Activity Immediate Optimistic Most likely pessimistic te

description predecessor
A ..... 4 7 10 7 1
B A 2 8 20 9 9
C A 8 12 16 12 1.777
D B 1 2 3 2 0.111
E D.C 6 8 22 10 7.111
F C 2 3 4 3 0.111
G F 2 2 2 2 0
H F 6 8 10 8 0.444
I E,G,H 4 8 12 8 1.777
J I 1 2 3 2 0.111
Ahmad Kmail 201610361

A START

E C
J

I G F

D B
a– te= (a+b+4m) /6 = 9.5 week

b – variance = ((20-2)/6)^2 = 9

-c

Paths Estimate time Activity variance


A-B-D-E-I-J 38=7+9+2+10+8+2 19.1=1+9+0.111+7.111+1.777+0.111
A-C-E-I-J 39=7+12+10+2+8 11.776=1+1.777+7.111+1.777+0.111
A-C-F-H-I-J 40=7+12+3+8+8+2 =1+1.777+0.111+0.444+1.777+0.111
5.22
A-C-F-G-I-J 34=7+12+3+2+8+2 4.78=1+1.777+0.111+1.777+0.111

d – 40 weeks

e – 5.22

42−40
f– Z= = 0.84 the probability is 0.322
√ 5.22