Professional Documents
Culture Documents
MANAGEMENT FRAMEWORK
September 2019
Contents
1. General ................................................................................................................................................ 2
1.1. Introduction ................................................................................................................................... 2
1.2. Key factors that affect the success of a Subcontracting ......................................................... 2
1.3. Practice of Subcontracting .......................................................................................................... 5
1.4. Objective of the Subcontracting Management Framework .................................................. 6
1.5. Scope and Goals ............................................................................................................................. 7
2. Overview of Subcontracting ............................................................................................................ 7
2.1. Why subcontracting?................................................................................................................... 7
2.2. Types of Subcontracting .............................................................................................................. 8
3. Subcontract Management ................................................................................................................ 8
3.1. Mandatory Subcontracting .......................................................................................................... 8
3.2. Time for Proposing Subcontractor .......................................................................................... 11
3.3. Evaluation criteria and Qualification Requirement ............................................................. 13
3.3.1. Selection Criteria ..................................................................................................................... 14
3.3.2. Selection Method ..................................................................................................................... 15
3.3.3. Multiple Awards ...................................................................................................................... 16
3.4. Employer Involvement on subcontracting............................................................................. 19
3.5. Standard Conditions of Contract for subcontracting ........................................................... 21
3.5.1. Approach to subcontract formulation:............................................................................. 22
4. Amendments recommended on the existing bidding document of the Main Contract ..... 28
5. General Remarks as a conclusion ................................................................................................ 29
6. Reference ............................................................................................................................................ 0
Table 1 Trend of Subcontracting in ERA road projects (raw data from September 2018)................. 5
Table 2 Selection Criteria at Pre-Qualification Stage ........................................................................... 34
Table 3 Selection Criteria at Pre-Contract Stage................................................................................... 35
Table 4 Selection criteria at construction stage...................................................................................... 35
Table 5 Selection of Subcontractor after Construction Stage .......................................................... 36
Page 1 of 106
1. General
1.1. Introduction
The primary goals of the subcontractor management framework are based on the subcontractors'
ability of management skills, technical expertise, and knowledge of contract administration in
comparison to project specific criteria, financial stability and current workload.
At the initial stage, the numbers of local contractors who can participate on the road construction
sector were very limited. To enhance the participation of local contractor in the road sector, the
government through the Ethiopian Roads Authority has implemented different initiatives and one
of the initiatives is development of local contractors through subcontracting. Even if
subcontracting has contributed a lot for the development of the industry and for equity allocation,
it is not properly handled and facing difficulties to achieve its objectives. These problems might
emerge both from the main contractor or the subcontractor. Some of the main issues are
discussed below as noted from study and literature reviews.
Page 2 of 106
1. Main Contractor related Issues
Basically the subcontract agreement is drafted by the Contractor and with this
opportunity; the contractor makes it more favorable for him rather than making it fair
for both parties. If a subcontract document is not well prepared and it doesn’t fairly
treat both particles, it will be burden for subcontractor instead of achieving its
objective.
There should be better subcontractor selection criteria, apart from the price.
According to Lavelle et al. (2007) the common criteria for subcontractor selection
should be Price, past performance, Health and safety record, Financial capability,
Current workload, Reputation, past relationships, Resources (both physical and
human), Technical/ managerial capability, Number of years the firm has been
working in the market, References, Location of firm, Appropriate insurance cover.
However, the contractor’s intention is to get a subcontractor with low price instead of
focusing on its compatibility for the assignment and it’s also done based on a personal
relationship with a subcontractor.
c. Subcontractor Management
2. Subcontractor related
A subcontractor with poor performance of works at project level could not meet
schedules and the quality standard. Subcontractors need to deploy the required
resources for the project according to their subcontract agreements. Sufficient skilled
labor need to be available on the subcontractor’s team. Substandard work of
Page 3 of 106
subcontractors is the main problem area as per the study conducted in Pakistan by
Choudhry et al. (2012).
3. Cooperation
a. Poor communication
b. Lack of teamwork
Stakeholders should work towards their common goal of executing project works as a
team. According to the study conducted by Mudzvokorwa (2017) in Zambia: lack of
cooperation, limited trust, and ineffective communication between the contractor and
the subcontractor are studied as the main causes of subcontracting problems.
c. Absence of Partnership
Page 4 of 106
1.3. Practice of Subcontracting
To achieve the benefits of subcontracting (from the Employer and the main Contractor point of
view) on construction projects, ERA has incorporated contractually binding subcontracting
clauses under its contracts for a minimum of 20% from the contract value at least for two local
subcontractors. However, subcontractors are engaged on very limited projects and even this
limited subcontracting is being implemented with improper manner like inappropriate selection
and approval process, unfairly drafted subcontract document which favor the main contractor,
lack of proper payment to the subcontractor, unpleasant management of the subcontractors and
so on. To the extreme, there might be no formal agreement between main contractor and
subcontractor at all. Besides, the subcontractors' failure to understand or not being fully aware of
the main contract also contributes for the failure of subcontracting.
The data collected from Contract Project Management Directorates shows that there is no
consistency and a single standard for selection of subcontractors. For instance, in laboronly
subcontracts, there is no formal contract. In addition, from sample of subcontract agreements, it
has been observed that important aspects of the contract such as workmanship standards, co
ordination and payment schedule has been undermined. The collected data has also confirmed
that the badly drafted subcontract document by the contractor has affected the subcontract
management and performance and this has been a reason of disputes between contractors and
subcontractors.
The following table shows the actual number and value of subcontract works under ERA projects
in comparison with the minimum expected number of subcontractors and value of subcontract
amount.
Table 1 Trend of Subcontracting in ERA road projects (raw data from September 2018)
Page 5 of 106
The data from the directorates shows that the practice of subcontracting at ERA is not only
minimal but also mainly dominated by laboronly works which are usually much lower in
amount than expected.
However, as mentioned herein there are no standard conditions in ERA to address the
subcontracting. This area necessarily needs focus so that the subcontractors may not suffer due to
the exacting contractual conditions imposed by the main contractor. Hence, in order to overcome
all these challenges, ERA definitely needs to produce subcontract management framework
standard conditions of subcontract keeping the benefit of all parties and considering important
documents like Ethiopian CIVIL Code, PPPA directives proclamation and other standard
conditions of contracts.
The main objective of this framework is to examine the current subcontracting management
practice and performance on ERA projects and design a framework for subcontract management
in lieu of capacity building, equity, and justice and transparency structure. More specifically the
study is expected to achieve the following objectives.
To provide standard selection criteria through a clear and transparent process in order to
ensure a fair competition among competitors involved in the subcontracting business.
To assist the capacity building of the local Subcontractors in the road construction sector in
a controlled and transparent manner with a clear pathway towards main contracting
capability;
To develop standard conditions of subcontract applicable for the subcontract works that
keep fair benefit of the contractor and the subcontractor.
Page 6 of 106
To make sure that local subcontractors are joining the road industry in a profoundly
manner.
To increase the contracting capacity of the main contractors and subcontractors especially
the local capacity of the home grown contractors in performance and contract
administration.
To make sure that equitable opportunities for all subcontractors are in place.
The framework will cover all subcontracting under ERA's Projects. The framework seeks to
provide as much guidance as is necessary through making a clear and transparent process in
selection of subcontractors in order to ensure a fair competition among competitors involved in
the construction business.
In general, the aim of the framework is to set a consistent standard for the selection and
management of subcontractors across ERA and thereby drive the behaviors required to operate to
the benefit of the contracting parties by ensuring value for money at every level.
2. Overview of Subcontracting
There may be different reasons for engagement of subcontractor beyond the basic objective of
this proposal to create compatible contractors in the industry and equity allocation among
citizens. To mention some:
Page 7 of 106
2.2. Types of Subcontracting
3. Subcontract Management
The aforementioned sections implies that due to the absence of standard rules and procedures for
selections of subcontractors, standard conditions of contract and other determinant requirements,
the industry didn’t achieve the expected result from the subcontracting instead; it is going down
and leading the subcontractors to be collapsed and affecting the quality of works. Therefore, it
needs rules and procedures and development of standard documents to make it healthy and
transparent keeping the interest of all the parties:
The sections bellow discuses about the rule and procedures, standard documents and other
determinant requirements to be practiced on the subcontracting under ERA projects with the
detail assessment and approach how those rules, procedures and standards are recommended.
To meet the intention of subcontracting for the development of the local construction industry
and for equity distribution among the citizens, it is not enough to depend on the subcontractors
proposed by the Contractors on its own intention; rather, there should be some mandatory
requirement which enforce the contractors to engage subcontractors on their projects. On the
current contracts, ERA has already introduced a mandatory subcontracting of 20% of the total
contract value for at least two domestic subcontractors contractors form the main components of
the road construction item to consider the subcontract work as experience for the subcontractors
Page 8 of 106
for participation on upcoming tenders. As mentioned in the earlier section, the already
introduced mandatory requirement is not also properly implemented due to different reasons.
One of the reasons is that Contractors are not interested to give subcontract from the main
component of the construction works like earth work, sub base, base, asphalt and other and there
is no proper management of subcontractors.
One of the reasons for the subcontracting is to increase the number of contractors in the road
sector. The contractor who could come to the road sector should fulfill the minimum
requirements requested for each project especially construction turnover and specific
construction experience. Therefore, contractors who are expected to be a sole or JV member
contractor through subcontracting should participate on an activities which should be consider as
specific experience for their future participation and it is the reason why recommended to
subcontract earthwork plus one structural layer which may be sub base, base course or asphalt
surfacing for the mandatory subcontracting. Except the earthwork, the structural layers are
optional and the contractor shall subcontract at least one of the structural layers plus the
earthwork. Furthermore, the contractor is at liberty to subcontract other elements of the works to
the same subcontractor in addition to the minimum requirements.
On the other the mandatory subcontracting may not be feasible on small sized projects due to the
following reasons.
The contractor can’t manage to buy heavy duty equipment like crusher plant, asphalt
plant and the like with the current higher cost of machineries keeping its cash flow if it is
forced to subcontract 20 % of the work from this amount.
The 20% mandatory requirement may be a smaller component from each item or it may
be total value of a single item. Therefore, subcontracting from the main component of the
works may be difficult because of the size of the main items.
The amount of subcontracting from such contract price is low and it doesn’t help the
subcontractor as experience in the future unless it is as considered for equity sharing.
Example:
For a project value of less than 500 million Birr, the 10% subcontract will be 50 million birr and
it is not sufficient to be considered as experience on any road construction projects under ERA.
In addition, it may be difficult to subcontract earthwork plus other structural layer of the road to
a subcontractor.
Therefore, taking in to consideration the aforementioned facts, the following is set as rules and
procedure are set on mandatory subcontracting for domestic subcontractors.
Page 9 of 106
A domestic bidder is one that meets the following criteria:
(ii) has more than 50 percent ownership by nationals of the country of the Employer ;
(iii) does not subcontract more than 10 percent of the Contract Price, excluding Provisional Sums,
to foreign contractors.
(i) individual member firms shall satisfy (a) (i) and (a) (ii) above;
(iii) The JV shall not subcontract more than 10 percent of the Contract Price, excluding Provisional
Sums, to foreign firms.
Mandatory
Main Contract Mandatory number Mandatory Items to be
I.No. %age to be
Project Value of subcontractors subcontracted
subcontracted
A Greater than or One subcontractor Minimum of earthwork
equal to ETB 1 for the 20% or two and one pavement
billion subcontractors each structural layer (sub
20%
for a minimum of base, base course,
10% asphalt or gravel
surfacing)
B less than ETB 1 One subcontractor Can subcontract any
billion and for the 20% or two components of the
greater than or 20% subcontractors each works as per the
equal to ETB for a minimum of contractor interest
500 million 10%
C less than ETB No mandatory N/A N/A
500 million Requirement
Page 10 of 106
3.2. Time for Proposing Subcontractor
The existing ERA’s standard bidding document has the following condition on engagement of
subcontractors.
Any subcontracting more than 10 % should be informed to the Employer during the
tendering stage
Any subcontracting need prior consent of the Engineer
The maximum amount of subcontracting is 40% of the contract price
There is 20% mandatory requirement of subcontracting (within the maximum 40%) for
two local subcontractors for capacity building and equity distribution purpose from main
component of the works
However, the actual practice of the subcontracting is not in line with the above conditions and
the following are facts of the existing subcontract management.
Contractors didn’t propose subcontractor for a value more than 10% of the contract price
during tendering stage
There is engagement of subcontractors without prior consent of the Engineer
Engagement of subcontractors for more than 40% of the contract price,
Contractors didn’t comply the mandatory requirement of 20% subcontracting for two
local contractors keeping the minimum mandatory requirements
No proper selection method and standard conditions of subcontract
The practice implies that allowing the contractor to propose subcontractor during the tendering
stage gives liberty for the contractor not to propose the mandatory subcontracting during
implementation stage time using the opportunity that the Employer will not be in a position to
terminate the contract or to take other contractual action because of the contractor inclination not
to propose a subcontract until the contractor is executing the works. Therefore, one of the options
is to enforce the contractor to propose the subcontractor during the tendering stage and makes it a
qualification requirement for the contractor. If qualification of the subcontractor couldn’t be a
requirement for qualification of the contractor, it leads to request for replacement during the
negation or implementation of the project and this leads to the already practiced enforcement
problem of subcontracting whatever condition we have in the contract document even as a
termination clause. Furthermore, selection of the subcontractor with the main contractor reduces
involvement of others in the selection process and it reduced any conflict of interest.
Given that ERA is administrating number of projects at a time, assessing the subcontractor
during the tendering stage will be an additional burden on the procurement process further to the
high workload. As a matter of solution the following two options were raised and discussed.
Page 11 of 106
1. to propose during contract negation before contract signing and
2. to propose before collecting the advance payment
However, those situations may delay the contract signing or affect execution of the project.
Therefore, it is advisable to be selective based on the value or other parameters for which the
selection of subcontractors to be carried out during the tendering stage with the main contractor.
Regarding Design and Build (DB) Projects, there is no design at the tendering stage and that
could be a difficult scenario for the contractor to propose subcontractor during the tendering
stage. Under such circumstances, it is better to allow the contractor to propose the subcontractor
during the projects implementation stage. However, for all the options of proposing
subcontractors during the project implication time, a binding clause should be set in the contract
for enforcement of subcontract at the right time.
