Professional Documents
Culture Documents
Submitted By:
Project Director, NHAI,
Bangalore
July 2013
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of
Chamarajanagar to Harohalli section of NH – 209 in the state of Karnataka
TABLE OF CONTENT
0. EXECUTIVE SUMMARY .................................................................................................................... i
0.1 PROJECT BACKGROUND .............................................................................................................. i
0.2 NEED OF THE PROJECT ............................................................................................................... i
0.3 PROJECT ROAD ............................................................................................................................. i
0.4 PROJECT INFLUENCE AREA ........................................................................................................ i
0.5 PROJECT PROPONENT ................................................................................................................. i
0.6 PROPOSED IMPROVEMENTS....................................................................................................... i
0.7 ENVIRONMENTAL IMPACT ASSESSMENT (EIA) STUDY IN THE PROJECT ........................... ii
0.8 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ............................................................ ii
0.8.1 Institutional Setting ...................................................................................................................... ii
0.8.2 Clearances .................................................................................................................................. ii
0.9 BASELINE ENVIRONMENTAL PROFILE ..................................................................................... iii
0.9.1 Physical Environment ................................................................................................................. iii
0.9.2 Biological Environment ............................................................................................................... iv
0.9.3 Social Environment .................................................................................................................... iv
0.10 PUBLIC INTERACTIONS & CONSULTATION............................................................................... v
0.11 POTENTIAL ENVIRONMENTAL IMPACTS ................................................................................... v
0.11.1 Impacts on Climate...................................................................................................................... v
0.11.2 Impact on Air Quality ................................................................................................................... v
0.11.3 Impact on Noise Levels ............................................................................................................... v
0.11.4 Impact on Water Resources and Quality ................................................................................... vi
0.11.5 Impact on Ecological Resources ................................................................................................ vi
0.11.6 Impact on Land........................................................................................................................... vi
0.11.7 Impact on Human Use Values ................................................................................................... vi
0.12 ANALYSIS OF ALTERNATIVES.................................................................................................... vi
0.13 MITIGATION AVOIDANCE AND ENHANCEMENT MEASURES ................................................. vi
0.14 INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN .................. vi
0.15 ENVIRONMENTAL MANAGEMENT PLAN .................................................................................. vii
0.16 CONCLUSIONS ............................................................................................................................ vii
1. INTRODUCTION................................................................................................................................ 1
1.1 INTRODUCTION ............................................................................................................................. 1
1.2 NEED OF THE PROJECT .............................................................................................................. 1
1.3 PROJECT ROAD ............................................................................................................................ 1
1.4 PROJECT INFLUENCE AREA ....................................................................................................... 2
1.5 PROJECT PROPONENT ................................................................................................................ 2
1.6 SCOPE OF WORK ......................................................................................................................... 2
1.7 PROPOSED IMPROVEMENTS...................................................................................................... 2
LIST OF TABLES
Table 1-1: Valued Ecosystem Components .................................................................................................. 3
Table 2-1: Existing Cross Section details ..................................................................................................... 6
Table 2-2: Existing Road Inventory ............................................................................................................... 7
Table 2-3: Widening Options ........................................................................................................................ 7
Table 2-4: Summary of Proposed Horizontal Alignment ............................................................................... 8
Table 2-5: Bypass Locations ....................................................................................................................... 10
Table 3-1: Country Level Environmental Laws & Regulations .................................................................... 13
Table 3-2: Summary of Clearances & NOCs ............................................................................................. 15
Table 4-1: Land Use of the Required Land (in ha) ..................................................................................... 18
Table 4-2: Details of Monitoring Station for Soil.......................................................................................... 19
Table 4-3: Physico-chemical Analysis of Soil Quality ................................................................................. 19
Table 4-4: Air Pollution Receptors Types Identified along the Project Road .............................................. 21
Table 4-5: Details of Monitoring Station for Air Quality ............................................................................... 22
Table 4-6: Ambient Air Quality within Project Corridor ............................................................................... 22
Table 4-7: Details of Water Quality Monitoring Station ............................................................................... 25
Table 4-8: Physical and Chemical Results of Water Samples.................................................................... 25
Table 4-9: Observed Noise Levels along Road .......................................................................................... 26
Table 4-10: Major Settlements along Project Road .................................................................................... 28
Table 4-11: Census Details ......................................................................................................................... 30
Table 4-12: Families within the Proposed Project Corridor ........................................................................ 30
Table 4-13: Social Stratification .................................................................................................................. 31
Table 4-14: Affected Households of Vulnerable Group .............................................................................. 31
Table 4-15: Educational Levels of Families ................................................................................................ 31
Table 4-16: Income Levels .......................................................................................................................... 31
Table 5-1: Public Consultation held at Different Stages of Project ............................................................. 33
Table 5-3: Addressal of General Issues and Concerns under the Project ................................................. 35
Table 6-6: Noise Impacts ............................................................................................................................ 48
Table 6-11: Proposed Land Requirement in the Project ............................................................................. 54
Table 6-13: Ownership Details of Structures Affected Due to the Project .................................................. 54
Table 6-14: Project Affected Families and Persons .................................................................................... 54
Table 7-1: "With and Without" Project Scenarios - A Comparative Assessment ........................................ 56
Table 7-2: Proposed Bypass Locations ...................................................................................................... 58
Table 7-3: Analysis of Alternatives for Kollegal Bypass .............................................................................. 59
Table 7-4: Analysis of Alternatives for Sathegala Bypass .......................................................................... 60
Table 7-5: Analysis of Alternatives for Halaguru Bypass ............................................................................ 61
Table 7-6: Analysis of Alternatives for Kanakapura Bypass ....................................................................... 63
LIST OF ANNEXURE
Annexure 2.1: Details of Bus Bays and Shelters
Annexure 4.1: Water Resources Along the Project Road
Annexure 4.2: Tree Schedule
Annexure 4.3: Cultural/Community Properties along the Project Road
Annexure 4.4: Noise Sensitive Receptors
Annexure 8.1: Guidelines for Identification of Debris Disposal Sites & Precautions
Annexure 8.2: Guideline for Rehabilitation of Dumpsites & Quarries
Annexure 8.3: Guidelines for New Quarry Management
Annexure 8.4: Guidelines for Existing Quarry Management
Annexure 8.5: Quarry Lead Chart
Annexure 8.6: Guidelines for Sediment Control
Annexure 8.7: Tree Plantation Strategy
Annexure 8-8: Traffic Control and Safety during Construction
Annexure 8.9: Guidelines for Sitting and Layout of Construction Camp
Annexure 10.1: Environmental Monitoring Plan
ABBREVIATIONS
Abbreviations Full Form Abbreviations Full Form
Ministry of Environment and
AAQ Ambient Air Quality MoEF
Forests
National Ambient Air Quality
AAQMS Ambient Air Quality Monitoring Station NAAQS
Standards
AIDS Acquired Immuno Deficiency Syndrome NGO Non Governmental Organisations
BOQ Bill of Quantities NH National Highway
National Highways Authority of
BPL Below Poverty Line NHAI
India
CD Cross Drainage Works NOC No-objection Certificate
CF Conservator of Forest NOX Oxides of Nitrogen
CO Carbon Monoxide ODR Other District Roads
CoI Corridor of Impact PAF Project Affected Family
CPCB Central Pollution Control Board PAH Project Affected Household
DFO Divisional Forest Officer PAP Project Affected Person
DLC District Level Committee PD Project Director
DPR Detailed Project Report PF Protected Forest
EIA Environmental Impact Assessment PIU Project Implementation Unit
EMP Environmental Management Plan PPP Public Private Partnership
FGD Focus Group Discussions PWD Public Works Department
GO Government Order R&R Resettlement and Rehabilitation
GoI Government of India RAP Resettlement Action Plan
GoK Government of Karnataka RF Reserved Forest
GWQMS Ground Water Quality Monitoring Station RHS Right Hand Side
HC Hydrocarbons ROW Right of Way
HQ Head Quarters SH State Highways
Independent Engineer (also known as
IE SO2 Sulphur Dioxide
Independent Consultant or IC)
IMO Indian Meteorological Organization SOS Strategic Options Study
IRC Indian Roads Congress SPCB State Pollution Control Board
IS Indian Standard PM Particulate Matter
Surface Water Quality Monitoring
LHS Left Hand Side SWQMS
Station
MDR Major District Roads TDS Total Dissolved Solids
0. EXECUTIVE SUMMARY
0.1 PROJECT BACKGROUND
National Highways Authority of India (NHAI) has been entrusted to implement the development of
stretches of NH under DPR/KAR/phase – IV B/2010 on BOT Mode / EPC mode. NHAI has decided for
carrying out feasibility study and detailed project preparation for 2-lane with paved shoulders (with
provision of capacity augmentation) / 4 lane standard as per the traffic volume.NHAI has appointed M/s.
Feedback Infra Pvt. Ltd. for providing the required consultancy services for the project in the state of
Karnataka.
deficiencies through curve improvements and the improvement of the various intersections
The proposed improvement includes repair / rehabilitation of existing cross-drainage (CD) structures
on the highway and provision of new CD structures at appreciate locations
To minimise the adverse impacts on the various settlements and to minimise land acquisition 4
bypass, 9 major realignment and 16 minor realignment/curve improvement has been proposed
The proposed works shall be limited to a proposed ROW of 30 m 2 Lanes undivided carriageway with
paved shoulder sections and 45m for 4 lanes divided carriageway with paved shoulder sections. It is
also proposed to have concentric widening to the extent possible to remove discrimination and local
conflicts
No Cattle/ pedestrian/ vehicular underpasses have been proposed.
1 Toll plaza at Km 363.000 (existing) has been proposed
1 Truck Lay byes at Km381.590has been proposed
52 Nos. of Bus-bays with bus shelter and 2Nos. of bus shelters are proposed at various locations
Proper drainage, grade-separation, road furniture, utilities and amenities wherever required shall also
be provided
controller of explosives
NOC for ground water extraction for construction and allied works from Ground Water Authority
Apart from the above clearances, the concessionaire also has to comply with the following:
Clearance of Engineer for location and layout of Worker’s Camp, Equipment yard and Storage yard.
Clearance of Engineer for Traffic Management Plan for each section of the route after it has been
handed over for construction.
An Emergency Action Plan should be prepared by the contractor and approved by the Engineer for
accidents responding to involving fuel & lubricants before the construction starts.
Submit a Quarry Management Plan to the Engineer along with the Quarry lease deeds
receptors (educational establishments like schools and colleges, health units etc.) identified
quite close to the road.
Water Hydrology and Drainage
According to CGWB based on the stage of ground water development in District Chamarajanagar 100%
area in Yalandur taluk falls in safe category. in Chamarajanagar and Kollegal taluk 76% and 40% area fall
in safe category respectively. In Mandya District, the stage of development for the whole district was
computed as 37.93 %. About 27.14 % area of the district is over exploited, 11.43% area of the district is
critical and 62 % of the area is safe. In District Ramanagar, about 45% area of the district is overexploited,
42.5% semi critical and only 12.5% of the area is safe. Surface Water includes drainage channels (rivers,
streams, and canals) and stagnant water bodies (lakes, ponds, tanks and other impounded water bodies).
A highway project can significantly alter the hydrological setting of the project area by acting as an
impediment to the natural drainage system of the region. Seven representative surface water and ground
water monitoring stations were selected based on their importance as source of irrigation and water
supply, size, future impacts and quantum of water available. By and large, the water quality is satisfactory
2
and the major physical and chemical parameters are within limits set by the Bureau of Indian Standards
for drinking water.
0.9.2 Biological Environment
Forest Resources
The alignment of the proposed project road passes through forest areas in 2 locations where requirement
for forest land diversion is involved. These forest areas are falling under the jurisdiction of Mandya and
Ramanagara Forest Division, Karnataka Forest Dept. No eco-sensitive area covered under Wild Life
(Conservation) Act, 1972 (like National Park, Wild life Sanctuary, Biosphere Reserve etc.) is coming within
10Km aerial distance of the project road section.
Educational Institutes
Some of the educational institutions are located on the edge of the road and is a serious concern from the
point of safety. Signage and Safety measures need to be built in the proposed road design at these
locations.
Places of Historical Importance / Cultural Heritage
There are no Historical Importance / Cultural Heritage structures on the project road.
Cultural Properties
The project highway traverses through a number of settlements and there are some religious and cultural
properties which though not of archaeological significance are nevertheless, significant to the community.
Agriculture Pattern
The major occupation of the project districts is agriculture. Major crops are rice and ground nut. Also
coconut, sugarcane, sunflower, cotton and mango plantations are there in few areas.
Highway Amenities
There are number of amenities and utility services located along the highway like Dhaba, hospitals, Petrol
Pumps, Bus Stops etc. The location of these amenities along the Highway is an issue of concern as the
haphazard siting of these amenities is contributing to congestion of the highway.
Truck Parking Lay-bys & Rest Areas
Truck parking lay-byes are proposed for 1 location at Km 376+550 and 54 Bus Bays/ Shelter has been
proposed
Land Use / Acquisition of the Proposed Corridor
A total of 242.62 hectares of land including forest, private and government will be acquired for the
construction of bypass, junction improvement and widening etc.
right from start of project life. Noise sensitive receptors have been identified along the project road.
0.11.4 Impact on Water Resources and Quality
The construction and operation of the proposed project roads will not have any major impacts on the
surface water and the ground water quality in the area. Contamination to water bodies may result due to
spilling of construction materials, oil, grease, fuel and paint in the equipment yards and asphalt plants.
This will be more prominent in case of locations where the project road crosses rivers, canals
distributaries, etc. Mitigation measures have been planned to avoid contamination of these water bodies.
0.11.5 Impact on Ecological Resources
There is no major loss of vegetation hence adverse impact in terms of availability of nesting sites for the
bird doesn’t arise. Furthermore, there is no sensitive ecological area along the existing project roads, so
the impact will be insignificant during construction period. But on the long run the project shall have a
positive impact due to the compensatory forestation and avenue plantation.
0.11.6 Impact on Land
During the construction of the proposed project, the topography will change due to excavation of borrow
areas, stone quarrying, cuts and fills for project road and construction of project related structures etc.
Provision of construction yard for material handling will also alter the existing topography. The change in
topography will also be due to the probable induced developments of the project. Benefits in the form of
land levelling and tree plantations in the vicinity of the project road shall enhance the local aesthetics.
0.11.7 Impact on Human Use Values
The PAPs shall be compensated as per the RAP. Accidents are bound to increase coupled with ribbon
development. There shall also be some impacts on cultural or religious properties along the corridor.
phase of the project, the Independent Engineer shall review the EMP and RAP to identify environmental
and social issues and arrive at a suitable strategy for implementation.
The environmental specialist of the engineer shall be Postgraduate in Environmental Science or
Environmental Management or Zoology or Botany or Ecology or Environmental Planning / degree in civil
engineering and specialisation in environment and 15 years of experience and a minimum of 5 years in
Supervision of implementation of Environmental Management Plan of highway projects.
For effective implementation and management of the EMP, The BOT / Annuity Concessionaire shall
contrive to establish a Safety, Health and Environment (SHE) Cell headed by an Environment Officer to
deal with the environmental & safety issues of the project. This officer shall interact with the contractor,
NHAI, IC and other departments to ensure that the mitigation and enhancement measures mentioned in
the EMP are adhered. The Environmental officer of the concessionaire shall be the interface between the
Environmental Specialist of IC and the Environmental Officer of the contractor. His prime responsibility
shall be to apprise the Environmental Specialist of the IC about the ground conditions. He shall also
procure the requisite clearances and the NOCs for the project and shall also strictly supervise that the
contractor adheres to the EMP. The officer shall also participate in training programmes and assist the IC
in preparing documentation for good practices in environmental protection.
This Environmental Officer should ideally be a Postgraduate in Environmental Science / Environmental
Management / Zoology / Botany / Ecology / Environmental Engineer / Environmental Planning. The EO
should have 10 years of total experience with a minimum of 3 years in the implementation of EMP of
highway projects and an understanding of environmental issues. The environmental officer can also look
after the additional charges of safety and health.
The Environmental Officer of the contractor should ideally be a Postgraduate in Environmental Science /
Environmental Management / Zoology / Botany / Ecology / Environmental Planning / Environmental
Engineer. The Environment Officer should have 5 years of experience with a minimum of 2 years in the
implementation of EMP of highway projects and an understanding of environmental, health and safety
issues. The Environmental Officer of the contractor shall report directly to the Resident Construction
Manager / Project Manager so that the pertinent environmental issues that he raises are promptly dealt
with. He shall also have a direct interaction with the Environmental Expert and the Environmental Officer
of the IC and the Concessionaire respectively.
The reporting system will operate linearly – contractor who is at the lowest rung of the implementation
system reporting to the Concessionaire, who in turn shall report to IC and the project proponent. All
reporting by the concessionaire shall be on a quarterly basis, while the reporting time of the contractor
shall be decided upon by the concessionaire. The project proponent Site Office will be responsible for
setting the targets for the various activities anticipated during construction phase in consultation with the
IC and obtaining agreement from the Contractor after mobilisation but before beginning of works on site.
The contractor will report from then on regarding the status on each of these. The project proponent’s Site
Office will monitor the activities through its own staff or the consultant’s Environmental Specialist after it
has obtained the Contractor’s report with the Consultant’s remarks on it during the construction phase.
During the operation phase, the supervision as well as reporting responsibilities will lie with the project
proponent’s Site Office.
0.16 CONCLUSIONS
Based on the EIA study and surveys conducted for the Project, it can be safely concluded that associated
potential adverse environmental impacts can be mitigated to an acceptable level by adequate
implementation of the measures as stated in the EIA Report. Adequate provisions shall be made in the
Project to cover the environmental mitigation and monitoring requirements, and their associated costs as
suggested in environmental budget. The proposed project shall improve Road efficiency and bring
economic growth. In terms of air and noise quality, the project shall bring considerable improvement to
possible exposure levels to population.
1. INTRODUCTION
1.1 INTRODUCTION
National Highways Authority of India (NHAI) has been entrusted to implement the development of
stretches of NH under DPR/KAR/phase – IV B/2010 on BOT Mode / EPC mode. NHAI has decided for
carrying out feasibility study and detailed project preparation for 2-lane with paved shoulders (with
provision of capacity augmentation) / 4 lane standard as per the traffic volume.NHAI has appointed M/s.
Feedback Infra Pvt. Ltd. for providing the required consultancy services for the project in the state of
Karnataka.
1.8.4 Consultations
Consultations with community members, PAPs Focus Group Discussions with teachers, women groups
and others and stakeholder meetings were carried out. The feedback generated through these meetings
has been incorporated as far as possible in the design and construction of the road. The consultation
process shall continue even during the implementation stage to gauge the general opinion. The details
are elaborated in chapter 5.
1.8.5 Assessment of Impacts
Assessments of general potential impacts were done based on the baseline data. Assessment of the
environmental impacts was carried out to ascertain that the direct and indirect impacts likely to be induced
due to the project are being adequately identified and addressed. The general impacts are land
acquisition and allied impacts on society, dust and air pollution due to removal of structures, trees and
vegetation, quarrying and other construction activities; noise pollution due to construction, loss of flora and
its impacts on the ecology and impacts on water resources. The chapter on Impacts assessment details
out the impacts.
1.8.6 Assessment of Alternatives
Various project alternatives including with and without scenarios have been assessed during the project.
The assessment of alternatives included that of realignments, widening options, service roads, noise
barriers in sensitive areas etc. The chapter on Analysis of Alternatives elaborates the process.
1.8.7 Mitigations and Enhancement Measures
All affirmative actions not only to avoid and deter but also to capitalise on the opportunities provided by
the project in order to improve the environmental conditions have been deliberated. The various mitigation
and enhancement measures proposed have been including the environmental budget and also in the
technical specifications for the aid of the concessionaire. Based on their applicability, both general and
case specific measures were incorporated as follows:
Generic measures: To avoid or mitigate impacts on environmental components, general mitigation
measures were identified based on the characteristic features.
Site Specific: At representative sensitive locations, site-specific mitigation measures and
enhancement designs have been formulated.
1.8.8 Environmental Management Action Plans
The EMP shall detail out the implementation of the proposed mitigation and enhancement measures. A
detailed study of the following has been carried out:
Prediction and addressal of impacts on the various environmental components;
Site specific designs for the mitigation measures provided;
Site specific enhancement designs for water bodies, cattle haats etc;
Traffic management plans during construction; and
Monitoring mechanisms and indicators during construction and operation periods.
2. PROJECT DESCRIPTION
This Chapter describes the project road and discusses the various improvement measures proposed as
part of the project. The project description includes details of existing condition of project road, existing
and proposed traffic, pavement conditions, road inventory, safety and community facilities.
2.1.4 Traffic
Mixed traffic flow is observed along the highway. The annual average daily traffic at four sections is
10902, 6726, 5040 & 23479 PCUs respectively.
The proposed span arrangement and other particulars of the structures are provided in the Design Report.
2.2.8 Other Structures
1 Truck Lay-Bye (existing Chainage Km 381.590), 54 Bus Bays with Bus Shelters and 1 Toll Plaza
(existing Chainage Km 363.000, near Village Sathegala) have been proposed along the project
road section.
No Underpasses or overpasses have been proposed along the project road section
No ROB/RUB have been proposed in the project road
2.2.9 Design of Intersections
All major (6) and minor junctions (100) have been studied thoroughly with respect to traffic volume and
geometric. The important minor junctions leading to villages and major settlements have been identified
and proper junction layouts (including road marking, and traffic signs) have been applied as per IRC-SP:
41-1994.
BILL
BILL NAME Total Amount in Crores
NO.
8 Junctions 3.28
9 Traffic Signs, Road Marking, and Other Appurtenances 9.34
10 Miscellaneous 7.81
11 Maintenance of Road during construction 1.23
Total Civil Cost 331.53
This chapter reviews the existing institutional and legislative set-up pertaining to the project at the National
and state levels. The chapter also elaborates on the various clearances and permissions required for the
project from Government of Karnataka, Ministry of Environment and forests, Government of India.
Implementing /
Sl. Law / Regulation / Applicable
Relevance Reason for application Responsible
No. Guidelines Yes / No
Agency
The Environmental
(Protection) Act.
Umbrella Act. Protection and All environmental MoEF, State
1986, and the
improvement of the environment. notifications, rules and Department of
1 Environmental Yes
Establishes the standards for schedules are issued Environment,
(Protection) Rules,
emission of noise in the atmosphere. under the act CPCB and SPCB
1987-2002 (various
amendments)
Identifies “(i) New National The project Highway is a
Highways; and (ii) Expansion of National Highway of
The EIA Notification,
National Highways greater than 30 more than 30 Km and
14th September
Km involving additional right of way involves additional ROW
2 2006 and Yes MoEF, SEIAA
greater than 20m involving land greater than 20m
subsequent
acquisition" (under item 7 (f) of involving land acquisition
amendments
schedule) as one of the projects and hence is a Category
requiring prior clearance A project
Reuse fly ash discharged from
Thermal Power Station to minimise
Notification for use of land use for dispersal and minimise No Thermal Power
3 Fly ash, 3rd borrow area material. The onus shall No Station located in 100 MoEF, SPCB
November 2009 lie with the implementing authority to Km radius of road
use fly ash unless it is not feasible as
per IRC
The Water Central and State Pollution Control Consent required for not
(Prevention and Board to establish/enforce water polluting ground and State Pollution
4 Yes
Control of Pollution) quality and effluent standards, surface water during Control Board
Act, 1974 monitor water quality, prosecute construction
Implementing /
Sl. Law / Regulation / Applicable
Relevance Reason for application Responsible
No. Guidelines Yes / No
Agency
offenders, and issue licenses for
construction/operation of certain
facilities.
Empowers SPCB to set and monitor Consent required for
The Air (Prevention
air quality standards and to establishing and State Pollution
5 and Control of Yes
prosecute offenders, excluding operation of plants and Control Board
Pollution) Act. 1981
vehicular air and noise emission. crushers
construction machineries
Noise Pollution
Standards for noise emission for and vehicles to conform State Pollution
6 (Regulation And Yes
various land uses to the standards for Control Board
Control) Act, 1990
construction
Forest Conservation and definition of forest State Forest
Diversion of forest land
7 (Conservation) Act, areas. Diversion of forest land No Department,
is involved in the project
1980 follows the process as laid by the act MoEF
Coastal Regulatory The project area is not MoEF, State
8 Zone Notification, Protect and manage coastal areas No within designated coastal Department of
2011 zone Environment
Project road is not
located within 10 Km
Wild Life Protection Protection of wild life in sanctuaries State & National
9 No radius of any National
Act, 1972 and National Park Wild Life Boards
Park or Wild Life
sanctuary
Ancient Monuments Archaeological
No archaeological
and Archaeological To protect and conserve cultural and Survey of India,
10 No monuments, area in the
sites and Remains historical remains found. State Dept. of
project area
Act 1958 Archaeology
Empowers State Transport Authority
to enforce standards for vehicular All vehicles used for
State Motor
The Motor Vehicle pollution. From August 1997 the construction will need to
11 Yes Vehicles
Act. 1988 "Pollution Under Control Certificate is comply with the
Department
issued to reduce vehicular provisions of this act.
emissions.
