TUN RAZAK EXCHANGE (TRX) LIFESTYLE

QUARTER
Work Method of Statements for Power Float and
Rectification Work
WCT BERHAD
TP02 : SUPERSTRUCTURE, FAÇADE AND
BLOCKWORKS
DOCUMENT NUMBER: WCT_TP02_MS_AR_0001
REVISION NO: 08 | Revision Date: 07/12/2019

SUBMISSION
PREPARED REVIEWED APPROVED
Signature Signature Signature

Name: Yong Chee Fei Name: Mohd Fauzi Bin Ujang Name: Ng Eng Beng
Position: Architecture Manager Position: QA/QC Manager Position: Senior Project Manager
Company: WCT Berhad Company: WCT Berhad Company: WCT Berhad
Date: 07/12/2019 Date: 07/12/2019 Date: 07/12/2019
REVIEW & APPROVAL
LLPM’S REVIEW CONSULTANT’S REVIEW APPROVAL (LLPM)
Signature Signature Signature

Name: Name: Name:


Position: Position: Position:
Company: Company: Company:
Date: Date: Date:
Comments: Comments: Comments:

A- Approved. B- Approved with Comment. C- Rejected.


WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

RESPONSE SHEET

NO. CONSULTANT’s COMMENT TRADE CONTRACTOR’s RESPONSE

1 Noted and comply. Refer response No. 2


to 5
2 Noted and comply. Refer Method
Statement WCT_TP02_MS_AR_0008 for
Screeding Work

3 Noted and comply. Refer Appendix A

4 Noted and comply. Refer Appendix B

5 Noted and comply. Refer Method


Statement WCT_TP02_MS_AR_0008 for
Screeding Work.

NO. LLPM’s COMMENT TRADE CONTRACTOR’s RESPONSE

1 Noted and comply. Comment on Item 1 &


3 shall refer to Method Statement –
WCT_TP02_MS_ST_0033 Rev.00 (Base
Concrete Rectification Works)
Comment on Item 2) – Refer Appendix B

Noted and comply. Refer Method


2 Statement – WCT_TP02_MS_ST_0033
Rev.00 (Base Concrete Rectification
Works). Item 6.3.6 rectification is not
relevant for power float rectification. It
being removed from this Method
3 All relevant comments of ITP page 2 of 2 Statement.
Noted and comply. Refer Appendix B
(ITP)
Noted and comply. Refer Appendix B
4 (Inspection Checklist)

Tun Razak (TRX) Lifestyle Quarter 2 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

REVISION CONTROL

Rev. No. Rev. Date Details of Amendment

00 24/08/18 First issue

Second issue

Item 3.3 Tools and equipment


3) Hand Trowel

Item 3.4 Material


a) Concure 90 Curing Compound
b) Lafarge Portland Cement (OPC)

Item 6.4 Sequential Method of Construction


01 11/10/18 a) Item 6.4.1 – Preparation Base Concrete
b) Item 6.4.2 – Application of Power Float
c) Item 6.4.3 –Curing and Protection
d) Item 6.4.4 – Application of Floor Hardener material
e) Item 6.4.5 – Rectification Works

Item 6.4.5 Rectification Works


 Defective surface will be chipped off.
 Patch back the chipped off area and smoothen by hand
trowel.

Third Issue

Item 3.2 Plant and


02 12/02/2019
Machinery Item 6.2

Temporary Works

Item 6.3 Sequential Method of Construction


6.3.1 Preparation of Base Concrete by ready mixed concrete

Fourth Issue

Item 3.4 Material


03 26/03/2019
Item 6.3.4.3 Application of Non- Shrink Grout
3) Item I and iv

Appendices 9 – ITP

Tun Razak (TRX) Lifestyle Quarter 3 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

Rev. No. Rev. Date Details of Amendment

Fifth Issue

04 17/04/2019 Item 2.0


Item 3.1
Item 3.3
Item 3.4
Item 5.0
Item 6.3

Sixth issue

05 10/07/2019 Item 6.3.1


Item 6.3.2
Appendix B
Appendix C

Seventh Issue
06 29/08/2019
Table of Content
Item 6.3.1, 6.3.2, 6.3.3, 6.3.5, 9.0
Appendix B
Added – Appendix C, D and E

Eight Issue
07 03/10/2019
Item 6.3.4 Rectification Work for rough surface

Adding Item 6.3.5 Rectification Work for uneven slab / sunken


surface

Nine Issue
08 07/12/2019
Remove Item 6.3.6
Changes of Appendix A and B

Tun Razak (TRX) Lifestyle Quarter 4 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

TABLE OF CONTENT

1.0 PURPOSE AND SCOPE ................................................................................................................... 6

2.0 REFERENCES ................................................................................................................................... 6

3.0 RESOURCE PLANNING ................................................................................................................... 6


3.1 PERSONNEL/ MANPOWER ............................................................................................................. 6
3.2 PLANT AND MACHINERY ................................................................................................................ 7
3.3 TOOLS AND EQUIPMENT ................................................................................................................ 7
3.4 MATERIAL ......................................................................................................................................... 8