Page 12 of 106
Project Time for Evaluati Remark
I.No. qualification
Value selection on
B less than At least Carried The Will be performance issue
ETB 1 During the out by subcontractor for tendering purpose for
billion projects the Criteria will not the main contractor and
and implementatio Engineer be part of the the contractor will be
greater n (The and to be tender document considered as non
than or contractor may reviewed but referred to performing for upcoming
equal to propose either by the the subcontractor tender if the contractor
ETB 500 during the Employer management couldn’t propose until half
million construction/i framework time of the original contact
mplementation The period
phase and/or subcontractor
during the should qualify
tendering the minimum
stage) requirement of
the framework
C less than N/A N/A N/A
ETB 500
million
Exceptions:
Subcontractors directly influence the success of a project and the overall reputation of the main
contractor in the eyes of Employer through the quality and timing of the work performed. As
the selection of qualified subcontractors stimulates the overall quality of projects, the
incorporation of value creation initiatives into the subcontractor selection model is paramount
to achieving success for both the project and future of the firm itself.
The selection process of subcontractors is also important because the nature of the main
contractorsubcontractor relationship is project based and therefore a proper selection and
management of subcontractors should be one of the key issues for contractors who want to
maintain good performance and reputation. It is equally important for ERA too to support local
subcontractors to provide an enabling environment in order to succeed in building their
performance and capacity.
Page 13 of 106
3.3.1. Selection Criteria
Advantage
o Good to prepare long list of subcontractors
o Consider performance of the contractor at different stages and with different
parameters
Disadvantage
o Has subjectivity
o May be barrier for new comers after the long list
o Less transparent
Though the two optional criteria has been identified and the performance based system is most
relevant for selection based on price, performance, quality, safety and environment; the formula
method is preferred taking into account that the disadvantages of the performance system are
most serious issues of procurement(subjective and less transparent) and the existing local
practice of selection of contractors is based on the formula method as released by the Public
Procurement and Property Administration Agency (PPPAA). However, for the future, ERA can
prepare long list of subcontractor or invite interested contractors to upload their data on ERA
website for subcontract works and ERA can do detail assessment and ranking of contractors
interested to work as subcontractors based on performance based procedure. Accordingly, and
contractors as well as a newly coming contractor can easily get the available subcontractors list
from abroad or anyone from ERA website.
Page 14 of 106
For the purpose of this framework, the formula is derived based on the Public Procurement and
Property Administration Agency (PPPAA) criteria framework to keep the consistency and
awareness of the contractors.
The basic intention of the mandatory subcontracting is to capacitate the road sector with number
of local contractors to meet the demand and for equity distribution. Therefore, with this
intention, it is not reasonable to request experience from the subcontractor especially specific
experience related to the works. On the other hand, giving this opportunity of high value
subcontracting for any subcontractor with no exposure of the construction sector is not also
recommended as it may affect the quality and performance of the works. Therefore, there should
be some basic criteria for the selection process. Accordingly, it is proposed to have General
Experience (years in the industry and annual construction turnover) and legality as requirement.
Annual turnover: the amount of the construction works handled by a subcontractor indicates
the subcontractor capacity how much work he can accommodate at a time. Even if this
requirement has a nature of capacity criteria and not considered in some countries subcontracting
procedure, it is considered for this framework as it is not specific to the road works and it
guardant the Contractor and the Employer to some level on performance and quality of the
subcontractor. The detailed criteria are shown in table 5 below.
The mandatory subcontracting is on items for which the contractor has already provided its rate
and responsible for any loss or gain with respect to its offer. In addition to enforcing the
mandatory subcontracting on the contractor’s offer, it is not fair to dictate the contractor to select
the subcontractor through open tendering or other recommended method of selection. If ERA has
an intention to make it transparent through open tendering or other procedure, the works to be
subcontracted need to be a Provisional Sum (PS) item and the selection could be done as
nominated or selected subcontractor following the government tendering procedure (Equal
opportunity for all subcontractors). For that reason what ERA can do on the mandatory
requirement is developing a standard requirement, standard conditions of contract and having
some level of involvement and regulatory action from the selection time until the execution of
the mandatory subcontracting as this framework discussed about.
However, for nominated subcontracting and for subcontractor to be assigned for other
Provisional Sum (PS) amount of the contract document, ERA can apply open tendering or other
procedure following the government tendering procedure (Equal opportunity for all
Page 15 of 106
subcontractors). On the other hand, selection of both nominated subcontractor and for other PS
amounts of the contract document will be addition burden for ERA further to the existing
workload. Therefore, the following procedures are recommended for selection of nominated
subcontractor and subcontractor for the PS amount.
Table 4: Rules and Procedures for selection of nominated subcontractor and subcontractor
for other PS amounts
Selection of the subcontractor is based on the interest of the main contractor since it is on his
own rate and therefore the contractor has the opportunity of proposing his friend and relatives. If
ERA has an intention to make it transparent through open tendering or other procedure, the
works to be subcontracted need to be a PS item and the selection could be done as nominated or
selected subcontractor following the government tendering procedure (Equal opportunity for all
subcontractors). Otherwise, it is the main contractor's right in choosing his subcontractor as long
as the subcontractor meets the minimum qualification requirement & evaluation criteria of this
framework.
With this approach what ERA can do is developing standards and regulates the subcontracting
not to be monopolized by few bidders and reduced the impact of interference or reduces conflict
of interest by any of the contracting parties. One of the mechanisms is to select the subcontractor
during the tendering stage with the main contractor, which is well discussed under the above
sections of this framework. The second most important mechanism is to limit the number of
Page 16 of 106
subcontract projects awarded to single bidder taking in to account it impact on the
subcontractors’ future and their capacity.
As per the PPPAA qualification and evaluation criteria framework of contractors, contractors can
be qualified for a tender by summing up two or three projects as specific construction
experience depending on the value of the construction works. For a project value of less than
ETB 1 Billion, one or two projects will be considered as specific experience. To be qualified for
a project value of ETB 1 billion; a bidder need to have one project with value of ETB 700
million or two projects each with a value of ETB 350 million.
Sub-Contractor
Criteria Requirement Compliance as Single
Entity
I. Certificate of Registration from Ministry of Must meet requirement
Urban Development and Construction
1. Legal Status
[grade and category of contractor should be as
per the requirement of the Directive related to
the subcontract amount]
Page 17 of 106
Sub-Contractor
Criteria Requirement Compliance as Single
Entity
for submission of the bids, and VAT
Registration Certificate; and
Must meet requirement
IV. Registration as supplier in the list of the
mandated public body, i.e. Public Procurement
and Property Administration Agency (PPPAA).
2.History of Non If ERA found Non-performance or Poor Performance Must meet requirement
Performing history of a Sub Contractor at any stage of the
Contracts tendering process, the SubContractor will not be
accepted and the bidder will be required to replace with
competent Subcontractor that fulfills the minimum
requirement specified in the bidding document.
F=0.5
Eg. For three years and 1 Billion Birr main contract, 10%
subcontracting, the required peak turnover requested
for the subcontractor is ETB 16.6 Million ETB, which
seems reasonable.
Page 18 of 106
Sub-Contractor
Criteria Requirement Compliance as Single
Entity
6. Multiple Award Maximum of subcontract projects with a total value
of ETB 700 Million are recommended for a
Must meet requirement
subcontractor to handle at a time from the
mandatory subcontracts. A Project at hand could be
considered as complete when its progress reaches
80% and the subcontractor can go for other project
keeping the maximum value of subcontracting on
the mandatory subcontracts.
Applicability of the Criteria:
The Employer, while negotiating the main contract with the contractor, want to make sure that
the main contractor will meet the performance requirements set out in the main contract. The
main intention of engaging a mandatory subcontractor is to develop the local industry on the
road sector and to meet the equity requirement without affecting the expected performance of the
works.
From the sample subcontracts on ERA projects, it has been observed that the subcontract
agreement was extremely unfair. Important aspects of the contract such as scope of work, care
and diligence of work, approval of work, performance and payment guarantee, taxes, insurance,
Page 19 of 106
permits and licenses, extra work, time and completion, defaults and termination, guarantee of
work, environmental and safety, way of solving disputes and etc has been undermined.
An effective contract with a subcontractor can save contractors a tremendous amount of time,
money and frustration. Unfortunately, far too often dealings with subcontractors are handled
informally and, as a result, exposing the contractor and the client in profoundly complicated
contractual implication situations. It is believed that fair and ethical treatment of subcontractors’
means having prompt payment practices, unbiased project supervision, and quality scheduling.
This has proven to be mutually beneficial to the contractor, subcontractor and the Employer.
Subcontractors should read the subcontract and the main contract agreement and assure specifics
to protect themselves from unfair risk.
As such, from the current adverse relation between the contractor and subcontractor, Employer
should go one step to the subcontract management to protect the subcontractor as well as the
works. This doesn’t mean that the Employer should have over involvement on the subcontract
management but the Employer need to have involvement on very few issues which have serious
impact on the subcontractors, otherwise; the Employer itself will sink in the cases and conflicts
of the contractor and the subcontractor. In addition to the very limited engagement of the
Employer, the Employer can attain healthiness of the industry using its regulatory power.
Table 6: Rule and procedures on Employer and Engineer contractual involvement and
regulatory action on subcontracting
Employer
The Engineer
contractual involvement regulatory power
To pay subcontractors Any subcontracting more than Review of subcontract
direct upon the 10 % should be informed to the selection and draft
certification of the employer during the tendering subcontract document based
Engineer, when the stage on the subcontract
Contractor has failed to The maximum amount of management framework
pay after collecting the subcontract should be 40% Any amount of subcontract
respective payment from Appointment of Nominated should get prior consent of
the Employer or to pay subcontractors and the Engineer except the
directly to the subcontractors of other PS following exclusions:
subcontractor as per the amounts (FIDIC sub clause 4.1)
subcontract agreement Giving approval on the selection
and assignment of the process and on the draft contract (a) the provision of labour,
Page 20 of 106
Employer
The Engineer
contractual involvement regulatory power
main contractor document of subcontracts (b) the purchase of materials
Taking contractual amounting > 5 % of the main which are in accordance
action for not or late contract price with the standards
deployment of Giving consent on the selection specified in the Contract,
mandatory process and on the draft contract or
subcontracting, document of subcontracts (c) the subcontracting of any
assignment of amounting < 5 % of the main part of the Works for
subcontractor without contract price which the Subcontractor
prior consent/Approval Evaluation of subcontractors is named in the Contract.
of the Employer and on during tendering stage with the
subcontracting of the Main contractor The Engineer shall have full
works beyond 40% of Control workload of control of the contractor’s
the contract price Subcontractors action on site in relation of
Drafting the standard conditions the involvement of
of subcontract subcontractor
Ascertain Provision of Quarry
sites and borrow areas to the
subcontractors by the main
contractor
Ascertain Subcontractors’
knowledge of the main contract
Ascertain Access of the
Subcontractor to the site
Ascertain provision of access,
quarry site and the main contract
document to the subcontractor
The main failure for subcontractor and subcontracting is lack of proper Conditions of
Subcontract. The existing conditions are drafted by the Contractor which:
Page 21 of 106
From the sample subcontracts on ERA projects, it has been observed that the subcontract
agreement was extremely unfair. Important aspects of the contract such as scope of work, care
and diligence of work, approval of work, performance and payment guarantee, taxes, insurance,
permits and licenses, extra work, time and completion, defaults and termination, guarantee of
work, environmental and safety, way of solving disputes and etc has been undermined.
From the main contractor’s perspective, it will be important that the terms of the main contract
are reflected in, or stepped down to, the subcontract. This avoids ‘gaps’ in the main
contractor’s obligations under the main contract and the subcontractor’s obligations under the
subcontract. Any gaps are likely to mean liability sitting with the main contractor (full
responsibility relies on the main contractor in fulfilling its obligations as per the main contract).
There is no fixed approach to subcontracting, and different approaches have their advantages
and disadvantage:
There are many different standard forms of subcontract which are recognized in the
construction industry. These seek to provide an “off the shelf” contract for the parties to
use:
The main advantage of using this method is avoiding the need to draft the subcontract
from scratch and hopefully saving time negotiating it. Standard forms can also be useful
if the same parties are involved on repeat projects:
The main disadvantages are:
They will not reflect projectspecific risks or unusual provisions in the main
contract;
They will usually be drafted to benefit one party more than the other. It is
important to remember that it will still be necessary to review the subcontract
and it is possible that amendments will be needed:
Some obligations cannot be stepped down to the subcontract:
The same standard form will not suit all subcontractors on all projects, and
should be reviewed regularly to ensure that changes in the law and lessons learned
on previous projects can be taken into account.
Page 22 of 106
Option -2 Incorporating the terms of the main contract by reference in to a framework
contract:
This is commonly a short subcontract obliging the subcontractor to identify and comply
with the relevant terms of the main contract:
Advantages of using this method are:
There is no need to amend or redraft the subcontract if changes are made to the
main contract, as these changes will simply be incorporated by reference;
Any issues caused by having to crossreference between the two documents will be
reduced or eliminated;
This method also encourages the subcontractor to focus on and carry out a proper review
of the provisions of the actual main contract;
The main disadvantages are;
The risk that the subcontractor will not identify everything and creating ‘gaps’
between the main contract and subcontract (see above);
Having to determine the contractual effect of main contract terms if these are not
clearly drafted – it is not always clear how certain terms would have been stepped
down to the subcontract;
Some terms are only relevant to the main contract and should not be stepped
down to the subcontract. This could lead to ambiguities and disputes about
whether or not the subcontractor should or should not have done something;
Certain clauses which are unique to the subcontract will still need to be drafted
In line of the above and to make the subcontracting agreement fair across the road
construction industry, this framework has design a subcontract agreement document based on
option 1 to be used across ERA road projects. The standard subcontract agreement document
contains General conditions of subcontract with the corresponding particular conditions of
contract and appendix to bid to reflect the project specific issues. Furthermore it contains
Page 23 of 106
forms of offer and agreement for the subcontract works. The standard sub contract document
is prepared for all works subcontracts except specialized subcontracting like geotechnical
investigation and material production.
The Standard subcontract document is prepared for ERA Projects based on the following
standard documents, directives and proclamations to be bounded under the procurement
regulations:
General conditions of contracts are those that apply to all types of contracts. They are generally
based on the conditions that have been formulated in light of provisions of FIDIC, while.
Particular/Special conditions are a tool to amend the clauses of general conditions of contract as
per the requirement of a specific project. These conditions of contract should only be a mean to
address the specifics of the project and the fundamentals of general conditions of contract
including the risk allocation.
As such, from the current adverse relation between the contractors, subcontractor, Employer and
supervision consultant, the following contractual relationships has been emphasized in designing
subcontract contract agreement.