Sets out the regulations as to If new quarrying
The Explosives Act
regards the use of explosives and operation is started by Chief Controller
12 (& Rules) 1884 Yes
precautionary measures while the concessionaire / of Explosives
(1983)
blasting & quarrying. contractor
Protection to the general public from Hazardous materials
Public Liability And State Pollution
13 accidents due to hazardous Yes shall be used for road
Insurance Act,1991 Control Board
materials construction
Hazardous wastes shall
Hazardous Wastes
Protection to the general public be generated due to
(Management and State Pollution
14 against improper handling and Yes activities like of
Handling) Rules, Control Board
disposal of hazardous wastes maintenance and repair
1989
work on vehicles
Chemical Accidents
(Emergency Handling of hazardous District & Local
Protection against chemical accident
Planning, (flammable, toxic and Crisis Group
15 while handling any hazardous Yes
Preparedness and explosive) chemicals headed by the
chemicals resulting
Response) Rules, during road construction DM and SDM
1996
Mines and Minerals
(Regulation and Permission of Sand
Permission of Mining of aggregates State Department
16 Development) Act, Yes Mining from river bed &
and sand of Mining
1957 as amended in aggregates
1972
The Building and
Other Construction
Workers (Regulation Employing Labour / District Labour
17 Employing Labour / workers Yes
of Employment and workers Commissioner
Conditions of
Service) Act, 1996
3.3 CONCLUSION
Review of environmental regulations indicates that the project requires Prior Environmental Clearance
from MoEF. However, clearance for the diversion of forest land and permission for cutting the trees within
the proposed right of way of the project road will be required from the Forest Department. In addition to
the above, the concessionaire would require the following NOCs & licenses from the authorities during
construction:
NOC And Consents Under Air, Water, EP Acts & Noise rules from Karnataka SPCB for establishing
This chapter assess the nature, type and dimensions of the study area and describes the physical,
biological, culture components along the Road. The baseline data on the environmental components was
generated by primary surveys conducted during project preparation, interactions at various levels with
local people and other stakeholders. The socio-economic profile has been distilled from the RAP Report.
normal of 345mm (35%),SW monsoon period has 363 mm (37%) and the NE monsoon period receive
263mm (27%) rainfall.
Wind
The wind speed ranges from 8.4 to 14.1 kmph in the project area.During October and November some of
the depressions and cyclonic storms originates in Bay of Bengal, which passes through the district
Chamarajanagar, causing wide spread heavy rains and high winds.
4.2.2 Land
Terrain
Terrain is classified by general slope of the country across the highway alignment. Based on these criteria
the project highway passes through plain terrain along the entire stretch.
Geology
Karnataka is constituted of rock formations ranging in age from 3300 m.y. to 5 m.y. Barring a narrow
coastal strip of about 5000 sq.km of Tertiary and Quaternary sediments and another 31,250 sq.km of
Deccan basalts, the remaining area is dominated by Archaean-Proterozoic rocks. Mysore Plateau,
geologically constituted of Dharwar Craton comprises of greenstone-granite belts, gneisses and
granulites.Greenstone belts essentially consist of meta-volcanosedimentary sequences, surrounded and
dissected by Peninsular Gneiss. At the southern end of the craton these give way to granulite suite of
rocks. The craton preserves a billion year orogenic history from 3400 m.a. to 2400 m.a. Epicratonic or
intracratonic sedimentary basins called Purana Basins occupy the northern segment of the craton whose
northern part in turn is concealed by Deccan basalts. Thus younging of lithosequence from south to north
is evident.
Land Use
The land use in the project area is mixed. The project corridor passes through mostly agricultural land
along with barren lands. There are also some settlements along the project road. Few Forest patches are
located along the project roads section.
The Land use according to the land requirement has been presented in below tables.
Table 4-1: Land Use of the Required Land (in ha)
Land Use of the Proposed Land for Acquisition (in ha)
Soil
The soils of the project districts varies from Medium black soils to Red loamy soils, Red sandy loam soils,
Red gravelly soils , Red sandy soils. The soils of the district Chamarajanagar are derived from Granitic
gneisses and Charnockite rocks. Red soil is present in upland areas and also noticed at the contact of
granites and schist. In Mandya District, The soils range from red sandy loams to red clay loam very thin in
ridges and higher elevations and comparatively thick in valley portions. A major part of the district
Ramanagara is occupied by red sandy soil (60%), and the remaining by red loamy soil. Red sandy soil
mainly occurs in Channapatna, Kanakapura and Ramanagara taluks in undulating land slopes.
Samples of soil have been collected and are tested for the physical and chemical properties. The
sampling and analysis of soil along the project corridor was carried out once during the month of March-
April 2013 by Noida Test Laboratories, Greater Noida on behalf of Feedback Infra Pvt. Ltd. Soil samples
were collected using Augur Sampler. The samples were homogenized and the quantity was reduced
using the coning and quartering method to provide a representative sample for analysis. They were stored
in air tight Polythene Bags and analyzed at the laboratory as per standard procedure provided in IS:2720.
Table 4-2: Details of Monitoring Station for Soil
Sl. No. Monitoring Station Code Chainage (Km) Location Sampling Date
1 SQMS 1 347.00 Sargur 30/03/2013
2 SQMS 2 392.00 Thoraikadanahalli 12/04/2013
3 SQMS 3 435.00 Jakkasandra 15/04/2013
1
IS 1893 (Part 1):2002 ‘Criteria for Earthquake Resistant Design of Structures: Part 1 General provisions and
Buildings’
Air Pollution Monitoring Stations were selected with an idea of establishing correlation between pollution
levels and road geometrics and air pollution and land use along the road. The methodology for the
monitoring instruments and techniques has been in accordance to the guidelines laid by the Central
Pollution Control Board (CPCB). The equipment was placed at a height of 4-5m above ground level at
each monitoring station, for negating the effects of windblown ground dust. The equipment was placed at
open space free from trees and vegetation, which otherwise act as a sink of pollutants resulting in lower
levels in monitoring results. With a view to collecting the samples, APM-460BL respirable dust samplers
(RDS) with provision for gaseous sampling APM-411 (Envirotech) were used for measuring the
concentrations of PM10, NO2 and SO2 in the ambient air while Carbon Monoxide was measured using
Ecotech Serinus 30 CO Analyzer. The APM-460 Respirable Dust Sampler has been provided with a
cyclone. The cyclone has been designed to provide separation of PM 10 particles. Atmospheric air was
drawn for ~24 hours through the cyclone and 20 X 25 cm glass fiber filter (GF/A) sheet at a flow rate of
0.8 to 1.2 m3min-1 and finally the average flow rate was calculated. As the air with suspended particulate
enters the cyclone, coarse non-respirable dust is separated from the air stream by centrifugal forces. The
suspended particulate matter falls through the cyclone’s conical hopper and gets collected in the cyclonic-
cup. The fine dust comprising the respirable fraction passes through the cyclone and gets collected on
GFF. The amount of respirable particulate per unit volume of air passed was calculated on the basis of
the difference between initial and final weights of the filter paper, and the total volume of the air drawn
during sampling. For gaseous (SO2 and NO2) sampling the impingers was exposed for ~24 hour at an
impingement rate of 0.2 lpm. SO2 was analyzed by the West-Gaeke method on UV-Visible
Spectrophotometer (Systronics) at wavelength of 560 nm. NO 2 was analyzed employing the Jacob-
Hochheiser modified method on spectrophotometer at wavelength of 540 nm. APM 550 Fine Particulate
Sampler (Envirotech make) was used for measuring PM2.5. This system is method for sampling fine
particles (PM2.5 fraction) and is based on impactor designs standardized by USEPA for ambient air quality
monitoring. Then PM2.5 is estimated by gravimetric method.
Although the selection of locations is not in direct connivance with the traffic locations, the total no of
stations have been distributed throughout the project road so as to get representative baseline of any
variation in land use as well as road geometrics and traffic conditions across the project road. The
purpose is also to establish a benchmark, which can form the reference for monitoring in the construction
and operation period. The following table gives the criteria for selection of the monitoring stations.
Table 4-4: Air Pollution Receptors Types Identified along the Project Road
Sl.
Location of Receptor Criteria for Selection
No
Near sensitive areas viz., educational To obtain baseline concentrations at sensitive receptors and benchmark
1
institutes, hospitals, forest areas, etc. existing pollution levels
As a representative for concentrations in urban areas and also to check the
2 Within urban areas
available concentrations and to benchmark existing pollution levels
In rural areas that present a pristine As a representative sample for obtaining the concentrations in rural areas and
3
environment to benchmark existing pollution levels
The occurrence of ground water in the district is mainly controlled by the topographic and structural
features present in the geological formations. The principal source of ground water is precipitation. Out of
the total rainfall received, a major part of it is lost as runoff and by evapotranspiration through soil and
vegetation. Only a small part of rainfall infiltrates down to reach ground water body. Groundwater occurs
mainly under water table conditions in all formations. The important water bearing formation besides
alluvium is the gneisses granites, schists, limestone and phyllites. In the hard rocks the occurrence and
movement of ground water is controlled through the foliation/bedding planes, fissures, joints, solution
cavities and other structural weak planes. The weathered mantle of the hard rocks yields good discharge
of water. In alluvium ground water occurs in the interstices of unconsolidated sand and gravel, locally
semi confined conditions are encountered both in hard rock and alluvium. According to CGWB based on
the stage of ground water development in District Chamarajanagar 100% area in Yalandur taluk falls in
safe category. in Chamarajanagar and Kollegal taluk 76% and 40% area fall in safe category respectively.
In Mandya District, the stage of development for the whole district was computed as 37.93 %. About 27.14
% area of the district is over exploited, 11.43% area of the district is critical and 62 % of the area is safe.
In District Ramanagar, about 45% area of the district is overexploited, 42.5% semi critical and only 12.5%
of the area is safe.
Surface Water
Surface Water includes drainage channels (rivers, streams, and canals) and stagnant water bodies (lakes,
ponds, tanks and other impounded water bodies). A highway project can significantly alter the
hydrological setting of the project area by acting as an impediment to the natural drainage system of the
region. It is therefore essential that all surface water resources and ground water resources and their
characteristics be identified and examined along the project road.
Figure 4-4: Photographs of Surface Water Bodies
Water Quality
Selection of Sampling Location
Seven representative surface water and ground water monitoring stations were selected based on their
importance as source of irrigation and water supply, size, future impacts and quantum of water available.
The samples were collected once in the month of May 2013, by Noida Testing Laboratories, Greater
Noida for testing on behalf of Feedback Infra. All the basic precautions were taken care to avoid any
contamination during the sampling. Water samples were collected from sampling locations in plastic jerry
can and 500 ml sterilized clean glass bottles for complete physico-chemical and bacteriological tests
respectively. Sample for DO was collected in a pre-cleaned BOD bottle. The water samples were
preserved and stored in polythene bottles. Sampling bottles were kept in airtight large plastic ice-cold
containers and were transported to laboratory for further processing. The physical and chemical
parameters of the collected samples were tested as per established standard methods and procedures
prescribed by CPCB and relevant IS Codes. The locations selected for water sampling are presented in
Table below. The monitoring has been carried out with the following objectives:
To establish the baseline water quality at critical locations to be impacted; and
To work out the extent of enhancement of water resources along the corridor in terms of
improvement of water quality.
2
Source: Indian Standard Drinking Water Specification – IS 10500, 1994
Max
Sl. SWQMS SWQMS SWQMS Permissible
Parameter Unit GWQMS 1 GWQMS 2 GWQMS 3 GWQMS 4 Desirable
No. 1 2 3 Limit
Limit2
(as K)
29 Temperature 0C 30 31 31 31 27 29 32 - -
30 Phosphate mg/l BDL BDL BDL BDL <0.01 BDL BDL - -
(as P)
31 BOD (at mg/l BDL BDL BDL BDL 2.80 2.50 2.90 - -
270C 3-
Days)
32 Faecal 0 Absent/100ml Absent/100ml Absent/100ml Absent/100ml Present Present Present 0 No
Coliform Relaxation
33 Total 10 Absent/100ml Absent/100ml Absent/100ml Absent/100ml 164 132 160 10 Max No
Coliform Max Relaxation
Near Honnaganahalli
N6 402.00
Govt High School
Silence Zone 46.77 39.16 50 40
Source: Field Monitoring; Note: The area categorisation has been done by the consultants based on the
sensitive features and not by the authorities.
4.3.2 Fauna
The baseline study included identification of faunal species native to the study area especially with
reference to the ROW and adjoining areas. Domesticated animals like cattle and sheep dominate faunal
species all along the project road. All these animals and birds as per IUCN’s conservation status fall in
Least Concern category.
Cultural properties along the project highway were identified and documented based on site surveys and
during strip mapping. The total list of cultural and community properties along the project road are given in
Annexure 4.3. These cultural properties can be broadly categorised as:
Religious Structures- 34
Graveyards, Samshan ghats and Samadhi - 8
Figure 4-7: Cultural Properties along Project Road
Social Stratification
Client: National Highways Authority of India Draft EIA Report
30
Consultant: Feedback Infra Pvt. Ltd July 2013
UNCONTROLLED IF PRINTED
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of
Chamarajanagar to Harohalli section of NH – 209 in the state of Karnataka
It was observed from primary census data that a total no. of 564 households whose properties are
affected due to up gradation of road, Out of the total, 379 belongs to general caste while 132, 49 & 4
families belongs to BC, SC, and ST respectively.
Table 4-13: Social Stratification
Caste No. of Families Percentage
GEN 379 67.20
BC 132 23.40
SC 49 8.69
ST 4 0.71
Total 564 100.00
Educational Level
It was observed from the census survey data that the education levels amongst the families along the
proposed project corridor are 19.68%, 23.23%, 12.41%, 8.51%, 0.18%, 2.30% and 30.50 % for Primary,
Middle, Inter, Secondary, Diploma, Post Graduates and Illiterates respectively.
Table 4-15: Educational Levels of Families
Sl. No Education Families Percentage
1 Primary 111 19.68
2 Middle 131 23.23
3 Inter 70 12.41
4 Secondary 48 8.51
5 Graduates 18 3.19
6 Diploma 1 0.18
7 Post Graduates 13 2.30
8 Illiterates 172 30.50
Total 564 100.00
Source: Primary survey (2013)
Income Group
It has been found through survey that there are 63.652% of BPL families in the project stretch. People
though were not forthcoming about their actual income level and the enumerators at times had to guess
their income from their surrounding and life style. A huge percentage (32.624%) refused to divulge their
income.
Table 4-16: Income Levels
Sl. No Income (in Rs/ Annum) Families Percentage
1 < 25000 359 63.652
2 25001-50000 15 2.660
3 50001-75000 3 0.532
As a part of the project preparation and to ensure that the community support is obtained and the project
supports the felt needs of the people; public consultations were carried out as an integral component. A
continuous involvement of the stakeholders and the affected community was obtained. The feedback in the
consultation sessions has led to substantial inputs for the project preparation – including, influencing
designs. Consultations involve soliciting people’s views on proposed actions and engaging them in a
dialogue. It is a two-way information flow, from project authorities to people and, from people to project
authorities. While decision making authority would be retained by the project authority, interaction with
people and eliciting feedback allows affected populations to influence the decision making process by raising
issues that should be considered in designing, mitigation, monitoring and management plans and the
analysis of alternatives.
This chapter documents the issues that are close to the community, their aspirations and their addressal by
the project. Information source for the chapter has been the similar documentation as part of the RAP, with
the social team conducting these sessions. The objectives of consultation sessions, the procedure adopted
and the outputs of the consultation conducted have been briefly described in the following sections.
5.1 OBJECTIVES
The main objective of the consultation process is to minimise negative impacts of the project and to
maximise the benefits from the project to the local populace. The objectives of public consultation as part of
this project are:
Promote public awareness and improve understanding of the potential impacts of proposed projects;
Identify alternative sites or designs, and mitigation measures;
Solicit the views of affected communities / individuals on environmental and social problems;
Improve environmental and social soundness;
Clarify values and trade-offs associated with the different alternatives;
Identify contentious local issues which might jeopardise the implementation of the project;
Establish transparent procedures for carrying out proposed works;
Inform the affected populace about the entitlement framework and to settle problems with mutual
consent; and
Create accountability and sense of local ownership during project implementation.
occasions. The contacted officials included revenue officers, industry department etc. Several meetings were
held with NHAI Officials and their inputs have been incorporated in the Reports.
5.2.2 Consultations during Design
Consultations were carried out at the design stages to identify:
Location specific social and environmental issues to be addressed through designs;
Socio-economic profile of community along the project route;
Extent of likely social and environmental impact due to the project;
Expectations and reservations of people towards project; and
Resettlement and rehabilitation options.
5.2.3 Location Specific Consultation Needs
Several project road specific consultation needs identified were:
Where owners of property, land and building / structures or their tenants are involved, consultations
are required;
Need for improvement of intersection, curves, etc. has to be ascertained from people through
consultation process;
The noise sensitive receptors if any are to be identified through public consultation process.
Table 5-2: Addressal of General Issues and Concerns under the Project
Issue / Concern Addressal under the project
Plantation of trees and shrubs along the highway and on median
Dust and Air Pollution Turfing on earthen slopes and earthen shoulders
Water spraying to be adopted near the crushers during construction stage.
Provision of Noise attenuating wall near sensitive receptors
No-horns signage near schools, colleges and hospitals
Increased noise levels
Tree plantation and development of green belts along the project corridor abutting settlements to
attenuate traffic noise
Improvement of intersections
Traffic Congestion Provision of Flyovers, bypasses, underpasses etc at suitable locations
Road widening itself will be a major factor to avoid traffic jams
Proper highway signals provided as per IRC SP:67
Widening of bridges to avoid accidents
Road safety
Grade level pedestrian , PUPs & CUPs crossing
Proper lighting at accident prone locations
Care has been taken to preserve sites of cultural heritage as far as possible.
Cultural properties Where unavoidable the religious structures within ROW to be relocated only after consultation
with local community.
Tree clearing within ROW has been avoided beyond what is directly required for construction
activities and or to reduce accidents
Fauna and flora
Compensatory afforestation would be done as per the directives of the forest department.
Fruit bearing trees and shade trees, to be planted on the roadside.
Rising of road sections and cross drainage structures in areas facing overtopping problems.
Roadside Drainage Location of structures based on hydrological study
Provision of proper drainage scheme for the settlements
In unavoidable cases provision for increasing depth of water bodies to increase its capacity is
Water bodies
made.
Provision of facilities like Rest Areas, Truck stoppage site (lay bye) and bus stops along the
Road side amenities
highway
Loss of Livelihood and income The PAPs will be compensated as per National R&R policy
restoration option RAP to detail out the assistance programme to the needy
Assistance to vulnerable Special provisions have been made in the entitlement framework for assisting vulnerable groups
groups to improve their quality of life.
Employment of locals during
Locals will be given preference for employment during the project implementation
construction
6. IMPACT ASSESSMENT
This chapter assesses the nature, type and magnitude of the potential impacts likely on the various
relevant physical, biological and cultural environmental components along the project corridor. For the
assessment of impacts, the baseline information based on the field visits and the primary surveys of the
various environmental components carried out. The description of the impacts on the individual
components has been structured as per the discussion in Chapter 4: Baseline Environmental profile of
this report.
The project involves widening to four lanes/two lanes with paved shoulder of Chamarajanagar to Harohalli
section of NH – 209 and the impacts are expected to be mostly direct and confined to the Proposed ROW.
Only at critical locations where the engineering, environmental and social aspects have warranted a shift
from the existing alignment, realignments have been proposed. The impacts on the various environmental
components can occur at any of the following stages of the project planning and implementation:
Planning and design stage;
Construction stage; and
Operation stage
The description and magnitude of impacts for the various environmental components as visualised for the
project are presented in the following sections.
Construction Stage
A major source of dust during the construction stage is from stone crushing operations from the crusher
and the vibrating screen. The dust, in addition to being a health concern also reduces visibility thereby
increasing safety concerns. As no new quarry needs to be opened for this project (majority of the material
shall be from cut operations, reuse of old materials and existing quarries within the site itself), therefore,
no new impacts are likely to arise due to quarrying operations. A properly enforced EMP could improve
the working conditions of workers in the existing quarry areas selected for the project.
Though the quarry materials are to be transported over long distances to the construction sites, almost all
the quarries identified have proper access roads, therefore, no major impacts during the hauling of
materials is envisaged. The issue of dust generation etc along the haul roads needs to be addressed
through proper enforcement of dust suppression measures.
Soil Erosion
Pre Construction Stage
The removal of roadside vegetation will cause erosion, and increased run-off would in turn lead to erosion
of productive soil. The direct impact of erosion is the loss of embankment soil and danger of stability loss
for the road itself. This impact is generally restricted to the ROW. The project has taken care of this issue
at the engineering design stage itself, as at design gradients of 1:2, the slopes of the embankments are
perceived to be stable for all stretches of road. These sections of the road embankment would need stone
pitching or any other suitable turfing.
Construction Stage
Elevated sections of road in all sections, particularly all high embankments along the bridges, ROBs and
the bridge approaches would be vulnerable to erosion and need to be provided proper slope protection
measures to prevent erosion. Construction of new bridges involves excavation of riverbed and banks for
the construction of the foundations and piers. If the residual spoil is not properly disposed off, increased
sedimentation downstream of the bridge is likely. Though during construction period, drainage alteration
and downstream erosion / siltation is anticipated, due to the improved design and added capacity of the
cross-drainage structures, there should be an improvement in the drainage characteristics of the
surrounding area. Adequate slope protection measures are proposed as part of engineering design.
Removal of trees to facilitate construction will cause erosion problems until the proposed compensatory
afforestation plantation is established. Silt fencing to be provided to prevent eroded material from entering
watercourses. The regular cleaning of the drains by the Concessionaire will ensure that these structures
will not be overloaded or rendered ineffective due to overload.
Operation Stage
No soil erosion is envisaged when the road is in operation as all the slopes and embankments of the
project road shall be stabilised through sound engineering techniques. The issue has been addressed at
the design stage itself and all slopes have been 1:2, which shall ensure stability of the embankment.
Appropriate landscaping measures such as pitching of slopes and turfing shall prevent soil erosion taking
place.
Compaction of Soil
Pre-Construction Stage
Compaction of Soil will occur in the pre-construction stage (particularly during site clearance stage) due to
movement of heavy machinery and vehicles. Transplantation of trees if carried out shall involve very
heavy machinery to uproot trees and haul them to the site of transplantation. Similarly, compaction will
take place during setting up of construction camps and stockyards. However, this is a short duration
impact. Appropriate measures need to be specified in the Environment Management Plan to minimise the
area of soil compaction.
Construction Stage
Compaction shall occur beyond the carriageway and within the vegetated area of the ROW by the
movement of vehicles and heavy machinery. Movement of vehicles during road construction is the major
cause of soil compactions. This impact is direct and will be the maximum in the ROW. It is necessary to
ensure that there is no adverse impact of soil compaction in areas other than the ROW, where vegetation
can grow and rain infiltration will take place.
Operation Stage
During the operation period compaction will be restricted to the CW itself. Compaction cannot be said to
be an impact of the operation stage as the pavement itself is a function of compacted base and sub base.
Contamination of Soil
Pre-Construction Stage
Contamination of oil in the pre-construction stage may be considered a short-term residual negative
impact. Soil contamination may take place due to solid waste contamination from the labour camp set up
during pre-construction stage. This impact is significant at locations of construction camps; stockyards,
hot mix plants etc. will come up in this stage.
Construction Stage
Contamination of soil during construction stage is primarily due to construction and allied activities. The
sites where construction vehicles are parked and serviced are likely to be contaminated because of
leakage or spillage of fuel and lubricants. Pollution of soil can also occur in hot-mix plants from leakage or
spillage of asphalt or bitumen. Refuse and solid waste from labour camps can also contaminate the soil.
Contamination of soil during construction might be a major long-term residual negative impact.
Unwarranted disposal of construction spoil and debris will add to soil contamination. This contamination is
likely to be carried over to water bodies in case of dumping being done near water body locations.
Operation Stage
During the operation stage, soil pollution due to accidental vehicle spills or leaks is a low probability as
one of the main objective of the project is to reduce accidents, but potentially disastrous to the receiving
environment should they occur. These impacts can be long term and irreversible depending upon the
extent of spill. There should be a disaster management plan in case of such major spills occurring.
6.2.3 Air
Air quality along the project corridor will be impacted both during the construction and operation
stages of the project.
Construction stage impacts will be of short term and have adverse impacts on the construction
workers as well as the settlements adjacent to the road, especially those in the down wind direction.
Operation stage impacts will not be as severe as the construction stage impacts and will be
confined generally to a band of width ranging from 50 to 75m from the edge of the last lane on
either side of the corridor.
Both the construction and operation stage impacts can be effectively mitigated if the impacts have
been assessed with reasonable accuracy in the design stage.
Generation of Dust
Pre Construction Stage
Generation of dust is the most likely impact during this stage due to:
Site clearance and use of heavy vehicles and machinery etc.;
Procurement and transport of raw materials and quarries to construction sites;
The impacts will mostly be concentrated in the PROW. If adequate measures such as sprinkling of
water on haul roads around sites where clearance activities are on, covering material trucks
especially those carrying sand and fly ash, then the impacts can be reduced to a great extent. It is
likely that impacts due to dust generation are felt downwind of the site rather than on the site itself.
Construction Stage
As the project corridor lies in a location where the major air pollution generating sources are stone
quarries (particularly in District Chamaraja Nagar) and the construction activities proposed to be carried
out during the dry season (when the moisture content would be less), dust generation, particularly due to
earthworks will be significant. Dust is likely to be generated due to the various construction activities
including:
Stone crushing operations in the crushers;
Handling and storage of aggregates in the asphalt plants;
Concrete batching plants;
Alteration of Drainage
Impacts of road construction, which lead to alteration of drainage, are generally widening at culvert or
bridge locations. This requires river and or gully training for the period during which the bridge is to be
constructed. Alteration of drainage can lead to soil erosion of adjacent areas, disturb local vegetation and
impair local ecology.
Pre Construction Stage
No drainage modification of surface flow of rivers / streams is envisaged during pre construction period.
However, about 18 ponds are likely to be partially affected due to the proposed development. The details
have been presented in Table 6-4.
Construction Stage
Though the constructions along the watercourses are to be carried out in the lean flow periods, as the
major rivers are perennial, the construction activities will necessitate the diversion of the waterway. This
diversion of flow can significantly harm the aquatic habitat, if any. The waterway will be constricted,
increasing velocity downstream of the bridge. This will mean increased sediment load with the flow,
thereby allowing less sunlight to penetrate into the water and can reduce growth of micro flora. The impact
shall be direct but short term in nature and shall last till the construction period. Short-term increase in
runoff during construction may occur due to the removal of trees, vegetative cover and compaction of the
surrounding soil during pre construction. Thus the increased sediment load will be a significant impact that
needs to be addressed for all water bodies along the corridor and adequate silt fencing measures need to
be provided. The design proposes the raising of the embankments from the existing levels to ensure that
the finished pavement is above the maximum flood level so as to prevent any impacts due to any water
seepage in the pavement. No significant impacts in the drainage pattern due to the raising of the road
profile are likely, as the road design itself takes care of the cross-pavement drainage.
