 22.80 22.45 22.35 21.80 22.20 20.50
10 4.85 3.11 2.80 2.05 2.00 19.07 22.65 22.45 22.35 21.95 2210 20.40
11 4.80 3.11 2.80 2.05 2.00 19.05 22.60 22.45 22.35 22.35 22.00 20.40
12 4.73 3.10 2.70 2.05 2.00 19.50 22.55 22.35 22.35 22.35 21.90 20.30
13 4.67 3.t0 2.70 2.05 2.00 19.50 22.55 22.35 22.25 22.35 21.85 20.25
14 . 4.55 3.90 2.70 2.05 2.00 20.00 22.60 22.35 22.35 22.35 21.75 20.20
15 4.50 3.80 2.70 2.05 2.00 21.50 22.70 22.40 22.35 22.35 21.75 20.10
18 4.45 3.70 2.60 2.05 2.00 21.30 22.90 22.40 22.35 22.35 21.70 20.00
17 4.41 3.60 2.55 2.05 2.00 21.50 22.75 22.40 22.30 22.40 21.70 19.90
18 4.41 3.60 2.50 2.00 2.00 21.60 22.60 22.40 22.30 22.40 21.60 19.80
19 4.35 3.60 2.40 1.90 2.00 21.80 22.55 22.40 22.30 22.40 21.50 19.70
20 4.30 3.60 2.30 1.80 2.00 22.35 22.50 22.40 22.30 22.40 21.55 19.60
21 4.30 3.50 2.30 1.80 2.00 22.40 22.50 22.40 22.30 22.40 21.65 1950
22 4.25 3.50 2.25 1.80 2.00 22.40 22.45 22.40 2230 22.40 21.60 19.40
23 4.25 3.40 2.25 1.80 2.00 22.45 22.40 22.40 22.30 22.40 21.60 19.35
24 4.20 3.12 2.25 1.80 2.50 22.50 22.35 22.40 22.30 22.40 21.55 19.25
25 4.15 3.11 2.20 1.80 3.80 22.50 22.35 22.40 22.30 22.35 21.55 1920
26 4.10 3.11 2.20 1.80 5.40 22.60 22.35 22.40 22.30 22.35 21.50 19.10
27 4.05 3.00 2.20 1.80 7.24 22.60 22.35 22.40 22.30 22.35 21.50 19.00
28 4.02 2.90 2.20 1.80 1.40 22.60 22.35 22.40 22.30 22.30 21.30 18.90
29 4.01 2.20 1.80 15.60 22.60 22.35 22.40 22.20 22.30 21.42 1880
30' 4.00 2.20 1.80 16.72 22.55 22.35 22.40 222.0 22.30 21.20 18.70
31 4.00 2.20 2.20 17.64 22.35 22.40 22.35 21.20 18.60
Table A2.4
Inchaban Dam Levels (It) - S
Date Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec
1992
1 18.500 15.00 11.60 7.70 3.90 4.90 22.30 2230 21.60 22.30 22.70 22.10
2 18.300 14.90 11.50 7.60 3.80 4.90 22.30 22.30 21.60 22.20 22.60 22.00
3 18.20 14.80 11.40 7.40 3.70 10.70 22.30 22.30 21.50 22.20 22.50 21.90
4 18.10 14.70 11.30 7.30 3.50 15.70 22.20 22.30 21.50 22.20 22.50 21.80
5 18.25 14.60 11.20 7.20 3.40 16.10 22.15 22.20 21.40 22.20 2250 21.80
6 17.95 14.50 11.10 7.10 3.20 17.10 22.30 22.20 21.40 22.15 22.70 21.80
7 17.95 14.A0 10.80 6.80 3.00 17.50 22.65 22.20 21.40 22.10 2270 21 70
8 17.85 14.30 10.70 6.70 2.80 17.70 22.50 22.20 21.30 22.00 22.60 21.70
9 17.70 14.15 10.50 6.60 2.80 18.10 22.50 22.20 21.30 21.90 22.60 21.70
10 17.60 14.00 10.40 6.50 2.90 18.60 22.50 22.20 21.20 21.80 22.60 21.70
11 17.50 13.85 10.30 6.30 2.80 18.80 22.50 22.20 21.10 21.70 22.60 21.60
12 17.30 13.75 10.20 6.20 2.70 18.90 22.50 22.00 21.10 21.80 22.60 21.45
13 17.20 13.65 10.10 S.90 2.60 18.90 22.50 21.90 21.00 21.90 22.60 21.40
14 17.25 13.55 10.00 5.80 2.90 20.00 22.40 21.90 20.90 21.90 22.60 21.35
15 16.90 13.45 9.90 5.70 2.90 20.70 22.40 21.50 20.90 22.0 22.60 21.30
16 16.80 13.35 9.80 5.60 2.90 20.70 22.40 21.80 20.85 21.90 22.60 21.20
17 16.625 13.25 9.65 5.50 2.90 22.50 22.40 21.70 20.85 22.00 22.60 21.60
18 16.50 13.50 9.50 5.40 2.90 22.50 22.40 21.70 20.80 22.00 22.60 22.80
19 16.40 13.00 9.40 5.30 2.90 22.50 22.40 21.60 20.70 22.50 Z50 22.50
20 16.30 12.90 9.20 5.20 3.20 22.50 22.40 21.60 21.65 20.60 22.40 22.50
21 16.20 17.70 9.10 4.90 3.40 22.50 22.40 21.60 20.90 22.60 22.40 22.50
22 16.10 12.50 8.90 4.80 3.50 22.50 22.40 21.60 20.95 22.60 22.35 22.50
23 16.00 12.40 8.70 4.70 3.70 22.40 22.40 21.60 20.95 22.60 22.30 22.50
24 15.90 12.20 8.60 4.60 4.20 22.40 22.40 21.60 21.50 23.10 22.35 2250
25 15.725 12.10 8.50 4.50 4.60 22.40 22.40 21.60 21.80 22.70 22.40 2245
26 15.600 12.00 8.40 4.40 4.60 22.40 22.40 21.60 22.0 22.60 22.30 22.40
27 15.500 11.90 8.30 4.30 4.80 22.40 22.40 21.60 22.50 22.0 22.30 2230
28 15.400 11.80 8.20 4.20 4.80 22.40 22.40 21.60 22.0 22.50 22.30 22.20
29 15.300 11.70 5.10 4.10 4.80 22.40 22.40 21.60 22.45 22.50 22.30 22 10
30 15.300 8. 4.00 4.90 22.40 22.30 21.60 22.35 22.50 22.20 22.00
31 15.100 7.90 4.90 22.30 21.60 22.70 21.90
Appendix B
Biological/FisheriesData
Appendix B
List of Tables
Number Tlitle
Number Title
Sole (CvnoalossesSDDS.)
Cassavafish(PseudotolithusSPD.)
Burrito (Brachydeuterus aurilus)
Burro (Pomadaysiubelioi)
Horse Mackerel (CaranxhipDos)
Round Sardines (Sardinellaaurila)
Flat Sardine(Sardinellamaderensis)
Longfinned herring (Illishaafricana)
Ribbonfish (TrichiurusleDturus)
Sharks(Carcharhiaidal p2)
Shrimps (Peueidael
Manta ray (Manta birostrus)
Cuttlefish (Sepiaofficinali)
Am. Sailfish (Istiophorusamaicanus)
Tuna (yellowfin)(Neothunnusalbacares)
Frigate mackerel(Auxis thazard)
D - dxW..
T -Ieu SaJdww.M
a. *AWL r
m - ~
I*dli ~
I-SW. ~ ~ m
m 0~~~~~~~
*~~~ ~~
G.T.m
AGEOG FROM
P...YNSN Y TAO-AD
F~~~~
F~O
FROMG.T.
AGYEPONG,
P.W.K.YANKSON,
YMNTIAMOA-BAIDU
UNIVERSITY
OFGHANA,
LEr'IN
MARCH1990
Fi. 61
VoHaRiverAuthorityF.