The subcontractor shall be deemed to have full knowledge of the main contract less details of
the main Contractor's price [subcontractors Right].
The importance of the Subcontract being read together with the applicable Main Contract,
putting in mind that the main contract and subcontract are independent contract documents.
The payment terms of the subcontract includes "paywhenpaid" clauses. This “paywhen
paid” provision applies both when the amounts are not certified by the Engineer under the
Page 24 of 106
Main Contract and when they are not paid by the Employer. When the amounts are not
certified, the Contractor is, however, prevented from relying on this failure if it was due to his
act or default. In addition, where payment has not been made by the Employer, the Contractor
takes the risk for Employer insolvency, with the insolvency of the Employer not being a
ground for the Contractor withholding payment.
With respect to the payment for works executed by the subcontractor, the following risks were
identified:
a) Non-certification risk: This is related with the power of the Engineer under the main
contract. The Engineer is the one, under main contract, to certify payment to the Employer.
This certification process is conducted by the Engineer after the monthly statements
[including the subcontract works executed by the subcontractor] submitted to the Engineer by
main contractor, under the procedure established under main contract. In such case, the non
certification risk can be happened, when the Engineer being late in certifying the main
contractor's monthly statement or when the Engineer is no certifying the monthly statement
of the main contractor in whole or in part. The reason for noncertification may or may not
relate to the subcontractor. The risk, however, is shared by the subcontractor in question.
b) Non-payment risk by the Employer: This may arise from the side of the Employer. Any
certified payment has to be paid by the Employer to the main contractor under the main
contract. The Employer might be late in paying the certified amount or refuse to paying the
certified amounts in full or in part; due to disagreement with the Engineer's certification or
inability to pay the certified amounts by reason of its financial difficulty, insolvency,
bankruptcy or bad faith. What so ever is the reason for any late payment and/or inability to
pay on part of the Employer may not have any connections with the subcontractor. However,
the subcontractor shares such kind of nonpayment risk under its subcontract.
c) Non-payment risk form the main contractor: which may arise from the side of the main
contractor [even if paid by the Employer] under the subcontract. This may be the case, if a
dispute between the subcontractor and the main contractor arises, or if the main contractor
suffers financial difficulty, insolvency, bankruptcy, or is in bad faith. Having noted all the
possible risks, the subcontract condition of contract have been prepared to cover the possible
risks as much as possible. For instance, as long as the subcontractor make to the Engineer
that it has not been paid in accordance the payment terms of the subcontract, the Engineer
can make a determination the main contractor is not in compliance with the subcontract and
promptly advise the Employer to effect the payment for the subcontractor after deducting
from the main contractor's certified amount as appropriate.
The subcontractor is entitled to the payment of interest, where the Employer has failed to pay
any amount the Engineer has certified or the main contractor has failed to pay any amount
Page 25 of 106
that is due and payable to the subcontractor, the main contractor will be liable to interest on
the overdue amount at the rate payable by the Employer to the main contractor under the
main contract.
The Main contractor shall upon receiving a written notice of claim for interest from the
subcontractor, pay interest to the subcontractor at the rate payable by the Employer to the
main contractor under the main contract.
The main contractor shall, from time to time, make available to the Subcontractors much of
the Site and such access Provision of quarry sites and borrow areas shall also be the
obligation of the main contractor.
The Subcontractor shall permit the Contractor, the Engineer, and any other authorized person
to have reasonable access to the Site.
The subcontractor shall indemnify the main contractor against any damages arising from the
misuse by the subcontractor, his agents, servants, or workmen, of the temporary works,
equipment and other facilities.
The general conditions of the subcontract contain no clause on liquidated Damages, since the
financial consequences of a subcontractor's delay are often unpredictable. However, a general
breach of the subcontract provision on the general conditions of the subcontract is included
under the provision of subclause 4.4 "possible effects of subcontract's breaches of
subcontract", which deals with breaches by the subcontractor of the subcontract that cause
damage to the main contract under the main contract. If the subcontract commits any
breaches of the subcontract, he shall indemnify the contract against any damage.
Page 26 of 106
of termination of the subcontract, the contractor should inform the Engineers as well as the
Employer in writing by stating the ground for termination.
The Subcontract contains quite standard provisions on termination with the Contractor
having the right to terminate whenever the Main Contract is terminated, but with the perhaps
notsostandard entitlement of the Subcontractor to both costs and loss of profit. It is the right
of the main contractor to terminate the subcontract by notice upon termination of the main
contract.
The main contractor has a right to terminate the subcontractor on notice in relation to the
time, quality and other breaches or defaults of the subcontractor. Grounds for termination can
be: Bankruptcy or insolvency; Repudiation of the subcontract; Failure to commence or
proceed with the subcontract; Failure to commence or proceed with the subcontract; Failure
to remove defective materials or remedying defective works; Neglecting to comply with any
of its obligations under the subcontract; Removal of the site as per the request of the
Engineer.
The Subcontract contains its own dispute resolution procedures as stated in the conditions of
subcontract.
If a dispute of any kind arises, the main contractor and the subcontractor are recommended
attempting amicable settlement before they submit their respective claims against the other,
to arbitration or other dispute settlement procedure. However, any dispute arising between
the contractor and the subcontractor and the agreed dispute settlement procedure shall not
have any impact or implication on execution or any other activities of the main contract.
Accordingly the subcontract agreement should obey the rights and obligations of the main
contract.
For Disputes arising between both Locals (main contractor and Subcontractor) or
Foreign and Local (main contractor and subcontractor):
If not been settled amicably within the time stipulated in the subcontract, then the case
can be referred to an adjudicator.
Page 27 of 106
If not again settled by adjudicator, then the case can be referred to the Federal Court of
Ethiopia or local Arbitration for its final settlement as the parties agreed.
For Disputes arising between foreign main contractor and foreign subcontractor:
If the dispute is not settled amicably, then the case may be referred to adjudicator(s), or
DRE or DRB.
If any of adjudicator(s), DRE or DRB has not become final and binding, and then the
dispute will be settled by Arbitration under the rules of Arbitration as to be agreed by
both parties.
The main contractor shall give extension of time (EOT) to the subcontractor due to:
EOT under the main contract (not more than given under main contract to the main
contractor. It is main Contractor's obligation to notify such case to subcontractor.
Instruction given by the main contractor even if Main Contractor may not be entitled for
EOT in relation to this instruction under the main Contract
Breach of the subcontract by the main contractor
The subcontractor shall submit to the main contractor notice of circumstances and detailed
particulars to justify the EOT. Interim EOT may also be granted to the subcontractor in case
of an event has a continuing effect as stated in the subcontract conditions.
In line with the preparation of the subcontract management framework, some amendments
are also required on the main contract document to meet the BacktoBack applications and
to reflect the Contractor obligation and the Employer right on subcontracting. Accordingly,
amendments are carried out on the following section of the main contract document/bidding
document.
Page 28 of 106
Amendment on bidding forms (additional & amendment)
Amendment on Appendix to Bid (items to be subcontracted)
Amendment on Conditions of Contract (protection and support)
Page 29 of 106
The subcontractor is obliged, under the subcontract, to commence, proceed and complete the
subcontract works, as stated in the subcontract agreement. Executing and completing the
subcontract works and remedying any defects therein shall be an obligation of the
subcontractor.
The subcontractor might be entitled to an extension of time
Making the main contract [less the details of the main contractor's prices] available for
inspection for subcontractor up on request shall be the obligation of the main contractor.
Availing site to subcontractor including permission to have access to site is obligation of the
main contractor. The Subcontractor shall also permit the main contractor, Engineer,
Employer, and any other person to have an access to the subcontract works or materials on
the site where any work or materials are executed, prepared or stored.
Subcontractor shall make variations of the subcontract works, as may be instructed by the
main contractor and/ or as may be instructed by the Engineer ( provided such variation
instruction of the Engineer be notified and confirmed by the main contractor)
Giving Notices, consents, approvals, certificates, confirmations & determinations all in
writing [Obligations of both the main contractor & subcontractor]
Instructing the subcontractor in writing [Main contractor’s obligation]
Obligation of the main contractor as stated in both main contract and sub contract
Subcontractor’s General Responsibility & its obligations as stated in subcontract
The Subcontract contains its own dispute resolution procedures as stated in the conditions of
subcontract.
The following factors would be useful in decision making for domestic subcontractor selection.
ERA should enforce the main contractor’s to sublet some portion works as per the works
contract agreement.
All Directorates of ERA especially Construction Management Directorates [CPMD] shall use
this frame work in consultation with their project consultants on selection of subcontractors
by contractors.
Price should not be taken as a major selection factor. Experienced and financially stable
subcontractors should have good chances of winning tenders more than those who attract
contractors’ attention by lowering tender prices or giving discounts.
Past performance of subcontractor’s through delivery of good quality work, should secure
subcontractors a place in the selection process.
Contractor should have a willing to work with subcontractors who can carry their work
professionally and confidently.
Page 30 of 106
Appendix A - Standard Subcontract Document
Page 31 of 106
Annex –1 Performance based selection criteria
Page 32 of 106
Annex -1: Performance based selection process [Prequalification process]
Even though it is easy for ERA to make sure that the enforcement is implemented as soon as
possible, the unmethodical selection of subcontractors by the contractor is very complex,
widespread, leading to poor performance of subcontractors (quality and execution problems). It
is therefore imperative that a certain selection criteria framework be developed in the interest of
ERA’s policy (building performance of subcontractors) and road construction industry.
However, on the other hand, a selection process which emphasis price (lowest bidder) can easily
ignore competent subcontractors in the selection process. A lower tender price does not equate to
competency nor does it guarantee good performance and therefore other factors should be taken
into consideration. Haksever et al, 1995, Kerfoot, 1994, Latham, 1994 and Oluwoyee et al (1996)
recommended that when the contractor is rating subcontractors, account should be made for the
ability of the subcontractor to meet the following criteria
Those factors are identified at different stages of the construction process, such as pricing,
financial, technical and managerial ability. The stages are:
1. Prequalification stage
2. Precontract stage(negotiation and on boarding)
3. Construction stage (management and performance Monitoring)
4. Post construction stage(Exit or Subcontract closure)
Page 33 of 106
1. Pre-Qualification Stage
This is the starting point of the process to evaluate whether the subcontractor may be short listed.
Technical and managerial competency, workforce skills, mobilization ability to site, competitive
rates, past records, work and financial capacity are among the factors. A demonstration by
subcontractors that they have adequate capacity may land them on the shortlist. The factors
should be adequately met by domestic subcontractor to ensure selection and could be used in the
framework to eliminate unsuitable domestic subcontractors.
Levels of influence: very influential = VI(5), Influential = I(4), Somewhat Influential= SI(3), Less Influential= LI(2)
and Not Influential= NI(1), TR= Total Response, MR= Mean Rate
Contractor’s needs from subcontractor’s at the prequalification Level of influence in TR MR Rank
stage the selection process
VI I SI LI NI
5 4 3 2 1
Legal Status of the SubContractor Business license
Article of
association/memorandum
of understanding
Power of attorney
Relevant professional
practice certificate issued
by ministry of
construction, association
and etc.
Technical and managerial competence and experience in the job at
hand
Size and resources: skills, experience and strength of own
workforce
Current workload, commitment and ability to mobilize on site when
needed
Competitive rates and lowest tender overall
Past records of working relationship with current contractor and/ or
reference from previous employers and financiers
Ability to provide own attendance needs: possession of special tools
and equipment that could reduce main contractor’s P&G costs
Financial capacity to undertake the job successfully
Compliance with statutory regulations: gender equality, workman’s
compensation act, tax regulation
Health and safety record
Location of the subcontractor and knowledge of the project
environment: local labour laws, site condition, material supplies, etc
Experience with the present contract form, terms and conditions
Page 34 of 106
2. Pre-Contract Stage(Negotiation and On-Boarding)
Before the contract is signed, the contractor needs to be sure of certain requirements. At pre
contract stage, it can be seen that the efficiency of the domestic subcontractor’s programing and
readiness to mobilize on site are influential. However, bond provisions and discounts are
relatively not viewed as influential. It can be seen from table 3 that at this stage, the contractor is
focusing more on how the subcontractor would be able to be in congruent with the overall
objectives as set by contractor and reflected in project main work programe.
Levels of influence: very influential = VI(5), Influential = I(4), Somewhat Influential= SI(3), Less Influential= LI(2)
and Not Influential= NI(1), TR= Total Response, MR= Mean Rate
Contractor’s needs from subcontractor’s at the precontract stage Level of influence in TR MR Rank
the selection process
VI I SI LI NI
5 4 3 2 1
Efficient programming of subcontract work and proper fit with
main contractor’s main work program for efficient coordination
purpose
Readiness to mobilize on site on schedule
Ability to submit error and omission on free bids that are reasonable
and comparable
Wellarticulated health and safety and environmental plan
Provision of necessary bonds or specific insurance requirements
Reasonable rates and discounts
The Construction stage is the stage at which the Contractor and subcontractor interact the most.
At this point they have already entered into an agreement and are carrying out work and if any
part is doing the contrary, consequences might lead to conflicts. Thus, for both contractors and
subcontractors the stage of the actual carrying out of the project is every influential. It is not a
surprise that all the requirement in this stage are viewed as very influential, notably quality, time,
and productivity as shown in Table 4 below:
Levels of influence: very influential = VI(5), Influential = I(4), Somewhat Influential= SI(3), Less Influential=
LI(2) and Not Influential= NI(1), TR= Total Response, MR= Mean Rate
Contractor’s needs from subcontractor’s at construction stage Level of influence in TR MR Ran
Page 35 of 106
the selection process k
VI I SI LI NI
5 4 3 2 1
Good quality of work consistent with general quality level of the
main job
Time performance
High productivity level
Good control of own workforce
Good working relations with main contractor’s team: good
tolerance, loyalty and minimum adversarial relation
Efficient management of own workforce
Scope management ability to manage changes without
unnecessary claims
Zero or minimal defects and rework
Compliance with specification for materials and methods
The domestic subcontractor’s ability to work quality works and complete maintain defects, the
offer of services within the defects liability period and keeping the site tidy are influential as
shown in Table 5. This means that what domestic subcontractors would do even after they have
carried out the actual construction work in terms of the agreement with the contractor has
influence on subsequent selection of the subcontractor for subsequent projects.
