Professional Documents
Culture Documents
BSRIA would like to thank the following sponsors for their financial
contributions which have led to the production of this publication. The
project was undertaken under the guidance of a project steering group
drawn from representatives of these companies, and BSRIA staff.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted in any form or by any means electronic or mechanical including
photocopying, recording or otherwise without prior written permission of the publisher.
©BSRIA 16117 December 2001 ISBN 0 86022 583 6 Printed by The Chameleon Press Ltd.
© BSRIA AG 13/2001
CONTENTS & APPENDICES
1 INTRODUCTION 1
2 BASIC PRINCIPLES 2
2.1 Underfloor heating - system description 2
3 SYSTEM DESIGN 5
3.1 Typical arrangements 5
3.2 Design criteria 8
3.3 System sizing - general 9
3.4 System schematics 9
4 INSTALLATION AND MAINTENANCE 11
4.1 Pre-installation issues 11
4.2 General installation process 12
4.3 Maintenance 15
4.4 Thermographic surveys 15
CONTACTS 43
REFERENCES 44
APPENDICES
© BSRIA AG 13/2001
FIGURES
© BSRIA AG 13/2001
INTRODUCTION 1
1 INTRODUCTION
Basic principles
Here the essential principles of underfloor heating are addressed to
promote an understanding of the technology.
System design
The key points associated with an underfloor heating system are detailed
here, including system components and arrangements. The purpose of
this section is to allow the inspection personnel to quickly identify all of
the various elements that constitute a complete underfloor heating
system.
Installation
Relevant site and good practice issues will be dealt with here to help
ensure that any important points are thought of before they become a
problem on site.
2 BASIC PRINCIPLES
2.1 UNDERFLOOR With conventional radiators, the heat output is a product of the amount
HEATING -
SYSTEM
of surface area of the emitter or radiator and the average temperature of
DESCRIPTION the water flowing through it. Therefore, for a given radiator size, the
output can be varied by changing the mean water temperature.
This is the principle applied to underfloor heating where the size of the
emitter, in this case the floor, is so large that the mean water temperature
can be reduced to below that commonly used in radiators and still
provide the required heat output.
System components
The major components of an underfloor heating system are:
© BSRIA AG 13/2001
BASIC PRINCIPLES 2
More recently, however, other sources have become available which are
ideally suited to providing the low-grade energy required, such as
ground-source heat pumps.
Circulating pump
The circulating pump circulates the hot water produced by the boiler, or
other heat source, around the system and is similar to those used in most
types of heating system.
From the manifolds, individual pipework coils are run and laid in the
floor to provide the heating to the space, each coil constituting a separate
controllable circuit. For larger rooms or spaces, more than one circuit
may be required.
The length of the manifold will depend on the number of circuits being
provided, and manifolds can serve anywhere from two to twelve circuits.
In larger commercial applications, several flow and return manifolds will
be needed. Also, depending on the layout of a building, it may be
advantageous to have more than one pair of manifolds, even though
there may only be a relatively small number of circuits.
Insulation
This is generally applied beneath the circuit pipework to prevent
downward heat loss, thus maximising the heat output into the room.
It is also very important to provide edge insulation around the perimeter
of the area where underfloor heating is installed. This will avoid the
transference of heat into the vertical structure and away from the area to
be heated. It also allows for an amount of expansion of the slab.
© BSRIA AG 13/2001
SYSTEM DESIGN 3
3 SYSTEM DESIGN
The inspection staff should satisfy themselves that the relevant approved
drawings have been prepared and checked by the appropriate person
before any installation work on the underfloor heating systems
commences on site. Guidance on the design information to be checked
prior to starting the installation is included in the appropriate checklist at
the back of this document.
The standards that apply to the design (and soon the installation) of
underfloor heating installations include:
• BS EN 1264-1: 1998 Floor heating - Systems and components Part 1.
Definitions and symbols 3
[ ]
• DIN 4725, Part 4: 1992 Hot water floor heating systems; design and
construction (plus Amendment A1, December 1994)[6]
• DIN 4725: 2001 - Floor heating, systems and components - determination
of thermal output, pipe coverings larger than 0·065 m 7 .
[ ]
Wherever possible the inspection staff should try to ascertain if the design
has been carried out in accordance with these standards, and which other
design information has been used.