Takoradi
ThermalF. :I1
Regional Vegetation Pattern of the Coastal Zone 1!'",-
Appendix C
Socioeconomic Data
Appendix C
List of Tables
Number Title
Production,transport,equipment
operators,labourers,and relatedworkers
- Total 79126 23820 30 3 546 5
- Male 54 518 16927 31 2 032 4
- Female 24 608 6 899 2 1 514 6
Employmentfor SelectedCommunities'
Number In Employment l
Agriculture
Total Huntilng
Aged 15 and Flshing
Locallty Sex over Total Forestry Unemployed Homemaker Other
Shama M 1927 1641 1199 135 16 236
F 2269 1736 72 69 245 219
Aboadzi M 715 567 455 41 9 98
F 903 750 14 18 44 82
Aboasi M 621 526 450 12 3 80
F 648 564 15 14 48 22
Sekondi M 9433 6363 285 842 84 1942
____________ F 8932 5135 95 646 2122 1029
Inchaban M 738 579 134 70 89
F 764 615. 232 21 61 63
Textiles,leathergoods
. Toal 9 725 2 498 417
- Male 2 661 504 131
- Female 6 064 1 994 286
Wood.wood products
- Total 7 032 2 073 258
- Male 6 707 1 989 255
* Female 325 84 3
Wholesale/retail.
restaurants,hotels
* Total 63207 21 691 5 894
- Male 7 516 2 690 184
- Female S5 691 19001 5 710
Transport.storageand communications
Total 16 655 8 902 669
Male 15 949 8 372 662
Female 706 528 7
Publicadministration
and defence
* Total 8 858 4 411 249
- Male 7 625 3 712 223
- Female 1 213 699 26
Socialand relatedcommunityservices
- Total 19 966 5 885 575
- Male 12 251 3 112 375
- Female 7 715 2 773 20
Ref.Censusof Ghana,1984.
Table C.4
Crop: Cassava
Crop: Yam
ShamaAhanta Fast - -
WassaWest 106 3.5 371
Aowin Suaman 890 5.7 5,073
WassaAmenfi 882 6 5,292
BibianVAnhwiaso/Bekwai 1,055 6 6,330
SefwiWiawso 1,580 6.4 10,112
NzemaEast
Jomoro
MpohorWassa East 114 5 570
AhantaWest 37 5 185
Juabeso Bea 2,420 7.4 16,940
Crop: Maize
Crop: Rice
Crop: Plantain
ShamaAhantaEast 90 4 3600
Wassa West 645 4.2 2.709
Aowin Suaman 4,331 5.6 24,254
Wassa Amenfi 5,829 6.6 38.471
BibianiAnhwiaso/Bekwai 5.256 6.5 34.164
Sefwi Wiawso 6,108 6.8 41.534
NzemaEast 133 4.3 572
Jomoro 1.900 5.4 10,260
Ahanta West 168 4.2 705
Juabeso Bea 7.050 7.1 50.055
Crop: Cocoyam
Crop:Maize,TraditionalMethod
Cost
(Cedis)
Subtotal 43,600
Contingencies (10%) 4,490
TOTAL 48,090
Total revenues, (Cl 30,000 per ton for 0.4t/acre) 52,000
Rice,TraditionalMethod
Land clearing and preparation(1 acre) 12,000
Planting(6 MD) 4.800
Harvestingand collection(4 MD) 6.000
Threshing (4 MD) 4.800
Carting (4 MD) 4.800
Sack (4 at 300 cedis) 1,200
Seed (40 kg at 200 cedis) 8,000
Hoe (amortised,single season 800
Cutlass(amortised,singleseason) 1,000
Table C.5
Crop Budget for Coastal Savanna Zone
(1992) per Acre, Western Reglon - 2
Subtotal 56,600
Contingencies 10% 5,660
TOTAL 62,260
Total revenues, (C230,000 per ton for 0.4 tlacre) 92,000
Cassava
Subtotal 51,400
Contingencies 10% 5,140
TOTAL 56,540
Total revenue ( 2.7t/acre at 35,725 cedis per ton) 96,457
Coconut
1 HA Local variety,no establishmentcosts
Subtotal 117,000
Contingencies 10% 11,700
TOTAL 128,700
Revenues (1 nut at 15 Cedks for 20 400 nuts) 306,000
Appendix D
!
I L'.>:s 'LJW
. * ... ~~~~~~~/2
2-
.. ./3
-
2321 PAE. 93
-.
inalluation of Custo-I I t
The c1anxani no ciersndicated that further
customary rites vould have to ae per4o:med bY VRA be.rOZe
actual work begins on thi site should the land be found
Duitable. The payment made at the meeting vas only to
SIord VRA the right to enter 'ho land -or the tests.
4.1 TnDe-otion of Stit
A team Made Up of the Chif'V representative, miembers
Of the Abradze family,CDR and tho VRA officials inspected
the site after the meeting.
BY
MRCORDED
..~~ ~ ~ ~ ~ ~
1~~~~~~6
lol ONi
A aN~
rH. hIiaL
ENYRDN*NAL
ZrC/20/Y.3
260iO9
EiWZR,-G1I A!Ltust, go
Ch*' Uscutv.e,
Vo2tc liver Authority,
D"r lsx
Your. faithfully,
(R. AEZOKVA-AIPADU)
DEP!M DIRECT OF P RCPMS
for: mZICUTV
CRAJUv
Minutes of Meeting July 12, 1993
Held In the offices of P1040802
Cape CoastUniversity
Cape Coast,Ghana
on Junw 22, 1993
Present:
LPK Reportedby
L. King
cc 0. Gaube
C. Mee
Minutesof Meeting July 12 1993
Held in the offices of P1040802
FisheryDepartment(Min. of Agriculture)
Sekondi.Ghana
on June 22, 1993
Present:
cc 0. Gaube
C. Mee
Minutes of Meeting July 13. 1993
Held In the offices of P1040802
Ministry of Health- RegionalOffice,
Sekondi.Ghana
on June 23,1993
Present:
District level data for was provided in the form of a copy of the 1992
ShamaAhanta East MetropolitanAuthorityAnnual Reportand Develop-
Minutes of Meeting - 2
LPK Reportedby
L King
A/AZ )eK
cc 0. Gaube
C. Mee
Minutes of Meeting July 13. 1993
Held In the offices of P i040B02
Ministryof Agriculture
Sekondi,Ghana
on June 23, 1993
Present:
D. Dei and L King briefly outlined the proposedproject and requested Action
Min. of Ag. assistance in obtaining site specific, district and regional
information to be used in the evaluationof project impacts and the Meet Mr. Lon-
preparationof an environmentalreport. E.Arkhurstdescribedthe major don the fol-
agricultural activities of the Shama Ahanta East District, and also lowing day, and
provided a report documenting production information as well as undertake site
outlining the Ministry'sseven year developmentplan for the District,to reconnaissance
the year 2000. visit.
Cropbudgetsformaize,cassava.coconutandricewereprovidedforthe
1992croppingyear,as wellas average1992pricesfor variouscrops.
LPK Reportedby . -- _
L King
cc 0. Gaube
C. Mee
Minutes of Meeting July 13, 1993
Held In the offices of P1040802
Public InformationCentre
Shama,Ghana
on June 23, 1992
Takoradi ThermalPlant
Feasibility Study
Present:
Information was requested on the species that comprise the major Action
components of the commercial catch, and those that are commonly
taken in ShamaBay and inshore(in the beach zone) along the front of
the project area.
Shrimp are also locally important in Shama Bay and in the Pra River
estuary. Rearing and foraging areas are both present in the estuary,
while breedinggroundsare presentalongthe shoreline.The abundance
of shrimp locally is also related to temperature(ie high temperatures
Minutesof Meeting- 2
bringIncreasesabundance).ShrimpfromtheShamaBayareasupply
an exportmarket.