Levels of influence: very influential = VI(5), Influential = I(4), Somewhat Influential= SI(3), Less Influential= LI(2)
and Not Influential= NI(1), TR= Total Response, MR= Mean Rate
Contractor’s needs from subcontractor’s after construction stage Level of influence in TR MR Rank
the selection process
VI I SI LI NI
5 4 3 2 1
Efficient and quick maintenance of defects
Zero defects within and beyond defects liability period
Readiness to partner with main Contractor on future jobs
Ability to be patient to be paid when the Contractor is paid
Provision of maintenance manual (such as built drawings) if needed
Quick disbandment from site on practical completion
Page 36 of 106
Page 37 of 106
Annex –2 Amendments on the Main Contract Document
Page 38 of 106
Requirement for the Main Contractor
1.4 Proposal for a) Any proposals for subcontracting elements of the works such Has to meet Has to meet N/A N/A Qualification and
subcontracting that the total of Subcontracting is at least 10 percent of the requirement requirement bid Submission
Bid Price; and Sheets
b) The Contractors shall propose two domestic Subcontractors
with a minimum of 10% of the contract price for each Must meet
subcontractor or one subcontractor with a minimum of 20% requirement
of the contract price who have any kind of projects with ERA Must meet
within a maximum total amount ETB 1 Billion Birr [grade [for 2012 EFY, requirement Qualification and
and category of contractor should be as per the requirement until advance bid Submission
of the Directive relative to the subcontract amount]; N/A N/A
collection and Sheets
precondition
c) The proposed Subcontractors will be evaluated and shall for advance
fulfill the requirements for subcontractors listed under this collection]
section of the bidding document
d) Detail proposals for subcontracting any highly specialized
elements of the Works to named specialist subcontractors; Must meet
requirement
The sub
contractors’
Has to meet qualification
requirement documents
enclosed with
Chida – Sodo Road Upgrading Project 12 - 2
Must meet the contractors
requirement application
N/A N/A
Has to meet
requirement
N/A N/A
Bidding Documents
Amendment of forms
Bidding Documents
QUALIFICATION SUBMISSION SHEET
Date: _____________________
To: ___________________________________________________________________
We, the undersigned, apply to be qualified for the referenced --------------------Road Project and declare
that:
(a) we, including any subcontractors or suppliers for any part of the contract subject to this
qualification do not have any conflict of interest, in accordance with ITB Sub-Clause 3.1 (b) of the
Bidding document
(b) we are not a publicly owned entity, and if we are, we meet the requirements of ITB Sub-Clause
3.3 of the Bidding document
(c) we, in accordance with, Section XII, Qualification Criteria, Sub-Factor 1.4 plan to subcontract the
following elements of the works:
_____________________
_____________________
(d) we, in accordance with, Section XII, Qualification Criteria, Sub-Factor 1.4 plan to subcontract two
subcontractors with a minimum of 10 % of the contract price for each or one subcontractor with
a minimum of 20 % of the contract price to the following subcontractors from the activities
listed under item (C) above:
_____________________
_____________________
_____________________
(e) We, in accordance with, Section II, Instructions to Bidders, Clause 4, plan to procure Materials,
Plant, Supplies, Equipment, and Services from eligible sources as follows:
_____________________
_____________________
_____________________
(f) we agree to abide by this bid until the date 120 days from the date of bid submission specified in
the Bidding Data and it shall remain binding upon us and may be accepted at any time before
that date.
Signed _______________________________
Address ________________________________________________________________
________________________________________________________________
Bidding Documents
FORM QUA – 1.2
Date: _____________________
Bidding Documents
FORM FIN – 3.1(B) (II)
FINANCIAL SITUATION
(A) SUMMARY SHEET: CURRENT CONTRACT COMMITMENTS / WORKS IN PROGRESS
Average monthly
Value of Estimated
Name of Employer, contact invoicing over last six
outstanding work Completion
contract address/Tele/fax months
(ETB) date
(ETB/month)
1.
2.
3.
4.
5.
etc.
N.B: Information related to value of outstanding work with regard to each project above shall be
accompanied by confirmation of the respective Supervising Engineers of the projects.
Bidding Documents
FORM FIN – 3.2.2
2015 / 16 _____________________________________
2014 / 15 _____________________________________
2013 / 14 _____________________________________
2012 / 13 ____________________________________
2011 / 12 _____________________________________
* the annual construction turnover calculated as total certified payments received for work
in progress or completed.
Bidding Documents
FORM OF BID
To:
Gentlemen:
1. In accordance with the Conditions of Contract, Specification, Drawings, and Bill of Quantities
and Addenda Nos. [insert Addenda nos.] for the execution of the above-named Works we, the
undersigned, offer to construct and install such Works and remedy any defects therein in
conformity with the Conditions of Contract, Specifications, Drawings, Bill of Quantities, and
Addenda for the sum of [insert amounts in numbers and words] as specified in the Appendix to
Bid or such other sums as may be ascertained in accordance with the Conditions of Contract.
We attach our Bid Security in the sum of [Insert amount], taken out with [Insert name and
3.
address of Bank or Insurance company].
4.
We undertake, if our Bid is accepted, to commence the Works as soon as is reasonably possible
after the receipt of the Engineer’s notice to commence, and to complete the whole of the
Works comprising the Contract within the time stated in the Appendix to Bid.
Bidding Documents
5.
We undertake, if our Bid is accepted, to deploy the following two sub contractors with a
minimum of 10 % of the contract price for each or one subcontractor with a minimum of
20 % of the contract price for sub contracting works stated in the Appendix to Bid sub clause
4.3.
1.---------------------
2. ---------------------
6. We agree to abide by this Bid until the date 120 days from the date of bid submission specified
in the Bidding Data and it shall remain binding upon us and may be accepted at any time before
that date.
7. Unless and until a formal Agreement is prepared and executed, this Bid, together with your
written acceptance thereof, shall constitute a binding Contract between us.
8. We understand that you are not bound to accept the lowest or any bid you may receive.
We certify/confirm that we comply with the eligibility requirements as per ITB Clause 3 of the
bidding documents.
9. Commissions or gratuities, if any, paid or to be paid by us to Agents relating to this bid, and to
contract execution if we are awarded the contract, are listed below:
10. We hereby certify that we have taken steps to ensure that no person acting for us or on our
behalf will engage in bribery.
Bidding Documents
Signature in the capacity of
Address:
Witness:
Name:
Address:
Occupation:
Signature :
Bidding Documents
APPENDIX TO BID
Bidders should fill in all the appropriate blank spaces. Bidders are required to sign each page of the
Appendix to Bid.
Conditions
of Contract
Sub-Clause
Bidding Documents
Biding data
Bidding Documents
Conditions of Contract
Bidding Documents
Add SubClause 1.1 (h):
Sub-Clause
1.1Definition Mandatory requirement of sub contracting refers to the contractor's
s obligation by the employer to sub contract part of the main works as
a mandatory requirement of the contract.
“The Contractor shall not subcontract the whole of the Works. Except
where otherwise provided by the Contract, the Contractor shall not
subcontract any part of the Works without the prior consent/approval
of the Engineer and the Employer. Any such consent or approval
shall not relieve the Contractor from any liability or obligation under
the Contract and he shall be responsible for the acts, defaults and
neglects of any Subcontractor, his agents, servants or workmen as
fully as if they were the acts, defaults or neglects of the Contractor,
his agents, servants or workmen.”
Bidding Documents
Subcontractors set out in the Appendix to Bid.”
Subcontract
Agreement
The Contractor shall use standard Conditions of Subcontract and
procedures set out in the Appendix to Bid when entering into a
Contract with the Subcontractors. To this end, the Contractor shall
submit for the Engineer's consent the draft subcontract agreement of
all subcontracts. The draft subcontract document of all subcontracts
with a subcontract amount above 5% for the main Contract Price
shall obtain approval from the Employer.
Payment to
Subcontractor
The Contractor shall pay to the Subcontractor when paid by the
Employer for the works executed by the Subcontractor that are
measured and certified by the Engineer. Alternatively, the parties (the
Contractor and Subcontractor) may agree that the Subcontractor to
collect the payment directly from the Employer with submission of
Bidding Documents
written agreement to the Employer.
Provided that, where the Engineer has certified and the Employer has
to pay direct as aforesaid, the Engineer shall, in issuing any further
certificate in favor of the Contractor, deduct from the amount thereof
the amount so to be paid, direct as aforesaid, but shall not withhold or
delay the issue of the certificate itself when due to be issued under the
terms of the contract.
Sub-Clause 4.7 Add SubClause 4.7:
Eligibility of
Subcontractors
“Subcontractors named in the Contract shall comply with the
eligibility rules and requirements of the Government financed
Projects and the Contractor shall be required to ensure that their
contracts include all the conditions applicable to the main contract”
Performance of
Subcontractors
“The Contractor, from time to time, shall evaluate the performance
of its subContractors based on predetermined key performance
indicator.”
Bidding Documents
Sub-Clause 4.9 Add SubClause 4.9:
Termination and
Replacement of
“The Contractor shall only be entitled to terminate the Subcontract
Subcontractors
agreement based on Subcontract agreement termination procedure.
The Contractor shall notify the Engineer any termination of
subcontract agreements. If the terminated Subcontractor is a
Subcontractor engaged as Mandatory Requirement, the Contractor
shall replace same following the Subcontractors selection procedure
stipulated in this contract.”
Provision of
Quarry sites and
“The Contractor shall provide to the SubContractor such portion of
borrow areas to
the quarry and borrow areas whereby the SubContractor shall
the
produce, process and stock pile materials required for the Sub
subcontractors
Contract Works in such manner as the SubContractor is able to
achieve the production required in accordance with the SubContract
Work Programme”
Sharing of
laboratory with
“The Contractor shall allow the subcontractors to use the contractor's
the
laboratory and the laboratory technicians for its sub contract work.”
subcontractors
Subcontractors’
knowledge of the
“The SubContractor shall be deemed to have full knowledge of the
main contract
provisions of the Main Contract and the Main Contractor shall
provide the SubContractor with a true copy of the Main Contract.
(Other than the details of the Contractor's prices stated in the bills of
quantities or schedules of rates and prices as the case may be) ”
Bidding Documents
Sub-Clause 4.13 Add SubClause 4.13:
Access of the
Subcontractor to
“The Main Contractor shall from time to time make available to the
the site
SubContractor such part or part of the Site and such means of access
thereto within the site as shall be necessary to enable the Sub
contractor or execute and complete the Subcontract Works in
accordance with the subContract agreement. ”
Sub-Clause 34.11 The Contractor shall arrange for the provision of a sufficient supply
of suitable food at reasonable prices for all his staff and labour for
Supply of the purposes of or in connection with the Contract.
