Professional Documents
Culture Documents
net/publication/307323617
CITATIONS READS
0 1,406
2 authors, including:
S. K. Dutta
The Maharaja Sayajirao University of Baroda
77 PUBLICATIONS 166 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Steel plant waste; Low grade iron ore; Coating on MS for corrosion resistance View project
All content following this page was uploaded by S. K. Dutta on 30 August 2016.
Electric Arc Furnace (EAF) is more popular due to good quality product of alloy steels. Construction and design
aspects of EAF are highlighted. Developments in EAF, with the aim of i) reducing operational cost, ii) improving
efficiency of the furnace, and iii) quality of products, are also discussed.
Introduction Construction
Electric Arc Furnace (EAF) is a furnace which supplies An electric arc furnace used for steelmaking consists
heat to the charging materials for melting by means of an of a refractory-lined vessel, usually water-cooled in larger
electric arc. Arc furnaces are range in sizes and capacities sizes, covered with a refractory roof, and through which
from small units of approximately one tonne capacity one or three graphite electrodes enter into the furnace. The
(used in foundries for producing casting products) to larger furnace is primarily consisting of main parts as follows:
units of up to 400 tonnes used for secondary steelmaking.
1. Furnace body
Temperatures of industrial electric arc furnace can be
increased to 1,800°C; while small laboratory units can be 2. Roof
gone up to 3,000°C. The first EAFs were developed by Paul
3. Gear for furnace body movement
Heroult of France, with a commercial plant established
in the United States in the year 1907. Figure 1 shows the 4. Electrode, their holder and support
basic layout of EAF[1]. Arc furnaces differ from induction 5. Electrical equipments like transformer, cables, electrode
furnaces, in that the charge materials is directly exposed control mechanism.
to an electric arc, and the current in the furnace terminals
passes through the charged materials. EAF process is 1) Furnace body
more popular due to: i) it requires less capital investment, It consists of shell, walls, door and spout.
ii) it has readymade market and easily available of raw
material (i.e. scrap) from local market, iii) it requires less a) Furnace Shell
installation period, and iv) it gives high metallic yield and The furnace shell is typically made of carbon steel
good quality product. High metallic yields compiled with sheets that are rolled and welded. The furnace shell must
high-quality of the product obtained in EAFs are fully have sufficient strength to hold weight of the lining and
exploited in the production of costly alloy steels. EAF can metal and withstand the pressure of the lining which
be operated in AC or DC sources. But AC – EAFs are more expands on heating; it also should not be heated to more
commonly used. than 100 to 150°C. The top of the shell is open and is
covered with a tight fitting but removable dome shaped
roof structure. Shape of the shell determines shape of
reaction chamber. Hearth can be cylindrical, conical or
cylindro-conical. The shell bottom is usually spherical
which ensures maximum strength. Other openings are
provided in the furnace shell for oxygen, lime and carbon
injections, oxy-fuel burners, etc. The hearth may be
hemispherical in shape, or in an eccentric bottom tapping
furnace. The hearth has the shape of a halved egg[2].
b) Furnace Walls
They are cylindrical in shape and extend from slag line
Fig. 1: Basic Layout of an EAF to top of the shell. Height depends on nature of charge
material. If the charge material is light in weight and lowered by manual or automatic controls. These controls can
oxygen lancing is done; then height of wall should be more. be operated manually when the bottoms of the electrodes
Gap is left in the wall during lining of wall for putting of are raised to the roof or when electrodes are shifted. The
taphole. The furnace is lined with refractory. Depending on mechanism of raising and lowering the electrodes are shown
type of melting practice, either acid or basic refractory are in Figure 4[2]. The furnace designer will make the electrode
used; generally basic lining is used to remove sulphur and circle as small as possible to increase the speed of melting.
phosphorus from the melt. For efficient melting, the arc must be stabilised to supply
uniform amount of energy. The electrodes should be vertical
c) Door
from all sightings around the furnace.
The shell has door openings cut into it and a cooling
frame welded around the door. The door-lifting supports
are also welded onto the shell. Charging door is
diametrically opposite to spout. The size of charging door
should be so chosen that free access for visual inspection
and fettling of the hearth and free entry of charging boxes
should be easily done. The door width is about 0.25 of
the diameter of reaction chamber and height is 0.8 of the
width. Door is lined with basic bricks and water cooled.
d) Spout
The spout opening is cut-out of the shell and the spout
frame attachment welded onto the shell. Tapping spout
is a U-shaped chute lined inside with fireclay brick. It Fig. 2: Furnace slide valve used to hold back slag
is attached to furnace shell at an angle of 10-12o. New
designs and changing the locations of tapholes may reduce
the physical and mechanical problems encountered with
the spout. One of these alternatives is the side slide gate
spout (Figure 2), and another is eccentric bottom tapping
with the use of a slide gate (Figure 3)[2].