4.0 DOCUMENT SUBMISSION & APPROVAL ...................................................................................... 8

5.0 HANDLING AND STORAGE............................................................................................................. 9

6.0 CONSTRUCTION METHODOLOGY ................................................................................................ 9


6.1 SITE ACCESS AND LOGISTIC ......................................................................................................... 9
6.2 TEMPORARY WORKS ..................................................................................................................... 9
6.3 SEQUENTIAL METHOD OF CONSTRUCTION ............................................................................. 10

7.0 INSPECTION AND TESTING .......................................................................................................... 14

8.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL ............................................ 14

9.0 APPENDICES .................................................................................................................................. 14


9.1 APPENDIX A – SITE ORGANISATION CHART ............................................................................. 15
9.2 APPENDIX B – ITP & INSPECTION CHECKLIST .......................................................................... 16
9.3 APPENDIX C – SWMS .................................................................................................................... 17
9.4 APPENDIX D – PLANT/EQUIPMENT/TOOLS CATALOGUE/CERTIFICATE DETAILS…………..18
9.5 APPENDIX E – RELEVANT DRAWINGS………………………………………………………………..19

Tun Razak (TRX) Lifestyle Quarter 5 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

1.0 PURPOSE AND SCOPE

This Method Statement describes the general procedures for method and construction for
Power Float at project Site including descriptions of all preventive actions to be taken in
order to achieve good quality and safety.

2.0 REFERENCES

Specification

1. Specification for Paving and Screeds DPA_AR_SPE_3210_00.GO REV


2. Specification for Cast-in-Place Concrete A
KTP_ST_SPE_0007_00.G0REV 03

Safe Work Method Statement (SWMS)

1. Floor Hardener and Power Float WCT_TP02_SWMS_AR_0015


2. Use of Power Tools & Generator Set WCT_TP02_SWMS_ST_0018

3.0 RESOURCE PLANNING

3.1 PERSONNEL/ MANPOWER

No. Positio Responsibilit


n y
1 Construction Manager Construction Manager responsible to ensure a project is
completed safely, making sure the project runs on time
and within the allocated budget allowance
2 Site Engineer Site engineer responsible to offers advice in the planning,
co- ordination and supervision of technical aspects of
construction projects
3 QAQC Engineer QAQC engineer responsible to ensure quality work
4 Site Safety Supervisor To ensure all the safety, health and environmental legal
requirement implemented during the work
5 Site Supervisor Completes construction projects by planning, organizing,
and controlling projects; completing quality inspections;
supervising sub-contractors and staff
6 Power Float Supervisor To ensure the works to be implemented as per
approved procedure/MS/specifications, equipment in
good conditions and functioning.

7 Skilled Workers Power float works

Tun Razak (TRX) Lifestyle Quarter 6 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

3.2 PLANT AND MACHINERY

No. Plant/
Machinery
1 Walk-behind power float machine

3.3 TOOLS AND EQUIPMENT

No. Material Pictur


e
1 Hand trowel

2 Bull float

3 3m Channel float

4 Squeegee

5 3m Straight Edge

Tun Razak (TRX) Lifestyle Quarter 7 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

6 Steel Wedge

7 Hand held grinder with wheel


cup

8 Hand held grinder with


polishing pad

3.4 MATERIAL

No. Material

1 Curing Compound – Concur 90


2 Lafarge Portland Cement (OPC)
3 Sika Grout - 215
4 Petrol
5 Canvas
6 Plywood

4.0 DOCUMENT SUBMISSION & APPROVAL

No. Description
1 Document Submission for Portland Cement (OPC)
2 Concure 90 – Curing Compound
3 Sika Grout - 215

Tun Razak (TRX) Lifestyle Quarter 8 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

5.0 HANDLING AND STORAGE

For this TP02 works, WCT lay down area located at off site in less than 2km away and this
place able to support adequate amount of materials and all materials needed to be deliver
were able to reach site on time approximately 20minutes.

All key construction materials shall be marked at source so that upon receipt at the site,
traceability of material during and after storage or incorporation directly into the works is
achieved. Site clerk is responsible to maintain material record up to incorporation in the
permanent works.

Delivery of material to the site shall be subjected to weekly and monthly reviews.

Upon arrival of materials at site, the consignment shall be checked and verified by
supervisor to match with the delivery order. Any damages of materials shall be rejected
and properly recorded. Only approved materials shall be transported into site for use.

Material shall not store in excess 1.5 meters in height and must be stored in racks or on
wheels. All materials to be elevated from the ground/slab surfaces to prevent any contact
with water and protected from weather. Besides, material shall not store within 3 meters
from any edge or opening.

All materials shall be properly stored and well maintained so that it is in neat and clean
condition throughout the construction period.

6.0 CONSTRUCTION METHODOLOGY

6.1 SITE ACCESS AND LOGISTIC

Gate 2 will be available for access for entire construction period, it will be used for ingress
and egress of the site along Jalan Utara and Jalan Barat, Therefore, the construction
materials and other resources can be supplied to the site using the access provided.

