You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/307323617

Aspect of Design and Developments in EAF

Article · December 2014

CITATIONS READS

0 1,406

2 authors, including:

S. K. Dutta
The Maharaja Sayajirao University of Baroda
77 PUBLICATIONS   166 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Steel plant waste; Low grade iron ore; Coating on MS for corrosion resistance View project

Processing of Low-grade Iron Ore View project

All content following this page was uploaded by S. K. Dutta on 30 August 2016.

The user has requested enhancement of the downloaded file.


STEEL MAKING VOL. 58 NO. 7

Aspect of Design and Developments


in EAF
Riddhi Oza and S. K. Dutta
Metallurgical and Materials Engg. Dept., Faculty of Tech. & Engg.
The M. S. University of Baroda, Vadodara

Electric Arc Furnace (EAF) is more popular due to good quality product of alloy steels. Construction and design
aspects of EAF are highlighted. Developments in EAF, with the aim of i) reducing operational cost, ii) improving
efficiency of the furnace, and iii) quality of products, are also discussed.

Introduction Construction
Electric Arc Furnace (EAF) is a furnace which supplies An electric arc furnace used for steelmaking consists
heat to the charging materials for melting by means of an of a refractory-lined vessel, usually water-cooled in larger
electric arc. Arc furnaces are range in sizes and capacities sizes, covered with a refractory roof, and through which
from small units of approximately one tonne capacity one or three graphite electrodes enter into the furnace. The
(used in foundries for producing casting products) to larger furnace is primarily consisting of main parts as follows:
units of up to 400 tonnes used for secondary steelmaking.
1. Furnace body
Temperatures of industrial electric arc furnace can be
increased to 1,800°C; while small laboratory units can be 2. Roof
gone up to 3,000°C. The first EAFs were developed by Paul
3. Gear for furnace body movement
Heroult of France, with a commercial plant established
in the United States in the year 1907. Figure 1 shows the 4. Electrode, their holder and support
basic layout of EAF[1]. Arc furnaces differ from induction 5. Electrical equipments like transformer, cables, electrode
furnaces, in that the charge materials is directly exposed control mechanism.
to an electric arc, and the current in the furnace terminals
passes through the charged materials. EAF process is 1) Furnace body
more popular due to: i) it requires less capital investment, It consists of shell, walls, door and spout.
ii) it has readymade market and easily available of raw
material (i.e. scrap) from local market, iii) it requires less a) Furnace Shell
installation period, and iv) it gives high metallic yield and The furnace shell is typically made of carbon steel
good quality product. High metallic yields compiled with sheets that are rolled and welded. The furnace shell must
high-quality of the product obtained in EAFs are fully have sufficient strength to hold weight of the lining and
exploited in the production of costly alloy steels. EAF can metal and withstand the pressure of the lining which
be operated in AC or DC sources. But AC – EAFs are more expands on heating; it also should not be heated to more
commonly used. than 100 to 150°C. The top of the shell is open and is
covered with a tight fitting but removable dome shaped
roof structure. Shape of the shell determines shape of
reaction chamber. Hearth can be cylindrical, conical or
cylindro-conical. The shell bottom is usually spherical
which ensures maximum strength. Other openings are
provided in the furnace shell for oxygen, lime and carbon
injections, oxy-fuel burners, etc. The hearth may be
hemispherical in shape, or in an eccentric bottom tapping
furnace. The hearth has the shape of a halved egg[2].
b) Furnace Walls
They are cylindrical in shape and extend from slag line
Fig. 1: Basic Layout of an EAF to top of the shell. Height depends on nature of charge