Thefollowingcostestimates wereprovidedbyAssefuafortheequipment
to initiatea newfishingoperation:
Present:
LPK Reportedby
L. King
cc 0. Gaube
C. Mee
Minutes of Meeting July 14, 1993
Held in the offices of P1040802
FisheriesDept., Researchand UtilizationBranch
Tema, Ghana
on June 25, 1993
Present:
LPK Reportedby
L King
A•E7 *;1r
cc 0. Gaube
C. Mee
Results of Site Reconnaissance July 14,1993
In associationwith P1040802
Ministryof AgricultureExtensionAgent
for ShamaAhanta East District
on June 24. 1993
Present:
Of the tree crops, Mr. London indicatedthat most of the oil palms on site
were wild, with only one fruiting plant observed. Coconut palms are
presenton the beachridge borderingthe ocean on each side of the site,
but are absent from the central portion of the site in the former area of
sand excavation. Scattered coconut palms are also present on the
centralknoll on high ground. Othertreesof significanceobservedon the
site, although scatttered and in low numbers,include mango, guava,
Minutesof Meeting - 2
LPK Reportedby
L. King
cc 0. Gaube
C. Mee
Minutes of Meeting July 7, 1993
Heldin the officesof P1040802
FisheriesDept.,Researchand Utilization
Branch
Tema,Ghana
on June21, 1993
Present:
Reportedby L. King / C
r7 - t,
cc 0. Gaube
C. Mee
Mlnutes of Meeting July 7, 1993
Held In the officesof P1040802
Dept. of Gameand Wildlife
Accra, Ghana
on June 21, 1993
Present:
LPK Reportedby
L King
cc 0. Gaube
C. Mee
Minutes of Meeting July 14, 1993
Held in the residenceof P1040802
Dr.Y. Ntlamoa-Baidu
Accra,Ghana
on June 24, 1993
Present:
LPK Reportedby
L King
cc 0. Gaube
C. Mee
Minutes of Meeting July 12, 1993
Held In the officesof P1040802
Institute of Aquatic Biology
Accra, Ghana
on June 22,1993
Present:
Met with Dr. Biney to enquireas to potentialfor him to accompanyD. Dei Action
and L King to Aboadze to assist with evaluation of nearshore and
Shama Bay fishery. Contact either
Dr. Blay,Jansen
Dr. Bineyexplainedthat the majorityof his previousexperiencehad been or Amehia at
with coastallagoon and freshwaterfisheries,and hence did not feelthat Cape Coast
he was the appropriateindividualto adviseon marine fishery, although University.
he was aware that Shama was an important fishing area. He did
howevernote that a new FisheriesBill had recentlybeen passed, which
would prohibit the taking of juvenilesby the seine fishery.
LPK Reportedby L Kn
L KingJ
cc 0. Gaube
C. Mee .
Minutes of Meeting July 8. 1993
Held In the offices of P1040802
EnvironmentalProtectionCouncil
Accra, Ghana
on June 22, 1993
Present:
D. Dei and L. King outlined the scope of the proposed project, and Action
enquiredas to the EPC'sregulatoryrequirementsor guidelinesfor such
a project. Environmental
report for-
J. Dansoindicated that the EPCwould requirean environmentalimpact warded to EPC
assessmentof a project of this scale. The Ministryof Environmentis for review and
currentlyin the processo; establishingregulatoryrequirements(presently comment as
in draft form) for various projects and operations,as well as an EIA part of project
ReviewBoard- The Boardis expectedto be establishedby mid-lateJuly. approval pro-
after which time,all projectproposalswould go through it for reviewand cess.
comment. Mr.Dansoindicatedthat the TechnicalServicesSectionof the
EPC would undertakean intemal reviewof the environmentalreportfor
this project,and providecommentswithin 10 - 14 days, if the reportwas
receivedprior to mid-July,1993.
Present:
D. Dei had arranged a meeting with Mr. J. Danso (Deputy Director - Action
TechnicalServices),however,J. Dansocould not attend. Upon review
of our (VRA/Acres)informationneeds. D. Amlalo indicated that he had Assesspotential
been involved in the preparation of the NationalOil Spill Contingency impacts of off-
Plan - 1985 (NOSCP). L. King noted that the potential for oil spillage shore oil spill on
would be increasedwith the installationand operationof the SPM,and sea water in-
that therewas no mentionof "dedicated" oil spill responseequipment in take, and whet-
the NOSCP,and enquiredas to its existencetoday. her it is ad-
ditional justif-
D. Amlalo noted that it was not feasibleat the momentto maintain any ication for the
dedicated oil spill recoveryequipment in the country, howeverthe plan establinhmentof
had provisionfor mobilizationof existing resources,either nationally or dedicated initial
internationallyas required, depending on the severityof the spill. He response capa-
indicated that the NOSCPwill be revised in the near future, with the bility.
assistance of the InternationalMaritime Organization,and various oil,
industryand governmentrepresentatives.A meetingis plannedwithin the
next six months,and VRAwould be invited,to input to the development
of a new plan.
Number TItle
E1.1 TakoradiThermalPlant
Gas Turbine Emissions
Number Title
E2.3(a) CO Emissions
E2.3(b) CO Emissions
E2.3(c) CO Emissions
E2.4 ParticulateEmissions
Appendix E
I - GasTurbineEmissions
Table E1.1
TakoradlThermal Plant
Gas Turbine Emisslons
F-rom GE PG9171(E)
een i tv ; 0l.
i 2 If t.t ,
@ 60 F arnd 14.696 psi;t
CO Density b
0. 0).730:i
lb/f t'3
@ 60' F and 14.696 psia
i-10"',
JQ 1265 lb/hr 01<
CO lb/hr
l2 OK
TakoradiGeneratingStation
OntarioRegulatoryAir Di persionModel Reg.308
EmissionRate(grn/s) 314.24 NOxppmVD& 15%& ISO 241
Exit Velocity(m/s) 21.2 NOxIbfh/130MW 1247
StackDiameter(m) 5.5 NOxng/J 447
Temperature(C)^ 175
C STABILITY
Run Stack NOx Conc. Wind NOx Concentrations |
No. Height1/2-h PeakDistance Velocity 1-h Avg 24-h Avg Annual
(m) (UG/m3) (m) (misec) (UG/m3) (UG/m3) (UG/m3)
34 140 57.4 3620 5.735 47.275 19.418 16.646
33 135 59.4 3548 5.735 48.922 20.095 17.226
32 130 61.6 3318 6.235 50.734 20.839 17.864
31 125 64.0 3247 6.235 52.710 21.651 18.560
30 120 66.5 3042 6.735 54.769 22.497 19.285
29 115 69.4 2972 6.735 57.158 23.476 20.126
28 110 72.4 2787 7.235 59.629 24.493 20.996
27 105 75.7 2625 7.235 62.347 25.609 21.953
26 100 79.3 2548 7.235 65.311 26.827 22.997
25 95 83.2 2336 8.735 68.524 28.147 24.128
24 E0 87.9 2201 9.235 72.394 29.737 25.491
23 85 93.1 2073 9.735 76.677 31.496 26.999
1 80 98.9 1952 10.235 81.454 33.458 28.681
2 75 105.6 1837 10.735 86.972 35.724 30.624
3 70 113.2 1685 11.735 93.232 38.296 32.828
4 65 121.9 1548 12.735 100.397 41.239 35.351
5 60 132.1 1422 13.735 108.798 44.689 38.309
6 55 144.2 1306 14.735 118.763 48.783 41.818
7 50 158.7 1176 16.235 130.705 53.688 46.023
8 45 176.5 1043 18.235 145.365 59.710 51.185
9 40 198.1 979 18.235 163.155 67.017 57.449
10 35 223.9 916 18.235 184.404 75.745 64.931
11 30 255.2 854 18.235 210.183 86.334 74.008
'Operatingin combinedcyclemode.
