Professional Documents
Culture Documents
DOI: 10.1002/suco.201800263
TECHNICAL PAPER
1
AECOM Middle East, Abu Dhabi, UAE
2
Abstract
School of Energy, Geoscience,
Infrastructure and Society, Heriot-Watt In this research, the effect of span and construction method on the designed cross
University, Dubai, UAE section, construction time, and cost of box-girder bridges has been explored. Two
types of construction techniques used in bridges were investigated and compared:
Correspondence
Mustafa Batikha, School of Energy, cast in-situ post-tensioned concrete and precast segmental bridge. To satisfy the
Geoscience, Infrastructure and Society, aim of this work, the structural design was analyzed for different span lengths
Heriot-Watt University, Dubai, UAE.
Email: m.batikha@hw.ac.uk
(40, 50, 60, 70, and 80 m) to evaluate the designed depth and required pre-
stressing strands, and then design outcomes were utilized in estimating the con-
struction duration and cost of cast in-situ and precast segmental construction
methods. Furthermore, the research has been extended to identify the impact of
construction duration on the total cost of studied bridges. This investigation
shows that the cost of a box-girder bridge is affected by the span and the con-
struction method where the precast segmental way was found to be less
expensive.
KEYWORDS
box-girder bridges, capital cost, cast in-situ concrete, construction duration, precast segmental
concrete, prestressed concrete
56 © 2019 fib. International Federation for Structural Concrete wileyonlinelibrary.com/journal/suco Structural Concrete. 2020;21:56–64.
HAIDER ET AL. 57
cheaper than using a prestressed-concrete I girder up to techniques in the UAE where the bridge number is rapidly
30 m span.7 It should be pointed out that the difference in in an increase. The effect of the bridge span on the construc-
the span limit among studies depends on the market prices. tion cost is discussed in this work through 10 bridges stud-
When the maintenance of the bridge (life cycle) is taken into ied. Furthermore, the construction duration was determined
consideration, all previous researches agreed that a and converted into a cost. So, the total cost was derived at
prestressed-concrete I girder is more economic for 20 m the end to provide a proper view of the decision maker.
span.3,7 The life cycle of a prestressed-concrete beam can It is worth mentioning that the casting of box
reach to a 45% less cost as indicated by Batikha et al.7 It section using “the one pour method” and “the precast seg-
may be noted that early maintenance actions guide to a bet- mental balanced cantilever technique”14 is studied in this
ter structural performance of the bridge.8 Therefore, the life research as they are the most common practice in the UAE.
cycle cost of a steel-concrete composite beam may dramati- The “one pour method” has two approaches to casting in-
cally increase. situ a box section. The first approach is casting the bottom
For spans more than 40 m, using cellular or box cross slab first through temporary holes in the top slab. Here, a
section becomes more economical. The construction of a minimum of 2 m deck-deep is required to allow the laborers
box-section bridge can be either in-situ concrete, precast to access the void space of the box section for spreading and
segments of 4–5-m longitudinal length or steel box section.5 vibrating the poured concrete. In the second approach, the
The latter can be used for the longest spans in order to concrete flows from the webs to reach the bottom slab.
decrease the self-weight of the bridge.5 The precast pres- Then, external vibrators can be utilized to complete the con-
tressed balanced cantilever box-girder bridges may achieve a creting process.14 In this research, the second approach has
150 m span.9 In fact, the need for accelerated bridge con- been used as it is more common and in line with the Middle
struction (ABC) through the precast method becomes an East local market practice.
urgent demand via many advantages this method offers such
as limitation in construction time, reducing the traffic disrup-
2 | STRUCTURAL ANALYSIS O F
tion and the construction impact on the surrounding busi-
DIFFERENT SPANS OF BOX-GIRDER
ness, high material quality-control, etc.4,10 Moreover, speed
BRIDGES
in construction is significantly wanted in countries with
severe weather such as the high heat (e.g., 55 C) and humid-
2.1 | Geometry, loadings, and material
ity (e.g., 90%) that the UAE has annually along almost properties
6 months.
