Siasat/Kaji latarbelakang Pemaju
• mengenalpasti sebarang risiko
LOA
LETTER OF
APPOINTMENT
(SURAT
PERLANTIKAN)
REFERENCE
RULE 29 / KAEDAH 29
CONDITION OF ENGAGEMENT OF PROFESSIONAL ARCHITECT (COE) /
SYARAT-SYARAT GUNA KHIDMAT ARKITEK PROFESIONALL
10 - PERKARA 5 - PERKARA 4 - PERKARA 3 - PERKARA 2 - PERKARA 1 - PERKARA
HAK MILIK KEMATIAN/
TANGGUNGJAWAB TANGGUNGJAWAB PENGGANTUNGAN KETIDAK-
KLIEN DOKUMEN / DWG
ARKITEK UPAYAAN
16. Pengantunggan ARKITEK
1. Beri perkhidmatan perundingan
•Kalau klien tak bayar fee
sepertimana skop kerja dalam MOA •Arkitek gantung kerja. 20. Dok./Dwg
antara Arkitek & Klien 11. Sediakan semua 23. 25.
•Mula dr notis (tarikh • Dok/dw adalah hak
maklumat. Pengantaraan
-fee kena ikut SOMF gantung kerja.) Ar. Kecuali telah Sekiranya jenis
dinyatakan dlm MOA. /Mediation praktis `sole-prop’
-Arkitek hanya disara dr fee yg 12. Adakan wakil klien. •Sampai fee dibayar
dibayar klien sahaja •Kalau tak bayar juga… maka guna
•Bawa ke 21. Jika penamatan Ar. khidmat akan
13. Arahan kpd MC hanya
2. Guna khidmat perunding oleh klien. melalui Arkitek Mediation/Arbitration. Sampai fasa 24. Timbangtara tamat
Dok.Kontrak dan klien /Arbitration
3. Guna khidmat perunding oleh Aritek 14. Beri keputusan segera. 17. Penamatan dah bayar fee : Klien
Ikut MOA boleh tamat boleh ulangi r/bentuk
15. Bayar fi & caj kpd. PBT bila2 masa. atas tapak yg sama &
4. Menyelaras kerja perunding. utk kerja selenggara @
utk kelulusan. Notis penamatan oleh
Klien/Ar. renovation.
5. Arkitek tidak.bertanggungjawab. 60 hari dr tarikh notis. –Ar
prestasi perunding yang diguna khidmat
kena teruskan servis 22. Penyerahan
hinggalah tamat 60 hari. dok,dwg,spesifikasi bila
oleh klien. MOA tamat & bayaran
diselesaikan
6. Arkitek Bertanggungjawab prestasi 18. Arkitek kemukakan
Akaun.
perunding yang diguna khidmat oleh klien. Ar kemukakan baki fee &
tuntutan2 lain & caj byr.an
7. Dapatkan persetujuan klien - 60 hari ganti rugi.
30 hari dr tamat MOA.
8. Tidak boleh keluar arahan V.O tanpa
persetujuan klien kecuali :
- arahan PBT 19. Perlantikan Ar. Lain
- klien dah dimaklumkan Klien dah bayar semua
-amaun telah dipersetujui dlm MOA. tuntutan Ar.
Ar keluarkan LOR.
Klien bleh lantik Ar. Lain.
9. Pemeriksaan kerja secara berkala.
17. Penamatan
Ikut MOA boleh tamat bila2 masa.
PENAMATAN
Notis penamatan olehKlien/Ar.
60 hari dr tarikhnotis. –Ar kena teruskan servis hinggalahtamat 60
COE 17 hari.
ARBITRATION
24.Timbangtara / Arbitration
COE 24 RUJUK LAM / PAM / KLRCA
ACT 646 - ARBITRATION ACT 2005
(AMENDMENT 2011)
KEMATIAN /
KETIDAK-UPAYAAN 25.
ARKITEK Dirujuk kepada jenis praktis. Perkhidmatan gunakhidmat
akan tamat
COE 25
Sample COE questions
1 . S14 <Copyright act 1987> all doc + design remain property of archt
unless otherwise agreed to transfer to client (term + consideration)
2. Contract Documentation Phase Completed, archt received fees Client can
implement project using on the original site
3. Termination
After settlement of all fees
Archt deliver to the client copies of dwgs, spec + other doc.