Flag man will control the traffic flow at ingress, egress and within the proposed project site
to ensure that the traffic flow is within the safety requirement.

Upon commencement of works, the public traffic flow will remain the same as the current
traffic flow where no heavy vehicle is allowed to be on the city roads during peak hours as
mention in the specification.

6.2 TEMPORARY WORKS

NO Item DESCRIPTION

1. Canvas -Expose work is being carried-out, cover the completed area


with canvas in case of rain and entrance heat.

Tun Razak (TRX) Lifestyle Quarter 9 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

6.3 SEQUENTIAL METHOD OF CONSTRUCTION

6.3.1 Preparation of Base Concrete

i. The base concrete shall be placed up to required level and compacted by


using vibrator screed which is operated by skilled operators.

ii. The concrete surface shall be levelled by using 3m channel float. Level
check to be carried out at 1m to 3m interval to ensure concrete to achieve
the required level and allowable tolerance limits to
KTP_ST_SPE_0007_00.G0 REV 03 Specification. Re-work the concrete
surface level if required.

iii. Smoothen the concrete surface by using bull float and consistently applied
equivalent pressure to achieve required tolerance floor flatness Ff20 and
floor levelness Fl17. For limited access area such as edges, corners and
around/adjacent to column, used hand trowel to manually smoothen the
surface.

6.3.2 Application of Power Float

i. Power float machine and OPC to be provided at designated area next to


area that going to be cast and power float. Proper inspection of power float
to be carried out to ensure the machine is functioning and blades in good
conditions (free from damages and waste concrete). Typically, the machine
and workers to be available at least 1 ½ to 2 hours after first concrete
delivery.

ii. Where concrete had stiffened sufficiently and free from bleed water the
concrete is ready to power float. The base concrete can be tested by make
step onto the slab measure the imprint. If the imprint is approximately only
2-3mm deep then the concrete is ready to power trowel.

iii. The concrete surface shall be mechanically floated by using power float
machine starting with ¾ speeds.

iv. Power trowel consistently over the concrete surface.

Tun Razak (TRX) Lifestyle Quarter 10 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

v. When finished floating the entire slab, turn the power trowel at 90° to the
first row and broadcast OPC cement evenly over the slab then start power
trowel at full speed to smoothen finish.

vi. All edges to be trowel manually. Junction and cold joint area to be given
special attention with additional of small amount of OPC to ensure the area
to be trowelled flat and smooth. Check and smoothen the concrete surface
to required tolerance of the floor flatness Ff20 and floor flatness Fl17.

vii. During power float activities it shall follow a direction of concreting sequence
(refer Figure 1). For the construction joint section, the preparation shall
refer to Figure 2 (Step 1 and Step 2). This to ensure the construction joint
will give an even surface for the next casting and ensure the surface is
smoothen and leveled before a power float activity later.

viii. Power float supervisor to perform checking on the power float surface. He
has to ensure the power float surface is generally flat with smooth surface.
Any surface delamination has to be rectified prior concrete stiffen.

Figure 1 – Example of power float direction similar with concreting sequence


(highlighted in Arrow direction – Start to Finish)

Tun Razak (TRX) Lifestyle Quarter 11 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

Note : the concrete hatch area to be power float and levelled


Figure 2 : Construction Joint Details

6.3.3 Curing and Protection

i. Barricade the power floated finished area to prevent unauthorized


entry prior concrete hardening which can cause damages to
completed surface.

ii. Approved curing compound shall be used as per manufacturer’s


recommendation to treat the floor immediately after the final troweling
by spraying onto the slab surface.

iii. If necessary, to protect the surface using plywood to prevent damages


cause by traffic or heavy loading.

Tun Razak (TRX) Lifestyle Quarter 12 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

6.3.4 Rectification Work for Rough Surface

i. To identify and mark up the rough surface.

ii. Grind the rough concrete surface by using hand held grinder with
wheel cup

iii. Grind the concrete surface until achieve flat surface.

iv. Check the flatness with 3m straight edge.

v. Re-grind the concrete surface if required.

vi. Polish the concrete surface with hand held grinder with polishing pad

vii. Polish the concrete surface until achieve smooth surface.

6.3.5 Rectification Work for Footprint/Chipped Off

i. Trial Mix of grout and application onto small area are required prior
application into larger area. This is to ensure the tone and bonding
of rectified power float slab surface after full curing are similar to
surrounding area.

ii. Clean the area to provide dust-free surface.

iii. Bonding agent to be pre-damp the surface before apply the well
mixed Sika Grout -215 onto the defective area.

iv. Level the surface with straight edge.

v. Re-work the surface with hand trowel to achieve flat surface.

vi. Allow the Sika Grout-215 to cure and harden.

vii. Polish the surface with hand held grinder with polishing pad.

viii. Polish the surface until achieve smooth surface.