Regarding the cost of the bridge construction, Turai and In order to achieve a rational comparison assessment
Waghmare11 show that a precast bridge is always less costly. between cast in-situ box girder and precast segmental brid-
The reduction in construction cost may reach a 31% cheaper. ges, five different two-span bridges of span lengths (40, 50,
Furthermore, the pay back period (PBP) of the invested cash 60, 70, and 80 m) are considered for each type of bridge
for a precast bridge is 2.5 years in comparison with 3.8 years construction technique.
for a cast in-situ bridge.11 Bakker12 studied many solutions The cross section of the box-girder bridge is shown in
for a bridge of two spans of 30 m each. Bakker's work sum- Figure 1 which illustrates the dead and live loading consid-
marized that the precast solution offers 61% less construc- ered for 10.4-m wide constant width box-girder section. The
tion duration than the in-situ activity. Although a precast bridge barrier load of 25 kN/m has been adopted considering
bridge registered a 5% higher construction cost than an in- the size of TL-4 type barrier in accordance with AASHTO
situ bridge, the CO2 emission was 26% lesser with a precast LRFD15 standard, while deck asphalt thickness of 100 mm
solution showing the positive impact of this solution on the has been assumed. HL-93 Live loads have been applied as
environment. It is worth mentioning that Florida Department article 3.6.1.2 of AASHTO standard15 where HL-93 loads
of Transportation13 estimates the construction cost of a long- consist of a truck load (Figure 2a) and tandem load
span precast high bridge from segmental concrete box girder (Figure 2b). The severe effect by one of them has been taken
with cantilever construction to be 24% less than the con- after adding a design lane load which is a uniformly distrib-
struction cost of a continuous bridge using prestressed uted load of 9.3 kN/m per lane.15 It should be noted that the
girder. However, the cost-comparison studies between the configuration of bridge section in Figure 1 allows for two
precast segmental bridges and the in-situ type of construc- lanes to occur. The dynamic allowance factor of 1.33 has
tion are still so limited. Moreover, the effect of the bridge been counted by enhancing the HL-93 Truck and HL-93
span on the cost of both kinds of construction is yet unclear. Tandem loadings.15
Therefore, the current study is trying to compare the cast in The concrete material was considered to have a cylindri-
place bridge and precast segmental bridge construction cal characteristic compressive strength equals to 50 MPa and
58 HAIDER ET AL.
modulus of elasticity of 38 GPa, while the steel reinforce- seven-wire strands were used where each strand has
ment has 500 MPa yield strength and 200 GPa elastic modu- 15.24 mm diameter and ultimate tensile strength of
lus. For prestressed section design, super low relaxation 1860 MPa.
HAIDER ET AL. 59
TABLE 1 Comparison summary of cast in-situ and precast box-girder design section in relation to span lengths
2.2 | FEM modeling and results simulated with beam elements and connected to the deck via
rigid link. The bottom of monolithic pier is fixed in both
Using finite element method by MIDAS Civil Ver 2.1,16
translation and rotation, taking into account the rigidity of
10 bridges have been simulated utilizing a two-node beam
element (Figure 3) where each node has six degrees of free- the footings founded on piles (Figure 3).
As seen in Table 1, the bending and shear diagrams have
dom. MIDAS software allows the time-dependent effect
(creep and shrinkage) to be undertaken into account during been obtained using a linear elastic analysis (LEA) and com-
the analysis. Bearings are modeled with elastic link by pro- pared with the ultimate capacities by AASHTO LRFD.15
viding relative fixity in X, Y, and Z direction and connected Moreover, Table 1 shows clearly that the section was almost
to the superstructure with the joint conditions that reflect the optimized since the margin of safety between the stress resul-
actual articulation of bridge bearings. The monolithic pier is tants and the capacities is within 10%.
60 HAIDER ET AL.
Deck Cross sectional Area (m2) 10.00 benefit to the deflection due to very long spans and heavy
9.50
Cast In-situ Box-Girder weight of cast in-situ deck with corresponding long-term
9.00 8.62
8.50
Precast Segmental Box-Girder creep effect due to deck weight and superimposed dead
8.00 loads. Therefore, the deck deflections of a cast in-situ con-
7.92
7.50 struction are found to be higher than a precast segmental
7.00 7.21
6.29 construction type.