Table E2.1(a)-2 - NOxConcentrationfor UncontrolledOperation
Takoradi GeneratingStation
Ontario RegulatoryAir DispersionModel . Reg. 308
EmissionRate (gm/s) 314.24
Exit Velocity (mIs) 21.2
Stack Diameter (m) 5.5
Temperature(C)^ 175
D STABILITY_
Run Stack NOx Conc. Wind NOx Concentrations
No. Height 112-hPeakDistance Velocity 1-h Avg 24-h Avg Annual
(m) (UGBm3) (m) (m/sec) (UGIm3) (UG/m3) (UG/m3)
34 140 28.6 10643 9.235 23.555 9.675 8.294
33 135 30.4 9833 9.735 25.037 10.284 8.816
32 130 32.3 9086 10.235 26.602 10.927 9.367
31 125 34.4 8401 10.735 28.332 11.638 9.976
30 120 36.7 7762 11.235 30.226 12.416 10.643
29 115 39.3 7389 11.235 32.367 13.295 11.397
28 110 42.2 7000 11.735 34.756 14.276 12.238
27 105 45.3 7000 11.235 37.309 15.325 13.137
26 100 47.2 6808 11.735 38.874 15.968 13.688
25 95 50.8 6327 12.235 41.839 17.186 14.732
24 90 54.8 5873 12.735 45.133 18.539 15.892
23 85 59.4 5317 13.735 48.922 20.095 17.226
1 80 64.8 4921 14.235 53.369 21.922 18.792
2 75 71.0 4447 15.235 58.476 24.019 20.590
3 70 78.2 4013 16.235 64.406 26.455 22.678
4 65 86.9 3547 17.235 71.571 29.398 25.201
5 60 97.2 3242 18.235 80.054 32.883 28.188
6 55 109.5 3007 18.235 90.184 37.044 31.755
7 50 124.0 2777 18.235 102.126 41.949 35.960
8 45 141.4 2553 18.235 116.457 47.836 41.006
9 40 162.6 2337 18.235 133.917 55.008 47.154
10 35 188.4 2127 18.235 155.166 63.736 54.636
11 30 220.5 1925 18.235 181.604 74.595 63.945
TAKORADIGENERATINGSTATION
ON1'AIO REGULATORYAIR DISPERSIONMODEL
12
9…-
4 -
0 --
140 135 130 125 120 115 110 105 100 95 90 8s5 0 75 70 65 60 55 50 45 40 35 30
STACKHEIGHT(M)
C STABILITY, D STABILITY
45000_
40000 0
350000
30000_
&3 25000
E
0~~~~~~~~~~~~~~~~
820000-
MA
15000 (wUntOeai)
10000-
WindDireclian: SW
sac:)o WindSpeed: 2.235 roos
o 0 0 0 0 0 0 0 0 o
o 0 0 0 0 o 0 0 0 0
o 0 0 0 0 0 0 0 0 0
In O in I)n 0 in 0 Ln 0
w- Ditatanca frornfSt,ac Cm) ) + t Ln
Takoradi Thermal Plant 157.12 gm/s N)
50000
45000 -
40000 - /o
35000 -
30000W
X
co 25000 -
E
20
8 20000-
0
15000 PonofIpneetlt
o 0 0 0 0 0 0o 0 0
0 0 0 0 0 0 0 0 0 00
0 0 0 0 0 0 0 0 0 0
In 0 In 0 tn 0 LI) 0 LI) 0
w- Dist ~an c WfroniPuStaoV( Cm)m 14 in
Table E2.1(b)-1 - NOx Concentrationfor UncontrolledOperation
Takoradi GeneratingStation
Ontario Regulatory Air DispersionModel - Reg. 308
EmissionRate (gmls) 314.24
Exit Velocity (mJs) 40
Stack Diameter (m) 6
Temperature(C)* 1100
l ~~~~~C
STABILI1
Run |Stdc NOx Conc. Wind NOx Concentrations
' Height 112-h Peak Distance Velocity 1-h Avg 24-h Avg Annual
(m) (UGIm3) (m) (misec) (UGIrn3) (UGlm3) (UGIm3)
46 140 13.3 4291 18.235 10.954 4.499 3.857
45 135 13.7 4218 18.235 11.283 4.635 3.973
44 130 14.2 4148 18.235 11.695 4.804 4.118
43 125 14.6 4075 18.235 12.025 4.939 4.234
42 120 15.1 4003 18.235 12.436 5.108 4.379
41 115 15.6 3932 18.235 12.848 5.277 4.524
40 110 16.1 3861 18.235 13.260 5.447 4.669
39 105 16.6 3788 18.235 13.672 5.616 4.814
38 100 17.2 3717 18.235 14.166 5.819 4.988
37 95 17.8 3645 18.235 14.660 6.022 5.162
36 90 18.4 3574 18.235 15.154 6.225 5.336
35 85 19.1 3504 18.235 15.731 6.462 5.539
12 80 i9.8 3432 18.235 16.307 6.698 5.742
13 75 20.6 3363 18.235 16.966 6.969 5.974
14 70 21.4 3292 18.235 17.625 7.240 6.206
15 65 22.2 3221 18.235 18.284 7.510 6.438
16 60 23.1 3150 18.235 19.025 7.815 6.699
17 55 24.0 3081 18.235 19.766 8.119 6.960
18 50 25.0 3011 18.235 20.590 8.458 7.250
18 45 26.1 2941 18.235 21.496 8.830 7.569
20 40 27.2 2872 18.235 22.402 9.202 7.888
21 35 28.4 2802 18.235 23.390 9.608 8.236
22 30 29.7 2733 18.235 24.461 10.048 8.613
Takoradi GeneratingStation
Ontario RegulatoryAir D persionModel-. Reg. 308
EmissionRate (gm/s) 314.24
Exit Velocity (mis) 40
Stack Diameter (m) 6
Temperature(C)@ 1100
D STABILITY
Run Stack NOx Conc. Wind NOx Concentrations
No. Height 112-h Peak Distance Velooity 1-h Avg 24-h Avg Annual
(m) (UG/m3) (m) (m/sec) (UG/m3) (UGIm^' (UG/m3)
46 140 5.6 20972 18.235 4.612 1.8t4 1.624
45 135 5.8 20367 18.235 4.777 1.962 1.682
44 130 6.1 19793 18.235 5.024 2.064 1.769
43 125 6.3 19224 18.235 5.189 2.131 1.827
42 120 6.6 18650 18.235 5.436 2.233 1.914
41 115 6.9 18090 18.235 5.683 2.334 2.001
40 110 7.2 17541 18.235 5.930 2.436 2.088
39 105 7.5 17005 18.235 6.177 2.537 2.175
38 100 7.9 16469 18.235 6.506 2.673 2.291
37 95 8.2 15939 18.235 6.754 2.774 2.378
36 90 8.6 15417 18.235 7.083 2.909 2.494
35 85 9 14902 18.235 7.412 3.045 2.610
12 80 9.5 14406 18.235 7.824 3.214 2.755
13 75 10.0 13909 18.235 8.236 3.383 2.900
14 70 10.5 13421 18.235 8.648 3.552 3.045
15 65 11.0 12942 18.235 9.060 3.721 3.190
16 60 11.6 12469 18.235 9.554 3.924 3.364
17 55 12.2 12009 18.235 10.048 4.127 3.538
18 50 12.9 11556 18.235 10.624 4.364 3.741
18 45 13.7 11108 18.235 11.283 4.635 3.973
20 40 14.5 10669 18.235 11.942 4.905 4.205
21 35 15.3 10233 18.235 12.601 5.176 4.437
22 30 16.3 9816 18.235 13.425 5.514 4.727
TAKORADI GENERATINGSTATION
ONTARIOREGULATORYAIR DISPERSIONMODEL
25
20 X0000
1501TW S J1111
15
10
Takoradi GeneratingStation
Ontario RegulatoryAir DispersionModel Re. 308
EmissionRate (gm/s) 209.2 NOx ppm VD & 155%& ISO 160
Exit Velocity (mIs) 21.2 NOx IbIhIl 30 MW 828
Stack Diameter (m) 5.5 NOx ngIJ 296.8
Temperature(C)* 175
C STABILIT
Run Stack NOx Conc. Wind NOx Concentrations _
No. Height 112-h PeakDistance Velocity 1-h Avg 24-h Avg Annual
(m) (UGIm3) (m) (m/sec) (UG/m3) (UGIm3) (UG/m3)
63 120 44.3 3042 6.735 36.485 14.987 12.847
62 115 46.2 2972 6.735 38.050 15.629 13.398
61 110 48.2 2787 7.235 39.698 16.306 13.978
60 105 50.4 2625 7.735 41.509 17.050 14.616
59 100 52.8 2549 8.735 43.486 17.862 15.312
58 95 55.4 2336 9.235 45.627 18.742 16.066
57 90 58.5 2201 9.735 48.181 19.791 16.965
56 85 62.0 2073 10.235 51.063 20.975 17.980