Bidding Documents
Foodstuffs
Default of
Contractor
(e) has contravened Sub-Clause 4.1 and Sub-Clause 4.3
Bidding Documents
Annex –2 Standard Subcontract Agreement and Conditions of Contract
Bidding Documents
CONTENTS
18
1. General ................................................................................................................................................ 2
1.1. Introduction ................................................................................................................................... 2
1.2. Key factors that affect the success of a Subcontracting ......................................................... 2
1.3. Practice of Subcontracting .......................................................................................................... 5
1.4. Objective of the Subcontracting Management Framework .................................................. 6
1.5. Scope and Goals ............................................................................................................................. 7
2. Overview of Subcontracting ............................................................................................................ 7
2.1. Why subcontracting?................................................................................................................... 7
2.2. Types of Subcontracting .............................................................................................................. 8
3. Subcontract Management ................................................................................................................ 8
3.1. Mandatory Subcontracting .......................................................................................................... 8
3.2. Time for Proposing Subcontractor .......................................................................................... 11
3.3. Evaluation criteria and Qualification Requirement ............................................................. 13
3.3.1. Selection Criteria ..................................................................................................................... 14
3.3.2. Selection Method ..................................................................................................................... 15
3.3.3. Multiple Awards ...................................................................................................................... 16
3.4. Employer Involvement on subcontracting............................................................................. 19
3.5. Standard Conditions of Contract for subcontracting ........................................................... 21
3.5.1. Approach to subcontract formulation:............................................................................. 22
4. Amendments recommended on the existing bidding document of the Main Contract ..... 28
5. General Remarks as a conclusion ................................................................................................ 29
FORM QUA – 1.2 ....................................................................................................................................... 2
FORM OF BID ............................................................................................................................................... 5
The Director General .................................................................................................................................... 5
Fax No. 251-1-514866 ............................................................................................................................ 5
SubClause 1.1Definitions ...................................................................................................................... 11
Add SubClause 1.1 (h): ............................................................................................................................. 11
SubClause 2.1 Engineer’s Duties and Authority ................................................................................... 11
CONTENTS ............................................................................................................................................... 18
PART I GENERAL CONDITIONS ............................................................................................................... 24
Definitions and Interpretation ............................................................................................................ 24
Definitions ........................................................................................................................................... 24
19
Headings and Marginal Notes ............................................................................................................. 26
Interpretation...................................................................................................................................... 26
Singular and Plural .............................................................................................................................. 26
Notices, Consents, Approvals, Certificates, Confirmations and Determinations ............................... 26
Instructions in Writing ........................................................................................................................ 26
General Obligations ................................................................................................................................ 26
Subcontractor’s General Responsibility .............................................................................................. 26
Performance Security.......................................................................................................................... 28
Programme to be Submitted by Subcontractor.................................................................................. 28
Assignment of ..................................................................................................................................... 28
Subcontract ......................................................................................................................................... 28
Sub subcontracting ............................................................................................................................ 28
Subcontract Documents ........................................................................................................................ 30
Language/s .......................................................................................................................................... 30
Governing Law .................................................................................................................................... 30
Subcontract Agreement ...................................................................................................................... 30
Priority of Subcontract Documents .................................................................................................... 30
Main Contract ......................................................................................................................................... 30
Subcontractor’s Knowledge of the main Contract.............................................................................. 30
Subcontractor's Responsibilities in Relation to Subcontract Works ................................................. 31
No Privity of Contract with Employer ................................................................................................ 31
Possible Effects of Subcontractor's Breaches of Subcontract ............................................................ 31
Temporary Works, Contractor's Equipment and/or Other Facilities (if A ny) .................................... 31
Subcontractor's Use of Temporary Works .......................................................................................... 31
Subcontractor’s use of Contractor’s Equipment and/or Other Facilities (if Any) in Common with
Other Subcontractors.......................................................................................................................... 31
Subcontractor's Exclusive Use of Contractor's Equipment and/or Other Facilities (if Any) ............... 31
Indemnification for Misuse of Temporary Works, Contractor's Equipment and/or Other Facilities(if
Any) ..................................................................................................................................................... 31
Material Testing Use of main contractor’s Laboratory by the subcontractor ................................... 32
Freeissue Materials ............................................................................................................................ 32
Site Working and Access ....................................................................................................................... 32
20
Working Hours on Site; Subcontractor’s Compliance with Rules and Regulations ............................ 32
Availability of Site to Subcontractor and Access to Site ..................................................................... 32
Subcontractor's Obligation to Permit Access to Subcontract Works ................................................. 32
Provision of Quarry sites and borrow areas for the subcontractors .................................................. 33
Commencement and Completion ........................................................................................................... 33
Commencement of Subcontract Works; Sub contractor’s Time for Completion.............................. 33
Extension of Subcontractor's Time for Completion ............................................................................ 33
Contractor's Obligation to Notify ........................................................................................................ 33
Instructions and Decisions ...................................................................................................................... 34
Instructions and Decisions under Main Contract................................................................................ 34
Instructions under Subcontract .......................................................................................................... 34
Variations ................................................................................................................................................ 34
Variations of Sub contract Works ...................................................................................................... 34
Instructions for Variations .................................................................................................................. 34
Valuation of Variations ........................................................................................................................... 34
Assessment of Value of Variations...................................................................................................... 35
Valuation by Reference to Measurement under Main Contract ........................................................ 35
Quantity Estimated and Quantity Executed ....................................................................................... 35
Daywork .............................................................................................................................................. 35
Notices and Claims .................................................................................................................................. 35
Notices ................................................................................................................................................ 35
Claims .................................................................................................................................................. 36
Effects of Failure to Give Notice ......................................................................................................... 36
Subcontractor’s Claim ......................................................................................................................... 36
Contractor’s Claim in Connection with the Subcontract .................................................................... 37
Incorporation by Reference ............................................................................................................. 37
Indemnities ............................................................................................................................................. 37
Subcontractor’s Obligation to Indemnify............................................................................................ 37
Contractor's Obligation to Indemnify ................................................................................................. 37
Outstanding Work and Defects............................................................................................................... 39
Subcontractor's Obligations before TakingOver................................................................................ 39
Subcontractor's Obligations after TakingOver................................................................................... 39
21
Defect Caused by Contractor's Act or Default .................................................................................... 39
Insurances ............................................................................................................................................... 39
Subcontractor's Obligation to Insure .................................................................................................. 39
Contractor’s Obligation to Insure; Subcontract Works at Sub contractor’s Risk .............................. 39
Evidence of Insurance; Remedy on Failure to Insure ......................................................................... 40
Payment .................................................................................................................................................. 40
Subcontractor's Monthly Statements ................................................................................................. 40
Contractor's Monthly Statements ...................................................................................................... 40
Payment Due; Payment Withheld or Deferred; Interest .................................................................... 42
Payment to the Subcontractor by the Employer ................................................................................ 44
Payment of Retention Money ............................................................................................................. 44
Payment of Subcontract Price and Other Sums Due ......................................................................... 44
Advance Payment ............................................................................................................................... 44
Cessation of Contractor's Liability....................................................................................................... 45
Termination of Main Contract ................................................................................................................ 45
Termination of Subcontractor's Employment .................................................................................... 45
Payment after Termination................................................................................................................. 45
Termination of Main Contract in Consequence of Breach of Subcontract ......................................... 45
Contractor’s and Subcontractor's Rights and Liabilities upon Termination ....................................... 48
Contractor's Powers ............................................................................................................................ 48
Default of Contractor .............................................................................................................................. 48
Default of Contractor .......................................................................................................................... 48
Removal of Subcontractor’s Equipment ............................................................................................. 48
Payment on Termination .................................................................................................................... 48
Subcontractor’s Entitlement to Suspend Work .................................................................................. 48
Resumption of Work ........................................................................................................................... 49
Settlement of Disputes ........................................................................................................................... 49
Amicable Settlement and Arbitration ................................................................................................ 49
Dispute arising between locals or Local and foreign contractor and subcontractor.......................... 49
Dispute arising Between Foreign contractor and subcontractor ....................................................... 50
Dispute in Connection with or Arising out of Main Contract Touching or Concerning Sub contract
Works .................................................................................................................................................. 50
22
Notices and Instructions ......................................................................................................................... 50
Giving of Notices and Instructions ...................................................................................................... 50
Change of Address .............................................................................................................................. 50
Changes in Cost and Legislation.............................................................................................................. 50
Increase or Decrease of Cost .............................................................................................................. 50
Base, Current and Provisional Indices ................................................................................................. 51
Subsequent Legislation ....................................................................................................................... 51
Currency and Rates of Exchange............................................................................................................. 51
Currency Restrictions .......................................................................................................................... 51
Rates of Exchange ............................................................................................................................... 51
PART II CONDITIONS OF PARTICULAR APPLICATION CONTENTS.......................................................... 52
PART II CONDITIONS OF PARTICULAR APPLICATION CONTENTS.............................................................. 53
Rules and Regulations ............................................................................................................................. 55
SUBCONTRACTOR'S OFFER ..................................................................................................................... 56
APPENDIX TO SUBCONTRACTOR'S OFFER ............................................................................................ 59
SUBCONTRACT AGREEMENT .................................................................................................................... 0
6. Reference ............................................................................................................................................ 0
23
PART I GENERAL CONDITIONS
24
by the Contractor of the Subcontractor's Offer.
(viii)"Subcontract Agreement" means the subcontract agreement (if any)
referred to in SubClause 3.3.
(ix) "Appendix to Subcontractor's Offer" means the appendix comprised
in the form of Subcontractor's Offer annexed to the Conditions of
Subcontract.
25
1.2 The headings and marginal notes in the Conditions of Subcontract shall not be
Headings and deemed part thereof or be taken into consideration in the interpretation or
Marginal Notes construction thereof or of the Subcontract.
1.3 Words importing persons or parties shall include firms and corporations and any
Interpretation organization having legal capacity.
In the Subcontract, expect where the context requires otherwise;
If it is stated that a subclause or provision of the Main Contract shall apply then
that subclause or provision of the Main Contract shall be read with necessary
changes, including that any reference to the Employer and/or the Engineer shall be
read as reference to the Contractor, any reference to the Contractor shall be read
as a reference to the Subcontractor and any reference to another Main Contract
Clause or defined term therein shall be read as a reference to the equivalent clause
or subclause or defined term of these Conditions.
1.4 Words importing the singular only also include the plural and vice versa where the
Singular and context requires.
Plural
1.5 Wherever in the Subcontract provision is made for the giving or issue of any
Notices, Consents, notice, consent, approval, certificate, confirmation or determination by any
Approvals, person, unless otherwise specified such notice, consent, approval, certificate,
Certificates, confirmation or determination shall be in writing and the words "notify", "certify",
Confirmations "confirm" or "determine" shall be construed accordingly. Any such notice,
and consent, approval, certificate, confirmation or determination shall not
Determinations unreasonably be withheld or delayed.
1.6 Instructions given by the Contractor shall be in writing, provided that if for any
Instructions in reason the Contractor considers it necessary to give any such instruction orally,
Writing the Subcontractor shall comply with such instruction. Confirmation in writing of
such oral instruction given by the Contractor, whether before or after the carrying
out of the instruction, shall be deemed to be an instruction within the meaning of
this Sub Clause. Provided further that if the Subcontractor, within 7 days,
confirms in writing to the Contractor any oral instruction of the Contractor and
such confirmation is not contradicted in writing within 7 days by the Contractor, it
shall be deemed to be an instruction of the Contractor.
General Obligations
2.1 The Subcontractor shall, with due care and diligence, design (to the extent
Subcontractor’s
provided for by the Subcontract), execute and complete the Subcontract Works
General and remedy any defects therein in accordance with the provisions of the
Responsibility Subcontract. The Subcontractor shall provide all superintendence, labour,
materials, Plant, Subcontractor's Equipment and all other things, whether
of a temporary or permanent nature, required in and for such design, execution,
completion and remedying of any defects, so far as the necessity for providing the
same is specified in or is reasonably to be inferred from the Subcontract, and
except as otherwise agreed in accordance with Clause 5 and set out in Part II of
26
the Conditions of Subcontract.
The Subcontractor shall give prompt notice to the Contractor of any error,
omission, fault or other defect in the design of or specification for the Subcontract
Works which the discovers when reviewing the Subcontract and/or the Main
Contract or executing the Subcontract Works.
The SubContractor shall provide and employ on the Site such Technical
Assistants, Subagents and Foremen as are competent to give proper supervision
and such skilled, semiskilled and unskilled labour as is necessary for the proper
and timely execution and maintenance of the SubContract Works.
The SubContractor shall ensure that no illegal immigrants are employed by it for
any work under the SubContract.
The SubContractor shall be responsible for arranging with the relevant authorities
for the provision of water, electricity, sewerage and other services required for the
purpose of executing the Sub Contract Works and the subcontractor’s staffs.
The subcontractor is required at all time to take reasonable steps to maintain the
health and safety of all personnel staffs at site in relation to the subcontract works.
27
2.2 If the Subcontract requires the Subcontractor to obtain security for his
Performance proper performance of the Subcontract, he shall obtain and provide to the
Security Contractor such security in the sum stated in the Appendix to Subcontractor's
Offer. Such security shall be in the form annexed to the Conditions of
Subcontract or in such form as may be agreed between the Contractor and the
Subcontractor. The institution providing such security shall be subject to the
approval of the Contractor. The cost of complying with the requirements of
this Clause shall be borne by the Subcontractor, unless the Subcontract
otherwise provides.
The performance security shall be valid until the Subcontractor has executed and
completed the Subcontract Works and remedied any defects therein in accordance
with the Subcontract. No claim shall be made against such security after the issue
of the Defects Liability Certificate in respect of the Main Works and such security
shall be returned to the Subcontractor within 28 days of the issue of the said
Defects Liability Certificate.
Prior to making a claim under the performance security the Contractor shall, in
every case, notify the Subcontractor stating the nature of the default in respect of
which the claim is to be made.
2.3 The Subcontractor shall, within the time stated in Part II of the Conditions
Programme to be of Subcontract after the date of the Contractor's Letter of Acceptance, submit to
Submitted by the Contractor for his consent a programme, in such form and detail as the
Subcontractor Contractor shall reasonably prescribe, for the execution of the Subcontract
Works. The Master Work Programme of the main contractor shall be the basis for
the production of the SubContract Work Programme. The Subcontractor shall,
whenever required by the Contractor, also provide in writing for his information a
general description of the arrangements and methods which the Subcontractor
proposes to adopt for the execution of the Subcontract Works.
If at any time it should appear to the Contractor that the actual progress of the
Subcontract Works does not conform to the programme to which consent has been
given or in case where revision is required on the Master Work Programme of the
main contractor , the Subcontractor shall produce, at the request of the Contractor,
a revised programme showing the modifications to such programme necessary
to ensure completion of the Subcontract Works within the Subcontractor's Time
for Completion.
2.4 The Subcontractor shall not, without the prior consent of the Contractor
Assignment of (which consent, notwithstanding the provisions of SubClause 1.5, shall be at
the sole discretion of the Contractor), assign the Subcontract or any part
Subcontract
thereof, or any benefit or interest therein or there under, otherwise than by:
2.5 The Subcontractor shall not subcontract the whole of the Subcontract Works, nor
Sub shall he subcontract any part of the Subcontract Works without the prior consent
subcontracting
28
of the Contractor and the Employer. Any such consent shall not relieve the
Subcontractor from any liability or obligation under the Subcontract and the
Subcontractor shall be responsible for the acts, defaults and neglects of any of his
subcontractors, including such subcontractor's agents, servants or workmen as
fully as if they were the acts, defaults or neglects of the Subcontractor, his agents,
servants or workmen. Provided that the Subcontractor shall not be required to
obtain such consent for:
(a) the provision of labour, or
(b) the purchase of materials which are in accordance with the standards
specified in the Subcontract and/or the Main Contract.
In the event of a subcontractor having undertaken towards the Subcontractor in
respect of the work executed, or the goods, materials, Plant or services supplied by
such subcontractor, any continuing obligation extending for a period exceeding
that of the Defects Liability Period under the Main Contract in respect of the Main
Works or of the Section or Sections or part or parts thereof in which the
Subcontract Works are comprised, as the case may be, the Subcontractor shall at
any time, after the expiration of such Period, assign to the Contractor, at the
Contractor's request and cost, the benefit of such obligation for the unexpired
duration thereof.
29
Subcontract Documents
3.1 Unless otherwise stated in Part II of the Conditions of Subcontract:
Language/s
(a) the language or languages in which the Subcontract documents shall be
drawn up shall be the same as the language or languages in which the Main
Contract documents have been drawn up, and
(b) if the Subcontract documents are drawn up in more than one language,
the Subcontract shall be construed and interpreted according to the Ruling
Language of the Main Contract.
3.2 Unless otherwise stated in Part II of the Conditions of Subcontract, the law of the
Governing Law country or state which applies to the Main Contract and according to which the Main
Contract is construed shall also apply to the Subcontract and be the law according
to which the Subcontract shall be construed.
3.3 The Subcontractor shall, if called upon so to do, enter into and execute the
Subcontract Subcontract Agreement, to be prepared and completed at the cost of the Contractor,
Agreement in the form annexed to the Conditions of Subcontract with such modification as
may be necessary.
3.4 The several documents forming the Subcontract, listed in the Contractor's Letter of
Priority of Acceptance or the Subcontract Agreement (if any), are to be taken as mutually
Subcontract Explanatory o f one another. Unless otherwise provided in the Subcontract, the
Documents priority of the documents forming the Subcontract shall be as follows:
(1) The Subcontract Agreement;
(2) The Contractor's Letter of Acceptance;
(3) Minutes if pre contract award discussion (if any)
(4) Appendix to subcontractor’s offer
(5) The Subcontractor's Offer;
(6) Part II of the Conditions of Subcontract;
(7) Part I of the Conditions of Subcontract; and
(8) the subcontract specification
(9) Subcontract Drawings
(10) Priced Bill of Quantities or Price Schedule
(11) Any other document forming part of the Subcontract.