6.50 6.88
5.89
6.00 5.66 6.34
5.50
5.20 5.53 3 | C O S T A N D T I M E A N A L Y S I S FO R
5.00
30 40 50 60 70 80 90 DIFFERENT TYPES O F BOX-GIRDER
Span length (m) BRIDGES
FIGURE 4 Deck cross-sectional area in terms of span length and
This section presents the cost and time analysis for both cast
method of construction
in-situ and precast segmental box-girder bridge. The con-
struction costs of 10 different bridge span lengths were esti-
22.00
Deck Cross sectional Inertia (m4 )
20.00
20.08 mated using unit rates of common types of bridge projects in
Cast In-situ Box-Girder
18.00 UAE. Comparisons and evaluation of the costs of the differ-
14.13
16.00 Precast Segmental Box-Girder ent bridge options were also conducted. Similarly, construc-
16.98
14.00
tion durations for the 10 bridge projects were developed
12.00
8.99 12.52 using Middle East project database. Furthermore, a study
10.00
8.00 8.97
was conducted to convert the effect of construction duration
4.64
6.00
2.80
into equivalent cost which was finally combined with con-
4.00 4.62 struction cost estimation to achieve overall bridge costs and
2.00 2.80
0.00
time comparisons for both cast in-situ and precast segmental
30 40 50 60 70 80 90 bridges. The cost analysis carried out in this study is based
Span Length (m) on the prices and work practices in the UAE. The findings
FIGURE 5 Deck cross-sectional inertia in terms of span length
of this research could be generalized in similar GCC coun-
and method of construction tries with similar market conditions. However, these out-
comes may not be applicable in other countries and regions
Figures 4 and 5 present the relative differences between with different market environment such as labor costs, mate-
precast construction and cast in-situ construction with rial costs, etc.
respect to span length of the bridge. As it can be shown from
Figure 4, cast in-situ construction offers 8% less area than 3.1 | Comparison and analysis of construction
precast construction for 40 m span because the obtained costs
shear force and bending moment by the precast bridge are
A detailed cost in Emirati Dirhams (AED) of five box-girder
19 and 15%, respectively, more than their counterparts of the
bridges of different spans and different section depths is pro-
cast in-situ bridge (Table 1). As the span length increases,
vided in Table 2. The additional costs required for a cast in-
the difference reduces till 60 m span; a cast in-situ box-
situ bridge cover the formwork installation. Whereas, the
girder area becomes higher by 20% compared with a precast additional costs of a precast bridge cover the precasting yard,
segmental deck section for 80 m span length, due to the lifting cranes, and transportation of the precast segments to
lower stress resultants for the 80 m precast bridge (Table 1). the construction site. Based on Table 2, it is worth noting
This means that the weight of the deck and dead loads will that the formwork cost for a cast in-situ bridge is about 22%
be higher for a long span bridge using cast in-situ construc- of the total cost, while the additional cost for a precast bridge
tion scheme and affects the design of piers and foundation is around 16% of the total cost. On the other hand, the mate-
which will result in large substructure sizes and less eco- rials cost in a precast bridge comes higher to balance with
nomic. On the other hand, the second moment of inertia the low value of other costs.
remains same from span length ranging from 40 to 60 m Table 3 and Figure 6 exhibit a comparison of the total
span length (Figure 5). Then after, the second moment of capital costs of the studied bridges projects. It can be
inertia for the cast in-situ box girder starts getting higher up observed that for span lengths ranging from 40 to 60 m the
to 18% than the precast-girder for 80 m bridge span. cost of cast in-situ box-girder bridge is less than precast seg-
Although the reduction in the inertia increases the deflection, mental box girder constructed using launching crane erection
18% gain of inertia for the cast in-situ deck will have minor method. For a span length of more than 60 m, it can be seen
HAIDER ET AL. 61
TABLE 2 Cost details of cast in-situ and precast segmental box-girder deck
TABLE 3 Cost comparison summary of cast in-situ and precast segmental box-girder deck
Cast in-situ Precast segmental Cast in-situ deck Precast segmental deck (precast/cast in-situ)
Span length (m) deck (AED) deck (AED) cost per meter (AED/m) cost per meter (AED/m) cost index
2 × 40 1,181,125 1,320,014 14,764 16,500 1.12
2 × 50 1,548,932 1,685,590 15,489 16,856 1.09
2 × 60 2,024,809 2,075,975 16,873 17,300 1.03
2 × 70 2,782,420 2,777,775 19,874 19,841 1
2 × 80 3,461,408 3,501,132 21,634 21,882 1.01
4,000,000
(Precast/Cast in-situ) cost
Cost of Box-Girder (AED)
1,548,932 1,685,590
2,000,000 0.80
1,181,125 1,320,014
1,500,000 0.60 Present study
1,000,000 0.40 FDOT Cost Index- Simple span
500,000 0.20 FDOT Cost Index- Continous span
0 0.00
40 50 60 70 80 40 50 60 70 80
Span Length (m) Span length (m)
FIGURE 6 Cost comparison of cast in-situ and precast box- FIGURE 7 Cost index of precast/cast in-situ box girder
girder bridge deck
TABLE 4 Construction duration summary of cast in-situ and precast segmental bridges
16
15.0 cost compared to other bridges. It was estimated that a con-
14
11.5
13.0 ventional construction for a bridge of 185 ft (56 m) may
Duration (Months)
12
9.0
10.0 9.5
take between 40 and 100% more time than using the precast
10
8.0 method. It can be seen that the determined time indexes in
8 Table 4 are almost within the range of the FHA report
8.5
6 in 2006.