IRON & STEEL REVIEW | 202 | DECEMBER 2014


STEEL MAKING VOL. 58 NO. 7

material. If the charge material is light in weight and lowered by manual or automatic controls. These controls can
oxygen lancing is done; then height of wall should be more. be operated manually when the bottoms of the electrodes
Gap is left in the wall during lining of wall for putting of are raised to the roof or when electrodes are shifted. The
taphole. The furnace is lined with refractory. Depending on mechanism of raising and lowering the electrodes are shown
type of melting practice, either acid or basic refractory are in Figure 4[2]. The furnace designer will make the electrode
used; generally basic lining is used to remove sulphur and circle as small as possible to increase the speed of melting.
phosphorus from the melt. For efficient melting, the arc must be stabilised to supply
uniform amount of energy. The electrodes should be vertical
c) Door
from all sightings around the furnace.
The shell has door openings cut into it and a cooling
frame welded around the door. The door-lifting supports
are also welded onto the shell. Charging door is
diametrically opposite to spout. The size of charging door
should be so chosen that free access for visual inspection
and fettling of the hearth and free entry of charging boxes
should be easily done. The door width is about 0.25 of
the diameter of reaction chamber and height is 0.8 of the
width. Door is lined with basic bricks and water cooled.
d) Spout
The spout opening is cut-out of the shell and the spout
frame attachment welded onto the shell. Tapping spout
is a U-shaped chute lined inside with fireclay brick. It Fig. 2: Furnace slide valve used to hold back slag
is attached to furnace shell at an angle of 10-12o. New
designs and changing the locations of tapholes may reduce
the physical and mechanical problems encountered with
the spout. One of these alternatives is the side slide gate
spout (Figure 2), and another is eccentric bottom tapping
with the use of a slide gate (Figure 3)[2].
2) Roof
The roof is a domed shape and rises about 1% in span
towards the centre. Roof has three holes to allow insertion
of the electrodes. There are three types of roofs: i) fixed
roof for small furnace and charging take place through the
door, ii) swing roof along with electrodes swings clearly
off the body of the furnace to allow charging from top; iii)
lifting roof is lifted from the furnace body and moves to one Fig. 3: Eccentric bottom taphole furnace (a) With slide gate attached to
side to facilitate top charging to the furnace. furnace bottom (b)

3) Gear for furnace body movement 5) Electrical Equipments


Body of furnace needs to be titled nearly through 450 on The electric arc furnace secondary electrical circuit
the tapping side and 150 on the slagging side. The tilting consists of several components including the delta closure,
gear is operated either by hydraulic or electric. Hydraulic power cables, bus tubes, etc. The regulating system
tilting arrangement is very smooth. maintains approximately constant current and power
input during the melting of the charge. The mast arms
4) Electrode System
holding the electrodes carry heavy bus bars, which may
A typical alternating current furnace has three be hollow water-cooled copper pipes carrying current to
electrodes and for direct current furnace has one electrode. the electrode holders. Heavy water-cooled cables connect
Electrodes are round in section, and typically in segments the bus tubes/arms with the transformer located adjacent
with threaded couplings, so that as the electrodes wear, to the furnace. To protect the transformer from heat, it
new segments can be added easily. The electrode can be is installed in a vault. A mid-sized modern steelmaking
graphite or carbon. The electrodes are supported on three furnace would have a transformer rated about 60 MVA,
separate arms and held to the electrode arm by a spring- with a secondary voltage between 400 and 900 volts and
clamped, pneumatically released electrode holder. The a secondary current in excess of 44 kilo amperes. To
electrode arms support the electrodes, holders, bus tubes, produce a tonne of steel in an electric arc furnace requires
and transformer power cables. The electrodes are raised and approximately 400 to 500 kWh per metric tonne.