55 80 65.9 1952 10.235 54.275 22.294 19.111
.54 75 70.3 1837 10.735 57.899 23.782 20.387
53 70 75.3 1685 11.735 62.017 25.474 21.837
52 65 81.2 1548 12.735 66.876 27.470 23.548
51 60 88.0 1422 13.735 72.477 29.770 25.520
D STABILITY
63 120 24.4 7760 11.235 20.096 S.255 7.076
62 115 26.2 7389 11.235 21.578 8.863 7.598
61 110 28.1 7000 11.735 23.143 9.506 8.149
60 105 30.1 7000 11.235 24.790 10.183 8.729
59 100 31.4 6809 11.735 25.861 10.623 9.106
58 95 33.8 6327 12.235 27.838 11.435 9.802
57 90 36.5 5876 12.735 30.061 12.348 10.585
56 85 39.6 5317 13.735 32.615 13.397 11.484
55 80 43.1 4921 14.235 35.497 14.581 12.499
54 75 47.2 4447 15.235 38.874 15.968 13.688
53 70 52.1 4013 16.235 42.910 17.625 15.109
52 65 57.8 3547 17.735 47.604 19.554 16.762
51 60 64.7 3242 18.235 53.287 21.888 18.763
TAKORADIGENERATINGSTATION
ONTARIO REGULATORY AIR DISPERSION MODEL
g9 i- 1____ 1
7-
8~-- _ _ _ _ _ _ _ _ __ __ _
02 4-
3-
6-~~~ _ STBLT_ _ TBLT
2 - _
_______ C STABILIT Y
Run Stack NOx Conc. Wind NOx Concentralions
No. Height 1/2-h PeakDistance Velocity 1-h Avg 24-h Avg Annual
(m) (UG/m3) (m) (m/sec) (UG/m3) (UG/m3) (UG/m3)
87 120 10.0 4003 18.235 8.236 3.383 2.900
86 115 10.4 3933 18.235 8.565 3.518 3.016
85 110 10.7 3861 18.235 8.813 3.620 3.103
84 105 11.1 3788 18.235 9.142 3.755 3.219
83 1OD 11.5 3717 18.235 9.471 3.890 3.335
82 95 11.9 3645 18.235 9.801 4.026 3.451
81 90 12.3 3574 18.235 10.4130 4.161 3.567
80 85 12.7 3504 18.235 10.460 4.296 3.683
79 80 13.2 3432 18.235 10.872 4.466 3.828
78 75 13.7 3363 18.235 11.283 4.635 3.973
77 70 14.2 3292 18.235 11.695 4.804 4.118
76 65 14.8 3221 18.235 12.189 5.007 4.292
75 60 15.4 3151 18.235 12.683 5.210 4.466
D STABILITY
87 120 4.4 18640 18.235 3.624 1.489 1.276
86 115 4.6 18090 18.235 3.789 1.556 1.334
85 110 4.8 17542 18.235 3.953 1.624 1.392
84 105 5.0 17007 18.235 4.118 1.692 1.450
83 100 5.2 16469 18.235 4.283 1.759 1.508
82 95 5.5 15939 18.235 4.530 1.861 1.595
81 90 5.7 15417 18.235 4.695 1.928 1.653
80 85 6.0 14901 18.235 4.942 2.030 1.740
79 80 6.3 14406 18.235 5.189 2.131 1.827
78 75 6.6 13907 18.235 5.436 2.233 1.914
77 70 7.0 13421- 18.235 5.765 2.368 2.030
76 65 7.3 12939 18.235 6.012 2.470 2.117
75 60 7.7 12469 18.235 6.342 2.605 2.233
Operating in bypassmode.
Figure E2.1(d)
TAKORADI GENERATINGSTATION
ONTARIOREGULATORYAIR DISPERSIONMODEL
20 - _ _
15
0-
120 115 110 105 100 95 90 85 80 75 70 65 60
STACKHEIGHT(M)
C STABILITY . D STABILITY
EmmissionRate209.20gmls
Temperature1100C
Table E2.1(a) - NOx Concentrationsfor Low NOxlWater Injectlon
D STABILITY
74 100 8.2 6810 11.735 6.754 2.774 2.378
73 95 8.8 6327 12.235 7.248 2.977 2.552
72 90 9.5 5876 12.735 7.824 3.214 2.755
71 85 10.3 5316 13.735 8.483 3.484 2.987
70 80 11.3 4921 14.235 9.307 3.823 3.277
69 75 12.3 4447 15.235 10.130 4.161 3.567
68 70 13.6 4013 16.235 11.201 4.601 3.944
67 65 15.1 3547 17.735 12.436 5.108 4.379
66 60 16.9 3242 18.235 13.919 5.717 4.901
65 55 19.0 3007 18.235 15.648 6.428 5.510
64 50 21.5 2778 18.235 17.707 7.273 6.235
108 45 24.6 2553 18.235 20.261 8.322 7.134
109 40 28.2 2337 18.235 23.226 9.540 8.178
110 35 32.7 2127 18.235 26.932 11.062 9.483
TAKORADI GENERATINGSTATION
ONTARIOREGULATORYAIR DISPERSIONMODEL
6
a]X-_ X - -
5-
I, -- __ - __
0 9
100 g 90 85 80 75 70 65 60 55 50 45 40 35
STACKHEIGHT(M)
C STABILITY D STABILITY
Emmbsion Rate 54.6 gm/s
Temperature 175 C
Table E2.1(f)- NOx Concentrationsfor Low NOx Water InjectionOperation
Takoradl GeneratingStation
Ontario RegulatoryAir Disperson Model- Reg. 308
EmlsslonRate(gnvs) 54.6 NO rppm VD & 15 ISO
A& 42
Exit Velocity (mis) 40 NOx Ib/h/130 MW 216
Stack Diameter (m) 6 NOx ngiJ 77.9
Temperature(C)9 1100
CSTAPILIT
Run Stack NOx Conc. Wind NOx Concentrations
No. Height 1/2-h PeakDistance Velocity 1h Ava 24-h Avg Annual
(m) (UG;m3) (mn) (mlsec) (UG/m3-) (UG/m3) (UGIm3)
98 100 3.0 3717 18.235 2.471 1.015 0.870
97 95 3.1 3645 18.235 2.553 1.049 0.899
96 90 3.2 3574 18.235 2.636 1.083 0.928
95 85 3.3 3503 18.235 2.718 1.116 0.957
94 80 3.4 3432 18.235 2.800 1.150 0.986
93 75 3.6 3363 18.235 2.965 1.218 1.044
92 70 3.7 3292 18.235 3.047 1.252 1.073
91 65 3.9 3221 18.235 3.212 1.319 1.131
90 60 4.0 3151 t8.235 3.294 1.353 1.160
89 55 4.2 3081 18.235 3.459 1.421 1.218
88 50 4.3 3011 18.235 3.541 1.455 1.247
111 45 4.5 2941 18.235 3.706 1.522 1.305
112 40 4.7 2871 18.235 3.871 1.590 1.363
113 35 4.9 2802 18.235 4.036 1.658 1.421
D STABILITY
98 100 1.4 16469 18.235 1.153 0.474 0.406
97 95 1.4 15939 18.235 1.153 0.474 0.406
96 90 1.5 15417 18.235 1.235 0.507 0.435
95 85 1.6 14908 18.235 1.318 0.541 0.464
94 80 1.6 14406 18.235 1.318 0.541 0.464
93 75 1.7 13907 18.235 1.400 0.575 0.493
92 70 1.8 13421 18.235 1.482 0.609 0.522
91 65 1.9 12939 18.235 1.565 0.643 0.551
90 60 2.0 12469 18.235 1.647 0.677 0.580
89 55 2.1 12013 18.235 1.730 0.710 0.609
88 50 2.2 11549 18.235 1.812 0.744 0.638
111 45 2.4 11109 18.235 1.977 0.812 0.696
112 40 2.5 10663 18.235 2.059 0.846 0.725
113 35 2.7 10233 18.235 2.224 0.913 0.783
TAKORADI GENERATINGSTATION
ONTARIOREGULATORYAIR DISPERSIONMODEL
20 - _ _ _ _ _ _
'5
to0 95 90 85 80 75 70 65 60 55 50 45 40 35
STACKHEIGHT(M)
_._C STABILITY + D STABILITY
EmmissionRate 54.6 gmJs
Temperature1100C
Table E2.2
TAKORADI GENERATINGSTATION
ONTARIOREGULATORY
AIRDISPERSION
MODEL- REG308
EMISSION
RATE(gml 67.06
EXITVELOCY(m/s) 21.2
STACKDIAMETER (m 5.5
TEMPERATUREtC) 1751
C STABILITY _D STABILITY
RUN# HEIGHT S02 CON. DIST. WIND S02 CON. DIST. WIND
(m) (UG/M3) (M) m/see) (UG/M3) (M) mJsec)
106 120 14.2 3041 6.735 7.8 7760 11.235
105 80 21.1 1952 10.235 13.8 4921 14.235
104 70 24.15 1685 11.735 16.7 4013 16.235
103 60 28.2 1422 13.735 20.8 3242 18.235
102 sO 33.9 1176 16.235 26.5 2778 18.235.