3.1 TYPICAL Although underfloor heating may be installed in almost any kind of
ARRANGEMENTS
construction, the three most common types of floor construction found
are:
The underfloor heating pipework is then laid onto the top of the
insulation and fixed by a number of methods including fixing rails or
individual clips. A third method is to fix the pipe to a steel mesh which
is embedded within the screed. All these methods can be used
individually, or in any combination to suit a particular application as
required.
A layer of screed is then laid on top of the pipework to form the heat
transfer medium, and to level and strengthen the floor ready for the final
floor finish of carpet, tiles or stone. With a screeded floor system it is
essential that the screed is allowed time to dry out thoroughly and that
such time is allowed in the construction programme. Failure of screed
due to insufficient moisture control can result in very expensive and
disruptive remedial works.
© BSRIA AG 13/2001
SYSTEM DESIGN 3
Floating floor
Floating floor installations are generally achieved by laying a pre-formed
high-density polystyrene panel on top of the prepared base, either an
existing flooring system or a new construction. The pipework is laid
into the pre-formed profile, with or without metal heat distribution
plates to distribute the heat over a wider area, and the floor decking –
generally chipboard or finished timber or laminate – is laid on top.
Although the decking sections are glued together, they are not fixed to
the insulation but left to ‘float’ on top of it. If carpet is to be used, this
can be laid onto the chipboard decking.
3.2 DESIGN CRITERIA Prior to commencement of the installation, the detailed design
information produced by the specialist supplier/installer should be
checked against the information or criteria provided originally by the
designer to ensure that what is being installed will suit the purpose for
which it is intended.
The design team should certify that certain criteria have been adhered to
during the detailed design, and the inspection staff should check the
appropriate checklist to see that this has been done. Some of the main
criteria are:
• internal and external temperatures
• U-values
• ventilation rates
• individual zones
© BSRIA AG 13/2001
SYSTEM DESIGN 3
3.3 SYSTEM SIZING - From the information provided by the design team, or agreed with the
GENERAL
client where the specialist is employed directly, the underfloor heating
specialist supplier/installer will carry out the design.
The inspection staff should try to ascertain whether or not the design has
been checked by the client/design team, and that the installation can
begin.
3.4 SYSTEM As well as detailed pipework layouts, the information provided should
SCHEMATICS
also include drawings showing the rest of the pipework in the system.
However, this latter information may not be provided by the underfloor
heating specialist as this may be outside their work package.
© BSRIA AG 13/2001
INSTALLATION AND MAINTENANCE 4
4.1 PRE- The actual installation process will run more smoothly if careful thought
INSTALLATION
ISSUES
is given to the process throughout the design and specification stage.
These should have been dealt with by the design team early in the
project. This will also make the inspector’s job easier because of
consideration at the appropriate stage in the project.
Design issues
It is easier and cheaper to resolve as many issues as possible at the design
stage rather than once on site, and typical points include programming
and builders’ work requirements.
Programme
• make sure that there is sufficient time allowed in the construction
programme for the works
• be aware of the implications that an underfloor heating installation
will have on the general programme. For example, the entire floor
area must be free of operatives from all other trades while the
pipework is installed
• before the pipework is laid the building should be protected from
[3,4,5,8]
inclement weather, as required by BS EN 1264
• the programme should also be arranged to have the screed laid as
soon as possible after the underfloor heating pipework has been
installed
• heavy traffic over the installation should be avoided.
Client issues
The client will have agreed certain key elements with the designers prior
to the design having been completed. These will be details such as:
• final floor finishes or coverings
• location of manifolds
• forms of control
• positioning of any items that need to be fixed to the floor.
Contractor issues
It is important for the contractor to understand the basic principles of the
underfloor heating installation so they are able to integrate it properly
and efficiently into the overall construction process. They will need to
give extra thought to the sequencing of the works on site to avoid delays
and lost production while the pipework is being laid, as the area having
the pipe installed needs to be free of all other staff, and damage to the
pipework once installed by arranging for the screed to be laid as soon as
possible after the installation of the pipework.
The contractor will also need to be made aware that the heating must
not be used to dry out the structure as soon as it is installed. Instead,
there is a lengthy running up period to actually bring the system into use
and this needs to be allowed for in the site organisation. This period also
includes for drying out of the screed, as discussed in Section 3.1.