Operation Stage
The project involves the widening of carriageway. One of the unavoidable aftermaths of road construction
is the increased surface run off. The new lanes, which are essentially a paved impervious surface, will
cause increased surface runoff along the roadsides. Increase in surface run-off is due to the creation of
impervious surfaces that prevent the flow of water into the ground. Impacts due to surface runoff include
increased soil erosion and local flooding or water logging. However, as the proposed lanes has been
designed with ditches on both sides to take care of surface runoff local flooding due to the proposed
increased runoff shall be taken care of effectively. Surface runoff shall be drained to the nearest cross
drainage structure. The engineering design includes design of cross drainage structures, which should
take care of the extra flow.
Water Required for the Project
Pre Construction and Construction Stage
The most likely significant impact on water during construction is depletion of water table. Rigid
pavements have been suggested at the toll plaza locations only. The cement concrete construction works
requires a considerable quantity of potable water for the various activities including construction of the
pavement, dust suppression, curing etc. The water requirements for the various construction activities are
presented in table below.
The peak demand of water to be used during the construction phase will be around 56 KLD. The demand
though is only indicative in nature and shall differ during the lean period of construction. The demand shall
be met through availability of ample supply both from surface sources (Like River Cauvery) and ground
water. Thus, it is apparent that the water requirement for the project will not be a major impact on the
environment. As the ground exploitation is not very prominent in the project districts, the ground water
resources may not be impacted due to the project activities. More over surface water sources shall also
be utilised (wherever available) for the project activities. To minimise the minor impacts of the project on
the water resources, water harvesting structures and ground water recharge measures have been
proposed.
Operation Stage
The depletion of water is predominantly restricted to the construction phase. The road operation does not
make a demand on the available water resources apart from time to time requirement during works such
as maintenance of road side tree plantations.
Water Quality
Pre Construction Stage
Water sources including flowing and stagnant water sources are likely to be contaminated due to activities
such as setting up workers camp near water sources or transportation of construction material such as
sand, borrow material etc without covering it. Due to tree felling soils around the water bodies and surface
drainage channels will be exposed during the pre construction stage, during which, the suspended
sediments and the associated pollutants can be washed in to these water sources. As soil all along the
corridor isn’t of alluvial type, the impacts due to the increased sediment load will not be a significant
impact that needs to be addressed for all water bodies along the corridor. Even then adequate silt fencing
measures need to be provided. Contamination of groundwater is another likely impact of road construction
and allied activities. The groundwater recharge areas may be reduced due to an increase in impervious
layers due to the construction. The contamination of the groundwater resources due to the project is likely
at the following locations:
Along construction sites, camps involving moving of construction equipments and machinery.
At the various community water bodies and sources of water supply such as hand pumps etc
Along the entire length of the corridor especially around urban areas and productive lands.
Construction camps or stockyards are not to be set up near Rivers, irrigation canals and water bodies to
prevent oil spills.
Construction Stage
The impacts on water quality will be of greater concern during the construction stage. Increased sediment
load during preparation of the site is the most likely adverse impact. The contamination by fuel and oil
from construction vehicles or bitumen from hot-mix plants is less likely and in any case expected to be
localised. Discharge from labour camps and vehicle parking areas will have to be treated before discharge
into any watercourse. It is during the operation stage that the leakage or spillage from vehicles damaged,
overturned or just badly maintained is more likely.
The construction activities around the surface bodies can affect the water quality due to the disposal of
solid and liquid wastes from labour camps, fuel and lubricant spills or leaks from construction vehicles,
fuel storage and distribution sites and from bitumen or asphalt storage at hot-mix plants.
Also, the raising of the road shall mean that more embankment surface is prone to erosion. However, the
engineering design shall ensure protection of embankment slopes. The spoil heaps around the
construction sites are also prone to erosion and contribute to the increased sediment load in the near-by
water bodies. The major parameter of concern would be the sediment load from the spoils. The major
pollutants of concern are suspended solids, oil and grease, lead and other heavy metals.
Concentration of suspended solids is likely to be highest during the construction stage and
immediately after the construction when vegetation has not been fully established on the
embankment slopes.
Oil and grease form a film on the water surface and hinder the transfer of oxygen into water.
Though the compounds of lead are suspected to be carcinogenic, it is unlikely that leads pollution to
have significant effects as 90-95% of lead in run-off is inert, and will be further diluted in the
receiving water bodies, where the lead concentrations are minimal.
Discharge from labour camps and vehicle parking areas will have to be treated before discharge into any
watercourse. It is during the operation stage that the leakage or spillage from vehicles damaged,
overturned or just badly maintained is more likely. The existing levels of contaminants, which can trace
their origin to road run-off, indicate that water quality degradation is not a significant impact. Normally
groundwater is shielded from the effects of such degradation, but if the discharges from construction
camps were disposed off using soak-pits / septic-tanks that were not adequately designed, the
consequences would be disastrous since restoration of groundwater quality is a much slower process.
The impacts of run-off laden with sediment may be felt in villages that depend on the fish living in the
water-body. Increased sediment load, lesser sunlight, difficulty to settle, etc will make the water more
turbid. If the concentrations are higher, smaller fish may be harmed. Large, heavy sediment, particularly
with slow moving water may smother algae and eventually alter the nature of the sub-stratum. Excessive
sediment loads may also mean disruption to areas where fish lay their eggs. However, it must be noted
that these effects are probable only during construction stage. The water quality of surface drainage
channels is likely to be impaired as long as the construction period continues. However, measures to
divert the passage of pollutants into the river can be adopted to minimise the impact.
Operation Stage
No contamination of any water source is envisaged during the operation period.
Volumetric Capacity of Water Resources affected
A total of 18 water bodies are getting affected due to the proposed project. The following steps have been
used for the determination of volumetric capacity of water bodies.
Step-1: Determining area of pond due to road (proposed alignment or widening) encroachment
Step-2: Finding approximate average depth of pond based on topo survey levels and generating
contours
Step-3: Finding volume of loss of water due to encroachment by multiplying area and depth
Table 6-4: Volumetric Capacity of Affected Water Resources
Design Chainage Volume of
Area affected Loss of
Approx
Sl. Side of due to Road Water Settlement/Villa
Depth Remarks
No. From To Pond Encroachme Retaining ge Name
(m)
nt (m2) Capacity
(m3)
1 318+930 318+975 Bothside 1709.222 2 3418.444 Santhemarahalli Realignment
2 319+885 319+920 RHS 2464.654 2 4929.308 Santhemarahalli Widening/Built-up
3 320+490 320+530 RHS 595.359 2 1190.718 Santhemarahalli Widening/Agricultural
4 322+080 322+200 RHS 4989.321 2 9978.642 Avala Kandahalli Widening/Built-up
5 327+330 327+380 RHS 3714.465 2 7428.93 Yeriyuru Widening/Built-up
6 327+390 327+420 RHS 656.813 2 1313.626 Yeriyuru Widening/Built-up
7 331+750 331+790 LHS 1188.896 2 2377.792 Madduru Widening/Agricultural
8 346+620 346+675 LHS 3344.982 2 6689.964 Saragur Widening/Built-up
9 346+705 346+740 LHS 1314.174 2 2628.348 Saragur Widening/Built-up
10 349+820 349+860 LHS 3704.925 2 7409.85 Danagere Widening/Agricultural
11 351+330 351+3995 LHS 3078.53 2 6157.06 Sattegala Widening/Agricultural
12 358+505 358+580 Bothside 4052.288 2 8104.576 Belekavadi Sathegala Bypass
14 379+560 379+575 LHS 476.384 2 952.768 Attavanahalli Realignment
15 385+140 385+160 LHS 755.78 2 1511.56 Halsahalli Widening/Agricultural
16 394+940 395+510 LHS 2739.969 2 5479.938 Gundapura Widening/Agricultural
17 399+560 399+580 LHS 191.072 2 382.144 Sasalapura Widening/Agricultural
18 399+705 399+720 RHS 155.463 2 310.926 Sasalapura Widening/Agricultural
supply sources has been strongly recommended and the cost of the relocation has been included as part
of the project cost.
Table 6-5: Impact on Water Resources
S.No. Chainage Distance from Existing C/L Structure Settlement Side Impact
Existing (Km) Name
Hand Pump
333.900 6 Hand Pump Mampalli RHS Yes
357.010 10 Hand Pump Satara RHS Yes
367.400 8 Hand Pump Pandithalli RHS Yes
387.210 18 Hand Pump Halasahalli RHS Yes
402.700 30 Hand Pump Honnaganahalli LHS No
409.950 12 Hand Pump Devegowdanadoddi LHS Yes
12 Hand Pump Uttampalya RHS Yes
Over Head Tank (OHT)
321.200 15 OHT Kandarahalli RHS Yes
329.850 15 OHT Maddur RHS Yes
353.200 15 OHT Satara RHS No/Yes
369.000 15 OHT Pandithalli RHS
369.990 15 OHT Vachanahalli LHS Yes
418.320 25 OHT Shivanahalli RHS No
20 OHT Kollegal RHS
10 OHT Kollegal LHS Yes
Water Tap/ Tank
369.000 12 Water Tank Satnur RHS Yes
370.200 25 Water Tank Basavapur LHS
386.880 10 Water Tap/Tank RHS Yes
406.850 10 Water Tap/Tank Tungne LHS Yes
410.900 12 Water Tap/Tank Kanakapura RHS Yes
412.900 15 Water Tap/Tank Jakkegowdanadoddi LHS Yes
413.150 8 Water Tap/Tank Jakkegowdanadoddi LHS Yes
418.300 15 Water Tap/Tank Upkeredoddi LHS Yes
424.800 10 Water Tap/Tank Vachanahalli RHS Yes
427.850 12 Water Tap/Tank Pandithalli RHS
Well
339.800 12 Well RHS Yes
The impacts on noise due to the project will be of significance in both the construction as well as the
operation stages.
Table 6-61: Noise Impacts
Sl.
Phase Source Impact
No.
Man, material and machinery movement Short duration
Pre
1 Establishment of camps, site office, stock yards, construction Localised impact
Construction
plants etc. Negligible
Plant site
Plant site: significant impact
Crushing, hot mix plants, machineries, batching plants,
within 500m
2 Construction excavation, grading, paving activities
Work zones: temporary and
Work zones
negligible
Community residing near the work zones
3 Operation Increase in traffic Negligible impact
Though the noise levels are within the stipulated standard, the noise levels are a concern due to the
number of sensitive receptors located along the project road. The impacts on the receptors shall basically
relate to increase in noise levels, access and physical damage to the structure. There are 29 educational
institutes, 4 administrative offices and 3 health units likely to be partially impacted, while another 1
school1 and 1 health units shall be directly impacted. Even though complaints of noise and vibration are
common, most of the receptors are quite far away from the road and hence the noise is dissipated.
Table 6-7: Sensitive Receptors – Impacts
Distance from C/L Structure
S.No Settlement Side Impact
(Existing) Name
Educational Institute
1 25 School Chamarajnagar LHS Partial
2 10 School Kandarahalli RHS Partial
3 20 College & School Yelandur LHS Partial
4 10 Teachers Training Institute Yelandur LHS Partial
5 20 School Yelandur LHS Partial
6 9 School Yeriyoor RHS Partial
7 18 School Maddur RHS Partial
8 15 School Uttampalya LHS Partial
9 30 School Kollegal LHS Partial
10 10 School Pandithalli RHS Partial
11 15 School Dassanadoddi LHS Yes
12 15 School Vachanahalli RHS Partial
13 15 Education Institute &Hostel Malavalli LHS Partial
14 25 College Malavalli LHS Partial
15 20 IT & Bed. Malavalli LHS Partial
16 10 School Chonalahalli RHS Partial
17 25 School Basavapur LHS Partial
18 15 High School Halasahalli LHS No
19 8 Primary School Kodehalli LHS Partial
20 12 Govt. High School Honnaganahalli LHS Partial
21 15 Primary School Jakkegowdanadoddi LHS Partial
22 12 Primary School Shivanahalli LHS Partial
23 10 School Pit Shivanahalli RHS Partial
24 25 Education Institute Kanakapura LHS Partial
25 30 School Tungne RHS No
26 50 University Jakkasandra LHS No
27 15 Jan College Jakkasandra LHS Partial
28 10 School Harohalli LHS Partial
29 20 College Kanakapura LHS Partial
supported by the roadside trees. Not only would the removal of trees lead to erosion, it would also mean
that the micro-ecosystems developed on the roadside with the birds, animals and insects using the
plantation over the years would be lost too. The only mitigation would be to ensure that the compensatory
afforestation required as per the MoEF guidelines for the project is carried out with native species and
proper care of the saplings is taken to ensure that the roadside plantation returns to its previous state as
quickly as possible. Co-operation of locals to ensure that local cattle do not damage the saplings during
the early stages of growth will be required.
The roadside plantations will need to be cleared for the project. Though the loss of these trees is an
irreversible and long-term impact, the loss of the roadside plantations shall have to be compensated in
accordance to the principles of the Forest (Conservation) Act.
Construction Stage
The construction of new road shall involve removal of topsoil and clearing of vegetation cover and felling
of trees. These activities will exert wide-ranging impacts on the surroundings as summarised in Table
below.
Table 6-8: Likely Impacts on Flora
Activity Impact
Cutting and removal of earth/rock Loss of vegetation cover (shrubs & grasses) canopies;
Road Construction Felling of 2431 trees of girth more than 30 cm;
Reduced shade and shelter for roadside fauna
Reduction in soil fertility, moisture and humidity
Workers Camps Use of plants and trees as fuel wood
6.3.3 Fauna
Domesticated animals dominate fauna species. There might be some endangered species within the
forest area near to the project, though straying of these animals outside the forest areas is not reported by
the inhabitants. There is likelihood of slight impact to local domestic animals, which graze in the area
especially after the road is constructed. Increased vehicle movement in the area might lead to accidents
involving animals. In areas with high traffic volumes, road kill can be a considerable or even the
predominant cause of mortality. To avoid such accidental kill, the project shall provide suitable animal
crossing as part of the project.
More over there shall be positive impact on the faunal species during the operational phase. The
plantation activity carried out, as part of the project component shall provide shelter and food for the
smaller avian and mammalian species, which in turn shall improve the overall food chain and food web
and ultimately the ecology of the area.
6.3.4 Aquatic Ecology
The construction of new bridges will cause some contamination of the river / canal water due to spillage of
construction material, sediment loading & increased turbidity downstream of the bridge location.
Construction activity during widening of road will directly or indirectly affect several water bodies located
adjacent to the road. This change shall have some impact on the flora and faunal species and change the
nature of the substratum resulting in decline in the number and diversity of plants and thus the food web.
No negative impacts are envisaged on the aquatic ecology during the operational phase.
Distance
Structure Settlement Side Impact
S.No. from C/L
Existing Name
3 20 Graveyard Yelandur LHS Partial
4 25 Graveyard Partial
5 13-10 Graveyard Halagur LHS Partial
6 150 Graveyard Kaglipura LHS No
7 35 Graveyard Chamarajnagar LHS No
8 12 Mission Graveyard Upkeredoddi LHS Yes
and towns through which the road passes. The improved transportation facility provides the linkages that
will allow much better access to previously difficult to reach markets (for buyers and sellers). This would
mean not only the people from congested areas in cities will want to move to the fringe, but also, people
from nearby rural areas would migrate to the city. Urban services are seldom able to keep pace with the
growth of a city. The growth of a city beyond the established spread network will mean piecemeal
arrangements for services like water supply, wastewater treatment and disposal, and transportation. All
the settlements along the project corridor will experience a sudden boom in activity and population around
the start of operation of the project corridor. Thus, a ribbon development is envisaged all along the project
road.
6.4.2 Cultural Properties
Relocation of Cultural Assets
Cultural properties (shrines, sacred and archaeological structures) lying near the ROW are most
susceptible to impacts due to pre construction and construction activities. Clearing of the site during
movement of road construction machinery is likely to require a belt of about 4-5m from the edge of the
carriageway, which is likely to adversely impact cultural properties. Cultural properties will be subjected to
varying degree of impact depending upon their placement in the ROW. Structures, which are close to the
proposed CW, are likely to need relocation. The project shall directly impact 14 religious structures which
have to be relocated. The construction shall also partially impact 14 religious structures. The access of
some of these cultural properties shall also be compromised. 5 cremation sites are likely to be affected.
However, best effort shall be given to avoid those sites.
Table 6-10: Impact on Cultural Properties
Structure
Distance from
S.No Settlement Side Impact
Existing C/L (m) Name
Religious Properties
25 Church Vasagapura RHS Partial
8 Mosque Yelandur RHS Partial
8 Temple Yelandur LHS Partial
5 Temple Mampalli RHS Yes
15 Temple Mampalli RHS Partial
15 Temple RHS Yes
45 Temple RHS No
25 Temple Pandithalli RHS Partial
20 Mazaar Malavalli LHS Partial
20 Temple Malavalli RHS Partial
15 Temple Malavalli LHS Partial
70 Temple TK Halli RHS No
45 Church TK Halli LHS No
10 Mosque Halagur RHS Partial
9 Mosque Halagur RHS Partial
8 Temple (small) RHS Yes
20 Temple Honnaganahalli LHS Partial
30 Mazaar/Idgaah Honnaganahalli RHS
30 Temple Satnur RHS Partial
8 Temple (small) Jakkegowdanadoddi RHS Yes
8 Temple (small) K. Doddi LHS yes
10 Temple Shivanahalli LHS Partial
7 Temple (small) Shivanahalli LHS Yes
5 Temple Kanakapura RHS Yes
15 Temple Kanakapura LHS Partial
15 Temple Kanakapura RHS yes
12 Temple (Small) Jakkasandra LHS Yes
7 Temple (small) Harohalli RHS Yes
10 Mosque Kaglipura RHS Yes
25 Temple Kaglipura RHS No
Temple Kaglipura RHS No
15 Temple Kaglipura RHS Yes
12 Temple Kollegal RHS Yes
12 Mazaar Kollegal LHS Yes
Cremation Sites
20 Christian Graveyard Malavalli LHS Partial
25 Graveyard LHS No
20 Graveyard Yelandur LHS Partial
25 Graveyard Partial
13-10 Graveyard Halagur LHS Partial
Structure
Distance from
S.No Settlement Side Impact
Existing C/L (m) Name
gradation of the existing road followed by curve improvements & service roads.
Table 6-2: Proposed Land Requirement in the Project
Parking &
amenities
Curve Service Eccentric Insufficient Toll Bus Total
Bypass Bridges including
improvement Roads Widening ROW Plaza bay land
Truck lay
bye
27.07 WITHIN
103.84 0 5 104.511 - - 2.199 242.62
ROW
6.5 CONCLUSION
Based on the analysis of environmental impacts in the above sections, it can be concluded that the project
is anticipated to cause the following environmental impacts:
Partial damage on 5 schools & 1 health unit
Direct & Full impact on 1 school and 1 health unit & these has to be relocated
Loss 5000 trees along the existing project road due to felling
Acquisition of 242.6 ha of land be required for the project
Direct & Full impact on 15 temples and 1 mazar & these has to be relocated
Partial impact on 3 temples
Loss of access to sensitive receptors, cultural properties and amenities
The specific and generic mitigation measures of and the management plan are discussed in details in
chapter 9 and 10.
7. ANALYSIS OF ALTERNATIVES
The chapter tries to compare feasible alternative to the proposed project with respect to site, technology,
design etc. The alternatives examined take into account all possible and feasible options and includes
both with and without project scenarios in terms of the potential environmental impacts for the justification
of the project. The chapter discusses how environmental parameters were assigned due importance and
were carefully considered in the analysis of alternatives.
Kollegal Bypass
Please state the key reasons for providing the bypass.
Alternative Analysis was carried out for the Bypasses considering environmental & social impacts,
engineering and economics aspects.
Sathegala Bypass
Please state the key reasons for providing the bypass.
Alternative Analysis was carried out for the bypass considering environmental & social impacts,
engineering and economics.
Figure 7-2: Proposed Sathegala Bypass- Alternatives
Alternate 2 (Following
Sl.No. Description Alternate 1 Alternate 3
Existing)
through
proposed
alignment
11 No of Structures 1 Major Bridge 1 Major Bridge. Existing bridge 1 Major Bridge.
is only 5m width.
12 Accessibilty - - -
13 Area Required, 29.61 14.139 26.352
Hectores
14 Social Impact Light Light Sathegala Builtup will be
affected.
15 Environmental Forest area required Heavy cutting due due isolated Hill cutting required.
Impact hills in the section
16 Recommendation Recommended Not recommended Not recommended
Halaguru Bypass
Please state the key reasons for providing the bypass.
Alternative Analysis was carried out for the bypass considering environmental & social impacts,
engineering and economics which has been presented in Table 7-5.
Alternate 3( Minor
Sl.No. Description Alternate 1 Alternate 2 (Following Existing)
Curve Improvement)
5 Length of 3.25 3.25 3.25
existing
alignment
Bypassed
6 Terrain Passing Through Plain Terrain Passing Through Plain Terrain Passing Through Plain
Terrain
7 Speed 100 km/hr 65Kmph 80km/hr
8 Geometrics Smooth horizontal and vertical Smooth horizontal and vertical Smooth horizontal and
geometrics is possible geometrics are not possible vertical geometrics is
possible
No of Curves =3 No of Curves =7 No of Curves =5
9 at Grade 3 5 0.0 Nos
Junction
Improvement
10 Existing Land Agricultural Builtup Area Agricultural &Builtup
use pattern
through
proposed
alignment
11 No of Structures 7 culverts 1 Minor Bridge I minor bridge
12 Accessibilty - - -
13 Area Required, 9.42 3.25 4.45
Hectores
14 Social Impact Light Heavy-70 structure to be demolished Heavy
15 Environmental Agriculture and few canals will be Considerable Builtup. Tank will be Considerable Builtup.
Impact affectd affected. Also fourlaing is required Tank will be affected.
Also fourlaing is
required
16 Recommendation Recommended Not recommended Not recommended
Kanakapura Bypass
Please state the key reasons for providing the bypass.
Figure 7-4: Proposed Kanakapura Bypass- Alternatives
Major Realignment
Major realignments have been proposed at the following 3 locations:
Table 7-8: Major Realignment Locations
Existing Chainage (Km) Proposed Chainage (Km)
Realignment Location Existing Length(m) Proposed Length(m) Side
From To From To
Santhemarahalli 317.100 318.750 318.320 319.670 1650 1350 Right
Yelandur 323.000 325.580 323.860 326.280 2580 2420 Left
Agaram 333.700 336.900 334.270 336.550 3200 2280 Left
Santhemarahalli Realignment
Please state the key reasons for providing the realignment
Yelandur Realignment
Please state the key reasons for providing the realignment.
No of Curves = 3 No of Curves = 5
7 Existing Land use pattern Agricultural Builtup
through proposed alignment
9 Proposed ROW - 30 m
Area Required, Hectares 7.74 Hec Total area required 3.87Ha
Sl.
Description Realignment Following Existing Alignment
No.
3. Optimal length proposed with 3. Length is more or less same as that of earlier
100km/hr speed proposal
5. Avoids built-up
13 Demerits 1. Fertile land to be acquired 1. Compromise to be made in technical aspects.
Design speed will have to be reduced to
65Kmph.
2. Two lane with paved shoulder will 2. Fourlane will be required to cater local traffic
suffice
Agaram Realignment
Please state the key reasons for providing the realignment.
Sl.
Description Realignment Following Existing Alignment
No.
7 Existing Land use pattern through Agricultural Builtup
proposed alignment
8 No of Structures affecting - More than 50 houses will be affectd
9 Proposed ROW 30 m 30 m
Area Required, Hectares 6.84 Hec 7.04 Ha
Asphalt cement is heated aggregate, combined, and mixed with the aggregate at an HMA facility. The
comparison between the two is given below:
Table 7-12: Analysis of Cold & Hot Mix Technology
Sl.
Parameter Cold Mix Hot Mix
No.
Hot mix asphalt is used primarily as paving material and
Street Cold Asphalt is a relatively new consists of a mixture of aggregate and liquid asphalt
product developed in 1995 through the cement, which are heated and mixed in measured
introduction of new polymer technology quantities.
and research into the manipulation of
Hot mix asphalt facilities can be broadly classified as
viscosity and material design, of the
either drum mix plants or batch mix plants, according to
1 Description various components of an asphalt mix -
the process by which the raw materials are mixed.
Street Cold Asphalt is soft and sticky out
In a batch mix plant, the aggregate is dried first, then
of the bag, but it quickly hardens after
transferred to a mixer where it is mixed with the liquid
application and the end result is a
asphalt.
pavement patch with better strength but
similar properties to hot asphalt. In a drum mix plant, a rotary dryer serves to dry the
aggregate and mix it with the liquid asphalt cement.
Cold patch, also known as cold mix or Hot mix asphalt concrete (commonly abbreviated as
cold asphalt, was first recognized as a HMAC or HMA) is produced by heating the asphalt
way to make road repairs quickly because binder to decrease its viscosity, and drying the
it can be applied right from the container aggregate to remove moisture from it prior to mixing.
without heating. Mixing is generally performed with the aggregate at
2 Requirements
Cold asphalt also doesn’t require any about 300 °F (roughly 150 °C) for virgin asphalt and 330
special heavy rolling machines or special °F (166 °C) for polymer modified asphalt, and the asphalt
applicators as it can be shoveled or cement at 200 °F (95 °C).
poured into a pothole or utility cut and Paving and compaction must be performed while the
tamped down with a hand tool. asphalt is sufficiently hot
Cold mix asphalt concrete is produced by
emulsifying the asphalt in water with
(essentially) soap prior to mixing with the
aggregate. While in its emulsified state the
asphalt is less viscous and the mixture is HMAC is the form of asphalt concrete most commonly
used on high traffic pavements such as those on major
easy to work and compact
highways, racetracks and airfields
3 Use The emulsion will break after enough
water evaporates and the cold mix will, Asphalt concrete has different performance
characteristics in terms of surface durability, tire wear,
ideally, take on the properties of cold
braking efficiency and roadway noise.
HMAC
Cold mix is commonly used as a patching
material and on lesser trafficked service
roads
Actually less expensive to use over the life
of a road repair
4 Merits Completely seals and patches potholes, Less expensive for new road construction
utility cuts, edge repairs, and even
overlays.