101 40 42.3 979 18.235 34.7 2337 18.235
Figure E2.2
TAKORADI GENERATINGSTATION
AIR DISPERSIONMODEL
ONTARIOREGULATORY
9-
8-
6-
t__~~~II
Carbon MonoxideConcentrations
for Uncontrolled Emissions
Point Sources
I~~AO
.4J20
a' ~ 00
*q.4
(
-5 0 -.. . . 1m.. .- .
-0000000.
C3 ~ Il(1 U( V
00 I I
(I)30
-400
~ ~ ~ ~ ~ ~ Dsane
_ .. ...
XY ISOPLETH AT A HEIGHT OF 0. CM)
Takoradi Generating Station. CO emissions
ju
-500
-1000-
~i 150 0 - 0 0C a
0
Ln
0
~0 in)
0 a
in 0
a
in)
Distance.mi
CD)
F 5000
ISOPLETH AT A HEIGHT OF
~~~XY 0. (M)
Takoradi Generating Station. CO emissions. from 2 so-.
4500-
4000
3500-
200
.10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
050
Table E2.4
Particulate Concentrations
for Uncontrolled Emissions
Point Sources
u 0~~~~I
i500 1
I.~ ~ ~ ~~ ~ ~ ~ ~
-i 5 0 0 _.......... ._._....__.._.3._..
n _ _ _0 0 0 _ _ 0 0
In ~0 In0nI
m m
~~~~~~~~~Distance.
l~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Appendix F
Thermal Plume Modelling
Acres Office Memorandum
File P10408.
From P. J. Rae cc
Subject TakoradiTGS
CondenserCoollng Water Disposal
characterize
nearfieldhydrodynamic mixingto determinethe behaviorof the CCW
dischargecurrentnearthe outfall,
Approach
Study Parameters
Key study parameterswere obtained from other project staff and incorporatedin the analysisas
foliows
CCW Characteristics
- normal ambientwater temperature 2C
- maximumtemperaturerise 9'C Phase 1
- maximumtemperaturerise 12"C Phase2
- CCWflow 6.4 m3/s Phase 1
- CCW flow 11.3 m3 /s Phase2
Outfall Characteristics
- distance to shoreline 1 250 m
- outlall pipeline diameter 2m
- water depth at outlet 6m
- elevationof outlet above bed 1m
Both singleport and multiportoutfallswereconsideredin the analysis. For the single port outfall
a port diameterof 2.0 m with the centerlineset at 1.0 m above the bed level was assumed. The
discharge was directed offshore. The multiport outfall assumed for the analysis had a 2.5 m
diameter manifold with 18 - 500 mm diameterdischargeports set at a spacing of 1.5 m. The
centerline axis of the diffuser would be aligned normal to the shorelinemwththe outlet ports
directed in the samedirection and line as the ambientcurrent (co-flowingdiffuser arrangement).
Three analyseswere performedwith the single port ouffall with variousCCWflows and ambient
current velocity.
L. P. King - 3 August 12, 1993
Case 1: CCW a = 6.4 m3 /s, Ambient V = 0.25 m/s, Temperature Rise £OT= 9
CO
The flow from the outlet is classifliedas a weakly deflectedlet in crossflowsince the
discharge from the outlet Is directed offshore and the longshore ambient current
deflects the let. The dischargevelocityIs 2.04 m/swhich resultsin mixingin the zone
Immediatelydownstreamfromthe outletreducingthe temperatureriseto approximate-
ly 4.5 C within a distanceof 10 m. Beyond10 m from the outlet a plumeforms which
continuesto be deflected by the ambientcurrentas it spreads on the ocean surface.
The flow continues to become diluted by mixing along the plume boundary. The
centerlinetemperatureis reducedto less than 1 C°aboveambientwithin a distance
of 1000 m from the outfall. The plume wIll continue to spread but the maximum
temperatureat the leading edge becomes much lower.
In the vicinityof the outfall the rising water is expectedto spread upstreamfrom the
outlet for a distanceof about 7 m. No effect on the intake location is expected.
Note that the above analysis provides a conservativeestimateof the CCW plume
development. Some surface heat exchange may occur to reduce the plume
temperaturesand waveinduced mixingmayalso occur to increasethe rate o1dilution.
This conditionis similarto Case 1 abovebut the plant CCWflow is increasedand the
temperatureincreaseabove ambientis 12 Co. The flow from the outlet is classified
as a weakly deflected jet in crossflowsince the dischargefrom the outlet is directed
offshoreand the longshore ambientcurrent deflectsthe jet. The dischargevelocity
is 3.59 m/swhich resultsin mixingin the zoneimmediatelydownstreamfrom the outlet
reducing the temperature rise to approximately6 Co within a distance of 13 m.
Beyond 13 m from the outlet a plume formswhich continuesto be deflected by the
ambientcurrent as it spreadson the oceansurface. The flow continuesto become
diluted by mixingalong the plume boundary. The centerlinetemperatureis reduced
to less than 1 C°aboveambientwithin a distance of 1000 m from the outfall. The
plume will continue to spread but the maximumtemperatureat the leading edge
becomes much lower. The majorityof the mixing occurs within the hydrodynamic
mixingzone which extends about 22 m from the outlet and producesa leading edge
temperaturerise of just over 1 CO.
This condition is similar to Case 2 above but with an increased ambient current
velocity. The generaldischargemixingconditionsare verysimilar,however,the extent
of the hydrodynamicmixing zone is smaller at 20 m. The temperaturerise at the
boundary of the mixing zone is approximately2 C°. Intrusionof the heated effluent
L. P. King - 4 August 12, 1993
upstream from the outlet Is reduced from 11 m In Case 2 to only 1 m wlth the
Increasedambientcurrentvelocity. The centerlinetemperatureis reducedto less than
approximately1 C°aboveambientwithin a distance of 1000 m from the outfall. The
plume will continue to spread but the maximum temperatureat the leading edge
becomes much lower.
This condition Is similarto Case 2 above but with low ambient current velocity. The
general discharge mixing conditions are very similar, however. the extent of the
hydrodynamicmixingzone is largerat over 200 m. As in Case2, the temperaturerise
above ambient is less than 6 C° within a distance of approximately13 m from the
outlet. The temperaturerise at the boundaryof the mixingzone is approximately0.5
CO. Intrusionof the heated effluent upstreamfrom the outlet is much larger at about
175 m. The centerlinetemperatureis, therefore.less than I C°aboveambientwithin
a distance of 1000 m from the outfall. The plume will continue to spread but the
maximumtemperatureat the leading edge becomes much lower. The key difference
in this case is the extent of the upstream intrusion by the plume. With the low
ambient currentvelocitythe fluid densitydifferenceis able to establish the upstream
flowing plume.
One analysis was performed with a multiple port outfall for comparisonwith the single port
conditions.
Discharge from the ports is directed in the direction of the ambient current at a
velocityof 3.02 m/s. Whencomparedto Case 1 with a singleport ouffall, the velocity
is higher and the dimensionsof the jets are reduced. This enhancesthe mixingof the
CCW effluentproducinga mixedflow with a temperaturerise of less than 1.5 COin the
immediatevicinity of the outlets. The dischargere-stratifiesat approximately13.5 m
from the outlet port with a temperature1.5 COabove ambient. A plume forms which
flowswith the ambientcurrentas it spreadson the oceansurface. The flow continues
to become diluted by mixingalong the plume boundary. The centerlinetemperature
is reducedto approximately0.5 C°aboveambientwithin a distanceof 1000m from the
outfall. The plume will continue to spread but the maximum temperature at the
leading edge becomes much lower.
Summary
The analyses performedindicate the CCW dischargefrom the TakoradiTGS can be effectively
mixed with the ambient ocean waterto producea plume with a reasonablylow temperaturerise
within a short distance from the ouffall. At 1000 m from the outlet the temperaturerise is less
than approximately1 COin all cases tested. The plume will flow with the ambient current and
L. P. King - 5 August 12, 1993
Further more detailed analysis'should be required as part of the final design. The analysis
prepared for this memorandumassumesdimensions for the outfall structure which must be
properlydevelopedby the designerand supportedby mixingzone and plume analyses.