General issues
Other general issues that need to be checked and closely monitored
during the installation works are:
• the use of the correct tools for working with the particular pipe and
fittings
• there should be no joints in the pipework that is to be covered
• there should be no kinks or creases in the pipework
• if there is a risk of freezing before the system is due to be fully
operative but has water in it, the underfloor heating specialist and
contractor must agree with the design team a suitable method of
preventing damage due to freezing. This may be achieved by
providing some additional local heating to raise the ambient
temperature, draining some of the water out of the system to allow
room for expansion or adding anti-freeze
• pipework should not overlap.
4.2 GENERAL The actual installation process followed by the underfloor heating
INSTALLATION
PROCESS
specialist may vary from project to project, for example taking into
account the different construction arrangements, contractual agreements
and work packages.
Provision of information
Make sure that sufficient information is provided by the underfloor
heating specialist. Final detailed design is done by the specialist and is
their responsibility, so make sure that you are satisfied with the
information they put forward. Things to check include:
© BSRIA AG 13/2001
INSTALLATION AND MAINTENANCE 4
Working drawings
Check the drawings that the underfloor heating specialist has produced
for working to and check the pipe routes carefully for possible conflicts
with other building elements.
Preparation
Make sure that the main contractor is aware of all the interfaces with the
other trades and that all the preparatory work has been done. This may
typically include holes through walls, laying of insulation (where not
provided by the underfloor heating specialist) and that all other trades are
out of the area and the space has been cleaned.
Installation of insulation
Make sure that the correct type and thickness of insulation has been used,
including the edge insulation. The edge insulation acts as an expansion
element as well as thermal protection. The insulation may be supplied
either by the underfloor heating specialist or the main contractor. It is
critical to check this as the main contractor or other members of the
design team may have agreed a change to the specification, for some
reason, which may affect the performance of the system. This should be
double-checked before the underfloor heating specialist starts work.
[3,4,5,8]
Expansion joints must also be allowed for, with BS EN 1264 stating
that they should be provided every 8 metres across the floor. Other
standards that may be applicable are DIN 18560 Parts 1-7[9] and
BS 8204 10 .
[ ]
With a suspended floor system, make sure that the insulation is installed
correctly and that it is adequately supported, with all joints sealed and a
vapour barrier installed where the insulation used may be porous.
Pipe should be laid straight and shall not have any kinks or creases.
There shall be no joints within the pipework.
In structural slab systems, once all the pipework has been installed on the
mesh, raise the mesh on spacers to give 40 mm cover over the pipework.
Pipework fixings
Ensure that the correct pipe clipping system is used, and that any clips are
fixed at the appropriate distances recommended by the manufacturer.
(See Section 3.1 Typical arrangements). When using anhydrite screeds,
it is essential to fix the pipework securely so that the pipework cannot
float above the screed.
© BSRIA AG 13/2001
INSTALLATION AND MAINTENANCE 4
9. check the flow and return temperatures. Again, this will depend on
the weather conditions at the time
10. check room temperatures
11. produce the commissioning report
12. check working drawings, modify as necessary and produce a
detailed set of record drawings.
The parts that are common to all heating systems, such as boilers and
circulating pumps, can be maintained as they would in any low
temperature hot water system.
Inspection staff will also need to carry out periodic checks for any leaks
around the manifolds and also to monitor the temperatures of the circuits
and compare these with the commissioning data.
4.4 THERMOGRAPHIC A very effective way of checking the quality of an installation, and also
SURVEYS
providing a record of the position of pipework within the floor, is to
have a thermographic survey carried out.
This can indicate not only the routes of the pipework but also provide
accurate information on floor surface temperatures to enable a quick
comparison with the design. This can highlight the causes of poor
performance of a system, as can be seen in Figure 6, which demonstrates
excessive floor surface temperature.
© BSRIA AG 13/2001
APPENDIX – PROJECT INFORMATION SHEET A
The basic information containing the contact details of the team involved
on the project are shown here. This is to be viewed as a
‘live’ document, and must be updated to reflect any changes in the
companies or personnel involved.
Date revised:
Revision No.