IRON & STEEL REVIEW | 204 | DECEMBER 2014


STEEL MAKING VOL. 58 NO. 7

➢ Height of reaction chamber


The diameter-to-depth ratio of the bath operating by the
basic process is usually taken as:
D = 5H ---- (1)
Where, D = bath diameter, m
H = total depth of the bath, m.
In existing furnaces, the height (h1), of the spherical
portion is roughly 1/5 of the total bath depth:
h1 = 0.2H ---- (2)
And the depth of the conical portion:
h2 = 0.8H ---- (3)
The total volume of the bath, Vb , is the sum of the
volumes of the truncated cone and that of the spherical
segment.
By virtue of the relationships given above:
Vb = 0.0968 D3 (m3) ---- (4)
Therefore,
0.0968 D3 = 16.675 (m3).
Fig. 4: Apparatuses for raising and lowering electrodes. [(a) Arrangement
of electrode, (b) Electrode arm arrangement with power-operated Therefore, from equations 1, 2 and 3; getting the
electrode holder, (c) Arrangement of electrode arm using power operated following values:
electrode holders using piston]
D = 5.564 m, H = 1.113 m,
Design of Furnace h1 = 0.223 m, h2 = 0.89 m.
The calculations for design of different parts of an Diameter of spherical bottom,
electric arc furnace are on the basis of the Figure 5[3]. d = D - 2(h2) = 5.564 - 2(0.89) = 3.784 m.
➢ Shape and dimensions of the bath ➢ Dimensions of the reaction chamber
The hearth is usually conical-spherical with the banks The banks of a furnace are usually made of 0.1 to 0.2 m
inclined at an angle of 450. This form ensures quick above the door sill level or the bath surface, to ensure that
melting. the slag does not contact the brickwork or reach the joint
between the wall blocks and banks.
Since density of steel at melting point is 6.88 x 103 kg/
m 3, hence one tonne of molten steel occupies 0.145 m3 The diameter of the reaction chamber is:
i.e. Vm=0.145 m3. Therefore, 100 tonnes molten steel will Drc = D + 0.2 (m) ---- (5)
occupy 14.5 m3. (Vm is volume of liquid steel.) Drc = 5.564 + 0.2 = 5.764 m.
The volume of slag, Vslag=15% of Vm i.e., Vslag=0.15 x It is recommended that the following relationship be used
14.5=2.175 m3. in determining the height of the reaction chamber (H1),
Therefore, total volume will be 16.675 m3. H1= (0.4 to 0.6) Drc ---- (6)
For large-capacity furnaces, taking the lower value (i.e. 0.4)
Therefore, H1= 2.306 m
The height of the roof (h3 ) is:
h3 = 0.15 D1 ---- (7)
Where, D1 is ≈ 1.0 m wider than Drc.
D1 = Drc + 1.0,
h3 = 0.15 (Drc + 1.0) ---- (8)
Therefore, h3 = 0.15 (5.764 + 1.0) = 1.015 m
The total height of the roof above the bath level is given
as:
H2 = H1 + h3 ---- (9)
Fig. 5: Cross-sectional cut-out of an EAF for design basis of calculations H2 = 2.306 + 1.015 = 3.321 m.

