You are on page 1of 7

UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: /6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1. Design, erection and
completion of
"Prefabricated steel
Structure Roof Trusses"
including all related steel
member such as purlin,
rafter, wall plates, valley,
valley board etc. and all
necessary accessories
i.e angle cleat, anchor
bolt and including all
plates, bolts and nuts,
welding, cutting, hoisting
and placing to position,
and all to Engineer's and
S.O approva
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: /6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2. Supply and fixed 30- 1 site
degree pitch roof clay 360m2 Metal saw supervisor Worker output 6 days
roof tile or other = 5m2/h
approved equivalent Drills 1 roofer
including all necessary
accessories all as per Bolt and nuts
1 unskilled 3 x 5m2/h= 15
manufacturer's details
Cutter labour
and to S. O’s approval.
15m2/h /
Measuring 360m2 / 8h
tape
=5.21 days

plyer
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: 3/6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3. Approved double side Hammer 1 site
aluminium foil on and 360m2 supervisor Worker output 4 days
including all necessary Mobile crane = 4m2/h
accessories all as per 1 roofer
manufacturer's details Bolts and nut
and to S.O's approval.
1 unskilled 3 x 4m2/h x
labour 8h= 96

360m2/h / 96

=3.75 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: 4/6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4. Approved Polygalas fiber Hammer 1 site
10Kg/m3 on and 360m2 supervisor Worker output 4 days
including all necessary Mobile crane = 4m2/h
accessories all as per 1 roofer
manufacturer's details Bolts and nut
and to S. O’s approval.
1 unskilled 3 x 4m2/h x
labour 8h= 96

360m2/h / 96

=3.75 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: 5/6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
5. Approved chicken wire Hammer 1 site
netting on and including 360m2 supervisor Worker output 4 days
all necessary accessories Mobile crane = 4m2/h
all as per manufacturer's 1 roofer
details and to S. O’s Bolts and nut
approval.
1 unskilled 3 x 4m2/h x
labour 8h= 96

360m2/h / 96

=3.75 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO:6 /7

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
6. Supply and fix cement Drills 1 site
plank facial board to 90m2 supervisor Worker output 2 days
manufacture detail and to Bolt and nuts = 2.5m2/h
S. O’s approval. 1 roofer
Cutter

Measuring 1 unskilled 3 x 2.5m2/h x


tape labour 8h= 60

90m2/h / 60
plyer
=1.5 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: ROOF PAGE NO: 7/7

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
7. Supply 600mm wide and Drills 1 site
fixed flashing on and 40m supervisor Worker output 2 days
including all necessary Bolt and nuts = 1.5m2/h
accessories all as per 1 roofer
manufacturer's details Cutter
and to S.O approval.
Measuring 1 unskilled 3 x 1.5m2/h x
tape labour 8h= 36

40m2/h / 36
plyer
=1.11 days

You might also like