2) Roof
The roof is a domed shape and rises about 1% in span
towards the centre. Roof has three holes to allow insertion
of the electrodes. There are three types of roofs: i) fixed
roof for small furnace and charging take place through the
door, ii) swing roof along with electrodes swings clearly
off the body of the furnace to allow charging from top; iii)
lifting roof is lifted from the furnace body and moves to one Fig. 3: Eccentric bottom taphole furnace (a) With slide gate attached to
side to facilitate top charging to the furnace. furnace bottom (b)
The recommended slope (S) for the inclination of the be done at a reduced power and short arcs (a lower tap).
wall is roughly 10% of the height from the line of banks to High power can be supplied to furnaces more easily by
roof skewbacks: increasing the secondary voltage.
Slope (S) = H1 x 0.1 = 2.306 x 0.1 = 0.2306 m The upper voltage tap of the secondary voltage for small
furnaces can be selected by using the following empirical
The diameter of the reaction chamber at the level of the
formulae.
roof skewbacks (i.e. at the level of the upper edge of the
furnace shell) is: For basic furnaces:
D1 = Drc + 2S ---- (10) = 490.6 V ---- (14)
D1 = 5.764 + 2 x 0.221 = 6.206 m. The largest furnaces have the upper voltage tap within
The thickness of the lining is found by thermal analysis a range of 450 to 840 V.
from the condition that the furnace shell should not be The lower voltage tap, which is resorted during the
heated above 200°C at the end of the furnace campaign. reducing period of heat, should not exceed 120 to 163 V
With the refractory lining d m thick, the furnace will have (greater values relating to the largest furnaces). A high
the following inside diameter of the shell: voltage, therefore longer arcs, might cause overheating of
Di.sh = Drc + 2 d ---- (11) the lining of the roof and walls; that make it difficult to
maintain optimum slag conditions in the furnace.
Where, d = 0.6 m for 100 to 200 tonnes capacity furnace.
Therefore, Di.sh = 5.764 + 2 x 0.6 = 6.964 m. Electrode Diameter
Thickness of shell is kept around 0.05 m. The electrodes possess an appreciable electric resistivity
Therefore, outer side diameter of the shell: and are heated by the passing current, which results in up
to 8% of the energy supplied being lost as heat. Electrical
Do.sh = 7.064 m.
losses could be reduced by using electrodes of a larger
Transformer Power and Furnace Productivity diameter, i.e. by lowering the current density.
Power of transformer can be found by means of energy The diameter of electrodes can be found by the formula:
balance for a given capacity and tap to tap time. Table 1
shows some recommendations on transformer power for
furnaces of different size, which are based on experiences
in many countries[3]. Where:
By analogy with the existing furnaces, the transformer
power (Pap) may be taken as 35 MVA. Noting the
inevitable switching off of the furnace during melting
required to push the scrap from the banks, partial I = linear current, (A),
operation of the furnace at a reduced voltage when the d = electrode resistivity at 500°C (for graphitised
arcs are open and radiation of much heat onto the walls electrodes d = 10 ohm. mm2/m),
and roof, the average power consumed during the melting K = coefficient (for graphitised electrodes K = 2.1 W/cm2).
period can be found by using a factor of 0.8 – 0.9:
The diameter of electrodes can also be found by the
Pav = 0.8 Pap = 0.8 x 35,000 = 28,000 KVA ---- (12)
allowable current density (A/cm2).
Useful power consumed during the melting period:
Energy Distribution[4]
Pu = Pav cos j hel = 28,000 x 0.85 x 0.9 = 21,420 KW --(13)
The energy required for melting of metal scrap:
➢ Voltage taps Q = mc (q2 - q2) + mL ---- (16)
For normal course of a melting process, it is necessary Where,
to vary the power and the length of arc during various m = mass to be melted (kg),
periods of heat. This is achieved by tapping the high c = specific heat capacity of metal to be melted (kJ/Kg°C),
voltage winding of the furnace transformer. The melting q2 = melting point of the metal (°C),
period is carried out at full power of the transformer and q2 = room temperature (°C), and
long arcs (the highest voltage tap), while refining can L = latent heat of fusion of the metal.
Table 1: Recommended Transformer Power for Furnaces
Furnace Capacity (t) g 25 50 75 100 150 200 250 400
Transformer Power for Alloy Steel, (MVA) 15 - 18 20 - 25 -- 30 - 35 -- 55 - 70 -- --
Transformer Power for Carbon Steel, (MVA) 18 - 22 28 - 32 30 - 45 40 - 50 45 - 60 60 - 80 90 120
Transformer Power for Super-powerful Furnace, (MVA) -- 40 -- 60 -- 125 -- 200