DAILY PROGRESS OF P.

WAY WORKS BETWEEN SHADNAGAR-GOLLAPALLY - NOVEMBER 2019 11-Nov-19


Shadnagar yard Shadnagar-Balanagar Balanagar yard Balanagar-Gollapally Gollapally Yard Gollapally-Jadcharla Jadcharla Yard Jadcharla-Divitipally Divitipalli Yard Divitipalli-MBNR MBNR Yard
CUMULATIVE PROGRESS
Ch: 58.121 to Ch:59.651 Ch:59.651 to Ch: 71.711 Ch:71.711 to Ch:73.104 Ch:73.104 to Ch:87.156 Ch:87.156 to Ch: 88.456 Ch:88.456 to Ch: 94.564 Ch: 94.564 to Ch:96.049 Ch:96.049 to Ch:102.495 Ch:102.495 to Ch:103.798 Ch:103.798 to Ch:112.029 Ch:112.029 to Ch:113.870

S.No Monitoring Item Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum. Day's Cum.
Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress Progress
1 Rail Pairing 0 0 240 7380 0 0 0 4570 0 0 0 0 0 5320 0 600 0 240 17700
2 Ballast dumping 0 0 200 5670 0 0 220 1155 0 0 0 0 0 5320 0 600 0 420 11260
3 Ballast spreading on the formation 0 0 200 4380 0 0 0 0 0 0 0 0 0 5320 0 600 0 200 10300
4 Sleeper Spreading on formation 0 0 0 4820 0 0 0 0 0 0 0 0 0 5320 0 600 0 0 10290
5 Rail Threading/Track Linking 0 0 0 4185 0 0 0 0 0 0 0 0 0 5320 0 600 0 0 10105
6 1st Round Packing 0 0 0 2240 0 0 0 0 0 0 0 0 0 5320 0 600 0 0 8160
2nd Round Packing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Welding of Rail Joints-MFBW 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Welding of Rail Joints-SKV 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 Assembling of Points & Crossings 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Insertion of Glued Joints 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 Assembling of SEJs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Insertion of SEJs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total
11 Activity wise Labour status
Labour
Rail Pairing 61/740-500 (9 men) 09 Nos
Sleeper Placement
Ballast dumping 62/230-410 80/440-660
Ballast spreading on the formation 68/520-720
Sleeper Spreading on formation
Rail Threading/Track Linking 09 NOS
1st Round Packing
2nd Round Packing
12 Supervisors
Sai sriram JE/P.WAY/PMC
PMC Saraiah, SSE/P.Way/PMC Uppala Swamy, SSE/P.Way
KPTL Md.Azarudding Arpit singh
1.52 kg - Cl.I Rails from SAIL Bhilai- H/O to KPTL- Qty:299.992MT(487 Nos)
13 Other Activities
2. 1 in 12 Switches: Qty received 13 Sets.(RH:09 sets,LH04 sets). GLY: 06 Sets and SHNR : 07 Sets unloaded

Day's Cum.
MATERIAL STATUS REMARKS
Progress Progress
14 Rails 0
a 60 kg 0 8166.122 MT
b 52kg 299.992 1924.27 MT
15 PSC Sleepers 0
a BG Track 1235 85679
b P&C - 1 in 8.5 0 0
c P&C - 1 in 8.5 Trap 0 14 SETS
d P&C - 1 in 12 0 11 SETS
e P&C - 1 in 16 0 0 SETS
f SEJ 0 0 SETS
g LC Sleepers 0 0 NOS
h Bridge Sleepers 0 305 NOS
i Bridge Approach Sleepers 0 25 SETS
16 Switches 0
1 in 8.5 0 0 SETS
1 in 8.5 Trap 0 0 SETS
1 in 12 13 26 SETS GLY:06 SETS SHNR :07 SETS
1 in 16 0 0 SETS