Main Contract
Subcontractor’s 4.1 The Contractor shall make the Main Contract (other than the details of
Knowledge of the the Contractor's prices thereunder as stated in the bills of quantities or schedules
main Contract of rates and prices as the case may be) available for inspection to the
Subcontractor and, if so requested by the Subcontractor, shall provide the
Subcontractor with a true copy of the Main Contract (less such details of the
Contractor's prices), at the cost of the Subcontractor. The Contractor shall, in any
event, provide the Subcontractor with a copy of the Appendix to Tender to the
Main Contract together with Part II of the Conditions of Main Contract and
details of any other contract conditions which apply to the Main Contract
which differ from Part I of the Conditions of Main Contract. The
Subcontractor shall be deemed to have full knowledge of the provisions
of the Main Contract (less such details of the Contractor's prices).
The subcontractor shall promptly give notice to the contractor of any ambiguity or
discrepancy which he discovers when reviewing the Subcontract and the Main
contract or executing the subcontract works.
30
4.2 Save where the provisions of the Subcontract otherwise require, the Subcontractor
Subcontractor's shall so design (to the extent provided for by the Subcontract), execute and
Responsibilities complete the Subcontract Works and remedy any defects therein that no act or
in Relation to omission of his in relation thereto shall constitute, cause or contribute to any
Subcontract breach by the Contractor of any of his obligations under the Main Contract. The
Works Subcontractor shall, save as aforesaid, assume and perform hereunder all the
obligations and liabilities of the Contractor under the Main Contract in relation to
the Subcontract Works.
No Privity of 4.3 Nothing herein shall be construed as creating any privity of contract between the
Contract with Subcontractor and the Employer
Employer
4.4 If the Subcontractor commits any breaches of the Subcontract, he shall indemnify
Possible Effects of the Contractor against any damages for which the Contractor becomes liable under
Subcontractor's the Main Contract as a result of such breaches. In such event, the Contractor may,
Breaches of without prejudice to any other method of recovery, deduct such damages from
Subcontract monies otherwise becoming due to the Subcontractor.
31
Works, his use by the Contractor.
Contractor's
Equipment
and/or Other
Facilities(if Any)
5.5 The required quality testing as per the main contract for the subcontract works shall
Material Testing be carried out by the main contractor’s laboratory technicians at the main
Use of main contractor’s Laboratory on site on the written request of the subcontractor with no
contractor’s additional cost to the Subcontractor. All the tests shall comply with the requirement
Laboratory by the of the specification of the main contract and be approved by the Employer’s
subcontractor Representative/ Engineer before proceeding to the subsequent works. The
subcontractor is responsible to request the tests required by the specification and
sampling of the materials.
5.6 The Contractor shall supply to the subcontractor, free of charges, the freeissue
Freeissue materials (if any) specified in Part II of the Conditions of Subcontract, at the
Materials place (s) specified in Part II of the Conditions of Subcontract and within the
times that shall be required to enable the Subcontractor to proceed with execution
and completion of the subcontract works in accordance with the Subcontract
programme. The supply of such freeissue materials shall be in accordance with the
detail and arrangements and upon the terms and conditions (if any) stated in Part II
of the Conditions of Subcontract.
When made available by the Contractor, the Subcontractor shall visually inspect the
freeissue materials and shall promptly give notice tot eh Contractor of any
shortage, defect or default in them. Unless the parties agree or the Contractor
instructs otherwise, the Contractor shal immediately rectify the notified shortage,
defect or default. After this visual inspection, the freeissue materials shall come
under the care, custody and control if the Subcontractor. The Subcontractor’s
obligation of inspection, care, custody and control shall not relive the Contractor of
liability for any shortage, defect or default not apparent from a visual inspection.
32
Works or procure reasonable access for the Contractor, the Engineer, and any person
authorised by either of them, to such places off the Site where work is being
executed or prepared by or on behalf of the Subcontractor in connection with the
Subcontract Works.
6.4 The Main Contractor shall provide to the SubContractor such portion of the quarry
Provision of and borrow areas whereby the SubContractor shall produce, process and stock pile
Quarry sites and materials required for the SubContract Works in such manner as the Sub
borrow areas for Contractor is able to achieve the production required in accordance with the Sub
the Contract Work Programme without interference.
subcontractors
33
Instructions and Decisions
8.1 Subject to Clause 9, the Subcontractor shall in relation to the Subcontract Works
Instructions and comply with all instructions and decisions of the Engineer which are notified and
Decisions under confirmed to him as an instruction by the Contractor, irrespective of whether such
Main Contract instructions and decisions were validly given under the Main Contract. The
Subcontractor shall have the like rights (if any) to payment from the Contractor in
respect of such compliance as the Contractor has against the Employer under the
Main Contract. Further, if any such instruction or decision notified and confirmed
as aforesaid is invalidly or incorrectly given by the Engineer under the Main
Contract, then the Subcontractor shall be entitled to recover such costs as may be
reasonable (if any) from the Contractor of complying therewith to the extent that
such costs were not caused or contributed to by any breach of the Subcontract by
the Subcontractor.
8.2 The Subcontractor shall take instructions only from the Contractor. The Contractor
Instructions shall have the like authority in relation to the Subcontract Works to give
under instructions as the Engineer has in relation to the Main Works under the Main
Subcontract Contract. The Subcontractor shall have the like obligations to abide by and comply
therewith and the like right in relation thereto as the Contractor has under the Main
Contract. The said authority of the Contractor shall be exercisable in any case
irrespective of whether the Engineer has exercised like authority in relation thereto
under the Main Contract.
Variations
9.1 The Subcontractor shall only make such variation of the Subcontract Works,
Variations of Sub whether by way of alteration, addition, or omission, as may be instructed by:
contract Works
(a) the Engineer under the Main Contract and
notified and confirmed as an instruction to the
Subcontractor by the Contractor, or
(b) the
Contractor.
Any instruction relating to the Subcontract Works which is given by the Engineer
under the Main Contract and constitutes a variation thereunder shall be deemed to
constitute a variation of the Subcontract Works, if notified and confirmed by the
Contractor in accordance with paragraph (a) of this SubClause.
9.2 The Subcontractor shall not act upon an unconfirmed instruction for the variation of
Instructions for the Subcontract Works which is directly received by him from the Employer or the
Variations Engineer. If the Subcontractor shall receive any such direct instruction, he shall
forthwith inform the Contractor thereof and shall supply the Contractor with a copy
of such direct instruction, if given in writing. The Subcontractor shall only act upon
such instruction as directed in writing by the Contractor, but the Contractor shall
give his directions thereon promptly.
Valuation of Variations
34
10.2 The value of all variations shall be ascertained by reference to the rates and prices
Assessment of (if any) specified in the Subcontract for the like or analogous work, but if there are
Value of no such rates and prices, or if they are inappropriate or inapplicable, then such value
Variations shall be such as is fair and reasonable.
10.3 Where a variation of the Subcontract Works, which also constitutes a variation
Valuation by under the Main Contract, is measured by the Engineer there under, then provided
Reference to that the rates and prices in the Subcontract permit such variation to be valued by
Measurement reference to measurement the Contractor shall permit the Subcontractor to attend
under Main any measurement made on behalf of the Engineer. Such measurement made under
Contract the Main Contract shall also constitute the measurement of the variation for the
purposes of the Subcontract and such variation shall be valued accordingly.
10.4 The quantities set out in the Subcontract Bill of Quantities are the estimated
Quantity quantities for the Subcontract Works, and they are not to be taken as the actual and
Estimated and correct quantities of the Subcontract Works to be executed by the Subcontractor in
Quantity Executed fulfillment of his obligations under the Subcontract.
No instruction shall be required for increase or decrease in the quantity of any work
where the cumulative increment of quantity doesn’t exceeds by more than 5% of
the total of the subcontract contract amount where such increase or decrease is not
the result of an instruction given under Clause 9, but is the result of the quantities
exceeding or being less than those stated in the Subcontract Bill of Quantities.
10.5 Where the Subcontractor has been instructed by the Contractor to carry out work on
Daywork a daywork basis the Subcontractor shall be paid for such work at the rates and
prices specified in the daywork schedule included in the Subcontract.
Provided always that the Subcontractor shall be excused any noncompliance with
this SubClause for so long as he neither knew nor ought to have known of the
Contractor's need of any such notice or information from him or such contemporary
records.
35
11.2 Subject to the Subcontractor's complying with this SubClause, the Contractor shall
Claims take all reasonable steps to secure from the Employer (including the Engineer) such
contractual benefits (including additional payments, extensions of time, or both), if
any, as may be claimable in accordance with the Main Contract on account of any
adverse physical obstructions or physical conditions or any other circumstances that
may be encountered during the execution of the Subcontract Works. The
Subcontractor shall, in sufficient time, afford the Contractor all information and
assistance that may be required to enable the Contractor to claim such contractual
benefits. On receiving any such contractual benefits from the Employer, the
Contractor shall pass on to the Subcontractor such proportion thereof as may in all
the circumstances be fair and reasonable, it being understood that, in the case of any
claim of the Contractor for an additional payment, the Contractor's receipt of
payment therefor from the Employer shall be a condition precedent to the
Contractor's liability to the Subcontractor in respect of such claim. The Contractor
shall notify the Subcontractor regularly of his steps to secure such contractual
benefits and of the Contractor's receipt thereof. Save as provided in this SubClause,
or in SubClause 7.2, the Contractor shall have no liability to the Subcontractor in
respect of any obstruction, condition or circumstance that may be encountered
during the execution of the Subcontract Works. The Subcontractor shall be deemed
to have satisfied himself as to the correctness and sufficiency of the Subcontract
Price to cover the provision and doing by him of all things necessary for the
performance of his obligations under the Subcontract. Provided always that nothing
in this Clause shall prevent the Subcontractor from claiming against the Contractor
for delays in the execution of the Subcontract Works, or other circumstances,
caused by the act or default of the Contractor.
11.3 If by reason of any failure by the Subcontractor to comply with the provisions of
Effects of Failure SubClause 11.1 the Contractor is prevented from recovering any sum from the
to Give Notice Employer under the Main Contract in respect of the Main Works, then, without
prejudice to any other remedy of the Contractor for such failure, the Contractor may
deduct such sum from monies otherwise due to the Subcontractor under the
Subcontract.
11.4 If the subcontractor considers himself to be entitled to any extension of the
Subcontractor’s subcontract time for completion and/or any additional payment, under any clauses
Claim of these conditions or otherwise in connection with the subcontract, Main contract
clause on Contractor’s Claims shall apply to subcontractor’s claims with
appropriate interpretation with the subcontract. Save that:
a) the period of notice applicable to Subcontractor’s claims shall be not later
than 21 days after the subcontractor becomes aware (or should have
become aware) of the event or circumstance giving rise to the claim;
b) the period for submission by the subcontractor of a full detailed claim shall
be not later than 35 days after the subcontractor becomes aware (or should
have become aware) ) of the event or circumstance giving rise to the claim,
or within such other period as may be proposed by the Subcontractor and
approved by the Contractor.
Provided also that, where an event has a continuing effect such that it is not
practicable for the Subcontractor to submit detailed particulars within the period of
21 days referred to in this SubClause, he shall nevertheless be entitled to an
extension of time provided that he has submitted to the Contractor interim
particulars at intervals of not more than 21 days and final particulars within 21 days
of the end of the effects resulting from the event.
36
11.5 If the Contractor Considered himself to be entitled to any payment under any clause
Contractor’s of these conditions or otherwise in connection with the Subcontract, the contractor
Claim in shall give notice to the Subcontractor describing the event or circumstance giving
Connection with rise to the claim. The notice shall be given 28 days after the Contractor becomes
the Subcontract aware of the event or circumstance giving rise to the claim and shall specify the
basis of the claim.
Not later than 28 days after the Contractor becomes aware of the event or
circumstance giving rise to the claim, the Contractor shall send to the Subcontractor
detailed particulars of the claim which includes substantiation of the amount to
which the Contractor considers himself to be entitled. The Contractor shall consult
with the Subcontractor in an endeavor to reach to an agreement to this amount. If
agreement is not reached, the Contractor shall make a fair decision as to the
appropriate and applicable amount, taking due account of the Subcontractor’s
views, the extent to which the claim has been reasonably substantiated, and all other
supporting circumstances. The Contractor shall give notice, with reasons and
supporting particulars to the Subcontractor of this decision.
This amount may be deducted from sums otherwise due to the Subcontractor. The
Contractor shall only entitled to make a deduction or otherwise to claim against the
Subcontractor, in accordance with the subclause.
Subcontractor's Equipment, Temporary Works and
Materials
12.1 The provisions of Main Contract in relation to Contractor's Equipment, Temporary
Incorporation by Works or materials brought on to the Site by the Subcontractor are hereby
Reference incorporated by reference into the Subcontract as completely as if they were set out
in full therein.
Indemnities
13.1 The Subcontractor shall, except if and so far as the Subcontract provides
Subcontractor’s
otherwise, indemnify the Contractor against all losses and claims in respect of:
Obligation to
Indemnify (a) death of or injury to any person, or
(b) loss or damage to any property (other than the Subcontract Works),
37
(c) damage to property which is the unavoidable
result of the execution and completion of the Subcontract
Works, or the remedying of any defects therein, in
accordance with the Subcontract, and
(d) death of or injury to persons or loss of or damage
to property resulting from any act or neglect of the
Employer, his agents, workmen or servants or other
contractors, not being employed by the Contractor, or in
respect of any claims, proceedings, damages, costs,
charges and expenses in respect thereof or in relation
thereto.
38
Outstanding Work and Defects
14.1 The Subcontractor shall remedy every defect therein from whatever cause
Subcontractor's
arising until a TakingOver Certificate is issued in respect of the
Obligations Subcontract Works or such Section or Sections or part or parts of the sub
before Taking contract works. Subject to Clause 15, the Subcontractor shall not be
Over entitled to any additional payment for so doing unless such defect is
caused by the act or default of the Employer, his agents, servants or
workmen under the Main Contract or of the Contractor, his agents,
servants or workmen under the Subcontract.
14.2 After a TakingOver Certificate is issued in respect of the subcontract
Subcontractor's
Works or of the Section or Sections or part or parts of the subcontract
Obligations after Works, as the case may be, the Subcontractor shall remedy such defects in
TakingOver the Subcontract Works as liable to remedy under the subcontract for the
period and terms as agreed by the subcontractor and the Contractor under
Part II, the Special Conditions of Subcontract.
14.3 Provided always that if any defect remedied by the Subcontractor under SubClause
Defect Caused by 14.l or 14.2 is caused by the act or default of the Contractor, his agents, servants or
Contractor's Act workmen, then, notwithstanding that the Contractor may have no corresponding
or Default right under the Main Contract, the Subcontractor shall be entitled to be paid by the
Contractor his costs of remedying such defect.