Site contact name: Revised by:
Telephone no. Signature:
This sheet should be completed by the *client/architect/project manager at the start of the project, and
updated thereafter as necessary. (*delete as necessary)
© BSRIA AG 13/2001
APPENDIX – THE DESIGNER’S CHECKLIST B
DESIGNER’S CHECKLIST
This checklist should be completed by the person responsible for the scheme design (ie consulting
engineer or architect) prior to commencement of the underfloor heating installation. Any answers that
require more than a yes or no or the space in the adjacent box is insufficient shall be detailed in the
Comments section on the reverse of this form.
Tel:
Fax:
E-mail:
2 Design information
2.1 Has the specification been produced as provided to the underfloor heating Yes
No
specialist?
2.2 Has the detailed design been produced by the underfloor heating specialist? Yes
No
2.3 Does the detailed design meet the specification? Yes
No
2.4 Are there any variations to the specification? Yes
No
2.5 Have the calculations been provided? Yes
No
2.6 Have the correct design criteria values been used? Yes
No
2.7 Have the correct drawing backgrounds been used? Yes
No
2.8 Are the calculations approved? Yes
No
2.9 Have the drawings been provided? Yes
No
2.10 Have the correct drawing backgrounds been used? Yes
No
2.11 Are the drawings approved? Yes
No
3 Approvals
3.1 Is the underfloor heating specialist authorised to proceed? Yes
No
3.2 Has the underfloor heating specialist been notified of the approval to start? Yes
No
3.2 Has the main contractor been notified of the approval to start? Yes
No
Comments:
© BSRIA AG 13/2001
APPENDIX – UNDERFLOOR HEATING SPECIALIST’S/INSTALLER’S CHECKLIST C
The company/s carrying out the detailed design and installation of the
underfloor heating system should complete this checklist.
Tel:
Fax:
E-mail:
2 Design information
2.1 Has the specification been produced by the designer? Yes
No
2.2 Has the detailed design been produced? Yes
No
2.3 Has all the necessary design information been provided? Yes
No
2.4 Has information on the heat source been provided? Yes
No
2.5 Does the detailed design meet the specification? Yes
No
2.6 Are there any variations to the specification? Yes
No
2.7 Have the calculations been submitted for approval? Yes
No
2.8 Have the calculations been approved? Yes
No
2.9 Have the drawings been submitted for approval? Yes
No
2.10 Have the drawings been approved? Yes
No
3 Site information
3.1 Has the builders’ work list been given to the main contractor? Yes
No
3.2 Have the builders’ work items been completed? Yes
No
3.3 Has the main contractor notified you of the approval to start? Yes
No
3.4 Has the work area been cleared? Yes
No
3.5 Has the insulation been laid? (if being done by the main contractor) Yes
No
Comments:
© BSRIA AG 13/2001
APPENDIX – THE MAIN CONTRACTOR’S CHECKLIST D
This inspection procedure should be carried out by the main contractor. Any answers that require
more than a yes or no shall be detailed in the Comments section on the reverse of this form.
1 Design
1.1 Has the designer’s checklist been provided? Yes
No
1.2 Has the designer’s checklist been completed? Yes
No
1.3 Is there any outstanding information required? Yes
No
1.4 Has commencement of the installation been approved? Yes
No
1.5 Has the underfloor heating specialist provided a builders’ work schedule? Yes
No
2 Preparation
2.1 Have the work areas been cleared? Yes
No
2.2 Are any other operatives working in the same area? Yes
No
2.3 Is the floor ready for installation of the insulation? Yes
No
2.4 Has all associated builders’ work been completed? Yes
No
2.5 Is the building watertight? Yes
No
3 Insulation
3.1 Has the insulation been installed? Yes
No
3.2 Has the insulation been installed as shown on the drawings? Yes
No
3.3 Is it of the specified material? Yes
No
3.4 Is it of the specified thickness? Yes
No
3.5 Is any remedial work required to the insulation installation? Yes
No
5 Inspection
5.1 Have all inspections been carried out? Yes
No
5.2 Is any remedial work required following the inspections? Yes
No
Comments:
© BSRIA AG 13/2001
APPENDIX – THE INSPECTOR’S CHECKLISTS – NO. 1–3 E
These checklists are for the inspector to complete, and plot the progress
of the installation from before the start on site to completion.
This inspection procedure should be carried out by the inspector prior to the commencement of the
underfloor heating installation. Any answers that require more than a yes or no or the space in the
adjacent box is insufficient shall be detailed in the Comments section on the reverse of this form.
