Project : MTHL - PK1 Location: Sewri, Mumbai Week : 3 November Year : 2019
Resident
Engineer Inspected by Sarang/Amol Position Senior Safety Engineer 23.11.2019
Unsafe Act/
Observation Date of
Date
Area
Sr No Observation Photo HSE Observation Risk Time line Unsafe References Compliance Photo Remarks
Category Condition Compliance
14.11.2019
PK1-1144
MP92
Flammable Unsafe
were not working and found in High Immediate Site Safety Plan, Annexure-1, pt no-
Materials Condition
broken condtion. 14.9
Temporary Access
Bridge, STP
19.11.2019
PK1-1146
Insoection tag not placed on Unsafe 1)Site Safety Plan, Annexure 1 Sec.
Work Equipment High Immediate
compressors kept at TAB. Condition no 13.3
WEEKLY
HSE INSPECTION REPORT ACTION PLAN - 62
HSE INSPECTION REPORT - 46
Project Mumbai Trans Harbour Link ProjectNo. Package-1 Location Sewri, Mumbai Week Ending
Resident
Engineer Inspected by Sarang/Amol Position Senior Safety Engineer 23.11.2019
Unsafe Act/
Observation Date of
Date
Area
Sr No Observation Photo HSE Observation Risk Time line Unsafe References Compliance Photo Remarks
Category Condition Compliance
Temporary Access
Bridge, STP
19.11.2019
PK1-1149
House keeping is not properly Unsafe 1)Site Safety Plan, Annexure 1 Sec.
Housekeeping High Immediate
maintained at Fingers of TAB Condition no 6
Batching Plant, STP
20.11.2019
PK1-1150
Safety latch of the hook is not 1) BOCW Central rules Chapter VII
Unsafe
STP
working for the crane available Construction Plant High Immediate 2)Site Safety Plan, Annexure 1 Sec.
Condition
near RMS shed in STP. no 17
pass test certificate. Height pass Project HSE Unsafe 1)Site Safety Plan, Annexure 1 Sec.
High Immediate
test is not being conducted at Documentation Condition no 1.8
belapur jetty site for all workmen
working in marine.
WEEKLY
HSE INSPECTION REPORT ACTION PLAN - 62
HSE INSPECTION REPORT - 46
Project Mumbai Trans Harbour Link ProjectNo. Package-1 Location Sewri, Mumbai Week Ending
Resident
Engineer Inspected by Sarang/Amol Position Senior Safety Engineer 23.11.2019
Unsafe Act/
Observation Date of
Date
Area
Sr No Observation Photo HSE Observation Risk Time line Unsafe References Compliance Photo Remarks
Category Condition Compliance
LP 13, Interchange,
20.11.2019
PK1-1154
plant, STP
used at PB2 in marine. Workmen Project HSE Unsafe 1)Site Safety Plan, Annexure 1 Sec.
High Immediate
and Engineers are neither training Documentation Condition no 24.4
is been provided nor aware of the
MSDS for the same.
Temporary Access
Bridge, STP
19.11.2019
PK1-1157