Less resilient and more vulnerable to
5 Demerits Expensive
cracking
Cold Mix technology is more suitable for repair of potholes and cracks on roads, bridges, overlays,
parking lots and other asphalt and concrete surfaces. Cold Mix is fast, permanent, easy to use and
environmentally preferable cold asphalt product. However for constructing of new roads hot mix
technology is better suited. The Concessionaire through his design engineer shall study the use of cold
mix technology in more details and utilise the same where ever suitable.
Sl.
Particular Impact Reason Mitigation / Enhancement
No
maintenance
Measures will be revised & improved to
Soil quality Effectiveness / shortfall (if any)
- mitigate / enhance environment due to any
monitoring Any unforeseen impact
unforeseen impact.
Change in Seismology
No negative impact on the seismological setting of the region is anticipated. Rather, as part of the project all
the existing structures will be checked and constructed as per the seismological requirements of the region
in conformity to the IS 1893(Part 1):2002.
Erosion
Incorporating appropriate type of treatments of slopes has reduced the potential for erosion of high
embankments and bridge fills. The soil is assumed to have an angle of repose corresponding to 1V: 2H.
Slope protection is normally required only for slopes steeper than this. The side slopes gentler than this will
be turfed with shrubs and grasses as per IRC: 56-1974: Recommended Practices for Treatment of
Embankment Slopes for Erosion Control.
Contamination of Soil
Contamination of soil can spoil the soil and can also contaminate the surface as well as ground water
sources. Details of the activities from which the contamination can occur are presented below:
Table 8-2: Mitigation Measures for Soil Contamination
Potential impact Mitigation
No scarification involved.
In case concessionaire decides to scarify then the material to be reused in the GSB layer.
Scarified Bituminous
Wastes Non reusable Bituminous wastes to be dumped in 30cm thick clay lined pits with the top 30cm layer
covered with good earth for supporting vegetation growth over a period only after obtaining permission
of Independent Engineer.
Scarified Non Bituminous
Used in the normal GSB layer (not the drainage layer)
Material
Reused as embankment, median & shoulder fill materials
Cut material Excess material to be used for filling up of borrow areas identified by the concessionaire and approved
by the Independent Engineer
Construction debris
Annexure 8.1 : Guidelines for Identification of Debris Disposal Sites & Precautions needed
generated from
dismantling of structures Annexure 8.2: Guideline for Rehabilitation of Dumpsites & Quarries will be applicable
An emergency response team to be created. The team shall contain members of the district and police
administration and also have specialist in remediation. Responsibility of Concessionaire to inform the
Soil Contamination due to team to take actions. The roles and responsibility of the members of the ram shall be framed in
accident spills conjunction with all the parties to address the situation arising out of the accidental spills resulting in
situation like water and soil contamination, health hazards in the vicinity of the accident spot, fire and
explosions etc.
Soil contamination due to
Improvements of design shall lead to less accidents and hence less spillage of oil and grease
Highway run off
Fuel storage will be in proper bunded areas.
Soil Contamination during All spills and collected petroleum products to be disposed off in accordance with MoEF and SPCB
construction stage from guidelines and as per the directions of the Emergency Response team.
fuel spills Fuel storage and fuelling areas will be located at least 300m from all cross drainage structures and
significant water bodies.
Operation of residential
Vehicle parking area will be made impervious using 75 mm thick P.C.C. bed over 150 mm thick rammed
facilities for labour
brick bats. The ground will be uniformly sloped towards to adjacent edges towards the road. A drain will
camps, Vehicle parking
take all the spilled material to the oil interceptor
areas
The stockpile shall be designed such that the slope does not exceed 1:2 (vertical to horizontal), and
the height of the pile be restricted to 2m. To retain soil and to allow percolation of water, silt fencing
shall protect the edges of the pile.
The stockpiles shall be covered with gunny bags or tarpaulin.
Such stockpiled topsoil will be returned to cover the disturbed area and cut slopes. Residual topsoil will
be distributed on a areas as identified by concessionaire and approved by the Independent Engineer
in a layer of thickness of 75mm - 150mm. Top soil shall also be utilised for redevelopment of borrow
areas, landscaping along slopes, medians, incidental spaces etc,
During construction, some land will be temporarily needed to create detours, store equipment and material,
site construction workers' camp and other amenities. The top 150 mm of soil from these areas will be
stripped off and stored in heaps of less than 2 m height. The slope of the pile will be maintained to lesser
than 1:4 to reduce removal of sediment with runoff and to enhance percolation through stored soil. The
stored soil will be used for:
Covering all disturbed areas including for the rehabilitation of borrow areas
Top dressing of the road embankments and fill slopes
Distribution over barren / unproductive areas, for a depth of 75-100mm, to make these lands
productive.
Quarries
Existing quarries that are already in operation with the required environmental clearances have been
recommended for this project, and no new quarries have been proposed. The existing quarries are suitable
for the requirement of coarse and fine aggregate required for the road works. In case the Concessionaire
decides in opening up of new quarries for the project, he shall follow the instructions / procedures as laid
out in Annexure 8.3: Guidelines for New Quarry Management. For all existing quarries from where the
concessionaire may source his supply of aggregates, Annexure 8.4: Guidelines for Existing Quarry
Management shall be followed.
Similarly natural sand quarries have also been identified for the project road. It has been found that the bed
of the rivers flowing in the vicinity of the project road contains good quality coarse sand in sufficient
quantities Table 8-3 & 4 shows details of quarry areas identified and recommended for the project. It needs
however, to be noted that recommendation on use of quarries is a guideline only and has been done to only
establish the feasibility of construction.
Table 8-3: Details of Stone aggregates Quarries
Sl. No Quarry Type Village Chainage RHS / LHS Distance to Quarry (Km) Approx Quantity (m3)
1 Quarry Gubbahalli 323+650 RHS 5.3 50000
2 Quarry Asangapura 384+400 LHS 4.5 1000000
Quarry with
3 Sasalapura 405+950 LHS 4.6 300000
crusher
4 Quarry Sasalapura 406+450 LHS 6.5 100000
Quarry with
5 Kanakapura 423+200 LHS 4.9 400000
crusher
Quarry with
6 Kanakapura 423+200 LHS 7.4 1000000
crusher
Sl.
Item Impact Impact (Reason) Mitigation / Enhancement
No.
Production facilities for the labour Rejected material will be laid as directed by IC.
and officers. Septic tank will be construction for waste
Routine and periodical maintenance disposal.
Effectiveness / shortfall (if any) Measures will be revised and improved to
Water quality
7. mitigate / enhance environment due to any
monitoring Any unforeseen impact
unforeseen impact.
themselves.
To ensure efficient flow of surface water and to prevent water logging along the side of the roads,
adequate size and number of cross-drainage structures have been provided
Detailed drainage surveys and hydrological investigations have been carried out and suitable design of
bridges and culverts proposed
Provision of lined drains at settlement areas and unlined drains at other areas
In addition to the above design requirements, the Contractor and the Concessionaire shall ensure that
during construction work the following are taken care of:
Construction work near water channels, irrigation canals and rivers have to be carried out in such a
way that flow of water is not blocked and even if it has to be blocked then the contractor and the
concessionaire must ensure that the local communities are informed about the same in advance. Work
near the water bodies should be carried out in dry season to avoid shortage of water,
Flooding of local drainage channels,
Measures to ensure that remnants from earthwork, stonework and other waste material do not hinder
the cross-drainage of rivers, nallahs,
In sections of the road near to watercourses or cross-drainage channels, the construction material
waste would be disposed off in a manner not to block the flow of water.
To maintain efficient storm water flow, the roadside drains will be cleaned regularly, especially before
the monsoon season.
Protection from Run off
Road run-off is let off into natural drains of adequate capacity from ditches at the end of formation to
prevent destabilisation of the embankment. Release of road run-off directly from the ditches can erode
edges of the water body into which the run-off is let off. Scouring of banks of flowing water bodies due to
high velocity run-off is also a potential danger. To ensure that run-off does not damage the water body it
enters, cascading for scour protection through stepped gabion is recommended.
Protecting Water Quality
To prevent any degradation of water quality of the various surface and ground water resources due to the
proposed project, the contractor and the concessionaire shall work out the following mitigative measures
during the construction period:
Provision of necessary mitigation measures at the various locations proposed in the design to prevent
contamination and degradation of water quality.
Construction work close to the streams or water bodies must be avoided during monsoon.
The discharge standards promulgated under the Environmental Protection Act, 1986 will be strictly
adhered to.
Impact on the river / nallah system can be minimised if the bridge construction is taken up during the
lean flow season and construction work close to the water bodies avoided during monsoon.
The fuel storage and vehicle cleaning area shall be stationed at least 500m away from the nearest
drain / water body
The slope of the embankments leading to water bodies shall be modified and re-channelled to prevent
entry of contaminants into the water body.
Provision of silt fencing and oil interceptors the details of which are given below
Silt Fencing
Silt fencing will be provided to prevent sediments from the construction site entering into the nearby
watercourses. The silt fencing consists of geo textile with extremely small size supported by a wire mesh
mounted on a panel made up of angle / wooden frame and post. It is expected a single person will be able
to drive the angles by pressing from the top. The frame will be installed at the edge of the water body along
which construction is in progress. The number of such units to be installed can be decided depending upon
the length of the water body along the side of the road construction.
To reduce noise and vibrations, noise barriers in the form of compound wall is proposed. In case of space
crunch, the use of concrete screens is also suggested. However the concessionaire shall identify such
areas where concrete screens shall be used. The noise barrier wall shall be constructed by excavation of
foundation, laying of brick masonry wall up to a height of 2m above ground, plastering and coping as per
the direction of the engineer and as laid in the specification. Creepers and paints shall be used in
consultation with the affected community to give an aesthetic look. Shade and flowering trees shall be
planted within the boundary of the sensitive receptor, between the building line and the compound wall,
wherever space shall be available, 5m centre to centre. Figure 8.4 shows the combination of compound
wall and trees which shall be used as noise barrier.
Table 8-10: Noise Impact on Sensitive Receptors and Mitigation
The measures adopted for noise attenuation for receptors (schools and hospitals for all type of land use)
identified above are as below:
Plantation within the premises if space available for plantation
Rising of existing boundary wall / construction of new wall up to 2m height
Planting creepers to provide aesthetic view
In urban areas the boundary wall can be painted with posters to provide aesthetic views. The option of
posters or creepers shall be agreed by the school / hospital administrator.
Noise Pollution Monitoring – Mitigation
The effectiveness of mitigation measures and further improvement in designs to reduce the noise level due
to construction and operational activity shall be monitored. The frequency, duration and monitoring plan
shall be functional in construction as well as in operation stages as per the Environmental Monitoring Plan.
Noise shall be monitored at all locations identified in Table 4-7 beside the plant sites. The country standards
are given in National Ambient Noise Standards in Annexure 10.1. Any value / result not within acceptable
limits shall be reported to engineer, for remedial measures.
8.2.6 Biological Environment
Flora
The major adverse impacts on flora shall involve the removal of trees, shrub and ground cover from within
the Corridor of Impact. As part of the project preparation, to minimise the loss of trees, clearance of only
those trees identified from the design will be removed.
Table 8-11: Summary of Mitigations for Impacts on Biological Environment
Sl.
Item Impact Reason Mitigation / Enhancement
No.
Minimum diversion of forest land
Direct
1. Forest area Acquisition of forest land Bearing the cost for NPV
Impact
Bearing the cost for Compensatory Afforestation
Direct No Presence of Wild Life Sanctuary or
2. Wild Life Nil
Impact National Park within 10 Km radius
Increase in soil erosion, silting of water Compulsory tree plantation in the ratio of 1:2.
3. Trees Cutting
No bodies. Option of compensatory afforestation through
Impact Dust and noise pollution Forest Department.
Loss of shade and loss of tree products Avenue plantation along corridor, where ever
Sl.
Item Impact Reason Mitigation / Enhancement
No.
possible.
Identification of incidental spaces (ox bow areas)
for group plantation.
Transplantation of trees also explored.
Clearing and grubbing will be minimised, and
sprinkled with water to reduce dust pollution.
Direct Increase in soil erosion, silting of water
4. Vegetation Exposed surface like embankment slopes will be
Impact bodies, noise pollution, dust pollution
protected with stone pitching and turfing.
Open land in and around plant will be vegetated.
Cattle No
5. No cattle grazing found Nil
Grazing impact
enhancement purposes.
Cost flowering, shade, medicinal, ornamental & fruit bearing trees in suitable area including plantation
and maintenance for the entire duration of the contract period has been budgeted. This number of
trees are excluding the trees to be planted for compensatory plantation
Pure avenue plantation with single species like Terminalia arjuna (arjuna), Magnifera indica (mango),
Azadirachta indica (neem) only to be planted for a few kilometres (or, the stretch between two market
places for example) to provide harmonious and pleasing look, and a regular and wavelike skyline. This
row of trees forms the first and innermost line.
Selection of tree species in outer rows (where multiple rows can be accommodated) has been
considered from economic point of view. Therefore, trees that provide fuel and fruit as well as small
timber for agricultural implements have been suggested.
ROW The plantation of trees shall be done subject to availability of space in the proposed ROW. A
total of 35.09 ha of incidental areas have been identified (ROW along the existing road which shall be
in disuse due to bypasses and realignments) given in table below. An approximate 35090 trees can be
planted in the incidental areas identified
Table 8-12: Incidental Areas Identified for Plantation
Protection of Species
Activities during the construction period are likely to have adverse impact on the plant species located along
the carriageway.
Landscaping Strategy
Plantation along medians shall screen headlights glare from approaching vehicles and prevent
distraction to the driver. Species like Bauhinia purpurea, Thespesia populnea, Jackaranda
mimosaefolia, Thevetia nerifolia etc. are recommended prevent glare from the headlights.
Proper landscaping of the traffic islands and the surrounding areas shall integrate these features with
the surrounding landscape. Junctions of relatively low importance shall be planted with flowering
shrubs in the first row of planting in the curves and shade trees in the next rows. If the traffic islands
are spacious enough small shrubs or ground cover shall be planted on them.
The floral species that shall be used for landscaping along river and canals are Ficus bengalensis,
Dalbergia sissoo, Eucalyptus sp., Azadirachta indica, Acacia nilotica indica, A. auriculaeformis etc. The
landscape treatment shall involve stepped access to the waterfront, seating beneath tree groves facing
the river side and stone pitching, gabion structures on road and other embankments.
Due to the realignment of the project road within the ROW to improve the geometries, many small
incidental or irregular spaces have been formed. These micro spaces have potential to add to the
visual quality of the road landscape and have been considered form the point of enhancement.
The locations for landscaping shall be identified by the concessionaire.
The Figures 8.5 & 8.6 shows thematic landscape sketches
of the moving traffic from the bus stop and comfort conditions within the bus stop. In places where bus
stops already exist, changes should be incorporated to increase the utility of these structures:
Bus shelters are proposed near to residences to minimise walking distance.
It should be positioned in straight and level sections of road and should be visible from a long
distance in both directions.
Bus bays are proposed as per the recommendations of IRC: 80-1981.
Bus bays with bus shelters are being provided at a total of XX locations. These locations are given in
Annexure 2.1.
New bus stops would be provided with shade, benches and railings.
Interpretative signage would be displayed in Hindi and English that could deliver information about
the bus numbers, origin & destination and routes of buses.
Rest areas
Roadside rest areas are intended for rest and relaxation intended for long distance travellers, and may
occasionally provide facilities for overnight stay also:
Parking facility shall be provided. Vehicle parking lay-by shall be provided at the frontage of these
locations.
Based on the location and availability of space landscaping shall comprise of walkways and soft
landscaped areas and outdoor seating spaces. Shade and fruit trees as well as flowering shrubs are
proposed in the rest areas.
The project proposes to provide the minimum required public conveniences such as toilets and
drinking water facilities at each of the rest areas.
Restaurant with outdoor and indoor seating spaces, Fast food joints, General stores, Chemists /
medicine shops, STD / PCO and Vehicle repairing shops shall be proposed
The locations of rest areas shall be advertised through signboards and overhead signs in advance.
Truck lay byes
The lay-byes have been proposed where congestion of heavy commercial vehicles was observed. An
additional pavement on both sides (but alternating with each other) shall be developed so that the flow of
traffic in carriageway is not obstructed. The locations of the proposed truck lay byes are given in table 2-17.
Landscaping shall comprise primarily of shade trees. Ornamental trees, shade trees and shrubs shall
be planted in order to develop the area aesthetically. Trees shall be planted to define the length of the
lay-by on its outer side as also depending on availability of space
The minimum required public conveniences such as toilets, bathing spaces and drinking water facility
shall be proposed at these locations.
Chemists / medicine shops, STD / PCO and Vehicle repairing shops shall be proposed
The locations of rest areas shall be advertised through signboards and overhead signs in advance.
Community / Cultural Resources
The project proposes the relocation I replacement of all community resources likely to be impacted. Apart
from replacing these community resources along the highway generic enhancement measures have been
worked out for the enhancement of these resources.
Table 8-16: Mitigation for Cultural & Community Properties
Distance Structure
Sl. No. from C/L Settlement Side Mitigation
Name
(Existing)
1 25 Church Vasagapura RHS relocation I replacement
2 8 Mosque Yelandur RHS relocation I replacement
3 8 Temple Yelandur LHS relocation I replacement
4 15 Temple Mampalli RHS relocation I replacement
5 25 Temple Pandithalli RHS relocation I replacement
6 20 Temple Malavalli RHS relocation I replacement
7 15 Temple Malavalli LHS relocation I replacement
8 10 Mosque Halagur RHS relocation I replacement
9 9 Mosque Halagur RHS relocation I replacement
10 10 Temple Shivanahalli LHS relocation I replacement
Distance Structure
Sl. No. from C/L Settlement Side Mitigation
Name
(Existing)
11 15 Temple Kanakapura LHS relocation I replacement
12 20 Mazaar Malavalli LHS relocation I replacement
13 5 Temple Mampalli RHS relocation I replacement
14 15 Temple RHS relocation I replacement
15 8 Temple (small) RHS relocation I replacement
16 8 Temple (small) Jakkegowdanadoddi RHS relocation I replacement
17 8 Temple (small) K. Doddi LHS relocation I replacement
18 7 Temple (small) Shivanahalli LHS relocation I replacement
19 5 Temple Kanakapura RHS relocation I replacement
20 15 Temple Kanakapura RHS relocation I replacement
21 12 Temple (Small) Jakkasandra LHS relocation I replacement
22 7 Temple (small) Harohalli RHS relocation I replacement
23 10 Mosque Kaglipura RHS relocation I replacement
24 15 Temple Kaglipura RHS relocation I replacement
25 12 Temple Kollegal RHS relocation I replacement
26 12 Mazaar Kollegal LHS relocation I replacement
kept in good working order, will be regularly inspected and properly maintained as per IS provision and to
the satisfaction of the Engineer.
Risk at Hazardous Activity
All workers employed on mixing asphaltic material, cement, lime mortars, concrete etc, will be provided with
protective footwear and protective goggles. Workers, who are engaged in welding works, would be provided
with welder’s protective eye-shields. Stonebreakers will be provided with protective goggles and clothing
and will be seated at sufficiently safe intervals. The use of any toxic chemical, if any will be strictly in
accordance with the manufacturer’s instructions. The Engineer will be given at least 6 working day’s notice
of the proposed use of any toxic chemical. A register of all toxic chemicals delivered to the site will be kept
and maintained up to date by the Contractor and the concessionaire. The register will include the trade
name, physical properties and characteristics, chemical ingredients, health and safety hazard information,
handling and storage procedures, and emergency and first and procedures for the product.
Risk of Lead Pollution
No man below the age of 18 years and mo woman will be employed on the work of painting with products
containing lead in any form. No paint containing lead or lead products will be used except in the form of
paste or readymade paint. Face masks will be supplied for use by the workers when paint is applied in the
form of spray or a surface having lead paint dry rubbed and scrapped.
Risk caused by Force’ Majure
All reasonable precaution will be taken to prevent danger of the workers and the public from fire, flood,
frowning, etc. All necessary steps will be taken for prompt first aid treatment of all injuries likely to be
sustained during the course of work.
Risk from Explosives
The contractor and the concessionaire will not use explosives except as may be provided in the contract or
ordered or authorized by the Engineer. Where the use of explosives is so provided or ordered or authorized,
the Contractor and the concessionaire will comply with the requirements of the following sub-clauses of this
clause besides the law of the land as applicable. The Contractor and the concessionaire will at all times
take every possible precaution and will comply with appropriate laws and regulations relating to the
importation, handling, transportation, storage and use of explosives and will, at all times when engaged in
blasting operations, post sufficient warning flagmen, to the full satisfaction of the Engineer. The Contractor
and the concessionaire will at all times make full liaison with and inform well in advance and obtain such
permission as is required from all government authorities, public bodies and private parties whatsoever
concerned or affected or likely to be concerned or affected by blasting operations.
Malarial Risk
The Contractor and the concessionaire will, at his own expense, conform to all anti-malarial instructions
given to him by the Engineer; including filling up any borrow pits which may have been dug by him. Gravid,
blood-laden mosquitoes cannot fly very far, so they generally bite within a kilometre or so of their breeding
place. Thus borrow pits and any other water bodies created during the construction process will be situated
1 to 2km away from the human settlements. Pits dug up closer than these will be adequately drained to
prevent water logging. Similarly compensatory measures for filling up part of the water bodies situated
adjacent to the project corridors will be directed towards deepening of the water bodies concerned. This
way the capacity of the water body remains the same, while water surface available for breeding of
mosquitoes is reduced. This will have an additional advantage of decreased evaporation losses, which will
be important in the water-scarce project corridor.
First Aid
At every workplace, a readily available first and unit including an adequate supply of sterilised dressing
material and appliances will be provided as per the Factory Rules. Workplaces remote and far away from
regular hospitals will have indoor heath units with one bed for every 250 workers. Suitable transport will be
provided to facilitate take injured or ill person(s) to the nearest applicable hospital. At every workplace an
ambulance room containing the prescribed equipment and nursing staff will be provided as prescribed.
Potable Water
In every workplace at suitable and easily accessible places a sufficient supply of cold potable water (as per
IS) will be provided and maintained. If the drinking water is obtained from an intermittent public water supply
then, storage tanks will be provided. All water supply storage will be at a distance of not less than 15m from
any latrine, drain or other source of pollution. Where water has to be drawn from an existing well, which is
within such proximity of any latrine, drain or any other source of pollution, the well will be properly
chlorinated before water is drawn from it for drinking water. All such wells will be entirely closed in and be
provided with a trap door, which will be dust proof and waterproof. A reliable pump will be fitted to each
covered well. The trap door will be kept locked and opened only for cleaning or inspection, which will be
done at least once a month.
Hygiene
The Contractor and the concessionaire during the progress of work will provide, erect and maintain
necessary (temporary) living accommodation and ancillary facilities for labour to standards and scales
approved by the resident engineer. Refer Annexure 8.9: Guidelines For Sitting And Layout Of Construction
Camp.
There will be provided within the precincts of every workplace, latrines and urinals in an accessible place,
and the accommodation, separately for each for these, as per standards set by the Building and other
Construction Workers (regulation of Employment and Conditions of service) Act, 1996. Except in
workplaces provided with water-flushed latrines connected with a water borne sewage system, all latrines
will be provided with dry-earth system (receptacles) which will be cleaned at least four times daily and at
least twice during working hours and kept in a strict sanitary condition. Receptacles will be tarred inside and
outside at least once a year. If women are employed, separate latrines and urinals, screened from those for
men and marked Woman in vernacular will be provided. There will be adequate supply of water, close to
latrines and urinals.
All temporary accommodation must be constructed and maintained in such a fashion that uncontaminated
water is available for drinking, cooking and washing. The sewage system for the camp must be properly
designed, built and operated so that no health hazard occurs and no pollution to the air, ground or adjacent
watercourses take place. Compliance with the relevant legislation must be strictly adhered to. Garbage bins
must be provided in the camp and regularly emptied and the garbage disposed off in a hygienic manner.
Construction camps are to be sited away from vulnerable people and adequate health care is to be
provided for the work force. Unless otherwise arranged for by the local sanitary authority, arrangement for
proper disposal of excreta by incineration at the workplace will be made by means of a suitable incinerator
approved by the local medical health or municipal authorities. Alternatively, excreta may be disposed off by
putting a layer of night soils at the bottom of a permanent tank prepared for the purpose and covering it with
15 cm layer of waste or refuse and then covering it with a layer of earth for a fortnight (by then it will turn
into manure). On completion of the works, the whole of such temporary structures will be cleared away, all
rubbish burnt, excreta or other disposal pits or trenches filled in and effectively scaled off and the whole of
the site left clean and tidy, at the contractor and the concessionaire’s expense, to the entire satisfaction of
the Engineer.
8.3 ENHANCEMENT
8.3.1 Generic Enhancement Measures for Cultural Properties
The project strives to improve the experience of highway travelling by strengthening the physical link
between the corridor and the cultural properties falling along the road. Depending upon site-specific
situations the project strives to improve the access to these properties by providing walkway to the property
from the highway. Locally available materials like stone and bricks have been preferred for paving. CC
flooring also shall be adopted for ground treatment. At places plantation shall be used in addition to hard
landscaping measures to define precinct boundaries.
8.3.1.1 Plantation
Trees not only enrich the visual quality of a space but also act as functional buffer screens to counter
pollution, define areas and provide shade. Plantation of trees has been a prime enhancement as well as
mitigation measure in the project. Tree bases have been proposed around existing as well as proposed
shade trees to form informal seating spaces, which are evidently preferred to the formal seating spaces. At
cultural and religious properties locations, trees with religious significance like Ficus religiosa (Pipal)
Emblica officinalis (Amia), F. bengalensis (Banyan), Azadirachta indica (Neem), Magnifera indica (mango),
and Anthocephalus cadamba (Kadam) shall be planted. Seating arrangement as given below shall be
adopted depending upon site conditions.
8.3.1.2 Seating Spaces
Creating formal and / or informal seating spaces and rest areas where feasible and as per the scale of the
property in question were tried. In the case of availability of space, cultural properties if coupled with rest
areas will prove to be beneficial not only to the highway travellers but also the users of the religious
structure.