Architects (Scale of Minimum Fees)
Rules 2010
____________________________________________
Sect. 35 Architects Act 1967
ARCHITECTS (SCALE OF MINIMUM FEES) 2010 - conferred by section 35 of Architects Act 1967 (Act 117)
PART I II III IV V
PRELIMINARY ARCH CONSULT SRVCS SCALE OF MIN FEES Method of Payment OTHER PAYMENTS GENERAL
SOMF rules
Citation & Reimbursable 1986
1 Commencement 6 Type of Services 23 Basic Services Fees expenses 31 revoked
(1) if before
3 categories complexity as (1 rules,
2 Intrepretation a 7 Phase of Basic Services (1) a schedule Basic Services Payment 30 ) a litography 32 continued
percentage of (i), (ii), (iii)- (2) sama
3 Payment of Fees a 8 Schematic Design Phase b schedule b tele mcm atas shj
If > 1 category. Fee calc postage/courie
4 Cost of Works b 9 Design Development Phase (2) separately 27 (1) 15%,30%,25%,25%,5% cr
1
5 Multiplier c 0 Contract Documentation Phase (3) Repetitive (2) payment monthly d travel
1 Contract Implementation & Non housing same
d 1 Management Phase a site/const period or intervals; e advert-tender/site staff
1 Non housing diff site
e 2 Final Completion Phase b and/or const period completion stage f fee to specialist under
b 13 Supplementary Services c housing equal to percentage ACP
(2 Taxes (latest
6c 14 Additional Services (4) conditions for repetitive (3) if only phase 4-5; ) 6%)
1
a 5 Advisory services (5) if vo reduction during const fees + 30%
1 Supplementary & additional
b 6 Survey & Investigation (6) if vo plus, base on 23(b) 28 Services Payment
1 Abandon/ABORTIVE
c 7 Planning & Development (7) WORKS 29 Fees cannot witheld even if
1 non completion phase client wtheld contractor for
d 8 Financial advisory (8) 1=time cost x multplier penalties
1 Exceptional Negotiations &
e 9 Protracted Involvement 24 Supplementary Services Fees LAD n other payments
2 Project Management
f 0 consultancy 25 Advisory services fees
2 Agreed between parties /
g 1 Miscellaneous 26 engagement
22 Specialist consultant
Type of Services Rule Fees Guidelines Rule
provided by ACP
Basic Services 7-12 Minimum Fees 23
Supplementary Services 13 MM / LAM / % 24
Additional Services 14-21 MM/Lump Sum / % 25
Basic Services of ACP
Basic Services Timeline
Schematic Design DO Submission
Communal block
10M 10M 10M
Condo Block A
Condo Block B
Condo Block C
5M
2M
8M
8M
27 (3) The ACP that engaged ONLY for the purpose of the CIMP & Final Completion Phase, the
ACP fees shall be paid increased by 30% of the fee payable for these phases .
Scenario:
You are new ACP that engaged for Work Progress at site is 60 %.
Calculate your fees.
Solution :
With that;
Rules 29 .... a Professional Architect shall only enter into an agreement for
architectural consultancy services according to the Architects (Scale of Minimum
Fees) Rules 2010, the Conditions of Engagement in Part One of the Third Schedule
and the Memorandum of Agreement in the Part One of the Fourth Schedule.
BASIC SERVICES + SUPPLEMENTARY (IF ANY)
+ ADDITIONAL (IF ANY) + OTHER PAYMENTS
COPC 3: Faithful discharge of duties and obligations.
(REIMBURSEMENT + SERVICE TAX)
(6) A Professional Architect shall prior to commencing architectural consultancy
services, notify the client in writing of the conditions of engagement and the
scale of professional fees and charges, including the method of calculating the RULES 23-26 SOMF
fees, in respect of the following :
(a) scope of work; RULES 6 -21 SOMF (* RULES 7 – BASIC SERVICES) SUPPLEMENTARY (IF ANY) +
ADDITIONAL (IF ANY)
(b) allocation of responsibilities; COE 1-10 = ARCHITECT; COE 12-15 = CLIENT
(c) limitation of responsibilities, if any; and COE 1-10 = ARCHITECT; COE 12-15 = CLIENT
REFERENCE
LOA Structure
ACP Address
Date
Address to (Client)
Project Title
Offer / Acceptance
Scope of work
a. Basic Services – SD, DD, CD, CI, FC
b. If any, Other Services – i.e. Supplementary , Additional Services
Other Contents
Suspension
Other Consultant
CONTENTS
Date : 31/02/2020 No. 1, Jalan Raya TAR
To, 11111 Bandar Baru Naik
CAKAP BESAR DEVELOPMENT SDN. BHD., Selangor
No. 58, Jalan Cari Makan
24567 Ulu Lurus Bendul
Selangor
(Attention : En. Amat Hebat)
The above matter is kindly referred. Subsequent to our earlier discussion, we thanked and accept
appointment as consulting Architect for the above project.