6.5 7.0
4 Cast In-situ Deck Construction Duration
The durations of cast in-situ and precast box girder were
2 Precast segmental Construction Duration
converted into their money value equivalent. The cost as a
function of time has also been considered and estimated to
0
40 50 60 70 80 make the total cost difference of both deck options. For this
Span Length (m)
purpose, the cost related items during construction activities
FIGURE 8 Construction duration of cast in-situ and precast box at site are considered in accordance to the price specified in
girder Spon's Civil Engineering and Highway Price Book, com-
piled by AECOM.19 The cost rates are based on UK con-
struction market; therefore, a conversion factor was used
Based on previous bridge construction projects in UAE,
based on international construction costs factors compiled
Table 4 and Figure 8 explore the durations for different
by Neal and Rawlinson20 where the international currency
span lengths and duration ratios of different types of deck
options for this study. Figure 8 shows that the cast in-situ conversion from UK to UAE has been estimated at 0.9 based
bridge duration for 40 m span is 9 months; however, as the on the international market Forex conversion rates in the
span increases the duration also increases to reach second quarter of 2015.
15 months for 80 m bridge span causing prolongation of Table 5 shows an estimation of the total cost of cast in-
construction duration of 6 months. This prolongation in situ box girder including the cost of general time-related
time is due to the progressive start and finishing of activi- items (e.g., site staff salaries, plant maintenance, site trans-
ties constraining early completion of cast in-situ bridges. port of staff, contractor office rental, etc.). The per month
On the other hand, the precast girder duration for 40 m general items costs as estimated in Table 5 were factored
span is 6.5 months and reaches up to 9.5 months for 80 m with construction duration difference between cast in-situ
span. The increase in duration is only 3 months due to the and precast box-girder bridges.
execution of multiple activities running in parallel; there- Figure 9 displays the total cost variation for different
fore, taking less time. Furthermore, Figure 8 demonstrates span lengths of both options of box-girder bridges. The cost
that the construction duration of cast in-situ and precast of concrete deck includes the cost of general items which
box-girder deck is directly proportional to the length of the increases the overall bridge cost. By comparison, it has been
bridge. It is also evident that the rate of increase of con- observed that, for span length of 40 and 50 m, the costs of
struction duration of a cast in-situ deck is faster than a pre- both options are almost similar. However, for span lengths
cast girder. The delay in construction of a cast in-situ more than 50 m, precast box girder is found to be efficient
bridge is expected due to the installing and removing of the and less expensive than the cast in-situ option. Although the
formwork together with the concreting works. Therefore, maximum relative difference between the cast in-situ bridge
precast construction achieves a considerable reduction in and the precast segmental bridge is 10% (Table 5). The
construction duration. A survey undertaken by the Federal shorter construction duration of a precast bridge in Table 4
Highway Administration (FHA) in the United States in impacts positively on other factors (e.g., transportation, envi-
200618 recorded that prefabricated bridges save time and ronment, surrounding business, etc.).
HAIDER ET AL. 63
TABLE 5 Total cost of cast in-situ and precast box girder including time related general costs
4,898,080
Total Cost of Cast in-situ Deck
5,000,000
3,871,896
tion of cast in-situ construction, precast segmental bridges
Total Cost Precast Segmental Deck
are less expensive up to 10% lower compared to a cast-in-
4,000,000
2,850,895
4,411,023
situ bridge for two 80 m long spans.
3,000,000 From structural standpoint, both the precast and cast in-
2,147,545 3,490,125
1,612,126 2,650,644
2,000,000 situ box-girder bridges are appropriate options. Both bridge
1,631,292 2,104,619 types have high structural redundancy, torsional restraint,
1,000,000
and aesthetically pleasing appearances. Nevertheless, if a
0 project has construction space constraints, short construction
40 50 60 70 80
Span Length (m)
duration, and large-scale construction works, then precast
segmental bridge is considered to be the most feasible option
FIGURE 9 Cost variation of cast in-situ and precast box girder taking into consideration the advantages resulting from the
with respect to span reduction of construction duration.
4 | CONCLUSI ON S OR CI D