TO DO ITEM- YELLOW HIGHLIGHT= URGENT ATTENTION, GREEN HIGHLIGHT=COMPLETE, RED=PAST DUE, ORANGE=NEW TO COMPLETE BY COMMENTS DATE COMPLETED

Gap over windows facing the Porch of PH2 June 30th July 10th
Vent at Social Bathroom in PH2 June 30th August 5th

Switch lights at porch to match PH1


May 25th June 15th
Molding at door social bathroom PH2 August 20th August 20th
Backplash at Social bathroom PH2 August 20th In progress, working at the same time as the vent August 20th
Steps at PH2 September 30th This has to come after the remodelation of bathroom
Venetian Plaster September 30th This has to come after the remodelation of bathroom
Realign Pipe outside office PH2 May 25th August 20th
Camouflage tile behind bed MB2 PH2 June 30th This is blend into the floor.

Remodel Remaining Bathroom We need to create a priority list because there is not
September 30th enough money to do all
Refinish all doors at second floor oh PH2 including closets September 30th
Details at ceiling outside MB PH2 August 30th
Citofono on 2nd floor PH2 August 30th
Number and signs to all apartments August 30th
Attach Alarms at Windows in 801 August 20th

Blinds in PH1
September 30th

Fumigate antz at PH2


August 30th Company to do it on Thursday 19th August 5th

New Acs in PH1


September 30th IN PROGRESS

Refinish built in BR3 PH1


September 30th

Remake Closet doors BR3 PH1


September 30th

Repaint Green Bathroom PH1


September 30th

Change old accessories and showerheads at PH1


September 30th

Re do outside of the windows facing the roof PH1


September 30th

Upgrade lights at bathrooms PH1 September 30th

Change tile of the 2nd floor PH1 September 30th IN PROGRESS


Change locks at PH2 main door September 30th 23-Sep
Change main door of PH1 September 30th 24-Sep