Distance

(km) Doubled Electrified Comments


Yelhanka-Rajanukunti 9 9 Expected to be ready for CRS inspection by 2019
Rajanukunti-Dodballapur 12 12 Expected to be ready for CRS inspection by 2019
Dodballapur-Oddarahalli 7 7 Earthwork done.
Earthwork done. Initial works for one major bridge at KM
50.7 are ongoing. New track laid on the Left Hand Side (LHS)
of the line proceeding from YNK to PKD. Not linked at MKL
Oddarahalli-Makalidurg 10 10 yet
Makalidurg-Thondebhavi 9 9 9
Thondebhavi-Someshwara 7 7 7
Someshwara-Gauribidanur 6 6 6
Gauribidanur-Vidurashwatha 6 6 6
Vidurashwatha-Devarapalli 6 6 6
Track bed completed on RHS @ KM 88.6 - KM 89.5. Hindupur
Devarapalli-Hindupur 11 11 (HUP) outer @ KM 98.3 - Earthwork completed on LHS
Hindupur-Malugur 10 10 Earthwork completed on LHS
Malugur-Chakarlapalli 13 13
Earthwork completed. Construction of bridges and culverts is
Chakarlapalli-Penukonda 14 14 ongoing
Penukonda-Makkajipalli 12 12
Makkajipalli-Nagasamudram 15 15
Nagasamudram-Dharmavaram 14 14
Penukonda-Narayanapuram 12 12
Narayanapuram-SSPN 8 8
SSPN-Katlichera 3 3
Katlichera-Basampalle 15 15
Basampalle-Dharmavaram 15 15
Ballast and sleepers have been placed on the track and bridge
Dharmavaram-Chigicherla 11 11 works were in progress. Track has been laid to some extent
Track has been laid in entire Zangalapalle - Chigicherla
section. Holes have been dug and cement work was being
done for installation of poles. Another bridge work is in
Chigicherla-Zangalapalle 9 9 progress
Earth work has been done & bridge work has been
completed. Ballast has been spread uniformly across the
leveled land. However, there is no sign of any electrification
work. At few places, sleepers have been placed and ballast
was being dumped on to the alignment. One major & small
bridge work is yet to be started. New PF & two storeyed
Zangalapalle-Prasannayapalli 9 9 railway station building is coming up in Zangalapalle
Not much progress is seen from Prasannayapalli till ATP
Outer. Just before a few kms of Prasannayapalli, earth
levelling has been done. New PF & two storeyed railway
Prasannayapalli-Anatapur 4 4 station building is coming up in Prasannayapalli
Anantapur-Taticherla 4 4 Earthwork complete.
Taticherla-Garladinne 8 8 Earthwork complete.
Garladinne-Kalluru 9 9 Bridge construction on Pennar river in progress
Kalluru-Pamidi 8 8 Earthwork complete.
Pamidi-Ramarjupalli 7 7 Earthwork complete.
Ramarjupalli-Turkapalli 5 5 Earthwork complete.
Turkapalli-Gooty 9 9 Earthwork complete.
Kalluru-Khaderpet 8 8
Khaderpet-Venkatampalle 11 11 11
Venkatampalle-Gulapalyamu 10 10 10
Gulapalyamu-Hanuman Circle 8 8 8
Hanuman Circle-Guntakal 3 3 3
Total 337 66 337
% Complete 20% 100%