Tun Razak (TRX) Lifestyle Quarter 13 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

7.0 INSPECTION AND TESTING

The purpose of quality control is to provide a guide lines for a proper operational framework
such that the following targets will be attained

a) To achieve consistent high-quality standards of workmanship in all aspects of the work


b) To provide a safe working environment
c) To follow work procedures to ensure the quality construction
d) The work to be carried out using the Application for Inspection (AFI) and Inspection
Form Checklist attached refer Appendix B and ensure the finishing quality of work be
acceptable by Main contractor and consultant.

The QAQC manager shall review all the AFI reports based on the criteria set in the
project specification for all completed works and materials. All inspections and AFI
records shall be kept and maintained. Refer Appendix A for the Inspection Test Plan.

8.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL

NO ACTIVITY POTENTIAL HAZARD


1 Mobilizing Material - Falling object, component falling and striking others
2 Curing -Contact with curing compound

Note – During curing compound activities, if the workers contact with this material, he/she
shall quickly wash with water. In case eyes contacted to the curing compound materials,
quickly get eye wash nearby at site and inform Site Safety Supervisor or anyone close by
for assistance.

9.0 APPENDICES

9.1 APPENDIX A – SITE ORGANISATION CHART


9.2 APPENDIX B – ITP & INSPECTION CHECKLIST
9.3 APPENDIX C – SWMS
9.4 APPENDIX D – PLANT/EQUIPMENT/TOOLS CATALOGUE/CERTIFICATE DETAILS
9.5 APPENDIX E – RELEVANT DRAWINGS

Tun Razak (TRX) Lifestyle Quarter 14 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

ATTACHMENT A –
SITE ORGANIZATION CHART

Tun Razak (TRX) Lifestyle Quarter 15 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER FLOAT AND
Revision No.: 07
RECTIFICATION WORKS
Doc. No:No: WCT_TP02_MS_AR_0001 Rev. Date : 03/12/2019

Senior Project Manager 1


Ng Eng Beng
019-387 0386

QA/QC 6 Structure Works 18

QA/QC Manager 1 Project Manager 0


Mohd Fauzi bin Ujang TBA
019-279 9316

QA/QC Engineer 2 North /West Zone 9 Central/East Zone 9

Sitti Julaiha bt Jindang


Site Manager 1 Construction Manager 1
019-536 4612
Mohamed Yasin bin Umar Lau Chee Chun Mohd Zulfarik bin Zahari
016-722 6197 019-265 1259 019-276 5165

QA/QC Officer 2 Site Engineer 2 Site Engineer 2


Nursyafiqah bt Ismail Muhammad Nazamir Azhar Ahmad Firdaus bin Hussain
013-527 3317 016-766 9664 019-615 1998
Syarul Hakimi bin Mohd Mohd Hamdan bin Hussin Hah Jian Feng
019-980 5213 017-625 9637 016-779 8087

Site Coodinator 1 Site Coodinator 1


Thong Koon Choy Kee Chee Ching
016-974 5147 010-463 1437

Site Supervisor 5 Site Supervisor 5


Ng Sin Keong Patrick Chang Wee Keat
012-711 8585 012-711 8585
Hasrin bin Mat Yaakob Kee Mun Kit
017-948 6339 012265 9707
Mohd Fairus bin Abdullah Sharvin A/L Namasivayam
016-249 8927 019-907 3473
Mohd Haswam bin Shaari Nicholas Foo
016-670 5773 017-301 1099
Mohd Faizul Mohd Shadan Harriz
014-773 6867 019-298 0991

Subcon (Frankie/Jacky Team)


0192668662 / 0162178712

Tun Razak Exchange (TRX) Lifestyle Quarter 1 MC02 Method Statement Submission
Template LLM_CN_TMP_3049_00.00(Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

ATTACHMENT B –
ITP & INSPECTION CHECKLIST

Tun Razak (TRX) Lifestyle Quarter 16 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
MAIN CONTRACTOR : LEND LEASE PROJECTS (M) SDN BHD Page No. 1 of 2
TRX LQ : TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS Doc Ref. No. WCT_TP02_ITP_AR_0001
INSPECTION & TEST PLAN Revision No 07
APPLICATION OF POWER FLOAT AND RECTIFICATION WORK Date 7-Dec-19

Action by
Reference to Specification/
Frequency of Trade
No Description of Work Standard/ Contract Characteristic Point of Inspection/ Test Acceptance Criteria Verifying Document Design Commissioning
Inspection Contractor/ LLPM - PM&C
Document Consultant Consultant
Supplier
SELECTION OF TRADE CONTRACTOR/ SUPPLIER
Source of qualified Trade
Trade Contractor/ Supplier as per Approved Trade Contractor/
1 Contractor / Supplier N/A Once Tender of work Verified via approved Trade Contractor/ Supplier List Trade Contractor/ Supplier List - - - A
Supplier List
Selection of successful
Trade Contractor/ Supplier qualification as stated in the tender Trade Contractor/ Supplier - Fulfil the requirements for tender (i.e.
2 Trade Contractors / N/A Once Before award of contract Letter of Award - - - A
contract Technical Proposal Evaluation)
Supplier
DOCUMENT ISSUANCE/ SUBMISSION & APPROVAL
Issuance of Approved
Construction Drawings to Issuance of Construction Drawings to Trade Contractor/ Supplier Once every revision of Prior to commencement of Construction drawings to comply with the technical specification
3 CS& & AFC Drawings - P NA R, A, I
Trade Contractor/ Waterproofing (Silcor 780) prior to start work on the Contract submission physical work at site and contract requirements
Supplier

