You are on page 1of 3

Portal RATOL & Rates PreMo

CAWANGAN KONTRAK DAN UKUR BAHAN 26.09.2018

Work Item Unit Overall Average (RM)


EXTERNAL WATER SUPPLY INSTALLATION No Location Range (RM) Average (RM) RM 70.00
Precast concrete; standard or stock pattern units
F 70.00 - 70.00 70.00
Marker Post
Precast concrete Grade 25 as specified marker post,
including all moulds finishing on exposed surfaces and
planted in ground, including symbol, lettering and
painting
For sluice valve
EXTERNAL WATER SUPPLY INSTALLATION Item Location Range (RM) Average (RM) RM 3750.00
EXTERNAL WATER SUPPLY INSTALLATION
E 2500.00 - 5000.00 3750.00
EXTERNAL WATER RETICULATIONS
Locating and tapping into Jabatan Bekalan Air's water
main
Allow for locating, arranging, attending, liaising and
obtaining approval from Jabatan Bekalan Air for
temporary water shut-off, cutting off from existing
water mains and tapping to 100mm diameter mild steel
pipe including coated cast airon offtake tee,
EXTERNAL WATER SUPPLY INSTALLATION Item Location Range (RM) Average (RM) RM 1208.33
EXTERNAL WATER SUPPLY INSTALLATION
A 500.00 - 500.00 500.00
EXTERNAL WATER RETICULATIONS
Sterrillisation B 2000.00 - 2000.00 2000.00
Sterrillisation as specified including cost water and C 1000.00 - 1000.00 1000.00
chlorine solution to the approval of the Architect and
the Authorities for all pipes and fittings. E 1000.00 - 2000.00 1333.33

EXTERNAL WATER SUPPLY INSTALLATION Item Location Range (RM) Average (RM) RM 2719.60
EXTERNAL WATER SUPPLY INSTALLATION
A 600.00 - 6700.00 2012.92
EXTERNAL WATER RETICULATIONS
Testing B 2000.00 - 3850.00 2950.00
On completion of the water reticulation system test and C 500.00 - 6180.00 3617.65
commision as specified all pipes and fitting and make
good all defects, re-test and leave whole in perfect D 1000.00 - 5750.00 2958.33
working order to the satisfaction of the Architect and E 1000.00 - 3060.00 2213.33
Authorities
F 500.00 - 4000.00 1910.00
H 1500.00 - 9000.00 3375.00

1/3
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 26.09.2018

Work Item Unit Overall Average (RM)


EXTERNAL WATER SUPPLY INSTALLATION No Location Range (RM) Average (RM) RM 120.00
EXTERNAL WATER RETICULATIONS
D 120.00 - 120.00 120.00
Thrust Block
Diaphram block, concrete support, thrust block, end
cap, anchor block and the like
750mm x 600mm x 600mm deep grade 20

2/3
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 26.09.2018

Nota Catatan
Sekiranya anda mempunyai sebarang pertanyaan, sila hubungi:
Ketua Penolong Pengarah Kanan
Bahagian Perolehan dan Khidmat Kos
Cawangan Kontrak dan Ukur Bahan
Ibu Pejabat JKR Malaysia
Tingkat 19, Menara Tun Ismail Mohamed Ali
No 25, Jalan Raja Laut
50582 Kuala Lumpur

u.p: En Husnan Husin


Tel: 03-26161111
Email: husnan@jkr.gov.my

3/3