1 Project information
1.1 Has the project information sheet been provided? Yes
No
1.2 Has the project information sheet been completed? Yes
No
1.3 Is there any outstanding information required? Yes
No
2 Design
2.1 Has the designer’s checklist been provided? Yes
No
2.2 Has the designer’s checklist been completed? Yes
No
2.3 Is there any outstanding information required? Yes
No
2.4 Has commencement of the installation been approved? Yes
No
2.5 Has the underfloor heating specialist provided a builders’ work schedule? Yes
No
3 Main Contractor
3.1 Has the main contractor’s checklist been provided? Yes
No
3.2 Have parts 1-3 of the checklist been completed? Yes
No
3.3 Is there any outstanding information in parts 1-3 required? Yes
No
3.4 Has commencement of the installation been approved? Yes
No
4 Preparation
4.1 Have the work areas been cleared? Yes
No
4.2 Are any other operatives working in the same area? Yes
No
4.3 Is the floor ready for installation of the insulation? Yes
No
4.4 Is the insulation being provided by the main contractor? Yes
No
4.5 If yes, have they installed it? Yes
No
4.6 Has all associated builders’ work been completed? Yes
No
Comments:
© BSRIA AG 13/2001
APPENDIX – THE INSPECTOR’S CHECKLISTS – NO. 1–3 E
This inspection procedure should be carried out by the inspector immediately following the installation
of the underfloor heating pipe, and before any flooring has been installed so that the pipe installation is
still clearly visible. Any answers that require more than a yes or no shall be detailed in the Comments
section on the reverse of this form.
1 Pre-commencement inspection
1.1 Has the pre-commencement inspection checklist been provided? Yes
No
1.2 Has the pre-commencement inspection checklist been completed? Yes
No
1.3 Is there any outstanding information required? Yes
No
1.4 Has commencement of the installation been approved? Yes
No
2 Insulation
2.1 Has the insulation been installed? Yes
No
2.2 Has the insulation been installed as shown on the drawings? Yes
No
2.3 Is it of the specified material? Yes
No
2.4 Is it of the specified thickness? Yes
No
2.5 Is any remedial work required to the insulation installation? Yes
No
3 Underfloor heating pipework
3.1 Has the builders’ work been completed? Yes
No
3.2 Has the underfloor heating pipework been installed? Yes
No
3.3 Has the pipework been installed as shown on the drawings? Yes
No
3.4 Is the pipework of the specified material? Yes
No
3.5 Is the pipework of the specified diameter? Yes
No
3.6 Is the pipework adequately clipped/secured? Yes
No
3.7 Have the manifolds been installed as shown on the drawings? Yes
No
3.8 Has the pipework been connected to the manifolds? Yes
No
3.9 Has the pipework been pressure tested? Yes
No
3.10 Has the test been witnessed and a certificate issued? Yes
No
3.11 Is any remedial work required to the pipework installation? Yes
No
Comments:
© BSRIA AG 13/2001
APPENDIX – THE INSPECTOR’S CHECKLISTS – NO. 1–3 E
This inspection procedure should be carried out by the inspector once they have been notified that the
installation of the underfloor heating system is complete. Any answers that require more than a yes or
no shall be detailed in the Comments section on the reverse of this form.