Four weeks prior to starting work on the Contract the Contractor


shall submit for approval details of the proposed sources of all
Submission of Method CSF & Method Statement - A (Approved)/ B
materials, together with full documentary evidence that the materials
Statement, Inspection & (Approved with Comments) Status
will comply with the specification.
Test Plan (ITP),
Once every revision of Prior to commencement of Method statement to comply with the technical specification and
4 Inspection Checklist & DPA_AR_SPE_0100_00.G0 B - Status : works allowed to proceed subject to all P R NA R, A
The Contractor shall submit method statements for approval submission physical work at site construction drawings
Safe Work Method works carried out as per comments. Revise MS/ ITP/
indicating full detailed proposals of the method of placing,
Statements (SWMS) for Inspection Checklist/ SWMS to be submitted for
compacting, finishing and curing the concrete. The method
approval Status A approval.
statement shall cover all principle types of concrete elements e.g. raft
foundation, walls, columns, beams and slabs, etc.

Submit for each system type, as specified. Shop drawings shall be


Submission of Shop Once every revision of Prior to commencement of Shop drawings to comply with the technical specification, design,
5 DPA_AR_SPE_0100_00.G0 endorsed by the respective waterproofing manufacturer as being CSF & AFC Drawings P R NA R, A
Drawings submission physical work at site construction drawings and contract requirements
approved and in accordance with its recommendation

CSF & SMES - A (Approved)/ B (Approved with


Comments) Status
Submission of Design Contractor to submit to Engineer the design calculations and shop Once every revision of Prior to commencement of Design Calculations to comply with the technical specification,
6 DPA_AR_SPE_0100_00.G0 P R,A NA R, A
Calculation (if any) drawing. submission physical work at site design, construction drawings and contract requirements B - Status : works allowed to proceed subject to all
works carried out as per comments. Revise SMES to
be submitted for Status A approval.
Submission of SMES for Approval

7
a) Portland Cement Once every revision of Prior to commencement of Cement complying with either BS 12 or ASTM C150 Type I but
KTP_ST_SPE_0007_00.G0 Ordinary Portland Cement P R,A, H NA R,A, H
(OPC) submission physical work at site containing maximum 8% by weight of tricalcium aluminate (Ca3Al)
AFI & Concrete Mix Design.
AFI closed-out status A (Inspection Passed)
The curing compound shall be compatible with subsequent surface Once every revision of Prior to commencement of Trial Mix Details provided as attachments
8 b) Curing Compound DPA_AR_SPE_3210_00.G0 As per Manufacturer's Specification P R,A, H NA R,A
finishes. submission physical work at site
CSF & SMES - A (Approved)/ B (Approved with
Comments) Status
c) Sika Non Shrink grout Repair concealed formed surfaces, where possible, that contain Once every revision of Prior to commencement of
9 KTP_ST_SPE_0007_00.G0 Repair work for concrete structure and Grouting Only. P R,A, H NA R,A
215 defects that affect the durability of concrete submission physical work at site B - Status : works allowed to proceed subject to all
works carried out as per comments. Revise SMES to
be submitted for Status A approval.
KTP_ST_SPE_0007_00.G1 SikaLatex -118 wis a syenthetic polymer emulsion for adding to
Once every revision of Prior to commencement of Thoroughly clean, dampen with water, and brushcoat
10 d) Sika Latex (3.18 Concrete Surface cement mortar, where good adhesion and water resistance are P R,A, H NA R,A
submission physical work at site the area to be patched with specified bonding agent
Repairs) required
MOCK-UP/ PROTOTYPE/ BENCHMARK PREPARATION & APPROVAL

Surface preparation and application shall be in accordance with the


DPA_AR_SPE_3210_00.G0 Once as per instructed Material/Structure to comply and approved to Engineer
11 Power Float Work manufacturer's recommendation, printed literature, and applicable Surface of product Method Statement, AFI P V,A NA V,AC,A
KTP_ST_SPE_0007_00.G0 by Engineer Specification
codes, standards and statutory requirements.

MATERIAL RECEIVE, HANDLING & STORAGE


Receiving of Material
a) Portland Cement
Shall be supplied in the manufacturer's sealed and unbroken bags or
12 (OPC) Label on material and unbroken cement bags as per approved
in bulk. Storage area shall be covered, dry, clean area and avoid to First delivery material Material type,quality, type,
KTP_ST_SPE_0007_00.G0 SMES. Acceptance criteria of storage area clean, dry, covered SMES Approval P W, A NA W,A, V
touch ground surface. on site and colour as per specs.
from raining/sun and above ground follow as per manufacturer
recommendation.