8.3.2 Specific Enhancement
As part of good environmental practices, enhancement measures for water bodies and community
properties shall be drawn after consultations with the community. The cost of the enhancement measures
has been included in the EMP budget.
9. IMPLEMENTATION ARRANGEMENT
9.1 INTRODUCTION
This chapter provides an assessment of the existing institutional arrangement within NHAI and, reflects on
capacity building / training issues that need to be addressed to ensure timely implementation of EMP. The
institutional arrangement proposed for this project has been presented here with newly defined roles and
responsibilities. The responsibility of implementing the mitigation measures lies with the NHAI. All
construction activities being taken up by the Concessionaire selected through International Competitive
Bidding. The Independent Engineer shall monitor the implementation of the work on behalf of NHAI. The
Concessionaire will be responsible for planning all Environmental Management Plan (EMP) activities. In the
pre-construction phase of the project the concessionaire shall study the EMP to identify environmental
issues and arrive at a suitable strategy for implementation.
Review and recommend the Contractors’ and Concessionaire’s Implementation Plans for approval
(with any changes that may be necessary) to ensure compliance with the environmental provisions of
the Contract
Monitor tree plantation programs and the periodic Environmental Monitoring (Air, Noise, Water, etc.)
Programs to ensure compliance with the State requirements and the EMP.
Hold regular meetings with NHAI and keep it updated on the progress of site works
Prepare and submit Environmental progress report to NHAI
Develop and organise environmental training programmes to upgrade the skills within the staff of the
environmental cell, contractors and the concessionaire
Document and develop good practices during project implementation for wider dissemination
The project will require continuous environmental supervision from the IC’s side. Since the Environmental
Specialist for IE projects are deployed on intermittent basis, it is desirable to have the field engineers
supervising the construction be trained on environmental aspects, who then shall apprise the Team Leader
and the Environmental Specialist of any significant development on environment.
9.3.2 Concessionaire
For effective implementation and management of the EMP, the Concessionaire shall contrive to establish a
Safety, Health and Environment (SHE) Cell headed by an Environment Officer to deal with the
environmental issues of the project. This officer shall interact with the contractor, NHAI, IC and other line
departments to ensure that the mitigation and enhancement measures mentioned in the EMP are adhered.
The Environmental officer of the Concessionaire shall be the interface between the Environmental
Specialist of IC and the Environmental Officer of the contractor. His prime responsibility shall be to apprise
the Environmental Specialist of the IC about the ground conditions. He shall also procure the requisite
clearances and the NOCs for the project and shall also strictly supervise that the contractor adheres to the
EMP. The environmental officer can also look after the additional charges of safety and health. The Draft
Qualification and responsibilities are given in box below:
Box 9-1: Draft Qualification and Responsibilities of Environmental Officer of Concessionaire
Qualifications & Experience
Postgraduate in Environmental Science / Environmental Management / Zoology / Botany / Ecology /
Environmental Planning / degree in Civil Engineering with specialisation in environment.
10 years of total experience with a minimum of 5 years in the implementation of EMP of highway
projects and an understanding of environmental, health and safety issues.
Prior practical experience in State and National Highways would be an advantage.
Roles & Responsibilities
He / She shall be reporting directly to the Chief Project Manager of the Concessionaire.
Primarily responsible for implementation of the EMP on site and ensuing that the environmental
quality is meeting the standards laid down by Central Pollution Control Board and other related
authority.
The EO shall implement the EMP by assigning the necessary resources (manpower, money and
machinery) and attend such meetings as are required for the effective implementation of the EMP
on site.
He shall maintain a “Complain Register” to record any grievances from members of public.
He shall maintain a register of all road side trees planted and present within ROW.
The EO shall be the interface of the concessionaire with the client and the IE.
9.3.3 Contractor
Execution of works will be the responsibility of the contractor. The concessionaire may himself be the
executioner of the project or might decide to outsource or hire contractor for highways and structures, who
may in turn sublet some part of their work to petty contractors. In case the concessionaire decides to
execute the work by himself then the responsibilities of the EO as given in Box 9.1 shall also be performed
by the EO of the concessionaire. If the concessionaire decides to outsource the work then the contractors
shall employ an Environmental Officer whose qualification and responsibilities shall be as per Box 9.2. The
contractor shall be responsible for both the jobs done by the petty contactor (if Sublet) as well by him. In
both the cases the concessionaire will implement the environmental measures (either through the
contractors or themselves). This has been done with a view to ensure that road construction and
Client: National Highways Authority of India Draft EIA Report
91
Consultant: Feedback Infra Pvt. Ltd July2013
UNCONTROLLED IF PRINTED
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of
Chamarajanagar to Harohalli section of NH – 209 in the state of Karnataka
addition, close interaction is required among members of the NHAI responsible for the Environmental and
R&R activities since it is envisaged that the two aspects will have a considerable overlap. It is envisaged
that the training as part of the project will include training on several issues important for both teams
simultaneously. The following modules can be taken up:
Table 9-2: Modules for Training
Sl
Timing Target Group Mode of training Short Description Responsibility
No.
Overview of responsibilities
Members of the NHAI site The roles and responsibilities of
office, Environmental the IE, Concessionaire and the
After finalisation Lectures, External
Specialist of the IE, Contractor
1 of Contracts for Presentations, Agency or
Concessionaire and the Reporting arrangements
Civil Works Discussions NHAI
Environmental staff of the Contractual obligations,
Civil Contractor Environmental Protection and
Social Development
Inter-Departmental Co-ordination
Clearance requirements and
Members of the NHAI site Lectures, prescribed procedures External
2.
During office, Counterpart staff from Discussions, Expectations of other Agency,
implementation other departments such as Presentations, departments – documentation Consultants,
Revenue, Forests, etc. Role Play and follow-up NHAI
Developing formats for ease of
reporting
NHAI
PD / CGM (Env) Chief Project Manager
(Concessionaire)
State Pollution
Control Board /
MoEF
Construction /
Project Manager
Team Leader
(Contractor)
(Independent Engineer)
Environmental Expert
(Independent Engineer)
Environmental
Officer
(Contractor)
Direct Indirect
3
Some of the mitigation measures are preventive in nature while some others include additional measures in terms of environmental conservation and involve
physical and construction work.
4
Unless otherwise stated, the Project Site covers area beyond ROW, such as borrow areas, access roads, service roads and equipment storage sites
(MoRT&H: 306.3).
5
Time frame refers to the duration or instant of time when the mitigation measures will be taken.
6
The contract requirements refer to the following:
Ministry of Shipping, Road Transport & Highways, (MoRT&H) Government of India, Specifications for Road and Bridge Works, Specific and general
conditions of the contract.
Client: National Highways Authority of India Draft EIA Report
98
Consultant: Feedback Infra Pvt. Ltd July 2013
UNCONTROLLED IF PRINTED
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of Chamarajanagar to Harohalli section of NH – 209 in the state of Karnataka
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Relocation of Utilities All community underground and overhead utilities will be Post design to R&R Officer, IE, NHAI Resettlement Action
shifted as per Utility Shifting Plan, prior permission will be Pre-construction Concessionaire / Plan (RAP), Utility
required from regional offices of Electricity, Contractor Relocation Plan
Telecommunications, OFC, Water works etc.
Loss of drinking water Private drinking water source replaced according to RAP Post design to Concessionaire / IE, NHAI Resettlement Action
source and public water sources replaced. Pre-construction Contractor Plan (RAP)
Temporary arrangements shall be provided, if the
existing water supply is disrupted accidentally.
Cultural Properties Cultural properties affected to be relocated as per RAP Table 8.16 Pre-construction Concessionaire / IE Resettlement Action
and Public Consultation. Contractor Plan (RAP), Table
Mitigation / enhancement measures have been 8.16, MoRT&H:
suggested for each of the cultural property individually. 301.5
Loss of existing bus stops Bus stops suitably relocated or integrated to the design. During design Design
and waiting shed facilities Bus lay byes and bus waiting shed designs are provided. stage. Consultants
Procurement of Crushers, Specifications of crushers, hot mix plants and batching Prior to Concessionaire / IE, NHAI Contract, MoRT&H:
Hot-mix plants & Batching plants, other Construction Vehicles, Equipment and mobilisation at Contractor 111, GoI Air & noise
Plants, other Construction Machinery to be procured will comply to the relevant site Standards,
Vehicles, Equipment and Bureau of Indian Standard (BIS) norms and with the Environment
Machinery requirements of the relevant current emission control Protection Act, 1986
legislations and OSHA Standards
Setting up of construction The construction camps will be located at least 500m All areas in During Concessionaire / IE, NHAI MoRT&H: 111.1,
camps away from habitations & 1 km away from sensitive immediate Establishm Contractor 111.14
locations (Refer Annexure 8.9) vicinity of ent, Annexure 8.9
The Concessionaire / Contractor during the progress of construction Operation
work will provide, erect and maintain necessary campsite chosen and
(temporary) living accommodation and ancillary facilities by the Dismantling
for labour to standards and scales approved by the IE. Concessionaire / of Such
Contractor and Camps.
approved by the
Independent
Engineer (IE).
Setting up of Hot mix Plants Hot mix plants, crushers and batching plants shall be All Hot mix During Concessionaire / IE, NHAI MoRT&H: 111.5
and crushers located at least 1000m away from the nearest habitation. Plants Batching erection, Contractor
The Concessionaire / Contractor shall obtain the consent Plants testing,
to operate the plants from the SPCB and submit a copy operation
to the Independent Engineer (IE). and
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
dismantling
of such
plants
Identification of dumping Location of dumping sites shall be finalized based on the Throughout the During Concessionaire / IE, NHAI Annexure 8.1
sites guidelines given in Annexure 8.1 and the Independent corridor mobilisatio Contractor
Engineer (IE) shall certify that : n
These are not located within designated forest areas.
The dumping does not impact natural drainage
courses
Settlements are located at least 1 km away from the
site.
CONSTRUCTION STAGE
Clearances and approvals Secure the following clearances prior to start of Construction NHAI, SPCB, CPCB, Concessiona General Conditions of
construction activity: stage (Prior to Chief Controller of ire / Contract.
Type of clearance Applicability initiation of any Explosives, District Contractor Clause 111.3,
NOC and consents under For establishment of work). Collector State MoRT&H
Air, Water & Environment construction camp. Time period in Department of Mines,
Act and noise rules from getting the State Ground Water
SPCB permission is 2-3 Board, State Irrigation
months. Department, Labour
NOC and consents under For operating
Commissioner Officer
Air, Water & Environment construction plant,
Act and noise rules from crusher, batching
SPCB plant etc.
Explosive License from For storing fuel oil,
Chief Controller of lubricants, diesel etc.
Explosives
Permission for storage of Manufacture storage
hazardous chemical from and Import of
CPCB Hazardous Chemicals
Borrow Area, approval from Borrow area for
District Collector, Consent excavation of earth
letter, lease agreement with
the Owner of land.
Quarry Lease Deed and Quarry operation (for
Quarry License from State new quarry)
Department of Mines
Permission for extraction of Extraction of ground
ground water for use in road water
construction activities from
State Ground Water Board
Permission for use of water Use of surface water
for construction purpose for construction
from irrigation department
Labour license from labour Engagement of
commissioner office Labour
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Provide a copy of all necessary clearances to the IC
Adhere to all clearance terms and conditions
Obtain written permission from private landholders to
conduct construction activities on their land prior to
commencing works.
Land
Soil Erosion and Main reason of soil erosion is rains. Concessionaire / Throughout Upon completion Concessionaire / IE, NHAI MORT&H
Sedimentation control Contractor should plan the activities so that No naked / Project Corridor, of construction Contractor Specification
loose earth surface is left out before the onset of Service roads and activities at these 305.2.2.2, 306, 307,
monsoon, for minimising the soil erosion following equipment sites. 308
preventive measures to be taken such as: storage sites, etc.
Embankment slopes to be covered, soon after During
completion. construction
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
reused as follows:
Covering all borrow areas after excavation is over.
Dressing of slopes of road embankment
Agricultural field, acquired temporarily
Compaction of Soil and Construction vehicles should operate within the Corridor Throughout During Concessionaire / IE, NHAI MORT&H
Damage to Vegetation of Impact avoiding damage to soil and vegetation. Project Corridor construction Contractor Specification 112.6,
Diversions, access road used will be redeveloped by and all areas 201.2
Concessionaire / Contractor, to the satisfaction of the temporarily
owner / villagers. acquired.
Construction vehicle, machinery and equipment shall
move or be stationed in the ROW only. While operating
on temporarily acquired agricultural land for any
construction activities, top soil will be preserved in
stockpiles.
Contamination of soil Guidelines of “Hazardous waste (management and At fuel storage During Concessionaire / IE, NHAI Chapter-8 of this
handling) rules, 1989 will be enforced. areas – usually Constructio Contractor Report.
at construction n.
Vehicle / machinery and equipment operation, camps,
maintenance and refuelling shall be carried out in temporarily
such a fashion that spillage of fuels and lubricants acquired site.
does not contaminate the ground. An “oil interceptor”
will be provided for wash down and refuelling areas.
Fuel storage shall be in proper bunded areas. All
spills and collected petroleum products shall be
disposed off in accordance with MoEF and SPCB
guidelines at designated locations.
Plant to be set up 500 m away from surface water
body.
Oil interceptor will be installed at construction site.
Septic tank will be constructed for safe disposal of
waste.
1. Quarrying Quarry material shall be sourced from approved and Table 8.3 & 8.4 During Concessionaire / IE, NHAI Annexure 8.3
licensed aggregate and sand quarries as given in construction Contractor MORT&H
Table 8.3 & 8.4. Copy of licenses to be submitted to Specification 111.3,
2. Material sources the IE. 302, 305.2.2.
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
shall be covered to prevent spillage. Operations to be
undertaken by the Concessionaire / Contractor as per
the direction and satisfaction of the IE.
Generation of Debris Debris generated due to the dismantling of the existing Throughout During Concessionaire / IE, NHAI MoRT&H: 112.6 &
pavement structure and the cutting of the hillside for the
widening shall be suitably reused in the proposed Project Construction Contractor 112.2
construction as fill materials for embankments Corridor.
Disposal of Debris The disposal of debris shall be carried out only at sites Sites identified During Concessionaire / IE, NHAI Annexure 8.1
identified for the purpose. The Concessionaire /
Contractor shall carry out the disposal as described in by the Construction Contractor, IC / SC
Annexure 8.1. Concessionaire
All arrangement for transportation during construction / Contractor
including provision, maintenance, dismantling and
and approved
clearing debris, where necessary will be considered
incidental to the work and should be planned and by the
implemented by the Concessionaire / Contractor as Independent
approved and directed by IE. Engineer (IE).
Air
Dust Generation Vehicles delivering materials should be covered to Throughout Beginning with Concessionaire / IE, NHAI MORT&H
Specification 111.1,
reduce spills and dust blowing off the load. Project & throughout Contractor 111.5, 111.8, 111.9,
Clearing and grubbing to be done, just before the start Corridor, all construction 111.10 & 118.1
of next activity on that site. access roads, until
In laying sub-base, water spraying is needed to aid temporarily asphalting is
compaction of the material. After the compaction,
water spraying should be carried out at regular acquired sites. completed and
intervals to limit the dust to below side slopes are
Road surface should be cleaned with air compressor covered.
and vacuum cleaners prior to the construction works.
Manual labour using brooms should be avoided, if
used labour to be provided masks.
Embankment slopes to be covered with turfing / stone
pitching immediately after completion.
The Concessionaire / Contractor shall take every
precaution to reduce the level of dust emission from
the hot mix plants and the batching plants up to the
satisfaction of the IE
All existing highways and roads used by vehicles of
the Concessionaire / Contractor, or any of his sub-
Contractor or suppliers of materials or plant and
similarly roads which are part of the works shall be
kept clean and clear of all dust/mud or other
extraneous materials dropped by such vehicles or
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
their tyres.
Plants, machinery and equipment shall be so handled
(including dismantling) as to minimise generation of
dust.
Equipment Selection, The discharge standards promulgated under the Throughout During Concessionaire / IE, NHAI MORT&H Spec 106,
Maintenance and Operation Environment Protection Act, 1986 shall be strictly Project Corridor, Construction. Contractor IRC: 72-1978, IRC:
adhered to. All vehicles, equipment and machinery all access roads, 90-1985, 111.5,
used for construction shall conform to the relevant sites temporarily 111.9, 111.10, 2013
Bureau of Indian Standard (BIS) norms. acquired and all
borrow areas.
All vehicles, equipment and machinery used for
construction shall be regularly maintained to ensure
that pollution emission levels comply with the relevant
requirements of SPCB and the Independent Engineer
(IE).
Pollution from Crusher All crushers used in construction shall conform to All Aggregate During Erection, Concessionaire / IE, NHAI
relevant dust emission control legislations. Clearance Crushing Plants. Testing, Contractor MoRT&H: 111.1
for siting shall be obtained from the SPCB. Operation and
Dismantling of
Alternatively, only crushers already licensed by the Such plants.
SPCB shall be used.
Water will be sprayed during the non-monsoon
months, regularly to minimise dust, in the whole
crusher plant area.
The suspended particulate matter contribution value
at a distance of 40m from a controlled isolated as well
as from a unit located in a cluster should be less than
500g/m3. The monitoring is to be conducted as
envisaged in the monitoring plan.
Water
Loss of water bodies/ No excavation from the bund of the water bodies. Near all water During Concessionaire / Concessionair MORT&H
surface / ground bodies construction Contractor e Specification 111.4,
No debris disposal near any water body. 201.2, 301, 304, 306
Prior written permission from authorities for use of & 305.4.1
water for construction activity will be submitted to IC.
Construction labours to be restricted from polluting
the source or misusing the source.
Shifting of source to be completed prior to disruption
of the actual source.
Alternate measures to be taken / ensured during
disrupted period.
Source to be replaced immediately, in case of
accidental loss.
Construction work shall be restricted to 3m – 4m
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
width from the existing formation near ponds.
The volume of water storage lost shall be
compensated for by excavation of an equal volume of
similar depth at closest possible location in the
direction of flow and shall be done with the approval
of the Independent Engineer (IE).
Alteration of drainage Diversions will be constructed during dry season, with Throughout
Project Corridor,
Whenever
encountered
Concessionaire /
Contractor
IE, NHAI MORT&H
Specification 201.2,
adequate drainage facility, and will be completely
removed before the onset of monsoon. all access roads, during 301, 304, 306, 312.
temporarily construction
Debris generated due to the excavation of foundation acquired sites.
or due to the dismantling of existing structure will be
removed from the water course.
Temporary Silt fencing to be provided on the mouth of
discharge into natural streams.
Continuous drain (lined / unlined) is suggested / will
be provided. Obstruction, if any, will be removed
immediately.
Runoff and drainage Throughout continuous drain is provided. During Concessionaire / IE, NHAI
Construction Contractor
Lined drain is provided at built-up locations for quick
drainage.
Increased runoff due to increased impervious surface
is countered through increased pervious surface area
through soak pits and rain water harvesting
structures.
Water requirement for Concessionaire / Contractor will provide a list of Throughout During Concessionaire / IE, NHAI
project sources (surface / ground) for approval from IE Project Corridor, Construction Contractor
all access roads,
Prior to use of source Concessionaire / Contractor will temporarily
take the written permission from authority, to use the acquired sites.
water in construction activity, and submit a copy to IE.
During construction only permitted quantity
(permission taken) from approved sources will be
used.
Concessionaire / Contractor will ensure optimum use
of water; discourage labour from wastage of water.
Silting / sedimentation Measures suggested under “Soil Erosion and Throughout Concessionaire / IE, NHAI MORT&H
Sedimentation control” will be enforced. construction Contractor Specification 111.4,
period 306
Silt fencing is provided around water bodies. EP Act, 1986
Construction activities will be stopped near water
bodies during monsoon.
Soil trap are suggested / will be provided in all
ancillary sites and camps.
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Contamination of water Measures suggested under “Contamination of soil” All areas in Throughout Concessionaire / IE, NHAI MORT&H
will be enforced. immediate construction Contractor Specification 111.1,
vicinity of period, During 111.4, 111.9, 111.13,
Construction work close to water bodies will be construction Establishment, 122, 201.2, 201.4,
avoided during monsoon. campsite chosen Operation and 301.1.3.10, 304.3.3,
Labour camps will be located away from water by the Dismantling of 306
bodies. Concessionaire / Labour Camps.
Contractor.
Car washing / workshops near water bodies will be
avoided.
Noise
Noise from Vehicles, Plants Noise standard at processing sites, eg. Aggregate Throughout Throughout Concessionaire / IE, NHAI MORT&H
and Equipment crushing plants, batching plant, hot mix plant will be Project Corridor, construction Contractor Specification No. 111,
strictly monitored to prevent exceeding of noise all access roads, 111.1, 111.13, 111.5
standards. sites temporarily & 111.6
acquired and all
Workers in vicinity of loud noise, and workers working borrow areas. Environment
with or in crushing, compaction, concrete mixing (Protection) Rules,
operations shall wear earplugs and their working time 1986.
should be limited as a safety measure.
In construction sites within 150 m of sensitive Table 8.10: Noise
receptors construction will be stopped from 22:00 to Impact on Sensitive
06:00. Receptors and
Machinery and vehicles will be maintained to keep
Mitigation.
their noise to a minimum.
Construction of noise barriers at sensitive receptors.
All vehicles and equipment used in construction shall
be fitted with exhaust silencers. During routine
servicing operations, the effectiveness of exhaust
silencers shall be checked and if found to be defective
shall be replaced.
Noise limits for construction equipment used in this
project (measured at one metre from the edge of the
equipment in free field) such as compactors, rollers,
front loaders, concrete mixers, cranes (moveable),
vibrators and saws shall not exceed 75 dB(A), as
specified in the Environment (Protection) Rules, 1986.
Noise from Blasting or Pre- Blasting shall be carried out only with permission of All Blasting and During Concessionaire / IE, NHAI MoRT&H: 302.1 &
splitting Operations the Independent Engineer (IE). All the statutory laws, Pre-splitting Preparation, Contractor 302.4
regulations, rules etc., pertaining to acquisition, Sites. Operation and
transport, storage, handling and use of explosives Closure of Such
shall be strictly followed. Sites.
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
made known to all people within 500m (200m for pre-
splitting) from the blasting site in all directions.
People, except those who actually light the fuse shall
be excluded from the area of 200m (50m for pre-
splitting) from the blasting site in all directions at least
10 minutes before the blasting.
Flora & Fauna
Loss of trees and Avenue Plant and maintain 64425 flowering, shade, medicinal, Annexure 8.7 After completion Concessionaire / IE, NHAI Annexure 8.7
Planting & transplantation ornamental & fruit bearing trees in suitable area for of construction Contractor MORT&H
the entire duration of the contract period activities Specification, 111,
111.5, 201.5, 306,
Plant and maintain a minimum 58109 ornamental, 308
medicinal & flowering plants and shrubs in the median
for the entire duration of the contract period
Transplant and maintain 6410 trees of various girth,
height and species for the entire duration of the
project period
Cost of plantation included in the EMP Budget.
Concessionaire / Contractor has to make sure that no
trees / branches to be fell by labourer for fuel, warmth
during winter. Enough provision of fuel to be ensured.
Vegetation clearance Clearing and grubbing should be avoided beyond that During cleaning Concessionaire / IE, NHAI MORT&H
which is directly required for construction activities. operations. Contractor Specification 201.2
During
Next activity to be planned / started immediately, to construction
avoid dust generation and soil erosion during
monsoon.
Turfing / re-vegetation to be started soon after
completion of embankment.
Fauna Construction workers must protect natural resources During Concessionaire / IE, NHAI MORT&H
and wild animals. construction Contractor Specification 111.1,
111.6.
Hunting will be prohibited.
Nesting grounds & migratory paths will be protected.
Socio – Economic Environment
Public Health and Safety Debris generated will be disposed to the satisfaction of During Concessionaire / IE, NHAI
Independent Engineer (IE). Construction Contractor
Monitoring of air, water, noise and land during
construction and operational phase.
Accidents The Concessionaire / Contractor will provide, erect and During Concessionaire / IE, NHAI
maintain barricades, including signs marking flats, lights Construction Contractor
and flagmen as required by the Independent Engineer
(IE).
Resettlement Action of A comprehensive resettlement action plan has been During Concessionaire / IE, NHAI
People prepared to improve the standard of living of the affected Construction Contractor, NHAI
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
population.
Sensitive community and Precaution to be taken for any accidental loss to During Concessionaire / IE, NHAI Table 8.16
cultural facilities community and cultural property Construction Contractor
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Traffic Control and Safety The Concessionaire / Contractor shall take all Entire Project During Concessionaire / IE, NHAI MoRT&H: 112.1 &
necessary measures for the safety of traffic during site. Construction Contractor 112.4
construction and provide, erect and maintain such Annexure 8.8
barricades, including signs, markings, flags, lights and
flagmen as may be required by the Independent
Engineer for the information and protection of traffic
approaching or passing through the section of the
highway under improvement.
All signs, barricades, pavement markings shall be as
per the MoRT&H specification. Before taking up
construction on any section of the highway, a traffic
control plan shall be devised to the satisfaction of the
Independent Engineer.
Risk from Operations The Concessionaire / Contractor is required to comply Entire Project During Concessionaire / IE, NHAI Factory Act
with all the precautions as required for the safety of site. Construction Contractor
the workmen as per the International Labour
Organisation (ILO) Convention No. 62 as far as those
are applicable to this contract.
The Concessionaire / Contractor shall supply all
necessary safety appliances such as safety goggles,
helmets, masks, etc., to the workers and staff.
The Concessionaire / Contractor has to comply with
all regulation regarding safe scaffolding, ladders,
working platforms, gangway, stairwells, excavations,
trenches and safe means of entry and egress.
No child labour shall be utilized in the project
Risk from Electrical Adequate precautions will be taken to prevent danger Entire Project During Concessionaire / IE, NHAI MoRT&H: 106
Equipment from electrical equipment. site. Construction Contractor
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Workers, who are engaged in welding works, would
be provided with welder’s protective eye-shields.
Stonebreakers will be provided with protective
goggles and clothing and will be seated at sufficiently
safe intervals.
