MOCKUP INSPECTION Resp

onsibil
e

- Material Submission Supervisor


Obtain material approval
- Project Specs. QA/QC
- BQ Engineer

Joint inspection and


Supervisor
selection of mockup
area

Proceeding mockup works Supervisor

Carried out inspection according to ITP Supervisor


(Issue Inspection Request Form) QA/QC
Engineer

Fa
Inspection il
Rectify the defect

Pas
s
Proceed for re-
Records results
(signed Inspection Request inspection
Form)
& checklist
CONSTRUCTION SEQUENCE
FLOWCHART

Material Submission (MSA)

Re
jec Reply
Consultant
te
Comments/Change
d
Ap
pr
Method Statement/ITP
ov
Submission
ed

Consultant Reply Comments

Delivery of Material at Site

Checking of delivered material


as per approved material list

Request for Inspection

No
Passed Rectification

Yes

Start Installation Process

Final No
Inspection

End/Filing Records