METAL OXIDE SURGE ARRESTED

WITHOUT GAPS TEST REPORT


Usage purpose Main transformer Installation location Ship unloading
1.Nameplate
Type Circuit
Manufacture
2.Test Insulation Resistance:
Phase R S T
Terminal R-G S-G T-G
Before Test (GΩ)
After Test (GΩ)
Applied instrument: UT512 2500V Megger
3. Test DC Reference Voltage & Leakage Current:
Phase R S T
Terminal R-G S-G T-G
DC Reference Voltage
at 1mA (KV)
Leakage Current
at 0.75U1 mA (uA)
Applied instrument:
4.Test conclusion:

Tested Date Temperature

Date: Date: Date:


Prepared & Inspection: Approved By: Witnessed By:

PT.TRUBA JAYA ENGINEERING CNTIC PLN / JMK