1 Screed/flooring installation
1.1 Has the screed/flooring system been installed? Yes
No
1.2 Has the final floor finish/covering been installed? Yes
No
1.3 Is it/is it to be the same as the specification? Yes
No
2 Underfloor heating pipework
2.1 Has the underfloor heating pipework been filled and tested? Yes
No
2.2 Has the pipework been connected to the heat source? Yes
No
2.3 Has the heat source been tested and commissioned? Yes
No
2.4 Have the appropriate certificates been provided? Yes
No
2.5 Has the underfloor pipework been connected to the heat source? Yes
No
2.6 Is the underfloor heating system water at working temperature? Yes
No
2.7 Is it the same as the specification? Yes
No
2.8 What are the water temperatures to/from the heat source system and manifolds?
Manifold No. 1: Flow: ºC Return: ºC
Manifold No. 2: Flow: ºC Return: ºC
Manifold No. 3: Flow: ºC Return: ºC
2.9 What are the water temperatures in the underfloor heating circuits?
Manifold No. 1:
Circuit No. 1: Flow: ºC Return: ºC
Circuit No. 2: Flow: ºC Return: ºC
Circuit No. 3: Flow: ºC Return: ºC
Circuit No. 4: Flow: ºC Return: ºC
Circuit No. 5: Flow: ºC Return: ºC
Manifold No. 2:
Circuit No. 1: Flow: ºC Return: ºC
Circuit No. 2: Flow: ºC Return: ºC
Circuit No. 3: Flow: ºC Return: ºC
Circuit No. 4: Flow: ºC Return: ºC
Circuit No. 5: Flow: ºC Return: ºC
Manifold No. 3:
Circuit No. 1: Flow: ºC Return: ºC
Circuit No. 2: Flow: ºC Return: ºC
Circuit No. 3: Flow: ºC Return: ºC
Circuit No. 4: Flow: ºC Return: ºC
Circuit No. 5: Flow: ºC Return: ºC
2.10 What are the circuit flow rates?
Manifold No. 1:
Circuit No. 1: l/min
Circuit No. 2: l/min
Circuit No. 3: l/min
Circuit No. 4: l/min
Circuit No. 5: l/min
Manifold No. 2:
Circuit No. 1: l/min
Circuit No. 2: l/min
Circuit No. 3: l/min
Circuit No. 4: l/min
Circuit No. 5: l/min
Manifold No. 3:
Circuit No. 1: l/min
Circuit No. 2: l/min
Circuit No. 3: l/min
Circuit No. 4: l/min
Circuit No. 5: l/min
2.11 What are the floor surface temperatures?
Room 1: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 2: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 3: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 4: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 5: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 6: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 7: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 8: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 9: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
Room 10: Max. temp. ºC Min. temp. ºC Ave. temp. ºC
2.12 Have the manifolds/circuits been commissioned? Yes
No
2.13 Have commissioning sheets been provided? Yes
No
2.14 Do the above readings match the design figures? Yes
No
2.15 Do the commissioning readings match the design figures? Yes
No
© BSRIA AG 13/2001
APPENDIX – THE INSPECTOR’S CHECKLISTS – NO. 1–3 E
Comments:
© BSRIA AG 13/2001
CONTACTS
CONTACTS
Unipipe Ltd
Web: www.unipipe.co.uk
Baxi Heating
Web: www.baxi.com
Range Cylinders
Web: www.range-cylinders.co.uk
REFERENCES
1 BS 7821 (all parts). British Standards relating to transformers and their use. BSI.
(Parts 1-4 published between 1995 and 1998.)
2 DIN 4726. Warm water floor heating systems and radiator pipe connecting - Piping of plastic materials.
Deutsches Institut für Normung e.V. 2000.
3 BS EN 1264-1: 1998. Floor heating - Systems and components. Part 1. Definitions and symbols.
BSI. 1998. ISBN 0 580 28910 9.
4 BS EN 1264-2: 1998. Floor heating - Systems and components. Part 2. Determination of the
thermal output. BSI. 1998. ISBN 0 580 28907 9.
5 BS EN 1264-3: 1998. Floor heating - Systems and components. Part 3. Dimensioning. BSI.
1998. ISBN 0 580 28901 X.
6 DIN 4725-4. Hot water floor heating systems - Part 4: Design and construction (plus Amendment A1,
December 1994). Deutsches Institut für Normung e.V. 1992.
7 DIN 4725-200: 2001. Floor heating, systems and components - Part 200: Determination of the
thermal output, pipe coverings larger than 0,065 m. Deutsches Institut für Normung e.V. 2001.
8 BS EN 1264-4: 2001. Floor heating - Systems and components. Part 4. Installation. BSI. 2001.
ISBN 0 580 38277 X.
9 DIN 18560 Parts 1-7. Screeds in building construction. Deutsches Institut für Normung e.V.
1992.
10 BS 8204 (all parts). Screeds, bases and in-situ floors. BSI. (Parts 1-5 published between 1993
and 1999.)
11 PEARSON C C AND BARNARD N. Guidance and the standard specification for thermal
imaging of non-electrical building services installations. FMS 6/2000. BSRIA. 2000.
ISBN 0 86022 540 2.
© BSRIA AG 13/2001