IRON & STEEL REVIEW | 206 | DECEMBER 2014


STEEL MAKING VOL. 58 NO. 7

The recommended slope (S) for the inclination of the be done at a reduced power and short arcs (a lower tap).
wall is roughly 10% of the height from the line of banks to High power can be supplied to furnaces more easily by
roof skewbacks: increasing the secondary voltage.
Slope (S) = H1 x 0.1 = 2.306 x 0.1 = 0.2306 m The upper voltage tap of the secondary voltage for small
furnaces can be selected by using the following empirical
The diameter of the reaction chamber at the level of the
formulae.
roof skewbacks (i.e. at the level of the upper edge of the
furnace shell) is: For basic furnaces:
D1 = Drc + 2S ---- (10) = 490.6 V ---- (14)
D1 = 5.764 + 2 x 0.221 = 6.206 m. The largest furnaces have the upper voltage tap within
The thickness of the lining is found by thermal analysis a range of 450 to 840 V.
from the condition that the furnace shell should not be The lower voltage tap, which is resorted during the
heated above 200°C at the end of the furnace campaign. reducing period of heat, should not exceed 120 to 163 V
With the refractory lining d m thick, the furnace will have (greater values relating to the largest furnaces). A high
the following inside diameter of the shell: voltage, therefore longer arcs, might cause overheating of
Di.sh = Drc + 2 d ---- (11) the lining of the roof and walls; that make it difficult to
maintain optimum slag conditions in the furnace.
Where, d = 0.6 m for 100 to 200 tonnes capacity furnace.
Therefore, Di.sh = 5.764 + 2 x 0.6 = 6.964 m. Electrode Diameter
Thickness of shell is kept around 0.05 m. The electrodes possess an appreciable electric resistivity
Therefore, outer side diameter of the shell: and are heated by the passing current, which results in up
to 8% of the energy supplied being lost as heat. Electrical
Do.sh = 7.064 m.
losses could be reduced by using electrodes of a larger
Transformer Power and Furnace Productivity diameter, i.e. by lowering the current density.
Power of transformer can be found by means of energy The diameter of electrodes can be found by the formula:
balance for a given capacity and tap to tap time. Table 1
shows some recommendations on transformer power for
furnaces of different size, which are based on experiences
in many countries[3]. Where:
By analogy with the existing furnaces, the transformer
power (Pap) may be taken as 35 MVA. Noting the
inevitable switching off of the furnace during melting
required to push the scrap from the banks, partial I = linear current, (A),
operation of the furnace at a reduced voltage when the d = electrode resistivity at 500°C (for graphitised
arcs are open and radiation of much heat onto the walls electrodes d = 10 ohm. mm2/m),
and roof, the average power consumed during the melting K = coefficient (for graphitised electrodes K = 2.1 W/cm2).
period can be found by using a factor of 0.8 – 0.9:
The diameter of electrodes can also be found by the
Pav = 0.8 Pap = 0.8 x 35,000 = 28,000 KVA ---- (12)
allowable current density (A/cm2).
Useful power consumed during the melting period:
Energy Distribution[4]
Pu = Pav cos j hel = 28,000 x 0.85 x 0.9 = 21,420 KW --(13)
The energy required for melting of metal scrap:
➢ Voltage taps Q = mc (q2 - q2) + mL ---- (16)
For normal course of a melting process, it is necessary Where,
to vary the power and the length of arc during various m = mass to be melted (kg),
periods of heat. This is achieved by tapping the high c = specific heat capacity of metal to be melted (kJ/Kg°C),
voltage winding of the furnace transformer. The melting q2 = melting point of the metal (°C),
period is carried out at full power of the transformer and q2 = room temperature (°C), and
long arcs (the highest voltage tap), while refining can L = latent heat of fusion of the metal.
Table 1: Recommended Transformer Power for Furnaces
Furnace Capacity (t) g 25 50 75 100 150 200 250 400
Transformer Power for Alloy Steel, (MVA) 15 - 18 20 - 25 -- 30 - 35 -- 55 - 70 -- --
Transformer Power for Carbon Steel, (MVA) 18 - 22 28 - 32 30 - 45 40 - 50 45 - 60 60 - 80 90 120
Transformer Power for Super-powerful Furnace, (MVA) -- 40 -- 60 -- 125 -- 200