MoRT&H: 111.6
The use of any toxic chemical shall be strictly in
accordance with the manufacturer’s instructions. The
Independent Engineer (IE) shall be given at least 6
working day’s notice of the proposed use of toxic
chemical. A register of all toxic chemicals delivered to
the site shall be kept and maintained up to date by the
Concessionaire / Contractor. The register shall
include the trade name, physical properties and
characteristics, chemical ingredients, health and
safety hazard information, safe handling and storage
procedures, and emergency and first aid procedures
for the product.
Risk caused by Force’ All reasonable precaution will be taken to prevent danger Entire Project During Concessionaire / IE, NHAI
Majure of the workers and the public from fire, flood, drowning,
etc. All necessary steps will be taken for prompt first aid site Construction Contractor
treatment of all injuries likely to be sustained during the
course of work.
First Aid At every workplace, a readily available first aid unit Entire Project During Concessionaire / IE, NHAI
including an adequate supply of sterilised dressing site. Construction Contractor MoRT&H: 1207.6,
material and appliances will be provided as per the Factories Act, 1948
Factory Act.
Workplaces, remote and far away from regular
hospitals will have indoor heath units with one bed for
every 250 workers. Suitable transport will be provided
to facilitate take injured or ill person(s) to the nearest
applicable hospital. At every workplace and
construction camp, equipment and nursing staff shall
be provided.
Safety Measures During All relevant provisions of the Factories Act, 1948 and All construction During Concessionaire / IE, NHAI Factories Act, 1948
Construction The Building and other Construction Workers sites construction Contractor and The Building
(regulation of Employment and Conditions of Service) and other
Act, 1996 will be adhered to. Construction
Workers
Adequate safety measures for workers during (Regulation Of
handling of materials at site will be taken up. Employment and
The register will include the trade name, physical Conditions of
properties and characteristics, chemical ingredients, Service) Act, 1996
health and safety hazard information, safe handling
and storage procedures, and emergency and first aid
procedures for the product.
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Hygiene Latrines shall be provided with septic tank. The All Worker’s During Concessionaire / IE, NHAI
effluents can be diverted for horticulture inside the Camps construction Contractor
camps.
The septic tank may be cleaned once in 6 months and
filter cleaned after a year.
All temporary accommodation must be constructed
and maintained in such a fashion that uncontaminated
water is available for drinking, cooking and washing.
Garbage bins must be provided in the camps and
regularly emptied and the garbage disposed off in a
hygienic manner.
Adequate health care is to be provided for the work
force. Unless otherwise arranged for by the local
sanitary authority, the local medical health or
municipal authorities.
On completion of the works, all such temporary
structures shall be cleared away, all rubbish burnt,
septic tank and other disposal pits filled in and
effectively sealed off and the outline site left clean and
tidy, at the Concessionaire / Contractor’s expense, to
the entire satisfaction of the Independent Engineer
(IE).
Clearing of Construction of Concessionaire / Contractor to prepare site restoration All Workers’ Concessionaire / IE, NHAI
Camps & Restoration plans for approval by the Independent Engineer (IE). The Camps Contractor
plan is to be implemented by the Concessionaire /
Contractor prior to demobilisation.
On completion of the works, all temporary structures will
be cleared away, all rubbish burnt, excreta or other
disposal pits or trenches filled in and effectively sealed
off and the site left clean and tidy, at the Concessionaire
/ Contractor’s expense, to the entire satisfaction of the
Independent Engineer (IE).
Residual topsoil will be distributed on adjoining /
proximate barren / rocky areas as identified by the
Independent Engineer (IE) in a layer of thickness of
75mm - 150mm.
Monitoring at critical The monitoring of Air, land, water and Noise to be carried Concessionaire / IE Table 4.4, 4.6 & 4.9
locations out identified critical locations as given in Table 4.4, 4.6 Contractor of chapter 4;
& 4.9 besides locations identified by IC along the project Table 11.1: EMP
corridor. Budget &
Annexure 10.1
OPERATION STAGE
Water quality degradation Silt fencing, Oil & Grease traps, etc. shall be provided at At sensitive During NHAI and / or SPCB NHAI As per Monitoring
due to road run-off sensitive water bodies to ensure that the water quality is water bodies Operational plan in Annexure
not impaired due to contaminants from road run-off. identified. Stage 10.1
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
Monitoring shall be carried out as specified in the As specified in
Monitoring plan the monitoring
plan
Contamination of Soil and Contingency plans to be in place for cleaning up of Entire Project During Concessionaire / IE, NHAI
Water Resources from spills of oil, fuel and toxic chemicals. corridor. Operational Contractor
Spills Accidents Stage
Spill of oil, fuel and automobile servicing units without
adequate disposal systems in place to be
discouraged.
Accidental spills are potentially disastrous, but its
probability is quite low as one of the objectives of this
project is to enhance road safety.
The Public will be informed about the regulations on
land pollution.
Land pollution monitoring program has been devised
for checking pollution level and suggesting remedial
measures.
Traffic and Accident Safety Depending on the level of congestion and traffic All along the During Concessionaire / NHAI / Through Operation
hazards, traffic management plans will be prepared. Project corridor Operational Contractor, Local Concessiona Stage.
and surrounding Stage Government Bodies, ire /
Traffic control measures including speed limits to be areas. Development Contractor
enforced strictly. Authorities.
Road control width to be enforced. Local government
bodies and development authorities will be
encouraged to control building development along the
highway.
Accidents involving Compliance with the Hazardous Wastes All along the During Concessionaire / NHAI, Motor
Hazardous Materials (Management and Handling) Rules, 1989 Project corridor Operational Contractor Vehicles
and surrounding Stage Department,
Creation of an Emergency Response team areas District
For delivery of hazardous substances, permit license, Administratio
driving license and guidance license will be required. n
Public security, transportation and fire fighting
departments will designate a special route for vehicles
delivering hazardous material. These vehicles will
only be harboured at designated parking lots.
In case of spill of hazardous materials, the relevant
departments will be intimated at once to deal with it
with the spill contingency plan.
Road side tree plantation Trees planted along the corridor shall be maintained All along the During Concessionaire / IE, NHAI
for a period of three years. Maintenance works corridor Operational Contractor
include, watering of the saplings, and all necessary Immediately from Stage
measures for survival of the sapling. the planting of
sapling
The avenue plantation should be completed,
Environmental Responsibility
Mitigation Measures3 Location4 Time Frame5 Cross reference6
Impact / Aspect Implementation Supervision
maintained and casualties to be replaced.
Discouraging local peoples from cutting tree /
branches for fuel, cattle food etc.
Educating people about the usefulness of trees.
Monitoring at critical The monitoring of Air, land, water and Noise to be carried Concessionaire / IE Refer chapter 4;
locations out identified critical locations as given in Table 4.4,4.6 & Contractor Table 10.1: EMP
4.9 besides locations identified by IC along the project Budget &
corridor. Annexure 10.1
Noise HORN PROHIBITED sign post will be enforced After completion
of construction
During
Operational
SPCB, State Police,
Traffic Police, State
IE IRC 35-1971
IRC 79-1981
Maintenance of noise barriers Throughout and Stage Forest Dept., Transport IRC 93-1995
Discouraging local people from establishing sensitive after project Dept., Concessionaire /
receptor near the road. development Contractor and
period Planning Authorities
The public will be informed about the regulations on
noise pollution.
The Environmental Monitoring Programme has been detailed out in Annexure 10.1 Successful
implementation of the Environmental Monitoring Program is contingent on the following:
The IC is to request the Concessionaire / Contractor to commence all the initial tests for monitoring
(i.e. for Air, Water Quality and Noise Levels) early in the Contract to establish 'base' readings (i.e. to
assess the existing conditions prior to effects from the Construction activities being felt).
The Independent Engineer is to request the Concessionaire / Contractor to submit for approval a
proposed schedule of subsequent periodic tests to be carried out.
Monitoring by the Independent Engineer’s Officer of all the environmental monitoring tests, and
subsequent analysis of results.
Where indicated by testing results, and any other relevant on-site conditions, IC to instruct the
Concessionaire / Contractor to:
Modify the testing schedule (dates, frequency)
Modify (add to or delete) testing locations
Verify testing results with additional testing as/if required
Require recalibration of equipment, etc., as necessary
Request the Concessionaire / Contractor to stop, modify or defer specific construction equipment,
processes, etc., as necessary, that are deemed to have contributed significantly to monitoring
readings in excess of permissible environmental "safe" levels.
10.4.1 Monitoring of Earthworks Activities
Most of the environmental problems related to the construction works are anticipated to be associated
with the earthworks, particularly for the Quarries and Borrow Areas. Details regarding the guidelines and
procedures adopted to minimise the environmental impacts of opening, operating and closing of Quarries
and Borrow Areas are presented in Annexure 8.3 & 8.4. Other environmental effects associated with the
earthworks include the development of adequate temporary drainage to minimise detrimental effects (e.g.
erosion) due to run-off, and safety aspects related to Works implementation.
10.4.2 Monitoring of Concessionaire / Contractor's Facilities, Plant and Equipment
All issues related to negative environmental impacts of the Concessionaire / Contractor's Facilities,
Plant and equipment are to be controlled through:
The Concessionaire / Contractor's self-imposed quality assurance plan
Regular / periodic inspection of the Concessionaire / Contractor’s plant and equipment
Monthly appraisal of the Concessionaire / Contractor.
Other environmental impacts are to be regularly identified and noted on the monthly appraisal inspection
made to review all aspects of the Concessionaire / Contractor's operation. The officer is to review all
monthly appraisal reports, and through the team leader is to instruct the Concessionaire / Contractor to
rectify all significant negative environmental impacts.
10.5 BUDGET
The environmental budget for the various environmental management measures proposed in the EMP is
detailed in Table 10-1. There are several other environmental issues that have been addressed as part of
good engineering practices, the costs for which have been accounted for in the Engineering Cost. Various
environmental aspects covered under engineering costs are listed below:
i. Turfing and Pitching of slopes
ii. Construction of slope protection works as retaining walls; breast walls toe walls, drains, and
gabions.
iii. Construction of roadside amenities as bus stops etc.
The rates adopted for the budget has been worked out on the basis of market rates and the Schedule of
rates.
Selection Criteria
Borrow areas were identified based on a number of selection criteria. These included:
Total amount of borrow area available and quantity that can be made available
Lead distance of the borrow area from the project road
Existing land use including Agricultural / Barren / Scrub / grazing / any other type (priority were
given to barren & non agricultural areas)
Ownership of the land
Vegetation / trees to be removed
Erosion / degradation potential
Distance and name of the nearest settlement
Distance from the nearest surface water body
Drainage pattern of the area
Suitability of material for sub grade and embankment use through material testing
Public Opinion (there were no objections or issues raised by the general public during the public
hearing on the selection of borrow areas)
Borrow Area Location Map
The borrow area Location map is given in Figure 11-1.
Agreement with Landowners
The Concessionaire will finalise the locations from the list given by Consultant's for procuring materials.
Once finalised the Concessionaire shall sign a lease / purchase agreements with the present owner of the
land. The concessionaire shall furnish the statement of ownership of the land along with lease / purchase
agreements to the IE & NHAI.
11.1.3 Baseline Environment
The air quality in the project area is moderately polluted. The detail air, noise & water quality status shall
be updated in the final report. The borrow areas are not located within 10 Km of any Sanctuary & National
Park. The borrow areas also do not require any diversion of forest areas. No endangered flora has also
been reported.
11.1.4 Procedure for Excavating Borrow Area
To avoid any embankment slippage, the borrow areas will not be dug continuously, and the size and
shape of borrow pits will be decided by the Engineer. Redevelopment of the borrow areas to mitigate the
impacts will be the responsibility of the Concessionaire. The Concessionaire shall evolve site-specific
redevelopment plans for each borrow area location, which shall be implemented after the approval of the
Supervision Consultant.
Precautionary measures as the covering of vehicles will be taken to avoid spillage during transport of
borrow materials. To ensure that the spills, which might result from the transport of borrow and quarry
materials do not impact the settlements, it will be ensured that the excavation and carrying of earth will be
done during day-time only. The unpaved surfaces used for the haulage of borrow materials will be
maintained properly. Borrowing of earth shall be carried out at locations recommended as follows:
Non-Cultivable Lands: Borrowing of earth will be carried out upto a depth of 2.0 m from the existing
ground level. Borrowing of earth shall not be done continuously. Ridges of not less than 8m width shall be
left at intervals not exceeding 300 m. Small drains shall be cut through the ridges, if necessary, to
facilitate drainage. Borrow pits shall have slopes not steeper than 1 vertical in 4 horizontal.
Productive Lands: Borrowing of earth shall be avoided on productive lands. However, in the event of
borrowing from productive lands, under circumstances as described above, topsoil shall be preserved in
stockpiles. The conservation of topsoil shall be carried out as described in section of this chapter. At such
locations, the depth of borrow pits shall not exceed 45 cm and it may be dug out to a depth of not more
than 30 cm after stripping the 15 cm top soil aside.
Elevated Lands: At locations where private owners desire their fields to be leveled, the borrowing shall
Record any public consultations involved while choosing and what the public concerns were, if
any.
Existing land use (Agricultural / Barren / Scrub / grazing / any other type)
Vegetation / trees to be removed
Erosion/degradation potential
Distance and name of the nearest settlement
Distance from the nearest surface water body
Drainage pattern of the area
Distance of the nearest Reserve Forest (if any)
Distance of the nearest Sacred Tree (if any)
Distance from the nearest school / hospital / primary health center
Daily / Occasional use of borrow area by the community
Any schemes or avenues for generation of income for adjoining community
Location and Layout
Sketch plans and photographs to be provided along with adequate details:
A map and sketch plan of the area showing the location of the proposed site with respect to the
project road, nearby villages and worker accommodation locations along with indicative distances of
the different sites from each other and from the road.
A detailed sketch plan of the borrow area showing approach and haulage roads, location etc.,
indicating which sites will be quarried in which year or phase, location of stock piles, location of guard
house, perimeter fence, location of water sources, amenities, and any further details.
Photographs of the site
Table 11-2: Probable Borrow Areas data (to be filled by Concessionaire)
Site identification Approximate Quantity (Cum)
Signature Signature
Name Name
Designation Designation
Concessionaire Independent Engineer
11.1.6 Impact
Significant borrowing of earth is required for the embankment fill material, and for the construction of the
pavement.
Pre Construction Stage
As the borrowing is to be carried out in accordance to the guidelines laid out in IRC-10-1961, no major
adverse impacts are anticipated. Also, productive agricultural areas have been avoided for borrowing.
However, the borrow area pits, if not treated properly after the borrowing is complete, can form stagnant
pools and pose health hazards to prevent which redevelopment of borrow areas need to be worked out.
Additionally, they can also act as breeding ground for vectors like mosquitoes just after monsoon. It is
expected that the implementation of the mitigation measures for borrow area redevelopment proposed as
part of the project will reduce these impacts to acceptable levels.
Construction Stage
Cartage of the borrow materials to the construction sites can be of significance, as almost all such areas
are accessible through dirt tracks only and therefore, spillage and compaction of soil along these tracks
will be a significant impact. Proper protections measures need to be worked out for the minimising of such
impacts during the haulage of borrow materials. Rehabilitation of borrow areas from which earth has been
excavated can be a major potential problem. In addition to visual blight, the other problems more down-to-
earth are the safety issues. At borrow area locations where the owners are willing to create ponds for
fisheries etc, proper protection measures for the drainage of the surrounding land and slope protection
measures need to be worked out.
The soils along the corridor are in general capable to produce high yielding agricultural produce and may
be negatively impacted if unduly borrowed. The loss of productive topsoil due to road construction is a
direct adverse long-term impact. The concessionaire should ensure that in all such locations topsoil must
be stacked aside and replaced after the borrowing activity is over. The soil heaps should be periodically
compacted and sprinkled with water to avoid loss. Emphasis should be laid on maximum use of the
stripped topsoil in medians, road junctions, redevelopment of borrow areas and additional landscaping
works in the road project. The project shall take enforcement measures to prevent / minimise the use of
topsoil from other locations such as borrow areas, stockyards, lands for diversions.
The impact of borrowing on air, water & noise has been documented in the chapter 6 under the relevant
sections.
11.1.7 Mitigations, Enhancement & Rehabilitation of Borrow Areas
The soils to be used, as sub-grade, select sub-grade and shoulder materials need to be hauled from
designated borrow areas. Similar to the identification of suitable quarries, suitable borrow areas for supply
of soil to the new road formation were also identified. Based on the total requirement and availability of
each soil type, estimates of soil quantity to be obtained from each of the borrow areas were worked out in
accordance with IRC: 10-1961: Recommended Practice for Borrow Pits for Road Embankments
constructed by Manual Operation. In the selection of the borrow areas, care was taken to ensure that:
Sufficient quantity of suitable soil is available from the borrow areas;
The borrow areas are as close to the project road as possible;
The loss of productive and fertile agricultural soil is minimum; and
There is minimum loss of vegetation.
For opening new borrow areas other than those identified the contractor and or concessionaire shall
follow section 11.1.5 above. The borrowing shall not be carried out in cultivable lands, unless and until, it
shall be agreed upon by the Engineer that there is no suitable uncultivable land in the vicinity for
borrowing, or there are private land owners willing to allow borrowing on their fields. Borrowing of earth
shall be carried out at locations recommended as follows:
Non-Cultivable lands: Borrowing of earth will be carried out to a depth of 1 m. The borrowing of
earth shall not be done continuously and the slope of the edges shall be maintained at not more than
1:4.
Productive lands: Borrowing of earth shall not be carried out on productive lands. However, in the
event of borrowing from productive lands, the contractor has to obtain the prior permission of the
Engineer. At such locations, the depth of borrow pits shall not exceed 45 cm and if may be dug out to
a depth of not more than 30 cm after stripping the 15 cm top soil aside and the topsoil shall be
carried out and preserved.
Borrow Areas near Settlements: Borrow pit location shall be located at least 0.8 km from villages
and settlements. If unavoidable, they should not be dug for more than 30 cm and should be drained.
To avoid any embankment slippages, the borrow areas will not be dug continuously, and the size and
shape of borrow pits will be decided by the Engineer. The borrow pits will be redeveloped by filling and
providing 150 mm thick layer of preserved top-soil; by creating shallow pond for water harvesting etc.
Replantation of trees along the edges of borrow areas will be carried out.
Precautionary measures as the covering of vehicles will be taken to avoid spillage during transport of
borrow materials. To ensure that the spills, which might result from the transport of borrow and
quarry materials do not impact the settlements, it will be ensured that the excavation and carrying of
earth will be done during day-time only, The unpaved surfaces used for the haulage of borrow
materials will be maintained properly.
Rehabilitation
The objective of the rehabilitation programme is to return the borrow pit sites to a safe and secure
area, which the general public should be able to safely enter and enjoy. Securing borrow pits sites in
a stable condition should be a fundamental requirement of the rehabilitation process. This could be
achieved by filling the borrow pit floor to approximately the access road level.
It is important to plan restoration from the outset and coordinate restoration activities. In addition to
the bio-diversity issues, land planning considerations are also taken into account when defining a
rehabilitation project in order both to preserve the environment and to generate income for the local
communities. In this framework rehabilitation often leads to the creation of wetlands and or recreation
areas.
Special borrow pit rehabilitation plan shall be specified according to the location and shaping of the
mining slopes after exploitation and overburdened dump, with different subsequent uses e.g. forest,
meadow, water body etc., the re-greening and replanting methods.
Other criteria which shall be followed for rehabilitation of quarry/ borrow pits are as given below:
Borrow pits can be backfilled with rejected construction wastes and will be given a vegetative cover.
If this is not possible, then slopes will be smoothed and depression will be filled in such a way that it
looks more or less like the original ground surface.
During works execution, the Concessionaire shall ensure preservation of trees during piling of
materials; spreading of stripping material to facilitate water percolation and allow natural vegetation
growth; reestablishment of previous natural drainage flows; improvement of site appearance; digging
of ditches to collect runoff; and maintenance of roadways where a pit or quarry is declared useable
water source for livestock or people nearby. Once the works are completed, and at own expense the
concessionaire and Concessionaire shall restore the environment around the work site to its original
splits.
Appropriate plant species for the planting programme have to be selected in consultation with
ecological consultant and local forest department. Depending on the limitations on the availability of
appropriate plant material, harsh growing conditions (lack of irrigation and hot summer) and ongoing
quarry rehabilitation operations there may be substantial loss of plantation and the planting
programme may have to be continued for over 3–5 years. As plantings are progressively established
they should be monitored before undertaking the next stage to ensure maximum plant survival rates.
The borrow pit immediate surroundings shall be developed as a low maintenance reserve, with
significant areas of native trees and shrubs and areas of longer grass and tussocks forming the open
spaces. Walkways around the borrow site may be constructed. Provision for a future drive-in picnic
area and car parking area may be developed.
Guidelines for Enhancement
As far as possible borrow area selected for enhancement shall be on government / community land in the
vicinity of settlement. The Concessionaire must ensure that any enhancement design proposed should be
workable, maintenance free and preferably worked out in consultation with the community and proposed
enhancement materials should be locally available. The borrow area can be developed either of the
following:
Vegetative Cover
Vegetative cover must be established on all affected land.
Topsoil must be placed, seeded, and mulched within 30 days of final grading if it is within a current
growing season or within 30 days of the start of the next growing season.
Vegetative material used in reclamation must consist of grasses, legumes, herbaceous, or woody
plants or a mixture thereof.
Plant material must be planted during the first growing season following the reclamation phase.
Selection and use of vegetative cover must take into account soil and site characteristics such as
drainage, pH, nutrient availability, and climate to ensure permanent growth.
The vegetative cover is acceptable if within one growing season of seeding:
The planting of trees and shrubs results in a permanent stand, or regeneration and succession rate,
sufficient to assure a 75% survival rate;
The planting results in 90% ground coverage.
The site shall be inspected when the planting is completed and again at one year to ensure
compliance with the reclamation plan.
Certificate of Completion of Reclamation
Concessionaires have to obtained certificate of satisfaction from the landowner and submit it to the
Engineer before final payment is to done.
Working Plan
The Concessionaire must prepare a working plan before enhancing the identified borrow areas. Following
are the inputs that provide the guidelines to the Concessionaire to formulate the working plan:
Access of Property / width of access / material
Orientation of property with respect to the road
Site Slope
Local Drainage / water logging etc if any
Location of nearest culvert etc if any to drain water if required
Any other community resources such as tube well/well etc in vicinity
Location of trees including Species / girth / foliage spread and afternoon shaded area on ground
Surrounding land use; nearby settlements (name of structure/pattern of settlement)
Mark on plan part of the borrow area, most suitable for storing and staking topsoil.
Drawings to be Prepared
The Concessionaire have to prepared the drawings showing both cross-section as well as plan of the
Sl.
ToR Points Compliance
No.
1 The Proposal indicates the acquisition of 0.1285 ha The proposed project shall involve diversion
Forest land. Necessary stage –I forestry clearance of 10.3000ha. forest land in Ramanagara
shall be obtained as per OM dated 31.03.2011 and and Mandya Forest Division of Karnataka
submitted along with final EIA report
Forest Dept.’s jurisdiction..
Application for obtaining Forest Clearance has
already been made. The application letter has
been attached as Appendix-1
2 It is indicated that 2431 trees fall within ROW, 24712 trees of various girth sizes present along
however bare minimum trees shall be cut, the the project corridor. The project is likely to impact
information should be provided about their species 19230 trees of various species as per joint
and whether it also involved any protected or verifications with forest department. Thus saving
endangered species. Necessary green belt shall be 5482 trees of various species.
provided on both side of the highway with proper No endangered / protected species.
central verge and cost provision should be made for Avenue plantation along the project road and in
regular maintenance. median is proposed & shall be carried out as per
IRC: SP: 21-2009 based on availability of land
Incidental area of 35.09 Ha. identified where
plantations can take place
Species details for felling is annexed in Annexure
4.3
Necessary prior permissions from the District
Collectors and the DCF has been requested for
felling
3 Explore the possibilities of cooled mixed technology Please refer Chapter- 7
instead of hot mix technology
4 Any litigation(s) pending against the proposed project No litigations are pending against the project road.
and/or any directions or orders passed by any court of
law/any statutory authority against the project is to be
detailed out.
5 Submit detailed alignment plan, with details such as Detailed Alignment Plan attached
nature of terrain (plain, rolling, hilly), land use pattern, Terrain along the project road is plain
habitation, cropping pattern, forest area, 10.3000ha of forest land will be diverted for the
environmentally sensitive places, mangroves, notified project.
industrial areas, sand dunes, sea, river, lake, details of There exist no mangroves along the project
villages, teshils, districts and states, latitude and corridor.
longitude for important locations falling on the
The project road section doesn’t fall within 10 Km
alignment by employing remote sensing techniques
radius of any Wild Life Sanctuary or National Park
followed by ground truthing and also through
secondary data sources. The project does not involve any sand dunes, sea
etc.
Project Districts: Chamarajanagar, Mandya,
Ramanagar
Tehsils: Chamaraja Nagar, Yelanduru, Kollegal in
Chamarajanagar District, Malavalli in Mandya
District and Kanakapura in Ramanagar District.
6 Describe various alternatives considered, procedures The project road is a NH and connects the urban
and criteria adopted for selection of the final and semi urban regions outside Bangalore. Hence
alternative with reasons. question of various alternatives for the project
road does not arise.
However to decongest built up areas along the
project route bypasses at Kollegal, Sathegala,
Sl.
ToR Points Compliance
No.
Halaguru and Kanakapura proposed along with
realignments. Different alternate route along with
widening of existing alignment are compared
considering the factors like road length, available
ROW, land acquisition, structures to be
demolished, project affected families and
construction cost.
The details of analysis of alternative are given in
Chapter 7.
7 Submit Land use map of the study area to a scale of The land use map based upon recent satellite
1:25000 based on recent satellite imagery delineating imagery and on desired scale shall be enclosed in
the crop lands (both single and double crop), the final report
agricultural plantations, fallow lands, waste lands,
water bodies, built-up areas, forest area and other
surface features such as railway tracks, ports, airports,
roads, and major industries etc. and submit a detailed
ground surveyed map on 1:2000 scale showing the
existing features falling within the right of way namely
trees, structures including archaeological & religious,
monuments etc. if any.
