Pending List Civil-Sh
Pending List Civil-Sh
PLEASE NOTE ALL COST APPROVALS FOR ANY DESIGN WORK SUBMITTED ON THE CIVIL FRONT HAVE TO BE TAKEN FROM DEEPAK SIR BEFORE
EXECUTION.
PLEASE ENSURE YOU GO THROUGHT THE NOTES AND BOOKS ISSUED TO YOU BY SHEENA INC
WE HAVE GIVEN ROUNDING FREEDOM TO THE CIVIL TEAM TIME AND AGAIN AS LONG AS THE JOINT IS IN THE CENTRE. WE SHALL NOT TAKE
FINISHING ISSUES LATER ON SITE.
PLEASE LET US KNOW THE WHEN CAN WE SEE THE PROTOTYPES OF THE SAME
FALSE CEILING DRAWINGS ARE READY WILL ISSUE WAITING FOR 601 PROTOTYPE
ON SITE MEETING
WHEN EXECUTION BEGINS
ELECTRICALS NA
MARKINGS WILL BE SEEN ON SITE
TILE DETAILS WILL BE SHARED
AWAITING FINAL DRAWINGS FROM BY 09.03.2020 WITH DEEPAK
KITCHEN
MAGGPIE SIR, HEMANG SIR AND KANNAN
SIR FOR PROCURMENT
302
401
STAFF BATHROOM ISSUED BY SHEENA INC PENDING
STAFF ROOM DRAWINGS NOT ISSUED NA
BATHROOM 1 ISSUED BY SHEENA INC
BATHROOM 2 ISSUED BY SHEENA INC
BATHROOM 3 ISSUED BY SHEENA INC
POWDER BATHROOM ISSUED BY SHEENA INC
402
501
502
STAFF BATHROOM ISSUED BY SHEENA INC PENDING
STAFF ROOM DRAWINGS NOT ISSUED NA
BATHROOM 1 ISSUED BY SHEENA INC WORK STARTED
BATHROOM 2 ISSUED BY SHEENA INC WORK STARTED
BATHROOM 3 ISSUED BY SHEENA INC WORK STARTED
ON HOLD AS PROTOTYPE TO BE
POWDER BATHROOM ISSUED BY SHEENA INC
APPROVED BY MR.BAJAJ
WAITING FOR 402 PROTOTYPE
BALCONY ISSUED BY SHEENA INC
601
602
10TH FLOOR
STAFF BATHROOM ISSUED BY SHEENA INC MARKING TO SEE ON SITE
STAFF ROOM DRAWINGS NOT ISSUED NA
BATHROOM 1 ISSUED BY SHEENA INC WORK IN PROGRESS
BATHROOM 2 ISSUED BY SHEENA INC WORK IN PROGRESS
BATHROOM 3 ISSUED BY SHEENA INC WORK IN PROGRESS
BATHROOM 4 ISSUED BY SHEENA INC WORK IN PROGRESS
POWDER BATHROOM ISSUED BY SHEENA INC WORK IN PROGRESS
BALCONY DRAWINGS NOT ISSUED NA
DRAWINGS ARE READY WILL ISSUE WAITING FOR SAMPLE
FALSE CEILING
ON SITE MEETING PROTOTYPE
WHEN EXECUTION BEGINS
ELECTRICALS NA
MARKINGS WILL BE SEEN ON SITE
AWAITING FINAL DRAWINGS FROM
KITCHEN NA
MAGGPIE