IRON & STEEL REVIEW | 208 | DECEMBER 2014


STEEL MAKING VOL. 58 NO. 7

Developments in EAF complexity of the fume and dust collection equipment


varies from a simple 4th hole connector to an entire
Developments in EAF take place with the aim of:
separate room for the melting furnace in which the
i) Reducing operational cost, ii) Improving efficiency of the
fumes and dust are collected and where the liquid metal
furnace, and iii) Quality of products.
is tapped into a ladle that is brought to the furnace and
Developments in EAF can be sub-divided into three then removed through a dust protection door. Noise can
heads as follows: be easily controlled by DC-EAF.
I Design Aspect: 8. 5th hole g Nowadays, 5th hole in the roof is common for
larger furnaces for continuous charging of sponge iron.
1. Rapid melting technology g The rate of melting of
solid charge determines the total heat time and hence II Process Modifications:
productivity of the furnace. Increasing size of EAFs has 1. Foams slag practice g That prevent radiation heating
been the application of High Power (HP) and Ultra High
to furnace wall from arc and help to penetrate lighter
Power (UHP) transformers to feed these furnaces. The
sponge iron charge in slag-metal interface.
use of lower power factors and higher currents allowed
high power inputs to be achieved with short arcs; that 2. Scrap preheating g Scrap preheating is done by hot flue
are the concept of UHP. Use of UHP in place of regular gases; due to that energy consumption of charge melting
power supply results in saving time of melting and is decreased.
refining of the order of 30% and 10% respectively. Single 3. Hot tundish and ladle g By pre-heating tundish and
electrode DC-EAF is also used for faster melting. ladle, chilling effect of liquid metal can be avoided.
2. Water-cooled panels g Use of water cooling systems Temperature of liquid metal can be maintained.
for walls and roof becomes absolutely necessary for 4. Coupling with ladle furnace g EAF-LF combination
economical operation. The water-cooled panels are give very good quality of products. Very low amount of
of tube-on-tube design of steel pipes and cover up to gases are present in the products. Productivity of EAF
85% of the wall above the slag line. Greater distance is also increased due to EAF act as melting unit only
between electrodes and side wall, as well as larger and refining of molten metal take place at LF. After
capacity for receiving light scrap are taking place due to melting of charges, molten metal is transferred to LF
water cooling panels. Water-cooled panels are reducing for refining and again furnace is ready for taking the
power-on time by 13% and increasing productivity by charges; so tap-to-tap time is drastically decreased and
10%. hence number of heats per day is increased.
3. Oxy–fuel burners g Oxygen – fuel burners are installed 5. Process automation g For meeting specifications of
in the cold spots of the furnace, so that the time taken
products, process automation is must. For proper heat
to melt scrap in these areas is the same as that taken
and mass calculations, automation is essential.
by the arc at the hotspots. Hence, lower electrical power
consumption results together with an improved heat III Charge Modifications:
balance. Oxygen/natural gas burners can help faster
1. Use of sponge iron g To substitute the scrap, sponge
melting the charge and reduce electrical consumption
iron can be used. Main advantages of sponge iron are: i)
and electrode usage while shortening the melting time
uniform composition, ii) uniform size, and iii) very low
from tap to tap. Improper use of these burners can
tramp elements (0.02%) with respect to scrap (0.13 to
cause excessive oxidation of the melt and the electrodes,
as well as that can reduce the life of the refractory 0.73% tramp elements). Hence, good quality of products
lining. can be produced by adding sponge iron as charge
materials.
4. Eccentric bottom tapping g Figure 3 shows the
eccentric bottom tapping with the use of a slidegate. 2. Use of hot metal in EAF g By using hot metal in EAF:
Eccentric bottom tapping ensures almost slag free liquid i) Energy consumption can be reduced; ii) Scrap
metal tapping in the teeming ladle. shortage can be overcome, iii) Tap-to-tap can be
decreased, and iv) Productivity can be increased
5. Automatic alloy feeder g With the increasing size of
drastically, i.e., more heats can be made per day.
EAF, the net addition has increased in proportion. For
meeting specifications of products, the additions have to References
be made more accurately. For these reasons, automatic
1) R. Preston, American Steel, Avon Books, New York, 1991.
weighting of additions as per the auto-control directions
are made. 2) ASM Metal Handbook Vol. 15 for Casting, 9th Edition
6. Coated electrode g Consumption of electrode surface Metal Handbook, pp. 537-547.
(40%) due to oxidation which can be reduced by coating. 3) F. P. Edneral, Electrometallurgy of Steel and Ferro-
7. Emission and noise control g For larger furnaces, 4th alloys, MIR Publishers, Moscow, 1979, pp.1-87.
hole system is common, where a duct tape is made 4) A.G.E. Robiette, Electric Melting Practice, Griffin,
directly onto the roof to evacuate smoke and fumes. The London, 1972, pp. 1-95.

IRON & STEEL REVIEW | 210 | DECEMBER 2014

View publication stats

You might also like