8 If the proposed road is passing through any hilly area, The project road doesn’t passes through any hilly
examine and submit the stability of slopes, if the area
proposed road is to pass through cutting or
embankment / control of soil erosion from
embankment
9 If the proposed route involves tunneling, the details of The project doesn’t involves any tunnelling nor
the tunnel and locations of tunneling with geological does it passes through any flood plain of rivers
structural fraction should be provided. The case the
road passes through a flood plain of the river, the
details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years
in the area should be examined
10 The project is located within 10 Km of sanctuary a The project road section is not located within 10
map duly authenticated by Chief Wild Life Warden Km of any sanctuary
showing these features vis-à-vis the project location
and the recommendations Chief Wild Life Warden
thereon should be furnished at the stage of EC
11 Study regarding the animal bypasses / underpasses No underpass is provided as there is no major
etc. across the habitation areas shall be carried out. cross traffic movement. Also in agricultural area 2
Adequate cattle passes for the movement of lane with paved shoulder is proposed.
agricultural material shall be provided at the stretches No cattle pass is provided since it 2 lane with
passing though habitation areas paved shoulder proposed in agricultural area
12 If the proposed route is passing through a city / town, Bypasses at 4 locations have been proposed for
with houses and human habitation on the either side smoother movement of traffic in densely
of the road, the necessity for provision of bypasses / populated areas.
diversions / under passes shall be examined and Chainage wise locations of bypass locations are
submitted. The proposal should also indicate the given in Chapter-2 of EIA report.
location of wayside amenities, which should include Details of wayside amenities are provided in
petrol station/service centre, rest areas including Chapter-2
public conveyance etc.
13 Submit details about measures taken for the 54 bus bays with bus shelters proposed along
pedestrian safety and construction of underpasses with 1 truck lay bye.
and foot-over bridges along with flyovers and 1 toll plaza at Existing Chainage Km 363.000 has
interchanges. been proposed.
Apart from these, provisions are proposed for
pedestrian safety, in Schedule C (Project
Facilities) and Schedule D (Standards &
Specifications) of the Concession Agreement
signed between the Concessionaire and project
Proponent.
14 Assess whether there is a possibility that the proposed During construction period, appropriate traffic
project will adversely affect road traffic in the management will be adopted to minimize
surrounding areas (e.g. by causing increases in traffic congestion.
congestion and traffic accidents). During Operation period, the proposed project
Sl.
ToR Points Compliance
No.
would smooth the traffic jams and congestion and
would minimize traffic accidents.
Detailed traffic management plan enclosed as
Annexure 8.8
The project shall improve connectivity in the
region, enhancing the inter-urban, inter-district
and inter-state mobility, and it will attract more
traffic in the form of diverted and generated traffic
from the influencing areas. Development of
project road will not lead to any congestion on
other roads in the areas, the measures for traffic
control / diversion while construction is proposed.
15 Examine and submit the details of use of fly ash in the No thermal power plant located within 100 km
road construction, if the project road is located within from the project road
the 100 Km from the thermal power plant
16 Examine and submit the details of sand quarry, borrow Details of quarry areas identified for the project is
area and rehabilitation. given in Tables 8-3 & 8-4. Quarry chart enclosed
as Annexure 8.5. Borrow area details given in
chapter 11
17 Climate and meteorology (max and min temperature, For climate and meteorology data kindly refer
relative humidity, rainfall, frequency of tropical cyclone Section 4.2.1 of Chapter 4 of EIA. Secondary
and snow fall); the nearest IMD meteorological station meteorological data have been obtained from
from which climatological data have been obtained to websites
be indicated.
18 The air quality monitoring should be carried out as per Air quality monitoring has been carried out as per
th
the new notification issued on 16 November, 2009. new notification for the period October –
December 2012. Please refer section 4.2.3 of
Chapter 4 of EIA report for monitoring results.
19 Identify project activities during construction and Impact evaluation and results and proposed
operation phases, which will affect the noise levels mitigation measures are given in section 6.2.5 &
and the potential for increased noise resulting from 8.2.5 of Chapter 6 & 8 of EIA report. Noise
this project. Discuss the effect of noise levels on prediction modelling shall be furnished in final EIA
nearby habitation during the construction and Report.
operational phases of the proposed highway. Identify
noise reduction measures and traffic management
strategies to be deployed for reducing the negative
impact if any. Prediction of noise levels should be
done by using mathematical modelling at different
representative locations.
20 Examine the impact during construction activities due Regular water sprinkling system will be adopted to
to generation of fugitive dust from crusher units, air minimize the dust emission.
emissions from hot mix plants and vehicles used for Raw materials with covered vehicles to avoid
transportation of materials and prediction of impact on fugitive emission;
ambient air quality using appropriate mathematical Modelling shall be furnished in final EIA Report.
model, description of model, input requirement and
reference of derivation, distribution of major pollutants
and presentation in tabular form for easy interpretation
shall be carried out.
21 Also examine and submit the details about the An environment management plan has been
protection to existing habitations from dust, noise, proposed to minimize the impact on habitation
odour etc. during construction stage. from dust, noise etc. during construction stage.
Please refer Chapter 10 of EIA report.
22 If the proposed route involves cutting of earth, the The borrow materials will be withdrawn as per
details of area to be cut, depth of cut, locations, soil IRC: 10-1961. The aggregate and sand will be
type, volume and quantity of earth and other materials procured from the Govt. approved licensed
to be removed with location of disposal / dump site quarries by paying the cost of material as well as
along with necessary permission. cost for rehabilitation.
The locations of borrow areas are given in chapter
11.
23 If the proposed route is passing through low lying No low lying areas exist along the project road
areas, details of fill materials and initial and final levels
after filling above MSL, should be examined and
submit.
Sl.
ToR Points Compliance
No.
24 Examine and submit the water bodies including the Inventory of water resources attached in
seasonal ones within the corridor of impacts along Annexure 4.1. volumetric capacity of impacted
with their status, volumetric capacity, quality likely water bodies given in section 6.2.4
impacts on them due to the project.
25 Examine and submit details of water quantity required Total water required for the project will be 56
and source of water including water requirement KLD, this will be sourced from both surface &
during the construction stage with supporting data and ground water during construction phase.
also classification of ground water based on the
CGWA classification.
26 Examine and submit the details of measures taken The schedule for construction of piles will be
during constructions of bridges across done, so that the existing volumetric flow of the
river/canal/major or minor drains keeping in view the river will not affect.
flooding of the rivers and the life span of the existing Cofferdam will be used.
bridges. Provision of speed breakers, safety signals, No excavated material will be dumped on river
service lanes and foot paths should be examined at bed / bank even though 500 m from the river
appropriate locations throughout the proposed road to bank.
avoid the accidents. Silt fencing will be provided to protect surface run-
off.
Speed breakers, safety signals and service lanes
will be provided as per IRC guidelines and codes.
27 If there will be any change in the drainage pattern after 396 culverts, 4 major bridge and 26 minor bridges
the proposed activity, details of changes shall be are proposed. Therefore, change in drainage
examined and submitted. pattern shall not happen.
28 Rain water harvesting pit should be at least 3 - 5 m. Rain water harvesting structures at 500m distance
above the highest ground water table. Provision shall in staggered pattern proposed. The Rain water
be made for oil and grease removal from surface harvesting pit shall be at least 3 - 5 m. above the
runoff. highest ground water table. Refer Rain Water
Harvesting in chapter 8.
Silt trap and oil interceptors provided for oil &
grease removal
29 Is there is a possibility that the construction / widening The concessionaire shall take necessary
of the road will cause impact such as destruction on precautions to minimize the possibility
forest, poaching, reduction in wetland areas, if so,
examine the impact and submit details
30 Submit the details of road safety, signage, service All safety provisions are being considered during
roads, vehicular under passes, accident prone zone design, construction and operation phases.
and the mitigation measures. Improvements of geometry have been proposed
as per IRC guidelines and codes
Bus shelters, truck lay bays, traffic signage will be
provided. The details are given in chapter 2
The provisions are as per Schedule C & D of the
Concession agreement and IRC: SP 84 – 2009,
‘Manual of Specifications & Standards for Four-
laning of Highways through Public Private
Partnership.
31 IRC guidelines shall be followed for widening & up- IRC guidelines have been followed for widening
gradation of road. and up-gradation of project road
32 Submit details of social impact assessment due to the Details of Social Impact Assessment is provided
proposed construction of road. in Section 6.4
33 Examine road design standards, safety equipment The entire project road is designed by maintaining
specifications and Management System training to the IRC codes, MoRT&H manual and other
ensure that design details take account of safety applicable guidelines for safety standards.
concerns and submit the traffic management plan. Provision of road safety has been kept as per
IRC: SP-44-1996 and IRC: SP-32-1998.
A traffic management plan is proposed as part of
the project.
34 Accident data and geographic distribution should be With the project the traffic congestion will reduce
reviewed and analyzed to predict and identify trends? along with reduction in accidents. Further densely
In case of expansion of the existing highway and habitat areas are bypassed. HTMS and highway
provide Post accident emergency assistance and patrolling, ambulance facility, computerised
medical care to accident victims. highway monitoring and Emergency call box
system will be there.
Sl.
ToR Points Compliance
No.
Accident data and their distribution and cause as
part of feasibility study was reviewed. The design
of new 4-lane facility is taking care of accident
black spots. The facility minimizes accident
possibilities with superior design and safety
features. Necessary measures have proposed to
take care post accident emergency / trauma care;
they are listed in the Schedules of the concession
agreement.
35 If the proposed project involves any land reclamation, Please refer Chapter-6.
details to be provided for which activity land to reclaim
and the area of land to be reclaimed.
36 Details of the properties, houses, businesses etc. A total of 3200 PAPs & 564 PAFs are to be
activities likely to be effected by land acquisition and impacted. A total of 564 properties are being
their financial loses annually. affected out of which there are 158 residential,
352 commercial and 54 resi-cum-commercial
properties
37 Detailed R&R plan with data on the existing socio- Compensation to the project affected families
economic status of the population in the study area (PAFs) will be as per NPRR 2007 and Govt. of
and broad plan for resettlement of the displaced Karnataka and NHAI policies. Separate R&R
population, site for the resettlement colony, alternative budget kept.
livelihood concerns/ employment and rehabilitation of
the displaced people, civil and housing amenities
being offered, etc and the schedule of the
implementation of the project specific
38 Submit details of Corporate Social Responsibility. The project is a Government of India project which
Necessary provisions should be made in the budget. aims at providing better connectivity and also
providing better economic development in the
region. Hence CSR details is not applicable for
the project
However the Concessionaire shall make
necessary provisions for Corporate Social
responsibility in their budgetary provisions
38 Estimated cost of the project including environmental The project will be on DBFO basis. Civil cost
monitoring cost and funding agencies, whether for the project is INR 331.53crores while the
governmental or on the basis of BOT etc and provide Total Project cost is INR INR 581.424
details of budget provisions (capital & recurring) for
Crores
the project specific R&R Plan.
EMP budget for INR 24.43 crores is presented in
Table 10-2
The LA and R&R cost is budgeted at INR 42.0
Crores.
39 Submit environmental management and monitoring Kindly refer Chapter 10 for Environment
plan for all phases of the project viz. construction and Management Plan of EIA report.
operation.
13.3 LABORATORY
Noida Testing laboratories, Noida, has carried out the sampling and analysis for various air, water, noise
samples as per procedure & guidelines of Central Pollution Control Board and the requirements of MoEF on
behalf of Feedback Infra. The laboratory is NABL accredited and MoEF approved Laboratory.
Annexure 2-1: Proposed Bus bay with Bus Shelters & Bus shelter
Proposed
Sl.no Existing km Side Location Remarks
Chainage
1 272.550 272+700 RHS Punjanur Village Busbay with shelter
2 272.650 272+890 LHS Punjanur Village Busbay with shelter
3 276.000 275+990 LHS Kolipalya Village Busbay with shelter
4 276.200 276+195 RHS Kolipalya Village Busbay with shelter
5 277.570 276+680 RHS Koremada village Bus shelter
6 277.570 277+570 LHS Koremada village Bus shelter
7 289.510 289+635 LHS Attigulipura Village Busbay with shelter
8 290.100 291.350 RHS Attigulipura Village Busbay with shelter
9 291.100 291+060 LHS Chikola Village Bus shelter
10 291.250 291+200 RHS Chikola Village Bus shelter
11 295.200 295+040 LHS Anganacettipura Village Busbay with shelter
12 295.200 295+685 RHS Venkatana Cettipura Village Busbay with shelter
13 297.500 297+585 RHS Arthanahalli Village Bus shelter
14 298.020 297+985 LHS Arthanahalli Village Bus shelter
15 300.620 300+140 LHS Start of Chamarajnagar Bypass Busbay with shelter
16 300.620 300+140 RHS Start of Chamarajnagar Bypass Busbay with shelter
17 306.650 308+040 LHS End of Chamarajnagar Bypass Busbay with shelter
18 306.650 308+040 RHS End of Chamarajnagar Bypass Busbay with shelter
19 307.350 308+550 LHS Village Busbay with shelter
20 307.500 308+935 RHS Village Busbay with shelter
21 308.530 309+505 LHS Madavapura Village Busbay with shelter
22 308.630 310+145 RHS Madavapura Village Busbay with shelter
23 312.630 313+545 LHS Mangala village Busbay with shelter
24 312.730 314+395 RHS Mangala village Busbay with shelter
25 320.900 321+837 LHS Anthanahalli Village Busbay with shelter
26 321.490 321+447 RHS Anthanahalli Village Busbay with shelter
27 325.700 326+460 LHS Eriyur Village Busbay with shelter
28 325.700 326+500 RHS Eriyur Village Busbay with shelter
29 336.950 337+590 LHS Start of Kollegal Bypass Busbay with shelter
30 336.950 337+390 RHS Start of Kollegal Bypass Busbay with shelter
31 346.900 346+240 LHS Dhangeveri Village Busbay with shelter
32 347.300 347+050 RHS Dhangeveri Village Busbay with shelter
33 349.630 349+030 LHS Dhangeveri Village Busbay with shelter
34 350.500 349+860 RHS Dhangeveri Village Busbay with shelter
35 368.830 364+040 LHS Dasanadody Village Busbay with shelter
36 368.830 365+150 RHS Hosadoddi Village Busbay with shelter
37 368.980 365+340 LHS Pandhahalli Village Busbay with shelter
38 368.980 365+940 RHS Pandhahalli Village Busbay with shelter
39 370.220 366+690 LHS Bashanahalli Village Busbay with shelter
Client: National Highways Authority of India Draft EIA Report
1
Consultant: Feedback Infra Pvt. Ltd July 2013
UNCONTROLLED IF PRINTED
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of Chamarajanagar to
Harohalli section of NH – 209 in the state of Karnataka
Proposed
Sl.no Existing km Side Location Remarks
Chainage
40 370.220 366+900 RHS Bashanahalli Village Busbay with shelter
41 372.230 369+360 RHS Doddy Village Busbay with shelter
42 379.750 376+190 RHS Cholenahalli Village Busbay with shelter
43 379.750 376+830 LHS Cholenahalli Village Busbay with shelter
44 383.500 381+020 RHS Cholenahalli Village Busbay with shelter
45 384.375 381+620 LHS H M Sarkal Village Busbay with shelter
46 384.375 382+130 LHS Basavanapura Village Busbay with shelter
47 385.275 382+350 RHS Basavanapura Village Busbay with shelter
48 387.000 383+860 LHS Basavanapura Village Busbay with shelter
49 387.000 384+160 RHS Basavanapura Village Busbay with shelter
50 390.200 386+915 RHS Basavanapura Village Busbay with shelter
51 391.925 388+450 RHS Kadanahalli Village Busbay with shelter
52 391.925 389+100 LHS Kadanahalli Village Busbay with shelter
53 398.200 395+955 LHS Dalavayikodi Village Busbay with shelter
54 400.200 396+795 RHS Dalavayikodi Village Busbay with shelter
55 401.810 398+475 RHS Honnaganahalli Village Busbay with shelter
56 406.225 403+115 RHS Sathanur Village Bus shelter
57 406.225 403+505 LHS Sathanur Village Bus shelter
58 413.125 409+255 LHS Acchalu village Busbay with shelter
59 413.125 409+555 RHS Jakkegowanadoddi Village Busbay with shelter
60 416.775 413+423 RHS Kallegowdanadoddi Village Busbay with shelter
61 416.775 413+920 LHS Kallegowdanadoddi Village Busbay with shelter
62 419.850 415+600 RHS Sivanahalli Village Busbay with shelter
63 419.850 415+600 RHS Sivanahalli Village Busbay with shelter
64 419.575 416+295 LHS Start of Kanakapura Bypass Busbay with shelter
65 419.675 416+505 RHS Start of Kanakapura Bypass Busbay with shelter
66 427.900 424+915 RHS End of Kanakapura Bypass Busbay with shelter
67 Bypass 425+160 RHS End of Kanakapura Bypass Busbay with shelter
68 428.850 425+700 LHS Kurigowdanahalli Village Busbay with shelter
69 429.650 425+145 LHS Thopagannahalli Busbay with shelter
70 430.150 424+905 RHS Thopagannahalli Busbay with shelter
71 451.540 448+545 LHS Somanahalli Village Busbay with shelter
72 451.540 452+090 RHS Somanahalli Village Busbay with shelter
73 454.350 450+895 LHS Kaggalipura Village Busbay with shelter
74 454.350 451+295 RHS Kaggalipura Village Busbay with shelter
75 458.580 455+465 LHS Lakshmipura Village Busbay with shelter
76 458.580 455+150 RHS Lakshmipura Village Busbay with shelter
8 OHT LHS
10 OHT RHS
11 OHT
45 Well RHS
Distance from
Sl. No C/L Structure Settlement Side
(Existing)
1 25 School Chamarajnagar LHS
2 10 School Kandarahalli RHS
3 15 Forest Department Yelandur LHS
4 20 College & School Yelandur LHS
Teachers Training
5 10 Yelandur LHS
Institute
6 35 Court Yelandur LHS
7 20 School Yelandur LHS
8 Police Station Yelandur LHS
9 20 Hospital Yelandur RHS
10 9 School Yeriyoor RHS
11 18 School Maddur RHS
12 8 Hospital Mampalli RHS
13 15 School Uttampalya LHS
14 30 School Kollegal LHS
15 10 School Pandithalli RHS
16 15 School Dassanadoddi LHS
17 15 School Vachanahalli RHS
Education Institute
18 15 Malavalli LHS
&Hostel
19 25 College Malavalli LHS
20 20 IT & Bed. Malavalli LHS
21 10 School Chonalahalli RHS
22 25 School Basavapur LHS
23 15 High School Halasahalli LHS
24 8 Primary School Kodehalli LHS
25 12 Govt. High School Honnaganahalli LHS
26 15 Primary School Jakkegowdanadoddi LHS
27 12 Primary School Shivanahalli LHS
28 10 School Pit Shivanahalli RHS
29 25 Education Institute Kanakapura LHS
30 30 School Tungne RHS
31 50 University Jakkasandra LHS
32 15 Jan College Jakkasandra LHS
33 15 Police Station Harohalli RHS
34 10 School Harohalli LHS
35 20 College Kanakapura LHS
Distance from
Sl. No C/L Structure Settlement Side
(Existing)
36 10 Court Kollegal LHS
37 10 Govt. Hospital Kaglipura RHS
38 10 Hospital Kollegal LHS
39 40 School Kanakapura RHS
40 30 School Kanakapura LHS
41 30 School Kollegal RHS
42 12 School Kollegal LHS
43 12 School RHS
Annexure 8.1: Guidelines for Identification of Debris Disposal Sites & Precautions Needed
Dumpsites
The dumpsites filled only up to the ground level could be rehabilitated as per guidelines below and to be decided by the
engineer and the supervision consultant
The dumpsites have to be suitably rehabilitated by planting local species of shrubs and other plants so that the landscape
is coherent and is in harmony with its various components.
In cases where a dumpsite is near to the local village community settlements, it could be converted into a play field by
spreading the dump material evenly on the ground. Such playground could be made coherent with the landscape by
planting trees all along the periphery of the playground.
Some of the dumpsites could be used either for plantation or for growing agricultural produce.
Care should always be taken to maintain the hydrological flow in the area.
Quarries
The contactor shall use materials from the existing and licensed quarry areas only. In case any new quarries are opened by
the contractor, he shall secure permissions for the same and shall follow the rehabilitation plan.
The objective of the rehabilitation programme is to return the quarry sites to a safe and secure area, which the general
public should be able to safely enter and enjoy. Securing quarry sites in a stable condition should be a fundamental
requirement of the rehabilitation process. This could be achieved by filling the quarry / quarry floor to approximately the
access road level.
It is important to plan restoration from the outset and coordinate restoration with quarrying activities. In addition to the bio-
diversity issues, land planning considerations are also taken into account when defining a rehabilitation project in order
both to preserve the environment and to generate income for the local communities. In this framework quarry
rehabilitation often leads to the creation of wetlands and natural reserves or recreation areas.
Special quarry / quarry rehabilitation plan should be specified according to the location and shaping of the mining slopes
after exploitation and overburdened dump, with different subsequent uses e.g. forest, meadow, water body etc., the re-
greening and replanting methods.
Other criteria which should be followed for rehabilitation of quarry sites are as given below:
Quarries will be backfilled with rejected construction wastes and will be given a vegetative cover. If this is not possible,
then slopes will be smoothed and depression will be filled in such a way that it looks more or less like the original ground
surface.
During works execution, the contractor shall ensure preservation of trees during piling of materials; spreading of stripping
material to facilitate water percolation and allow natural vegetation growth; reestablishment of previous natural drainage
flows; improvement of site appearance; digging of ditches to collect runoff; and maintenance of roadways where a pit or
quarry is declared useable water source for livestock or people nearby. Once the works are completed, and at own
expense the contractor shall restore the environment around the work site to its original splits.
To create a safe environment under the terms of The Mines and Quarries Act the faces have to be reduced to a naturally
stable slope or be adequately fenced to prevent access to the top and bottom of the faces. Such a fence must be of a
height as prescribed under The Mines Act with a barbed wire top strand designed to exclude the public from the quarry
area. Depending on the location of the site presence of a permanent lake is considered to be a satisfactory alternative to
a fence.
Appropriate plant species for the planting programme have to be selected in consultation with ecological consultant and
local forest department. Depending on the limitations on the availability of appropriate plant material, harsh growing
conditions (lack of irrigation and hot summer) and ongoing quarry rehabilitation operations there may be substantial loss
of plantation and the planting programme may have to be continued for over 3–5 years. As plantings are progressively
established they should be monitored before undertaking the next stage to ensure maximum plant survival rates.
The quarry or quarry immediate surroundings should be developed as a low maintenance reserve, with significant areas
of native trees and shrubs and areas of longer grass and tussocks forming the open spaces. Walkways around the
quarries may be constructed. Provision for a future drive-in picnic area and car parking area may be developed.
1.2.8 Safety
Contractor to divulge safety measures to the SC.
Ensure that workers at the quarry sites are aware of the appropriate sections of the safety plan.
1.2.9 Workers Accommodation
Contractor to provide details of how many workers will be accommodated on site and what the accommodation
arrangements and standard will be.
2. Environmental Management
2.1 Environmental Management during Operation
2.1.1 Removal of trees and plants
Contractor to describe briefly the floral species that have had to be removed (it will be helpful give local names if
English or scientific names are not known), and roughly how many.
2.1.2 Overburden
Contractor to state where this will be deposited (indicate on the sketch map), and what methods will be taken to
contain it, if any.
2.1.3 Silt management
Contractor to state how silt arising from quarry operations will be managed, e.g. provision of a silt retention pond, and
show where this is on the sketch map. Say how the silt retention pond will be managed (i.e. how often it will be
dredged).
2.1.4 Surface water drainage
If it will be necessary to provide drainage channels, contractor to show on the sketch map where these are and
confirm that they will be kept free of blockages.
2.1.5 Soil and water contamination
Contractor to list sources of possible contaminants to the soil (fuel stores, etc) and what will be done to control it
(minimise spillages, control leaks from plant, etc).
2.1.6 Air pollution
What are the sources of air pollution?
Details of air pollution control measures in each case.
Details of worker protection equipment along with appropriate reference to the safety plan.
2.1.7 Noise
Sources of noise, distance from settlement, labour camp and proposed mitigation to the population / workers
exposed.
2.1.8 Traffic
Impact of quarry operations on traffic and how this may be controlled.
2.1.9 Approach road
Contractor to state whether this will be maintained, and if so in what condition.
2.2 Environmental Management at Closure of the site
2.2.1 Dismantling and removal of machinery
Contractor to state whether and when this shall be done.
2.2.2 Slope stabilisation and / or protection
Measures taken to protect the slope and to guard against any possible serious rockfall, or any measures to safeguard
against hazards like this.
2.2.3 Rehabilitation
Rehabilitation plan of the quarry.
The contractor shall be responsible for the Redevelopment Plan prior to completion after five years, during the defect
liability period. The SC and the NHAI shall be responsible for reviewing this case of redevelopment prior to the issuing the
defect liability certificate.
Signature Signature
Name Name
Designation Designation
Contractor Supervision Consultant
The Contractor will finalise the locations from the list given by Consultant's for procuring materials. The Contractor
shall establish a new quarry only with the prior consent of the Supervision Consultant (SC) only in cases when: (i)
Lead from existing quarries is uneconomical and (ii) Alternative material sources are not available. The Contractor
shall prepare a Redevelopment Plan for the quarry site and get it approved by the SC.
The construction schedule and operations plans to be submitted to the SC prior to commencement of work shall
contain a detailed work plan for procuring materials that includes procurement, transportation and storage of
quarry materials.
CONSTRUCTION STAGE
Development of site: To minimise the adverse impact during excavation of material following measures are need
to be undertaken:
i) Adequate drainage system shall be provided to prevent the flooding of the excavated area
ii) lt the stockpiling locations, the Contractor shall construct sediment barriers to prevent the erosion of
excavated material due to runoff
iii) Construction of offices, laboratory, workshop and rest places shall be done in the up-wind of the plant to
minimize the adverse impact due to dust and noise.
i) The access road to the plant shall be constructed taking into consideration location of units and also slope
of the ground to regulate the vehicle movement within the plant.
iv) In case of storage of blasting material, all precautions shall be taken as per The Explosive Rules, 1983.