In reference to Rule 29, Architect Rules 1986 we shall only enter an agreement for architectural consultancy
services according to the Architects (Scale of Minimum Fees) Rules 2010, the Conditions of Engagement and
the Memorandum of Agreement.
Our terms of appointment are as follows:
1. Scope of work of Basic Services (according to Rules xx, SOMF 2010) as the following phases
a. Schematic Design Phase SD
b. Design Development Phase DD
c. Contract Documentation Phase CD
d. Contract Implementation Phase CI
e. Final Completion Phase FC
Perenggan 3: Situasi
Perenggan 4: Tidak diperlukan
Perenggan 5: Pengecualian oleh LAM
Perenggan 6: Prosedur
Perenggan 7: Tanpa pengetahuan
Apakah LOR?
1. Surat yang dikeluarkan oleh Arkitek
pertama sesuatu projek
2. yang pernah dilantik oleh klien
3. untuk melepaskan tugas dan
tanggungjawab projek tersebut
4. bagi membolehkan Arkitek kedua
mengambilalih tugas dan
tanggungjawab projek tersebut
5. tertakluk kepada syarat dan keadaan
pada Pekeliling Am Bil 2/2007 LAM
Perenggan ke-3: Situasi
Pekeliling Am Bil 2/2007 LAM: Garispanduan Mengenai Surat Perlepasan
Contoh keadaan:
• A Consortium would like to appoint you as the Professional Architect for a new suburbia township of 50
hectares comprising mixed commercial development and condominiums. The Consortium has bought the
adjoining site of 200 hectares with planning approval obtained for residential development of terrace
house, apartments, semi-D’s and bungalows to be developed separately at a later date under Phase 2.
• The estimated costs in construction of the following components in the new suburbia town centre are as
follows ;
Kos = RM 300,000,000.00
=RM 2, 727,500
Cont’ Jawapan 2008
Kos = RM 400,000,000.00
Kos = RM 15,000,000.00
Yuran professional bagi satu blok = [(RM 15 Juta – RM 8 Juta) x 5.0%] + RM 477,500
= [RM 350,000] + RM 477,500
= RM 827,500
1 100% RM 827,500
7 75% RM 827,500 x 75% x 7 = RM 4,344,375
= RM 5,171,875
Cont’ Jawapan 2008
• Total Fees
Jumlah RM 34,111,875.00
Cukai 6% RM 2,046,712.50
JUMLAH RM 36,158,587.50
2007
QUESTION 2 (total 20marks)
• You have been approached by your uncle who intends to develop his 100 hectares of rubber estate with
proposed construction of terrace houses, bungalows, shop office and condominiums to be carried out at
different phases of development.
• Candidates are to note all the following questions are based on the above scenario.
• Having formalized your practice, write a Letter to your uncle accepting your appointment as the Architect
for the proposed development, outlining your professional fees and mode of payment for the following
phase development at estimated construction cost comprising :-
Kos = RM 200,000.00
Kos = RM 300,000.00
TOTAL RM 704,250
Sambungan Jawapan 2007
• PHASE 4 : 6 Blok Kondominium 20 tingkat( Kategori 2 )
Kos = RM 10,000,000.00 bagi satu blok & RM 5,000,000.00 bagi Common Facilities
TOTAL RM 2,941,041.70
Cont’ Jawapan 2007
• Total Fees
Jumlah RM 5,441,541.68
Cukai 6% RM 326,492.50
JUMLAH RM 5,768,034.20
2012
QUESTION 2 (total 25marks)
• Harta SA SB has requested you to submit your fee proposal for Plot B of the develoment as follows:
• Three (3) storey podium with 2 storey basement car park comprising :
* Lobby, Communal & recreational facilities (GFA 1240 sq.m)
* 2 levels of elevated car park (GFA 12,000 sq.m)
* 2 storey basement car park (GFA 15,000 sq.m)
a) Based on the following cost estimates, compute the minimum fees for your fee proposal. (5 marks)
b) Write a letter offering your architectural consultancy services to the developer. (8 marks)
Cont’. 2012