KTP_ST_SPE_0007_00.G0 Material deliver in good condition and in accordance to the First delivery material Material type,quality, type, Material delivered to be tagged and marked to facilated sorting and
13 b) Curing Compound SMES Approval, AFI P W, A N/A W,A,V
(REV.03) requrements specified for repair work as per approved SMES on site and colour as per specs. placing.

c) Sika Non Shrink grout KTP_ST_SPE_0007_00.G0 Material deliver in good condition and in accordance to the First delivery material Material type,quality, type, Material delivered to be tagged and marked to facilated sorting and
14 SMES Approval, AFI P W, A N/A W,A,V
215 (REV.03) requrements specified for repair work as per approved SMES on site and colour as per specs. placing.

KTP_ST_SPE_0007_00.G0 Material deliver in good condition and in accordance to the First delivery material Material type,quality, type, Material delivered to be tagged and marked to facilated sorting and
15 d) Sika Latex SMES Approval, AFI P W, A N/A W,A,V
(REV.03) requrements specified for repair work as per approved SMES on site and colour as per specs. placing.

Note: P = Prepare; R = Review; A = Approved; H = Hold; W = Witness; V = Verified; AC = Acknowledge; I = Issuance; AFI = Application for Inspection; CSF = Contractor Submission Form; ER = Client/ Employer's Representative; N/A = Not Applicable; CCS = Concrete Characteristic Strength
Prepared By: Reviewed & Verified By: Approved By:
Initial: Initial: Initial:
Name: Sitti Julaiha Binti Jindang Mohd Fauzi Bin Ujang Name: Name:
Designation: QAQC Engineer QAQC Manager Designation: Designation:
(Trade Contractor/ Supplier) WCT Berhad WCT Berhad (Design/ Commissioning Consultant) (LLPM)

LLM_CN_TMP_3013_00.00 Revision No: 02


TRX LQ/ITP Template for LLPM.doc Revision Date: 22/03/2019
MAIN CONTRACTOR : LEND LEASE PROJECTS (M) SDN BHD Page No. 2 of 2
TRX LQ : TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS Doc Ref. No. WCT_TP02_ITP_AR_0001
INSPECTION & TEST PLAN Revision No 07
APPLICATION OF POWER FLOAT AND RECTIFICATION WORK Date 7-Dec-19

Action by
Reference to Specification Frequency of Trade
No Description of Work Characteristic Point of Inspection Test Acceptance Criteria Verifying Document Design Commissioning
(Contract Document) Inspection Contractor/ LLPM - PM&C
Consultant Consultant
Supplier
Material Handling & Storage (Site - Storage Yard/Working Area)

a) Portland Cement The concrete curing compound shall be of an approved type,


(OPC) which shall be readily distinguishable upon the concrete surface
b) Curing Compound To prevent of premature water loss in concrete. Storage area shall be Prior commencement of for at least four hours after application. The curing compound shall
16 KTP_ST_SPE_0007_00.G0 Storage on site Material Receiving Inspection and Checklist P W NA W
c) Non- Shrink Grout covered, dry, clean area and avoid touch to ground surface. physical work at site be compatible with subsequent surface finishes. Acceptance
d) Sika Latex 118 criteria of storage area clean, dry, covered from raining/sun and
above ground as per manufacturer recommendation.

DOCUMENTATION FOR INSPECTION


Once every AFI
AFI submitted earlier to the consultant, complete submission AFI
17 AFI Submission DPA_AR_SPE_0100_00.G0 Details of Works Inspection e.g. Location, Date and time Issuance of Slab & Subject to AFI submission Application for Inspection Form (AFI) P,I A NA A,V
form
Beam works
PRE-CONSTRUCTION STAGE
The structure shall be built to dimension and levels shown on the
18 Setting out KTP_ST_SPE_0007_00.G0 Once Alignment and verticality All setting out dimension : +/- 5mm AFI, Checklist P W,A,H NA W,A, H, AC
Engineer's drawing taking building movement into consideration

Once before The base concrete is stiffened and free from bleeding prior to
KTP_ST_SPE_0007_00.G0 Prior to commencement of
19 Base concrete The base concrete surface ready for the next stage power float. commencement of power float. Acceptance criteria for flatness and levelness shall AFI, Checklist (CHK_AR_0001) P W,A,H NA W,A, H, AC
DPA_AR_SPE_3210_00.G0 physical work at site
work area refer to KTP/DPA specification.
IN-PROCESS INSPECTION / ON-GOING CONSTRUCTION STAGE

Apply float finish to monolithic slab surfaces to received trowel finish


to areas such carparks and driveways to the Engineer's requirement.
1) Power floating as per direction of concreting sequence
Begin floating, using float blades or float shoes only, when surface
Prior to commencement of 2) Surface is smooth & levelled
20 Power Float KTP_ST_SPE_0007_00.G0 water has disappeared, and concrete has stiffened sufficiently to Once AFI P V,A,H NA V,AC
physical work at site 3) Surface even & flat for subsequent casting at CJ
permit operation of power-driven floats, or both.
4) Surface delamination rectified before concrete stiffen
Consolidate surface with power-driven floats or by hand-floating if
area is small or inaccessible to power units.