QUARRY OPERATIONS INCLUDING SAFETY
i) Overburden shall be removed and disposed inline with Guidelines for Debris Disposal Site and
management giving in Annexure-8.1
ii) During excavation, slopes shall be flatter than 20 degrees to prevent their sliding. In cases where quarry
strata are good and where chances of sliding are less this restriction can be ignored.
iii) In case of blasting, procedure and safety measures shall be taken as per The Explosive Rules, 1983
iv) The contractor shall ensure that all workers related safety measures shall be dune as per guidelines for
Workers and Safety.
v) The Contractor shall ensure maintenance of crushers regularly as per manufacturer's recommendation.
Topsoil will be excavated and preserved during transportation of the material measures shall be taken to minimize
the generation of dust and prevent accidents.
The SC shall review the quarry site for the management measures during quarry operation, including the
compliance to pollution norms.
POST CONSTRUCTION STAGE
The Contractor shall restore all haul roads constructed for transporting the material from the quarries to
construction site to their original state.
The IC shall be entrusted the responsibility of reviewing the quarry site for the progress of implementation
of Redevelopment Plan.
The redevelopment of exhaust quarry shall be the responsibility of the agency providing the permit to
ensure the implementation of Redevelopment Plan.
For existing quarry managed directly by a third party from whom the contractor is sourcing the materials, the plan
should contain the following:
REMARKS
Signature Signature
Name Name
Designation Designation
Conctractor Supervision Consultant
Project Name: Consultancy Services for Preparation of DPR for Rehabilitation and Upgradation of Tamil Nadu/ Karnataka
Border - Bangalore Section NH 209 under NHDP-IVB
Bangalore(OOR)
Ch. 469+310 End of the Project stretch
C
0.5 km 2.7 km Ch 449+000
Ch 445+350 2.1 km
Q S
0.1 km Ch 438+000
B
1.2 km 4 km Ch 432+200
0.9 km SH 3
2.2 km
Q&C
Q&C Kanakapura
Ch 414+000 0.1km
B
5.8 km Ch 406+450
0.7 km
2.1 km Ch 405+950
Q
2.5 km
Q&C
0.1 km Ch 400+700
B
4.5 km Ch 384+400
Q
Malavalli
0.3 km Ch 364+100
B
0.1 km Ch 357+000
B
1.7 km 1.0 km
S
1.9km 1.1 km Ch 342+700
SH 79 Kollegal
2.0 km Ch 337+300
S 1.2 km 0.8 km
Yelandur
Ch 323+650 5.3 km
Q B
3.2 km
B
Ch 313+700 0.1km
B
C
0.4 km Chamarajanagar
0.5 km
C
2.4 km 9.3 km Ch 296+000
LEGEND:
Q Quarry
Sand
S
All materials shall meet commercial grade standards and shall be approved by the Engineer before being used in
the work.
CONSTRUCTION STAGE
Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for approval, his
schedules for carrying out temporary and permanent erosion / sedimentation control works as are applicable for
the items of clearing and grubbing, roadway and drainage excavation, embankment / sub-grade construction,
bridges and other structures across water courses, pavement courses and shoulders. He shall also submit for
approval his proposed method of erosion / sedimentation control on service road and quarries and his plan for
disposal of waste materials. Work shall not be started until the erosion / sedimentation control schedules and
methods of operations for the applicable ' construction have been approved by the Engineer.
The surface area of erodible earth material exposed by clearing and grubbing, excavation, quarry and fill
operations shall be limited to the extent practicable. The Contractor may be directed to provide immediate control
measures to prevent soil erosion and sedimentation that will adversely affect construction operations, damage
adjacent properties, or cause contamination of nearby streams or other watercourses. Such work may involve the
construction of temporary berms, dikes, sediment basins, slope drains and use of temporary mulches, fabrics,
mats, seeding, or other control devices or methods as necessary to control erosion and sedimentation.
The Contractor shall be required to incorporate all permanent erosion and sedimentation control features into the
project at the earliest practicable time as outlined in his accepted schedule to minimize the need for temporary
erosion and sedimentation control measures.
Temporary erosion, sedimentation and pollution control measures will be used to control the phenomenon of
erosion, sedimentation and pollution that may develop during normal construction practices, but may neither be
foreseen daring design stage nor associated with permanent control features on the Project.
Where erosion or sedimentation is likely to be a problem, clearing and grubbing operations should be so
scheduled and performed that grading operations and permanent erosion or sedimentation control features can
follow immediately thereafter if the project conditions permit; otherwise temporary erosion or sedimentation control
measures may be required between successive construction stages. Under no conditions shall a Large surface
area of credible earth material be exposed at one time by clearing and grubbing or excavation without prior
approval of the EO / Engineer.
The Engineer may limit the area of excavation, quarry and embankment operations in progress, commensurate
with the Contractor's capability and progress in keeping the finish grading, mulching, seeding and other such
permanent erosion, sedimentation and pollution control measures, in accordance with the accepted schedule.
Temporary erosion is sometimes caused due to the Contractor's negligence, carelessness or failure to install
permanent controls. Sedimentation and pollution control measures then become necessary as a part of the work
as scheduled or ordered by the Engineer, and these shall be carried out at the Contractor's own expense.
Temporary erosion, sedimentation and pollution control work required, which is not attributed to the Contractor's
negligence, carelessness or failure to install permanent control, will be performed as ordered by the EO /
Engineer.
Temporary erosion, sedimentation and pollution control may include construction work outside the right of way
where such work is necessary as a result of road construction such as quarry operations, service roads and
equipment storage sites.
The temporary erosion, sedimentation and pollution control features installed by the Contractor shall be
maintained by him till these are needed, unless otherwise agreed by the Engineer.
1. INTRODUCTION
NHAI has decided to widen and strengthen the Project road within a ROW of 30m in urban areas and 45in rural areas
including bypasses and realignments proposed. Due to this purpose, trees are to be felled. To offset this impact, compensatory
afforestation programme through tree plantation, median plantation, horticulture and landscaping strategy has been prepared,
based upon the experiences of successful implementation of a number of ongoing and completed projects.
2. OBJECTIVE
The main objectives are as follows:
Climatic amelioration
Identification of the plantation stretches along with NHAI and or Supervision Consultant.
Planting of saplings in the nurseries during the construction period so that the saplings are a minimum 24 months old
Maintenance for three years including watering, removal of weed, litter and debris from the vicinity of the plantation.
Ensure the protection of the tree guards provided to the saplings from trampling and browsing by the cattle.
5. GUIDELINES FOR HORTICULTURE PLANTATION AND LANDSCAPING
5.1. General
5.1.1. Scope
Contractor to furnish all materials, labour and related items necessary to complete the work indicated on drawing and specified
herein.
Its name
The first row of plants along the highways will be of small to medium height plants planted at a spacing of 3m c/c and the
distance from the second row should be 3m. The second row should be in staggered. The distance from the toe of the
Flowering shrubs shall be planted in the median in rows as per width availability. Where the width is less than 1.5m grass
turfing is to be done. One row of plantation to be done at a spacing of 1.5m c/c.
For special landscaping, embankment slopes and ground cover, herbaceous species to be used. Turfing to be done by grass.
5.3. Tree Planting
5.3.1. Plants and Shrubs
Trees should be supplied with adequate protection as approved. After delivery, if planting is not to be carried out immediately,
balled plants should be placed back to back and the ball covered with sand to prevent drying out. Bare rooted plants can be
heeled in by placing the roots in prepared trench and covering them with earth, which should be watered into, avoid air pockets
round the roots and shrubs shall be planted with the approval of Site Supervision Engineer / Environmental Engineer.
5.3.2. Digging of Pits
Tree pits shall be dug a minimum of three weeks prior to backfilling. The pits shall be 120cms in diameter and 120cms deep.
While digging the pits, the topsoil up to a depth of 30cms may be kept aside, if found good (depending upon site conditions),
and mixed with the rest of the soil.
If the side of the below, it shall be replaced with the soil mixture as specified further herein. If the soil is normal it shall be mixed
with manure; river sand shall be added to the soil if it is heavy. The bottom of the pit shall be forked to break up the subsoil.
5.3.3. Back Filling
The soil back filled watered through end gently pressed down, a day previous to planting, to make sure that it may not further
settle down after planting. The soil shall be pressed down firmly by treading it down, leaving a shallow depression all -round for
watering.
5.3.4. Planting
No tree pits shall be dug until final tree position has been pegged out for approval. Care shall be taken that the plant sapling
when planted is not be buried deeper than in the nursery, or in the pot. Planting should not be carried out in waterlogged soil.
Plant trees at the original soil depth; soil marks on the stem is an indication of this and should be maintained on the finished
level, allowing for setting of the soil after planting. All plastic and other imperishable containers should be removed before
planting. Any broken or damage roots should be cut back to sound growth.
The bottom of the planting pit should be covered with 50mm to 75mm of soil. Bare roots should be spread evenly in the
planting pit; and small mound in the centre of the pits on which the roots are placed will aid on even spread. Soil should be
placed around the roots, gently shaking the tree to allow the soil particles to shift into the root system to ensure close contact
with all roots and prevent air pockets Back fill soil should be firmed as filling proceeds, layer by layer, care being taken to avoid
damaging the roots. The balance earth shall be filled in a mixture of 1:3 (1 part sludge to 3 part earth by volume) and 50gms
potash, (Mop) 50gms of Super Phosphate and 1 Kg. Neem oil cake. Aldrin or equivalent shall be applied every 15 days in a
mixture of 5ml in 5 litres of water.
5.3.5. Staking
Newly planted trees must be held firmly although not rigidly by staking to prevent a pocket forming around the stem and newly
formed fibrous roots being broken by mechanical pulling as the tree rocks.
The main methods of staking shall be:
A single vertical shake, 900mm longer than the clear stem of the tree, driven 600mm to 900mm into the soil.
Two stakes as above driven firmly on either side of the tree with a cross bar to which the stem is attached. Suitable for
bare- rooted or Ball material.
A single stake driven in at an angle at 45 degrees and leaning towards the prevailing wind, the stem just below the lowest
branch being attached to the stake. Suitable for small bare- rooted or Ball material
For plant material 3m to 4.5m high with a single stem a three- wire adjustable guy system may be used in exposed
situations.
The end of stake should be pointed and the lower 1 m to 1.2m should be coated with a non-injurious wood preservative
allowing at least 150mm above ground level.
5.3.6. Tying
Each tree should be firmly secured to the stake so as to prevent excessive movement. Abrasion must be avoided by using a
buffer, rubber or Hessian, between the tree and stake. The tree should be secured at a point just below its lowest branch, and
also just above ground level: normally two ties should be used for tree. These should be adjusted or replaced to allow for
Sludge or organic well-rotted dry farm yard manure: 0.05 cum or tussle.
Urea 25gm.
Carry out seed sowing before the onset of monsoon [May & June] so as to achieve the desired results. The watering of
the surface will be by tankers till the onset of the monsoon.
Ensure that a mulch of prepared and dried out herbs is laid over the whole seeded area after sowing, in a thin layer, so
that the grass is not affected by direct sunlight and transpiration loss.
The grasses recommended for are Cynodon dactylon, Cythoclinc purpurea, Solanum nigrum, Xanthium strumerium etc.
5.5.5. Maintenance
As soon as the grass is approximately a 3cm high it shall be rolled with a light wooden roller - in fine, dry weather - and when it
has grown to 5 to 8cms, above to ground weeds must be removed and regular cutting with the scythe and rolling must be
begun. A top-dressing of an ounce of guano to the square yard or well decomposed well broken sludge manure shall be
applied when the grass is sufficiently secure in the ground to bear the mowing machine, the blades must be raised an inch
above the normal level for the first two or three cuttings. That is to say, the grass should be cut so that it is from 4 to 5cms in
length, instead of the 3cm necessary for mature grass.
In the absence of rain, in the monsoon, the lawn shall be watered every ten days heavily, soaking the soil through to a depth of
at least 20cms. Damage failure or dying back of grass due to neglect of watering especially for seeding out of normal season
shall be the responsibility of the Landscaping Contractor. Any shrinkage below the specified levels during the contract or defect
liability period shall be rectified at the Landscaping Contractor's expense. The Landscaping Contractor is to exercise care in
the use of rotary cultivator and mowing machines to reduce to a minimum the hazards of flying stones and brickbats. All rotary
mowing machines are to be fitted with safety guards.
5.5.6. Rolling
A light roller shall be used periodically, taking care that the area is not too wet and sodden.
5.5.7. Edging
These shall be kept neat and must be cut regularly with the edging shears.
5.5.8. Fertilising
The area shall be fed once in a month with liquid manure prepared by dissolving 45gms of ammonium sulphate in 5 litres of
water.
5.5.9. Watering
Water shall be applied at least once in three days during dry weather. Watering whenever done should be thorough and should
wet the soil at least up to a depth of 20cms.
5.5.10. Weeding
Prior to regular mowing the Landscaping Contractor shall carefully remove rank and unsightly weeds.
5.6. Maintenance of Plants
5.6.1. Cultivating
The Contractor through the Landscaping Contractor shall maintain all planted areas within contract boundaries for one year
until the area is handed over in whole or in phases. Maintenance shall include replacement of dead plants, watering, weeding,
cultivating, control of insects, fungus and other diseases by means of spraying with an approved insecticide or fungicide,
pruning, and other horticulture operations necessary for proper growth of the plants and for keeping the sub-contract area neat
in appearance
5.6.2. Pruning and Repairs
Upon completion of planting work of the sub-contract all trees should be pruned and all injuries repaired where necessary. The
amount of pruning shall be limited to the necessary to remove dead or injured twigs and branches and to compensate for the
loss of roots and the result of the transplanting operations. Pruning shall be done in such a manner as not to change the
natural habit or special shape of trees.
5.6.3. Tree Guards and Protective Fencing
According to local environment, shrubs shall be protected adequately from vandalism until established. Where the tree guards
are necessary, care should be taken to ensure that they do not impede natural movement or restrict growth. The specifications
of the tree guard proposed are given below:
The tree guards shall normally be brick in urban and bamboo guards in rural and semi urban areas. The specifications of
the cement guards should be as per the relevant IS specification. In certain cases, if required by the IE Circular Iron Tree
Guard with Bars shall be provided. The specifications of such tree guard shall be as per relevant IS specification. The IE
Client: National Highways Authority of India Draft EIA Report
24
Consultant: Feedback Infra Pvt. Ltd July 2013
UNCONTROLLED IF PRINTED
Widening & upgradation of existing 2 - lane carriageway to 4 – lanes from km 307.810 to km 435.250 of Chamarajanagar to
Harohalli section of NH – 209 in the state of Karnataka
shall spell out in details about the cases where such exception shall be. In absence of any proper specification the
decision of the Supervision Engineer and or NHAI shall be binding.
5.7. Nursery Stack
Planting should be carried out as soon as possible after reaching the site. Where planting must be a necessity and / or be
delayed, care should be taken to protect the plants from pilfering or damage from people / animals. Plants with bare-roots
should be heeled-in as soon as received or otherwise protected from drying out, and others set closely together and protected
from the wind. If planting is to be delayed for more than a week, packaged plants should be unpacked, the bundles opened up
and each group of plants heeled in separately and clearly labelled. If for any reason the surface of the roots becomes dry th e
roots should be thoroughly soaked before planting.
5.8. Completion
On completion, the ground shall be formed over and left tidy.
6. SPECIAL CONDITIONS AND PARTICULAR SPECIFICATIONS.
Wherever applicable, work shall be done according to specifications in vogue, at the time of invitation of tender.
The Plantation area should avoid the stretches within the settlement area and the Ecological Sensitive area.
The stretches identified should be free from encumbrances and should not lead to impact on any private or community
asset. No fresh land acquisition shall be made under the project for the purpose of plantation.
Contractor through the Landscaping Contractor shall make his own arrangement for drawing water from there.
The work included in the schedule of Quantities includes grassing as well as planting of trees and shrubs. The quoted
rates shall include execution of these works at different levels and nothing extra shall be paid for any item, for working at
these levels
The Landscaping Contractor shall not be entitled to any compensation for any losses suffered by him and/or revision in
the rates originally quoted by him.
o On account unforeseen delay in commencing the work, whatever the cause of such delays is.
o On account of reduction in the scope of work.
o On account of suspension of work, or abandon after award of work.
The Contractor shall provide all facilities to Environmental Specialist / Project Engineer and / or his authorized
representatives to make frequent inspection of their Nursery and ascertain the process / quality of various categories of
trees / plants etc., grown by them.
The quote rate shall include the cost of transportation of tools and plants to and from the site, sales tax, excise duty,
octroi, etc. It shall be clearly understood that no claim for any extra payment on account of sales tax, excised duty, octroi
etc., shall be entertained after the opening of the tender.
The safe custody and up-keep of various categories of plants brought to site is the sole responsibility of the Contractor
and he shall employ sufficient supervisory personnel to ensure the safety of these items.
The site of work may be handed over to the Contractor in phases, as soon as the same are available and the Contractor
in turn shall work in these areas forthwith. Nothing extra shall be payable for such phased execution of work.
While excavating / executing the work the Contractor shall ensure that the existing cables / pipe lines / structures / fittings
are not damaged and if due to his negligence, these are damaged, the same shall be set right with no extra cost to the
clients.
The Contractor shall co-ordinate his work with other agencies employed by the Clients and ensure that the works of other
agencies are not hampered in any way during the duration of contract.
The Contractor shall keep the site of works neat and clean during the execution of the work. Any debris found at or near
the site of work shall be moved immediately as and when so required by the Environmental Specialist / Project Engineer.
On completion of the work, the site of work shall be thoroughly cleaned and all debris removed before the work is handed
over satisfactorily.
The Contractor shall, without any additional charge to the clients, renew or replace any dead or defective plants/grass for
a period of 12 months after the certified date of completion.
"General condition of contract and standard contract Forms of shall also form part of the contract.
Small trees and shrubs shall be well formed with the crown typical of the species or variety.
General requirements of plants
Plants shall be typical of their species and variety, well-developed branches, and well foliated with fibrous root system.
Plants shall be free from defects and injuries. Plants shall not be pruned before planting.
All trees, soon after planting, shall be properly supported with bamboo stocks to ensure their safety against winds or any
other factor, which may affect it adversely.
Protection of "tree to be preserved"
The Contractor through the Landscaping Contractor shall be responsible for the protection of tops, trunks and roots of
existing trees on site. Existing trees subject to the construction damage shall be boxed, fenced or otherwise protected
before any work is started.
General Requirements of Earth Manure and Fertilisers
EARTH: Good earth shall be agricultural soil of loamy texture, free from kankar, morrum, shingles, rocks, stones, building
rubbish and any other foreign matter. The earth shall be free from clods or lumps of sizes bigger than 50mm in any
direction. It shall have pH ranging in between 6.5 to 7.5.
MANURE: Manure shall be of well-decayed organic matter obtained in dry state from the Municipal dump or other similar
source approved by the Environmental Engineer/ Project Engineer. The manure shall be free from earth, stone or other
extraneous matter. Manure shall be supplied, at site well screened.
FERTILISER: If the soil tests indicate pH value not as per the above specification namely in between 6.5 to 7.5, following
measures need to be taken.
If pH exceeds 7.5, aluminium sulphate or equivalent fertilizer should be added at the rate of 1 kg per cubic metre to lower
the pH by one full point.
If pH is below 6.5, add ground limestone or equivalent fertilizer at the rate of 1 kg per cubic metre to raise pH by one full
point.
7. TEAM FOR THE ASSIGNMENT
The Contractor is free to recommend a team commensurate with the requirements of the project.
8. DATA TO BE PROVIDED BY THE CLIENT
Client will provide to the Contractor the map showing settlements and the forest areas
SITING
The contractor based on the following guidelines shall identify the location of the construction site. The construction site shall
be located:
The construction camps will be located at least 500 m away from habitations at identified sites. The living accommodation
and ancillary facilities for labour shall be erected and maintained to standards and scales approved by the resident
engineer.
On non agricultural lands, as far as possible
Not within 1000m of either side of locations of Forest areas.
All sites used for camps must be adequately drained. They must not be subject to periodic flooding, nor located within
300 feet of pools, sink holes or other surface collections of water unless such water surface can be subjected to mosquito
control measures.
The camps must be located such that the drainage from and through the camps will not endanger any domestic or public
water supply.
All sites must be graded, ditched and rendered free from depressions such that water may get stagnant and become a
nuisance.
(B) LAYOUT
A conceptual layout of a typical construction site has been presented in Figure A. The Contractor during the progress of work
will provide, erect and maintain necessary (temporary) living accommodation and ancillary facilities for labour to standards and
scales approved by the engineer. All temporary accommodation must be constructed and maintained in such a fashion that
uncontaminated water is available for drinking, cooking and washing. Safe drinking water should be provided to the dwellers of
the construction camps. Adequate washing and bathing places shall be provided, and kept in clean and drained condition.
Construction camps are to be sited away from vulnerable people and adequate health care is to be provided for the work force.
Sanitation Facilities: Construction camps shall be provided sanitary latrines and urinals. Sewerage drains should be provided
for the flow of used water outside the camp. Drains and ditches should be treated with bleaching powder on a regular basis.
The sewage system for the camp must be properly designed, built and operated so that no health hazard occurs and no
pollution to the air, ground or adjacent watercourses takes place. Compliance with the relevant legislation must be strictly
adhered to. Garbage bins must be provided in the camp and regularly emptied and the garbage disposed off in a hygienic
manner
Shelter at Workplace: At every workplace, there shall be provided free of cost, four suitable shelters, two for meals and two
others for rest, separately for use of men and women labourers. The height of shelter shall not be less than 3m from floor level
2
to lowest part of the roof. Sheds shall be kept clean and the space provided shall be on the basis of at least 0.5m per head.
Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers wherever it is
considered necessary. The contractor shall conform generally to sanitary requirements of local medical, health and municipal
authorities and at all times adopt such precautions as may be necessary to prevent soil pollution of the site.
First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of sterilized dressing
materials and appliances will be provided as per the Factory Rules. Workplaces remote and far away from regular hospitals
will have indoor health units with one bed for every 250 workers. Suitable transport will be provided to facilitate taking injured
and ill persons to the nearest hospital. At every workplace an ambulance room containing the prescribed equipment and
nursing staff will be provided.
Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities through
health centres temporarily set up for the construction camp. The health centre should have at least a doctor, nurses, duty staff,
medicines and minimum medical facilities to tackle first-aid requirements or minor accidental cases, linkage with nearest higher
order hospital to refer patients of major illnesses or critical cases.
The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart
from this, the health centre should provide with regular vaccinations required for children.
Day Crèche Facilities: At every construction site, provision of a day crèche shall be worked out so as to enable women to leave
behind their children. At construction sites where 20 or more women are ordinarily employed, there shall be provided at least a
hut for use of children under the age of 6 years belonging to such women. Huts shall not be constructed to a standard lower
than that of thatched roof, mud walls and floor with wooden planks spread over mud floor and covered with matting. Huts shall
be provided with suitable and sufficient openings for light and ventilation. There shall be adequate provision of sweepers to
keep the places clean. There shall be two maidservants (or aayas) in the satisfaction of local medical, health, municipal or
cantonment authorities. Where the number of women workers is more than 25 but less than 50, the contractor shall provide
with at least one hut and one maidservant to look after the children of women workers. Size of crèches shall vary according to
the number of women workers employed.
Extended to 25 only if
Colour, Hazen Above 5, consumer acceptance toxic substances, in
1 5 25 3025 (part4) 1983
Units, Max. decreases absence of alternate
sources.
Test to be conducted
3025 (part 8):
3 Taste Agreeable - - only after safety has
1984
been established
Mercury (as Hg) Beyond this the water becomes (See not mercury To be tested when
10 0.001 No relaxation
mg/1, Max. toxic ion analyses) pollution is suspected
Cadmium (as cd), Beyond this the water becomes To be tested when
11 0.01 No relaxation (See note)
mg/1, Max. toxic pollution is suspected
Selenium, (as Se). Beyond this the water becomes To be tested when
12 0.01 No relaxation 28 of 3025:1964
mg/1, Max. toxic pollution is suspected
Arsenic (As) mg/1, Beyond this the water becomes 3025 (part 37); To be tested when
13 0.05 No relaxation
Max. toxic 1988 pollution is suspected
Cyanide (as CN) Beyond this the water becomes 3025 (part 27) To be tested when
14 0.05 No relaxation
mg/1, Max. toxic 1988 pollution is suspected
Lead (as Pb), mg/1, Beyond this the water becomes To be tested when
15 0.05 No relaxation (See note)
Max. toxic pollution is suspected
Beyond this limit it can cause
Zinc (as Zn) mg/1, astringent taste and an To be tested when
16 5 15 39 of 3025:1964
Max. opalescence taste and an pollution is suspected
opalescence in water
Anionic detergents
Beyond this it can cause a light Methylene-blue To be tested when
17 (as MBAS) mg/1, 0.2 1
froth in water extraction method pollution is suspected
Max.
Chromium (as Cr6+) May be carcinogenic above this To be tested when
18 0.05 No relaxation 38 of 3025:1964
mg/1, Max. limit pollution is suspected
Poly nuclear
aromatic hydra May be carcinogenic above this
19 - - - -
carbons (as PAH) limit
mg/1, Max.
Beyond this limit undesirable Gas
Mineral oil mg/1,
20 0.01 taste and odour after chlorination 0.03 Chromatography -
Max.
take place. method
Pesticides mg/1,
21 Absent Toxic 0.001 - -
Max.
22 Radioactive material - - - 58 of 3025:1964 -
Alpha emitters bq/1,
23 - - 0.1 - -
Max.
Beta emitter pci/1,
24 - - 1 - -
Max.
Aluminium (as Al) Beyond this limit taste becomes
25 200 600 13 of 3025:1964 -
mg/1, Max. unpleasant
Aluminium (as Al) Cumulate effect is reported to
26 0.03 0.2 31 of 3025:1964 -
mg/1, Max. cause dementia