Insurances
15.1 The Subcontractor shall effect insurance against such risks as are specified in Part II
Subcontractor's of the Conditions of Subcontract and in such sums and for the benefit of such
Obligation to persons as are specified therein. Unless otherwise stated in Part II of the Conditions
Insure of Subcontract, the Subcontractor shall keep in force such insurance from the time
that so much of the Site and such access is made available to him as may be
required to enable him to commence and proceed with the execution of the
Subcontract Works in accordance with the Subcontract until he has finally
performed his obligations under the Subcontract.
Provided that the Subcontractor shall insure against the liability in respect of any
person employed by him on the Subcontract Works in such manner that the
Employer and/or the Contractor is indemnified under the policy.
15.2 The Contractor shall keep in force, until such time as a TakingOver Certificate is
Contractor’s issued in respect of the Main Works or the Main Works have ceased to be at his risk
Obligation to under the Main Contract, the policy of insurance specified in Part II of the
Insure; Conditions of Subcontract.
Subcontract
Works at Sub In the event of the Subcontract Works, Temporary Works, materials or other things
contractor’s Risk belonging to the Subcontractor being destroyed or damaged during such period in
such circumstances that a claim is established in respect thereof under the said
policy, then the Subcontractor shall be paid the amount of such claim, or the
amount of his loss, whichever is the less, and shall apply such sum in replacing or
repairing that which was destroyed or damaged. Save as aforesaid the Subcontract
Works shall be at the risk of the Subcontractor until a TakingOver Certificate is
issued in respect of the Subcontract Works or Section or Sections or part or parts of
the Subcontract Works. The Subcontractor shall make good all loss or damage
occurring to the Subcontract Works prior thereto at his own expense. The
Subcontractor shall also be liable for any loss or damage to the Subcontract Works
occasioned by him in the course of any operations carried out by him for the
purpose of complying with his obligations under SubClause 14.2.
39
15.3 Where by virtue of this Clause either party is required to effect and keep in force
Evidence of insurance, he shall if so required by the other party provide evidence of insurance
Insurance; and the receipt for the payment of the current premium.
Remedy on
Failure to Insure
If either the Contractor or the Subcontractor fails to effect and keep in force any of
the insurances required under the Subcontract, or fails to provide evidence of
insurance, when required, then and in any such case the other party may effect and
keep in force any such insurances and pay any premium as may be necessary for
that purpose and may from time to time deduct the amount so paid from any monies
due or to become due to the party in default, or recover the same as a debt due from
the party in default, as the case may be.
Payment
16.1 The Subcontractor shall submit to the Contractor, 7 days after the end of each
Subcontractor's
month (the "Specified Day"), 7 copies of a statement, in such form as the
Monthly Contractor may from time to time prescribe (the "Statement"), showing the
Statements amounts to which the Subcontractor considers himself to be entitled up to the
end of such month in respect of:
The value of work done shall be calculated in accordance with the rates and
prices specified in the Subcontract, but if there are no such rates and prices, or
if they are inappropriate or inapplicable, then such value shall be such as is fair
and reasonable.
16.2 Subject to the Subcontractor having submitted a Statement for any month to the
Contractor's Contractor, the Contractor shall include, unless inappropriate, the amounts set out
Monthly therein in the Contractor's next statement for payment under the Main Contract.
Statements
In any proceedings, whether arbitral or other, instituted by the Contractor against
the Employer to enforce payment of monies due under any certificate issued by the
Engineer in accordance with the provisions of the Main Contract there shall be
included all sums certified and unpaid in relation to the Subcontract Works, without
prejudice to the Subcontractor's rights under Clause 20.
40
41
16.3 Within 77 days of the Specified Day or otherwise as agreed but subject as
Payment Due; hereinafter provided, the amounts included in a Statement shall be due and
Payment payable to the Subcontractor, subject to deduction of previous payments and of
Withheld or retention monies at the rate(s) specified in the Appendix to Subcontractor's Offer
Deferred; Interest until such time as the limit of retention money (if any) therein specified has
been reached.
The Contractor shall be entitled to withhold or defer payment of all or part of
any sums otherwise due pursuant to the provisions hereof where:
(a) the amounts included in any Statement together
with any sums to which the Subcontractor might
otherwise be entitled in the opinion of the Contractor, but
after all retentions and deductions, are less in the
aggregate than the minimum amount (if any) stated in
the Appendix to Subcontractor's Offer,
(b) the amounts included in any Statement together
with any other sums which are the subject of an
application by the Contractor under the Main Contract
in accordance with SubClause 16.2, but after all
retentions and deductions, are insufficient in the
aggregate to justify the issue of an Interim Payment
Certificate by the Engineer under the Main Contract,
(c) the amounts included in any Statement are not
certified in full by the Engineer, providing such failure to
certify is not due to the act or default of the Contractor,
Any payment withheld under the provisions of paragraphs (c), (d) or (e) above
shall be limited to the extent that the amounts in any Statement are not certified,
not paid by the Employer or are the subject of a dispute, as the case may be.
In the event of the Contractor withholding or deferring any payment he shall notify
the Subcontractor of his reasons there for as soon as is reasonably practicable but
not later than the date when such payment would otherwise have been payable.
The provisions of paragraphs (a) and (b) of this SubClause with regard to the
time for payment shall not apply to the amounts in any Statement by the
Subcontractor which are included in the Contractor's Final Statement to the
42
Engineer under the provisions of the Main Contract. In respect of any such
amounts payment shall be due 14 days after receipt by the Contractor of any
payment which includes a sum in respect of such amounts.
In the event of the Contractor failing to make payment of any sum properly due
and payable to the Subcontractor or in the event of payment being withheld or
deferred pursuant to paragraph (d) of this SubClause, the Contractor shall,
upon receiving a notice of claim for interest from the Subcontractor, which
should be made within 7 days of the date when such sum became payable, pay to
the Subcontractor interest on such overdue sum at the rate payable by the
Employer to the Contractor under the provisions of the Main Contract.
Provided always that, in the event of the Contractor not receiving a notice of
a claim for interest within 7 days of the date when such sum became payable
as aforesaid, interest shall be payable by the Contractor on such sum at such
rate from the date of receipt of the said notice of claim.
Notwithstanding the terms of this Clause or any other Clause of the Subcontract
no amount shall be due and payable to the Subcontractor until the performance
security, if required under the Subcontract, has been provided by the
Subcontractor and approved by the Contractor.
43
16.4 In the event of the Contractor failing to make payment of any sum properly due
Payment to the and payable to the Subcontractor by the contractor within fourteen days (14) when
Subcontractor by paid by the Employer for the Works of the subcontractor that are measured and
the Employer certified by the Engineer, the subcontractor has the right to claim his payment to
be paid by the Employer.
The Contractor entitled the Employer to pay such subcontractor direct, upon the
certificate of the Engineer, all payment, less retentions, provided for the
subcontractor, which the Contractor has failed to pay to such subcontractor and to
deduct by way of setoff the amount so paid by the Employer from any sums due
or to become due from the Employer to the Contractor if the contractor fails to
supply such proof then, unless the Contractor;
(a) Satisfies the Engineer in writing that he has reasonable cause for withholding
or refusing to make such payments, and
(b) Produces to the Engineer reasonable proof that he has so informed such
subcontracts in witting.
16.5 Within 35 days of the issue by the Contractor of the TakingOver Certificate with
Payment of respect to the whole of the Subcontract Works or, where the Subcontract Works are
Retention Money completed by Sections or parts, the Contractor shall pay to the Subcontractor one
half, or such other proportion as the Contractor reasonably determines having
regard to the relative value of such Section or part of the Subcontract Works, of the
retention monies under the Subcontract.
Upon the expiration of the Defects Liability Period for the subcontract Works the
other half of the Retention Money shall be certified by the Contractor for payment
to the Subcontractor. Provided that, in the event of different Defects Liability
Periods having become applicable to different Sections or parts of the Permanent
Works, the expression "expiration of the Defects Liability Period" shall, for the
purposes of this SubClause, be deemed to mean the expiration of the latest of such
periods.
16.6 Within 91 days after the Subcontractor has finally performed his obligations under
Payment of Clause 14, or within 14 days after the Contractor has recovered full payment under
Subcontract the Main Contract in respect of the Subcontract Works, whichever is the sooner,
Price and Other and provided that 35 days have expired since the submission by the Subcontractor
Sums Due of his statement of final account to the Contractor, the Contractor shall pay
to the Subcontractor the Subcontract Price and any additions to or deductions from
such sum as are provided for in the Subcontract, or are otherwise payable in
respect thereof, less such sums as have already been received by the
Subcontractor on account.
16.7 Upon the request of the Subcontractor and as agreed by the Subcontractor and the
Advance Payment Contractor under Part II, Particular Condition of the subcontract, the Contractor
may provide an interestfree advance payment to the Contractor exclusively for the
costs of mobilization in respect of the Works in an amount named in the Letter of
Acceptance of the Subcontract, payable in the agreed proportions of foreign and
local currencies of the Contract Price.
44
16.8 The Contractor shall not be liable to the Subcontractor for any matter or thing
Cessation of arising out of or in connection with the Subcontract or execution of the Subcontract
Contractor's Works, unless the Subcontractor has given a notice of claim in respect thereof to the
Liability Contractor before the issue of the Defects Liability Certificate in respect of the
Subcontract Works.
17.3 If the Contractor's employment under the Main Contract is terminated, or if the
Termination of Main Contract is otherwise terminated, by the Employer in consequence of any
45
Main Contract in breach of the Subcontract by the Subcontractor, then the provisions of the
Consequence of preceding Sub Clause as to payment shall not apply, but the rights of the
Breach of Contractor and the Subcontractor hereunder shall be the same as if the
Subcontract Subcontractor had by such breach repudiated the Subcontract and the Contractor
had by his notice of termination under SubClause 18.1 elected to accept such
repudiation.
Default of Subcontractor
Termination of 18.1 If:
Subcontract (a) the Subcontractor is deemed by law unable to
pay his debts as they fall due, or enters into voluntary or
involuntary bankruptcy, liquidation or dissolution (other
than a voluntary liquidation for the purposes of
amalgamation or reconstruction), or becomes insolvent,
or makes an arrangement with, or assignment in favour
of, his creditors, or agrees to carry out the Subcontract
under a committee of inspection of his creditors, or if a
receiver, administrator, trustee or liquidator is appointed
over any substantial part of his assets, or if any act is
done or event occurs with respect to the Subcontractor or
his assets which, under any applicable law, has a
substantially similar effect to any of the foregoing acts
or events, or if the Subcontractor has contravened Sub
Clause 2.4, or has an execution levied on his goods,
(b) the Subcontractor has repudiated the
Subcontract,
(c) the Subcontractor, without reasonable
excuse, has failed to commence or proceed with the
Subcontract Works in accordance with SubClause
7.1,
(d) the Subcontractor refuses or neglects to
remove defective materials or remedy defective
work after being instructed so to do by the
Contractor under this Sub Clause,
(e) the Subcontractor, despite previous warning
from the Contractor, in writing, is otherwise
persistently or flagrantly neglecting to comply with
any of his obligations under the Subcontract,
(f) the Subcontractor has contravened Sub
Clause 2.5, or
(g) the Contractor is required by the Engineer to
remove the Subcontractor from the Main Works after
due notice in writing from the Engineer to the
Contractor in accordance with the Main Contract,
then in any such event, and without prejudice to any other rights or remedies, the
Contractor may by a notice to the Subcontractor forthwith terminate the
Subcontractor's employment under the Subcontract and thereupon the Contractor
may take possession of all materials, Subcontractor's Equipment and other things
whatsoever brought on to the Site by the Subcontractor and may by himself or any
46
other contractor use them for the purpose of executing and completing the
Subcontract Works and remedying any defects therein and may, if he thinks fit, sell
all or any of them and apply the proceeds in or towards the satisfaction of monies
otherwise due to him from the Subcontractor.
47
18.2 Upon such a termination, the rights and liabilities of the Contractor and the
Contractor’s and Subcontractor shall, subject to the preceding SubClause, be the same as if the
Subcontractor's Subcontractor had repudiated the Subcontract and the Contractor had by his notice
Rights and of termination under the preceding SubClause elected to accept such repudiation.
Liabilities upon
Termination
18.3 The Contractor may in lieu of giving a notice of termination under this Clause take
Contractor's part only of the Subcontract Works out of the hands of the Subcontractor and may
Powers by himself or any other contractor execute and complete such part of the
Subcontract Works and remedy any defects therein and in such event the Contractor
may recover his costs of so doing from the Subcontractor, or deduct such costs from
monies otherwise becoming due to the Subcontractor.
Default of Contractor
19.1 In the event of the Contractor:
Default of
(a) failing to pay to the Subcontractor the amount due under any certificate within 28
Contractor
days after the expiry of the time stated in SubClause 16.3, within which payment
is to be made, subject to any deduction that the Contractor is entitled to make
under the Subcontract,
(b) interfering with or obstructing or refusing any required approval to the issue of
any such certificate,
(c) becoming bankrupt or, being a company, going into liquidation, other than for the
purpose of a scheme of reconstruction or amalgamation, or
(d) giving notice to the subcontractor that for unforeseen economic reasons it is
impossible for him to continue to meet his contractual obligations, the
Subcontractor shall be entitled to terminate his employment under the Subcontract
by giving notice to the Contractor, with a copy to the Engineer. Such termination
shall take effect 14 days after the giving of the notice.
19.2 Upon the expiry of the 14 days' notice referred to in SubClause 19.1, the Contractor
Removal of shall, notwithstanding the provisions of SubClause 12.1, with all reasonable
Subcontractor’s despatch, remove from the Site all Contractor’s Equipment brought by him thereon.
Equipment
19.3 The Contractor shall pay to the Subcontractor the amount of any loss or damage to
Payment on the Subcontractor arising out of or in connection with or by consequence of such
Termination termination.
19.4 Without prejudice to the Subcontractor’s entitlement to interest under SubClause
Subcontractor’s 16.3 and to terminate under SubClause 19.1, the Subcontractor may, if the
Entitlement to Contractor fails to pay the Subcontractor the amount due under any certificate within
Suspend Work 28 days after the expiry of the time stated in SubClause 16.3 within which payment
is to be made, subject to any deduction that the Contractor is entitled to make under
the Contract, after giving 28 days’ prior notice to the Contractor, with a copy to the
Engineer, suspend work or reduce the rate of work. If the Subcontractor suspends
work or reduces the rate of work in accordance with the provisions of this SubClause
and thereby suffers delay or incurs costs the Contractor shall, after due consultation
with the subcontractor, determine:
(a) any extension of time to which the subcontractor is entitled under Clause 7, and
(b) the amount of such costs, which shall be added to the Contract Price, and shall
notify the Subcontractor accordingly, with a copy to the Engineer.