.PJ
PJR A ,/ .. '-
Date: Aug 11. 1993
FILE: TAK_THER.WOI
RE: Thernal Plots ior Taikoradi
Came
Buoyant Ambient Spreading
CASE DESCRIPTION
SITE NAME: West African Coast - Ghana
DISCHARGER NAME: Takoradi TGS Thermal Discharge Plume
POLLUTANT NAME: Condenser Cooling Water
FLUX VARIABLES
QO =0.6400E+01 MO =0.1304E+02 JO =0.1890E+00 SIGNJO = 1.0
ASSOCIATED LENGTH SCALES (METERS)
LQ = 1.77 LM = 15.78 Lm = 14.44 Lb = 12.10
Lmp = 99999.90 Lbp = 99999.90
NON-DIMENSIONAL PARAMETERS
FRO = 8.38 R 8.15
FLOW CLASSIFICATION
Cas 4
Buoyant Ambient Spreading
PREDICTION
x Y Z S C P
0.00 0.00 1.6o 1.0 0.100E+03 1.00
---------------------------------------------------------- ____---------------__
CROSSFLOWING DISCHARGE
PROFILE DEFINITIONS:
B = Gaussian l/e (37%) half-width, normal to trajectory
C = centerline concentration
S = corresponding centerline dilution
PREDICTION
X Y Z S C B
0.00 0.00 1.00 1.0 0.100E+03 1.08
0.15 -0.56 1.17 1.1 0.945E+02 1.15
0.31 -1.11 1.34 1.1 0.895E+02 1.21
0.48 -1.67 1.52 1.2 0.S51E+02 1.27
0.66 -2.22 1.69 1.2 0.Sl1E+02 1.34
0.85 -2.78 1.87 1.3 0.774E+02 1.40
1.05 -3.33 2.06 1.4 0.740E+02 1.46
1.25 -3.89 2.24 1.4 0.710E+02 1.53
1.46 -4.45 2.43 1.5 0.681E+02 1.59
1.68 -5.00 2.62 1.5 0.655E+02 1.65
1.92 -5.56 2.82 1.6 0.63lE+02 1.72
2.15 -6.11 3.02 1.6 0.609E+02 1.78
2.40 -6.67 3.22 1.7 0.588E+02 1.84
2.66 -7.22 3.43 1.8 0.568E+02 1.91
2.92 -7.78 3.64 1.8 0.550E+02 1.97
3.20 -8.33 3.86 1.9 0.533E+02 2.03
3.48 -8.89 4.08 1.9 0.517E+02 2.10
3.77 -9.45 4.30 2.0 0.502E+02 2.16
4.07 -10.00 4.53 2.1 0.487E+02 2.22
4.38 -10.56 4.76 2.1 0.474E+02 2.29
4.70 -11.11 5.00 2.2 0.461E+02 2.35
PROFILE DEFINITIONS:
B = Gaussian l/e (37%) half-width, normal to trajectory
C = centerline concentration
S = corresponding centerline dilution
PREDICTION
X Y Z S C B
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5,00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.95
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
4.70 -11.11 5.00 2.2 0.461E+02 2.96
--------------------------------------------------------------- __------------__
CONTROL VOLUME
PROFILE DEFINITIONS:
BV = top-hat thickness,measured vertically
BH = top-hat half-width, measured horizontally in Y-direction
C = average (bulk) concentration
S = corresponding average (bulk) dilution
ZU = upper plume boundary (Z-coordinate)
ZL = lower plume boundary (Z-coordinate)
PREDICTION
X Y Z S C B
CONTROL VOLUME INFLOW
4.70 -11.11 5.00 2.2 0.461E+02 2.96
x Y Z S C BV BH ZU ZL
CONTROL VOLUME OUTFLOW
13.78 -11.11 6.00 11.4 0.878E+01 8.03 18.16 6.00 0.00
PROFILE DEFINITIONS:
BV = ton-hat thickness,measured vertically
BH a top-hat half-width, measured horizontally in Y-direction
C - average (bulk) concentration
S = corresponding average (bulk) dilution
ZU upper plume boundary (Z-coordinate)
ZL = lower plume boundary (Z-coordinate)
End of Output
CORMIXI: Submerged Single Port Discharges EPA Version 1.40 (February 1992)
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Start of session:
DISCHARGE/ENVIRONMENT DATA:
ENVIRONMENT PARAMETERS:
Cross-section = unbounded
Average depth HA = 6.00 m
Depth at discharge HD = 6.00 m
Ambient velocity UA = 0.1000 m/s
Darcy F F = 0.0097
Stratification Type STRCND = U
Surface density RHOAS = 1022.67 kg/m-3
Bottom density RHOAB = 1022.67 kg/m^3
DISCHARGE PARAMETERS:
Nearest bank = left
Distance to bank DISTB = 1250 m
Port diameter DO = 2.0000 m
Total area of opening AO = 3.1416 m-2
Discharge velocity UO = 3.59 m/s
Discharge flowrate QO = 11.3003 m^3/s
Discharge port height HO = 1 m
Vertical discharge angle THETA = 15.00 deg
Horizontal discharge angle SIGMA = 270.00 deg
Discharge density RHOO = 1018.43 kg/m-3
Density difference RHOD = 4.23 kg/m-3
Buoyant acceleration GPO = 0.0407 m/s-2
Discharge concentration Co = 100.000000 percent
______________________________________________________________________________
NON-DIMENSIONAL PARAMETERS:
Port densimetric Froude number FRO = 12.6
Velocity ratio R = 35.9
In this case, the upstream intrusion is very large, exceeding ten (10)
times the local water depth.
This may be caused by the small ambient velocity, perhaps in combination
with the strong buoyancy of the effluent, or alternatively, a strong
ambient stratification.
If the ambient conditions are quite unsteady (e.g. tidal), then the
CORMIX steady-state predictions of the upstream intrusion are probably
unrealistic. The plume predictions in the immediate near-field, prior
to the intrusion layer formation, are acceptable, however.
DESIGN CASE: Full plant with low ambient FILE NAME: st5 01
End of session: 7-29-1993 13:23:16
CORMIXI: Submerged Single Port Discharges EPA Version 1.40 (February 1992)
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
CORNELL MIXING ZONE EXPERT SYSTEM
CORMIXI: Submerged Single Port Discharges EPA Version 1.40 (February 1992)
------------------------------------------------------------- __--------------__
CASE DESCRIPTION
SITE NAME: Ghana
DISCHARGER NAME: Takoradi GS
POLLUTANT NAME: COW
FLUX VARIABLES
QO =0.1130E+02 MO =0.4065E+02 JO =0.4595E+00 SIGNJO = 1.0
ASSOCIATED LENGTH SCALES (METERS)
LQ = 1.77 LM = 23.75 Lm = 63.75 Lb = 459.44
Lmp = 99999.90 Lbp = 99999.90
NON-DIMENSIONAL PARAMETERS
FRO = 12.61 R = 35.97
FLOW CLASSIFICATION
_______________________________________ ______________________________________
BEGIN MOD101: DISCHARGE MODULE
PROFILE DEFINITIONS:
B - Gaussian 1/. (37%) half-width, normal to trajectory
C - centerline concentration
S * corresponding centerline dilution
PREDICTION
X Y Z S C B
0.00 0.00 1.00 1.0 0.100E+03 1.00
CROSSFLOWING DISCHARGE
PROFILE DEFINITIONS:
B - Gaussian l/e (37%) half-width, normal to trajectory
C = centerline concentration
S = corresponding centerline dilution
PREDICTION
X Y 2 S C B
0.00 0.00 1.00 1.0 0.100E+33 1.08
0.04 -0.64 1.18 1.1 0.937E+02 1.16
0.08 -1.28 1.36 1.1 0.882E+02 1.23
0.13 -1.91 1.55 1.2 0.832E+02 1.30
0.17 -2.55 1.73 1.3 0.788E+02 1.37
0.22 -3.19 1.92 1.3 0.749E+02 1.45
0.28 -3.83 2.11 1.4 0.713E+02 1.52
0.33 -4.47 2.30 1.5 0.681E+02 1.59
0.39 -5.10 2.50 1.5 0.651E+02 1.66
0.45 -5.74 2.69 1.6 0.624E+02 1.74
0.51 -6.38 2.89 1.7 0.599E+02 1.81
0.58 -7.02 3.09 1.7 0.575E+02 1.88
0.65 -7.66 3.29 1.8 0.554E+02 1.95
0.72 -8.29 3.49 1.9 0.534E+02 2.03
0.79 -8.93 3.70 1.9 0.516E+02 2.10
0.87 -9.57 3.91 2.0 0.498E+02 2.17
0.95 -10.21 4.12 2.1 0.482E+02 2.25
1.03 -10.85 4.34 2.1 0.467E+02 2.32
1.11 -11.48 4.56 2.2 0.453E+02 2.39
1.20 -12.12 4.78 2.3 0.440E+02 2.46
1.29 -12.76 5.00 2.3 0.427E+02 2.54
PROFILE DEFINITIONS:
B = Gaussian l/e (37%) half-width, normal to trajectory
C = centerline concentration
S = corresponding centerline dilution
PREDICTION
X Y Z S C B
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.65
1.29 -12.76 5.00 2.3 0.427E+02 3.6S
CONTROL VOLUME
PROFIIE DEFINITIONS:
BV - top-hat thickness,measured vertically
BH = top-hat half-width, measured horizontally in Y-direction
C - average (bulk) concentration
S = corresponding average (bulk) dilution
ZU = upper plume boundary (Z-coordinate)
ZL = lower plume boundary (Z-coordinate)
PREDICTION
X Y Z S C B
CONTROL VOLUME INFLOW
1.29 -12.79 5.00 2.3 0.427E+02 3.65
X Y Z S C BV BH ZU ZL
CONTROL VOLUME OUTFLOW
228.25 -12.79 6.00 35.5 0.282E+01 4.41 453.92 6.00 1.59
PROFILE DEFINITIONS5
BV - top-hat thickness,measured vertically
BH - top-hat half-width, measured horizontally in Y-direction
C - average (bulk) concentration
S * corresponding average (bulk) dilution
ZU - upper plume boundary (Z-coordinate)
ZL - lower plume boundary (Z-coordinate)
End of Output
CORMIX1: Submerged Single Port Discharges EPA Version 1.40 (February 1992)
11111111111111 11111111111111111111111111111111111111111111111111111111111111111
Appendix G
TechnicalSpecifications
(fromTenderDocuments)
*
13-23
13.3.1 General
1 Thissectiondescribesthe requirements
forclearingthesite,accessroadto
thesite,on-siteaccessroadsandparkingareas,andfueltransferfacilitiesai Sekondi
for SchemeB.