POST-CONSTRUCTION STAGE

New concrete must be thoroughly dry and cured a minimum of 7 days As per project specification Clause 3.05 (Method B) - use
DPA_AR_SPE_3210_00.G0 Prior to commencement of
21 Curing and protection prior to application of liquid hardener, for best results cure for a full 28 Once approved chemical curing agent and sprayed over the entire AFI P V,A NA V,AC
Clause 3.05 physical work at site
days surface and follow manufacturer's specification.

Material or work fails to meet specified requirement may be rejected


DPA_AR_SPE_3210_00.G0 Once, Power Float Once Power Float done at AFI, Approved Method Statement of Power Float
22 Post Inspection by the Engineer whenever found at any time prior to final acceptance Material or works to follow the requirement P V,A NA V,AC
Clause 3.08 Done on SIte site and Rectification Work
of the works regardless or previous inspection

Works carried out as per approved method


i. Rectification Work for Rough Surface In process of rectification
23 Rectification Work (if any) DPA_AR_SPE_3210_00.G0 Rectification Work (WCT_TP02_MS_AR_0001) as below : AFI, Checklist (CHK_AR_0002) P V,A,H NA V,AC
ii. Rectification Work for Footprint/Chipped Off works until completon
Surface finish smooth and flatness as per acceptable tolerance.

TESTING

DPA_AR_SPE_3210_00.G0 -
Check and level surface plane to tolerances of Ff20-Fl 17 or Whole
Clause 3.03 (D) & Upon completion of When the Slab is fully
area within +/- 3mm under 3000mm long straight edge or not greater Works will carry out against as built survey data Vs thickness
24 Flatness or Levelness KTP_ST_SPE_0007_00.G0 Power Float and Slab hardened, get data for As AFI, Checklist (TBA in separate Method Statement) P V, A, H NA V, AC
than +/- 1.5mm for each 500mm or 5mm Surface Level (5m straight gauge measurement to check the levelness
(Clause 3.14 C Item 5), (Clause finish are fully hardened Built
edge), Surfce Level to Datum 10mm.
3.16 Item B)
Note: P = Prepare; R = Review; A = Approved; H = Hold; W = Witness; V = Verified; AC = Acknowledge; I = Issuance; AFI = Application for Inspection; CSF = Contractor Submission Form; ER = Client/ Employer's Representative; N/A = Not Applicable; CCS = Concrete Characteristic Strength
Prepared By: Reviewed & Verified By: Approved By:
Initial: Initial: Initial:
Name: Sitti Julaiha Binti Jindang Mohd Fauzi Bin Ujang Name: Name:
Designation: QAQC Engineer QAQC Manager Designation: Designation:
(Trade Contractor/ Supplier) WCT Berhad WCT Berhad (Design/ Commissioning Consultant) (LLPM)

LLM_CN_TMP_3013_00.00 Revision No: 02


TRX LQ/ITP Template for LLPM.doc Revision Date: 22/03/2019
PM&C : Page No. : 1 of 1
Doc Ref. : WCT_TP02_CHK_AR_0001
LENDLEASE PROJECTS (MALAYSIA) SDN BHD No.
Project : TRX LQ THE EXCHANGE
TRADE CONTRACTOR/ SUPPLIER: Trade
TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS : TP 02
Package

POWER FLOAT INSPECTION CHECKLIST


Description of Works/ Elements/ Structure: AFI No. :

Location/ Zone/ Sub-Zone/ Level/ Block /Unit/ Area : Drawing Ref. No. :

Date of Inspection : Material : (Approved / Not Approved)


Time : Method Statement : (Approved / Not Approved)
Trade
Consultant LLPM
Description of Works Contractor Remarks
(√ / X ) (√ / X ) (√ / X )
Material & Equipment check :
a. Power float blades are cleaned and free from concrete
waste/damages
b. OPC as per approved SMES

Base concrete preparation :


a. Concrete surface levelled by using 3m channel float

b. Acceptable surface smooth (edges, corners, around/adjacent

Power float works :


a. Bleed water before start power float work
Concrete had stiffened sufficiently and free from
b.
roughness/damages
c. Adequate usage of OPC

d. Power float work follow direction of concrete sequence

e. Concrete level within tolerance limits


Concrete surface, corners/edges levelled and smoothen, free
f.
from roughness/damages
g. Check surface evenness within tolerance limits

Curing and Protection


Curing compound used as per Approved Material and
a.
application as per manufacturer's recommendation
Power float area were barricaded/protected from entry/other
b.
work.