48
19.5 Where the Subcontractor suspends work or reduces the rate of work. having given
Resumption of notice in accordance with SubClause 19.4, and the Contractor subsequently pays the
Work amount due, including interest pursuant to SubClause 16.3, the Subcontractor's
entitlement under SubClause 19.1 shall, if notice of termination has not been given,
lapse and the Subcontractor shall resume normal working as soon as is reasonably
possible.
Settlement of Disputes
20.1 If a dispute of any kind whatsoever arises between the Contractor and the
Amicable Subcontractor in connection with, or arising out of, the Subcontract or the
Settlement and execution of the Subcontract Works, whether during the execution of the
Arbitration Subcontract Works or after their completion and whether before or after
repudiation or other termination of the Subcontract, then the Contractor or the
Subcontractor may give a notice of such dispute to the other party, in which
case the parties shall attempt for the next fifty-six days to settle such dispute
amicably before the commencement of arbitration or other agreed dispute
settlement procedure specified under Part II, Particular Conditions of the
Subcontract. Such notice shall state that it is made pursuant to this Clause.
Any dispute which has not been amicably settled within fiftysix days after
the day on which such notice is given shall be finally settled by one of the
following procedures as defined under Part II, Particular Conditions of the
Subcontract.
Disputes of any kind whatsoever arises between the Contractor and the
Subcontractor in connection with, or arising out of, the Subcontract or the
execution of the Subcontract Works, whether during the execution of the
Subcontract Works or after their completion and whether before or after
repudiation or other termination of the Subcontract shall not suspend or
impede and shall not have any impact execution or any other activities of
the main contract.
20.2 (A) Any dispute which has not been amicably settled within fifty-six days after
Dispute arising the day in which such notice is given where the Contractor and the Sub
between locals or
Contractor are both from the Country of the Main Contract (Ethiopia) or
Local and foreign
contractor and when one of the parties is from the country of the Main Contract, shall be
subcontractor first refereed to an adjudicator or Adjudicators to be appointed under the
Adjudication Rules of Addis Ababa Chamber of Commerce and Sectoral
Association Institute.
(B) Any dispute in respect of which the recommendation, if any , of the
Adjudicator or Adjudicators has not become final and binding shall finally
settled by court of the county of the main contract or Arbitration under the
Rules of Arbitration of Addis Ababa Chamber of Commerce & Sectoral
Association by one or more Arbitrators appointed under such Rules, as
agreed by the parties.
(C) Referral to Adjudication or Arbitration/court may be commenced prior to
or after completion of the Sub Contractor works provided that the
obligation of the Contractor or the Sub Contractor shall not be altered by
reason of the adjudication or the arbitration being constituted during the
progress of the Sub Contract works,
49
20.3 (A) Any dispute which has not been amicably settled within sifty six days after the
Dispute arising day in which such notice is given where the Contractor and the Sub Contractor
Between Foreign are both from other countries which are/is not the country of the main contract,
contractor and the dispute may be referred to an Adjudicator/s, Dispute Review expert (DRE)
subcontractor
or Dispute Review Board (DRB) to be appointed under the Rules of any
institute or ad hock as the parties agree as indicated in Part II; the Particular
Condition of Contract .
(B) Any dispute in respect of which the recommendation if any, of the Adjudicator
Dispute Expert or Dispute Review Board has not become final and binding
shall be finally settled by Arbitration under the Rules of Arbitration as to be
agreed by the parties indicated in Part II; the Particular Conditions of Contract,
20.4 If a dispute of any kind whatsoever arises between the Employer and the Contractor
Dispute in in connection with, or arising out of, the Main Contract or the execution of the
Connection with Main Works, whether during the execution of the Main Works or after their
or Arising out of completion and whether before or after repudiation or other termination of the Main
Main Contract Contract, including any dispute as to any opinion, instruction, determination,
Touching or certificate or valuation of the Engineer, and the Contractor is of the opinion that
Concerning Sub such dispute touches or concerns the Subcontract Works and arbitration of such
contract Works dispute under the Main Contract commences, the Contractor may by notice require
that the Subcontractor provide such information and attend such meetings in
connection therewith as the Contractor may reasonably request.
21.2 Either party may change a nominated address to another address in the country
Change of where the Subcontract Works are being executed by prior notice to the other party.
Address
50
22.2 The base cost indices or prices shall be the base cost indices or prices of the Main
Base, Current and contract in the case where the subcontractor is assigned together with the Contractor
Provisional in the Main Contract or the current indices or prices of the Contractor under the
Indices Main Contract for the prevailing date on the day 28 days prior to the latest date for
submission of bids by the Subcontractor is considered as a base indices or price for
the subcontract. Current indices or prices shall be the Current indices or prices of
the main contract those prevailing on the day 28 days prior to the last day of the
period to which a particular Interim Payment Certificate is related.
22.3 If, on or after the date the Subcontract is executed, there occur in the country in
Subsequent which the Subcontract Works are being or are to be executed changes to any
Legislation National or State Statute, Ordinance, Decree or other Law or any regulation or bye
law of any local or other duly constituted authority, or the introduction of any such
State Statute, Ordinance, Decree, Law, regulation or byelaw which causes
additional or reduced cost to the Subcontractor, other than under SubClause 22.1,
in the execution of the Subcontract, such additional or reduced cost shall be agreed
between the Contractor and the Subcontractor, and shall be added to or deducted
from the Subcontract Price, to the like extent that such additional or reduced cost
shall be added to or deducted from the Contract Price under the Main Contract, but
no further.
23.2 Where the Subcontract provides for payment in whole or in part to be made to the
Rates of Exchange Subcontractor in foreign currency or currencies, such payment shall not be subject
to variations in the rate or rates of exchange between such specified foreign
currency or currencies and the currency of the country in which the Subcontract
Works are to be executed.
51
PART II CONDITIONS OF PARTICULAR APPLICATION CONTENTS
52
PART II CONDITIONS OF PARTICULAR APPLICATION CONTENTS
CLAUSE 1
Definitions 1.1 (a) (i) The Employer is (insert name)
(a) (ii) The Contractor is (insert name)
(a) (iv) The Engineer is (insert name)
(b)(i) The Main Contract between the Employer and the
Contractor is composed of the following contract documents
(insert particulars of the Main Contract)
( e) (ii) The Subcontract Works are (insert description,
including, 1f applicable, any matter of design or specification of
any part of the Permanent Works or of any Plant (as defined in
the Conditions of Main Contract) to be incorporated therein to
be provided in connection with any Provisional Sum (as
defined in the Conditions of Main Contract)
Performance 2.2 [Two example forms of performance security are given on pages
Security 6, 7 and 8 of Part II of the Federation Internationale des
IngenieursConseils' "Conditions of Contract for Works of Civil
Engineering Construction, Fourth Edition 1987 Reprinted 1992
with further amendments". The wording of the example forms
must be adapted to the Subcontract and may have to be varied to
comply with the law of the Subcontract which may require the
forms to be executed under seal.]
Programme to be 2.3 The time within which the programme shall he submitted by
Submitted by the Subcontractor shall be (insert number) days.
Subcontractor
CLAUSE 3
Language/s 3.1 The language is similar with the language of the mail contract
Governing Law 3.2 [If the governing law of the Subcontract is not the same as the
law of the country or state which applies to the Main Contract
and according to which the Main Contract is construed, this
should be indicated here as follows:]
53
Priority of 3.4
priority of part of the contract document is as follows:
Subcontract
Documents
(1) The Subcontract Agreement (if any);
(2) The Contractor's Letter of Acceptance;
(3) Minutes if pre contract award discussion (if any)
(4) Appendix to subcontractor’s offer
(5) The Subcontractor's Offer;
(6) Part II of the Conditions of Subcontract;
(7) Part I of the Conditions of Subcontract; and
(8) the subcontract specification
(9) Subcontract Drawings
(10) Priced Bill of Quantities or Price Schedule
(11) Any other document forming part of the Subcontract.
CLAUSE 4
Possible Effects of 4.4 If the Subcontractor is delayed in the execution of the
Subcontractor's Subcontract Works by circumstances which do not entitle the
Breaches of Subcontractor to an extension of the Subcontractor's Time for
Subcontract Completion then this would ordinarily be a breach of the
Subcontract. If as a result of such breach the Contractor became
liable for liquidated damages under the Main Contract the
Subcontractor would, under this SubClause 4.4, be liable to
indemnify the Contractor against the same.
CLAUSE 5
Subcontractor's Use 5.1
of Temporary
Works
Subcontractor's 5.2 The Contractor's Equipment and/or other facilities (if any) for
Use of Contractor's Subcontractor's use in common with other subcontractors are
Equipment and/or (insert description and specify terms and conditions of use, if
Other Facilities (if any)
Any) in Common
with Other
Subcontractors
54
CLAUSE 6
Working Hours on 6.1 The working hours of the Contractor, to be observed by the
Site; Subcontractor, is as per the main contract
Subcontractor's
Compliance with
Rules and
Regulations
Availability of Site 6.2 [If the Contractor is bound to give the Subcontractor exclusive
to Subcontract or control of any part of the Site, this should be stated here.]
and Access to Site
CLAUSE12
Incorporation by 12.1 [The parties may wish to agree on whether, and the extent to
References which, the Contractor shall assist the Subcontractor in respect of
customs clearance and reexport of Subcontractor’s Equipment.]
CLAUSE14
Subcontractor's 14.2 The period and terms as agreed by the subcontractor and the
Obligations after Contractor should be stated here.
TakingOver
CLAUSE15
Subcontractor's 15.1 The risks insured (or the insurances effected) by the Subcontractor
Obligation to Insure are (insert description, including sums and names ( of
beneficiaries)
CLAUSE20
Amicable 20.2/ [The Contractor and the subcontractor shall discussed and agreed
Settlement and 20.3 the dispute resolution procedure based on the Part I, the General
Arbitration Condition of Contract and the detail shall be discussed here.]
55
SUBCONTRACTOR'S OFFER
NAMEOFSUBCONTRAC *--------------
Gentlemen,
or such other sum as may be ascertained in accordance with the said Conditions.
5. Unless and until a formal Subcontract Agreement is prepared and executed this Offer,
together with your written acceptance thereof, shall constitute a binding contract
between us.
6. We understand that you are not bound to accept the lowest or any offer you may
receive.
Dated this Signature day of _ 199
Address _
Witness _
Address _
Occupation _
(Note: All details marked * shall be inserted before issue of Offer
documents.)
APPENDIX TO SUBCONTRACTOR'S OFFER
SubClause
Repayment of Advance
Payment (if any)
Percentage of Retention
SUBCONTRACT AGREEMENT
day of20
Between _
1. In this Subcontract Agreement words and expressions shall have the same meanings
as are respectively assigned to them in the Conditions of Subcontract hereinafter
referred to.
2. The following documents shall be deemed to form and be read and construed as part
of this Subcontract Agreement, viz:
1. The Subcontract Agreement (if any);
2. The Contractor's Letter of Acceptance;
3. Minutes if pre contract award discussion (if any)
4. Appendix to subcontractor’s offer
5. The Subcontractor's Offer;
6. Part II of the Conditions of Subcontract;
7. Part I of the Conditions of Subcontract; and
8. the subcontract specification
9. Subcontract Drawings
10. Priced Bill of Quantities or Price Schedule
11. Any other document forming part of the Subcontract
In Witness Whereof the parties hereto have caused this Subcontract Agreement to
be executed the day and year first before written in accordance with the laws of the
Main Contract County.
[Authorized Representative]
In the presence of
Name _______________________
Signature _______________________
In the presence of
Name _______________________
Signature _______________________
For and on behalf of [insert name of Subcontractor]
________________________________________________
[Authorized Representative]
In the presence of
Name _______________________
Signature _______________________
In the presence of
Name _______________________
1. Ayalew, T., Dakhli, Z. and Lafhaj, Z. (2016). Assessment on Performance and Challenges of
Ethiopian Construction industry. Journal of Architecture and Civil Engineering Volume 2 ~
Issue 11 pp.: 0111
2. Talukhaba AA and Mapatha M CIB world Building Congress, Selection Framework for
Domestic Subcontractors by Contractors in the Construction Industry School of Construction
Economics and Management Faculty of Engineering and Built Environment University of
the Witwatestand South Africa
3. Hakseerver, A.M, Kim H.S and Pickering, G, 1995, collaborative long term relationship in
UK construction industry: a lost opportunity in proceeding of the 11th ARCOM Conference,
University of York, UK
4. Oluwoye, J.O Macleannan H.M and Caolan C.G, 1996 Modeling building subcontractor
performance: a case stdy of the NSW construction industry. In proceeding of CIB working
commission 55 international symposium, Zagreb, Croatia,
5. Information on Subcontracting/Subletting parts of works including sample contract
agreements from CMD, EAST, West, South, Design and Build and North Regions
6. Chamara, KGA, S. and Harshini, M. (2015). Evaluating Subcontractor Performance in
Construction Industry. Paper presented at the 6th International Conference on Structural
Engineering and Construction Management, Kandy, Sirlanka.
7. Choudhry, R., Hinze, J., ASCE, M., Arshad, M. and Gabriel, H. (2012). Subcontracting
Practices in the Construction Industry of Pakistan. Journal of Construction Engineering and
Management. Volume 132~ Issue 12
8. Dykstra, A. (2011). Construction Project Management: A Complete Introduction. San
Francisco: Kirshner publishing company.
9. ERA. (2016). Annual road projects performance report .Available at:http://www.era.gov.et/
10. Hair, J. F,Black, W.C, Babin, B. J andAnderson, R. E (2010). Multivariate Data Analysis: A
Global Perspective, 7th edition. Published by Pearson Education
11. Kaliba, C. (2010). Cost Escalation, Schedule Overruns and Quality Shortfalls On
Construction Projects. Unpublished dissertation, University of Zambia
12. Lavelle, D., Hendry and Steel, G. (2007). The selection of subcontractors: Is price the major
factor? Paper presented at the 23rd Annual ARCOM Conference, 35 September 2007,
Belfast.
13. Lebas, D.L. (2014). Entering into Construction Contracts and Subcontracts, Construction
Law Seminar, Austin, Texas. [14] Lin, L. (2011). Supply chain quality management for
subcontracting systems in the construction industry. MEng thesis. Wollongong, New South
Wales: University of Wollongong.