13.3.2 Definitions
13.3.4 MinimumTechnicalRequirements
13.4.3 MinimumTechnicalRequirements
3 Prior to placing fill over existing ground, the Contractor shall scarify the
ground surface. Zones of fill materialshall be placed and compacted in layers as
specified in the applicable sections of these specifications.
13.5.1 General
5 Backfillingof culvertand pipe work shall not be done priorto the Employer's
RepresentativeInspectionand approvalof the work.
13-29
13.6.1 General
1 This section describes the requirementsfor controlling water inflow on
construction areas so that these areasare maintainedIn a dry state.
13.6.2 Defintilons
13.6.4 MinimumTechnicalRequirements
13.7.1 General
13.7.2 Definitions
1 Borrowareasinvolveexploitation
ofoverburden
orsimilarmaterialsasdefined
in Section13.12,OpencutExcavation In Overburden.
4 Therehabilitation
of borrowareasshallbe donesothat the areais properly
drainedanddoesnotinterfere withnaturalwatercourses. Ditchingand bermingshall
be usedto prevenm
long-termerosionof excavation or fill slopesdue to runoff.
13.81 General
1 Thissectiondescribes therequirementsforhauling,dumping,andpermanent
disposalof all wastematerialswhichare unusableas fill arisingfromopencutand
underground excavations.
2 Surfacesof disposedmaterials
shallbe trimmedto regularlinesand grades
satisfactory
to the Employer'sRepresentative.
13.8.3 MinimumTechnicalRequirements
13.13.1 General
2 Thissectionalsodescribes
the requirements
for the transportation
and
permanent disposal of excavatedrock which is unsuitablefor constructionand the
transportation
of acceptable
materialto locationswhereit can be stockpiledIn
readinessforfuturetemporary
orpermanent useasrequiredbytheContractor.Rock
materialfor submarineexcavation
shallbe disposedof offshoreat a location
designated bytheEmployer'sRepresentative,
vAthina radiusof 10kmof thesite.
13.13.2 DefinItlons
1 Rockexcavation
isdefinedastheremoval
anddisposal
of bouldersinexcess
3
of 1.5m involume,in-situbedrock,
andanymaterial
withan in-situcompression
wavevelocity,
Vp,in excessof 1500m/s.
2 Dental
excavation
consists
oftheremovalanddisposal ofunsuitablematerial
foundin excavated
locksurfaces,
generallyinconfinedspacesoutsidethelinesand
gradesshownonthedrawingsrequiring
theuseof lightequipment
andconsiderable
manuallabour.
3 Controlled
perimeter blasting
includes,butis notlimitedto, presplitting
(also
knownaspreshearing), cushion blasting
andlinedrilling;inallcases,specialdrilling
andblastingmethods shallbeemployed to produce smoothrockfacesconforming
to the prescribedneatlinesandto minimize anyoverbreak andblasting-induced
fracturesin therockfacesoutsidetheexcavation lines.
4 Presplitting
consists ofdrillinga singlerowof closelyspacedholes,loading
all or selectedholeslightlyandcontinuously, andfiringthemsimultaneously before
anyadjoiningmainexcavation areais blastedto producea crackalongthelineof
presplitholesto whicha subsequent primaryblastcanbreak.Completion of the
blastingtechniques necessary to removethe adjoiningrockrequiresa suitable
burden/spacing ratio,a reducedexplosive chargein the lineof holesnearestthe
presplitlineanda limitonthedistance between thepresplitlineandthenearestline
of primaryblastholes.
13-58
- not loading the holesexcept for the possible useof specialexplosiveto split the
rock webs betweenadjacent holes
13.13.5 MinimumTechnicalRequimements
- for concrete and grout in place more than 60 hours, the maximum particle
velocities shall not ecceed 50 mmrs measuredat the concrete surface
13-61
- for existing structures Including structures not forming part of this Contract
adjacent to excavationareas, the maximumparticle velocitiesshall not exceed
50 mm/s measuredat these structures.
4 Should the results of this blast monitoring indicate that the Contractor's
blasting methods endanger either completed excavaton, completed grouting,
concrete work, or adjacent structures,the Contractorshall be required to alter his
blasting methodsto preventsuch damage.
13-62
Mapping
Anon, 'The Preparationof Maps and Plans in Terms of EngineeringGeology",
OuarterlyJournal of EngineeringGeology,Vol 5. pp 293-381, 1972.
Rock Descriptlons
InternationalSociety for Rock Mechanics,"Suggested Method for Quantitative
Descriptionof Discontinuitiesin Rock Masses', IntemationalJournal of Rock
Mechanics and Mining Sciences and GeomechanicsAbstracts, Vol 15, No. 6,
1978.
7 All mapping and other records shall remain available for review by the
Employer'sRepresentativeover the durationof the contractand become part of the
permanent project records handed over to the Employerat the completion of the
project. All maps shall show the site grid or survey referenceson each sheet.
13-63
13.14 UndergroundRockExcavation
13.14.1 General
13.14.2 Definitions
1 The Contractorshall assume full and sole responsibilityfor the safety of all
excavationsperformedunder this section unti final acceptanceof the Work.
6 The fresh air supply for the tunnels shall not be less than the greater of
- 5.5 m3 /min at the lace of the tunnel for each man underground plus
2 m3 /min/brake horsepower for all diesel units operating in the underground
excavations.
13.14.5 MinimumTechnicalRequirements
2 TheContractorshalldevelop,bytrial,controlled perimeterdrillingandblasting
techniqueswhichwill resultin a minimumof overbreak anda minimumof fracturing
of the rock beyondthe excavation linestherebyproducingsoundand reasonably
uniformsurfacesto thecompletedexcavations. Forthispurpose,theContractor shall
performtrialcontrolled
perimeter blastingin theunderground excavations, varyingthe
roundlength,burncut locationandgeometry, drill holepattern,explosivetypeand
quantity,blastingsequenceanddelaypattern.
3 Presplitting
shallnotbe usedas a controlledperimeterblastingtechniquein
undergroundexcavations.
4 Particlevelocitiesfor blastingshallgenerallynotexceedthefollowinglimits:
4 Should the results of this blast monitoring indicate that the Contractor's
blasting methods endanger either completed excavation, completed grouting,
concrete work or adjacent structures, the Contractorshall be required to alter its
blasting methodsto preventsuch damage.