Others if any…

STATUS OF INSPECTION
We have carried out all necessary inspections and verify that the above items/ activities conform to the contract specifications/ document
Checked By: Checked By: Checked By:

Initial : Initial : Initial :


Name : Name : Name :
Position : Position : Position :
Date : Date : Date :
NSC (if applicable) : Trade Contractor (if applicable) : Lendlease Projects (M) Sdn Bhd
Checked By: Approved By : Acknowledged by:

Initial : Initial : Initial :


Name : Name : Name :
Position : C.o.W/ ARE / ARA Position : RE / RA Position :
Date : Date : Date :
Client's Consultant : Client's Consultant : Lendlease Projects (M) Sdn Bhd
WCT_TP02_CHK_AR_0001 Rev: 04 Effective Date : 03/10/2019

LLM_CN_TMP_3014_00.00 Revision No: 01


TRX LQ/ Inspection Checklist Template for Trade Contractor.doc Revision Date: 7/09/2018
PM&C : Page No. : 1 of 1
Doc Ref. : WCT_TP02_CHK_AR_0002
LENDLEASE PROJECTS (MALAYSIA) SDN BHD No.
Project : TRX LQ THE EXCHANGE
TRADE CONTRACTOR/ SUPPLIER: Trade
TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS : TP 02
Package

POWER FLOAT INSPECTION CHECKLIST (RECTIFICATION)


Description of Works/ Elements/ Structure: AFI No. :

Location/ Zone/ Sub-Zone/ Level/ Block /Unit/ Area : Drawing Ref. No. :

Date of Inspection : Material : (Approved / Not Approved)


Time : Method Statement : (Approved / Not Approved)
Trade
Consultant LLPM
Description of Works Contractor Remarks
(√ / X ) (√ / X ) (√ / X )
Rectification Work for Rough Surface

a. Grind rough concrete surface to achieve flat surface.

b. Polish concrete surface to achieve smooth surface.

c. Flatness check with 3m straight edge within tolerance limits.

Rectification Work for Footprint/Chipped Off

a. Surface free from dust

b. Pre-damp surface before apply well mixed Sika Grout 215

c Polish surface to achieve smooth surface.

d Flatness check with 3m straight edge within tolerance limits.

STATUS OF INSPECTION
We have carried out all necessary inspections and verify that the above items/ activities conform to the contract specifications/ document
Checked By: Checked By: Checked By:

Initial : Initial : Initial :


Name : Name : Name :
Position : Position : Position :
Date : Date : Date :
NSC (if applicable) : Trade Contractor (if applicable) : Lendlease Projects (M) Sdn Bhd
Checked By: Approved By : Acknowledged by:

Initial : Initial : Initial :


Name : Name : Name :
Position : C.o.W/ ARE / ARA Position : RE / RA Position :
Date : Date : Date :
Client's Consultant : Client's Consultant : Lendlease Projects (M) Sdn Bhd
WCT_TP02_CHK_AR_0002 Rev: 05 Effective Date : 07/12/2019

LLM_CN_TMP_3014_00.00 Revision No: 01


TRX LQ/ Inspection Checklist Template for Trade Contractor.doc Revision Date: 7/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

ATTACHMENT C –
SAFE WORKS METHOD STATEMENTS

SWMS related to this Method Statements to refer :

TITTLE : SWMS for Power Float & Floor Hardener


DOCUMENT REF. : WCT_TP02_SWMS_AR_0007
REVISION NO. : 00
REVISION DATE : 17/8/2018
ACONEX REF. : WF-002859
TITTLE : SWMS for Power Tools & Generator Set
DOCUMENT REF. : WCT_TP02_SWMS_ST_0018
REVISION NO. : 00
REVISION DATE : 07/8/2018
ACONEX REF. : WF-000809

Tun Razak (TRX) Lifestyle Quarter 17 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

ATTACHMENT D –
PLANT/ EQUIPMENT/ TOOLS CATALOGUES/
CERTIFICATES DETAILS

SMES related to this Method Statements to refer :

TITTLE : SMES for PORTLAND CEMENT (LAFARGE MALAYSIA)

DOCUMENT REF. : WCT_TP02_SMES_AR_0002


REVISION NO. : 00
REVISION DATE : 10/10/2018
ACONEX REF. : WF-001124
TITTLE : SMES for Grouting: SIKA Grout - 215 (SIKA Kimia
Sdn. Bhd)
DOCUMENT REF. : WCT_TP02_SMES_ST_0005
REVISION NO. : 02
REVISION DATE : 15/09/2018
ACONEX REF. : WF-000929
TITTLE : SMES for Concure 90 (Fosroc Sdn Bhd)
DOCUMENT REF. : WCT_TP02_SMES_ST_0025
REVISION NO. : 01
REVISION DATE : 23/11/2018
ACONEX REF. : WF-001435

Tun Razak (TRX) Lifestyle Quarter 18 MC02 Method Statement Submission Template
LLM_MT_STD_3049_00.00 Rev 02 Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR POWER
Revision No.: 08
FLOAT AND RECTIFICATION WORK

Doc. No: WCT_TP02_MS_AR_0001 Rev. Date : 07/12/2019

ATTACHMENT E –
DRAWINGS
(N/A)