This document provides a summary of distance, doubling, and electrification progress for various sections of a railway line totaling 337 km from Yelhanka to Guntakal. It notes that earthworks are largely complete but some bridge works are ongoing. Track laying has progressed on some sections but others show little work, and only 20% of the line has been doubled while electrification is 0% complete.
This document provides a summary of distance, doubling, and electrification progress for various sections of a railway line totaling 337 km from Yelhanka to Guntakal. It notes that earthworks are largely complete but some bridge works are ongoing. Track laying has progressed on some sections but others show little work, and only 20% of the line has been doubled while electrification is 0% complete.
This document provides a summary of distance, doubling, and electrification progress for various sections of a railway line totaling 337 km from Yelhanka to Guntakal. It notes that earthworks are largely complete but some bridge works are ongoing. Track laying has progressed on some sections but others show little work, and only 20% of the line has been doubled while electrification is 0% complete.
Yelhanka-Rajanukunti 9 9 Expected to be ready for CRS inspection by 2019 Rajanukunti-Dodballapur 12 12 Expected to be ready for CRS inspection by 2019 Dodballapur-Oddarahalli 7 7 Earthwork done. Earthwork done. Initial works for one major bridge at KM 50.7 are ongoing. New track laid on the Left Hand Side (LHS) of the line proceeding from YNK to PKD. Not linked at MKL Oddarahalli-Makalidurg 10 10 yet Makalidurg-Thondebhavi 9 9 9 Thondebhavi-Someshwara 7 7 7 Someshwara-Gauribidanur 6 6 6 Gauribidanur-Vidurashwatha 6 6 6 Vidurashwatha-Devarapalli 6 6 6 Track bed completed on RHS @ KM 88.6 - KM 89.5. Hindupur Devarapalli-Hindupur 11 11 (HUP) outer @ KM 98.3 - Earthwork completed on LHS Hindupur-Malugur 10 10 Earthwork completed on LHS Malugur-Chakarlapalli 13 13 Earthwork completed. Construction of bridges and culverts is Chakarlapalli-Penukonda 14 14 ongoing Penukonda-Makkajipalli 12 12 Makkajipalli-Nagasamudram 15 15 Nagasamudram-Dharmavaram 14 14 Penukonda-Narayanapuram 12 12 Narayanapuram-SSPN 8 8 SSPN-Katlichera 3 3 Katlichera-Basampalle 15 15 Basampalle-Dharmavaram 15 15 Ballast and sleepers have been placed on the track and bridge Dharmavaram-Chigicherla 11 11 works were in progress. Track has been laid to some extent Track has been laid in entire Zangalapalle - Chigicherla section. Holes have been dug and cement work was being done for installation of poles. Another bridge work is in Chigicherla-Zangalapalle 9 9 progress Earth work has been done & bridge work has been completed. Ballast has been spread uniformly across the leveled land. However, there is no sign of any electrification work. At few places, sleepers have been placed and ballast was being dumped on to the alignment. One major & small bridge work is yet to be started. New PF & two storeyed Zangalapalle-Prasannayapalli 9 9 railway station building is coming up in Zangalapalle Not much progress is seen from Prasannayapalli till ATP Outer. Just before a few kms of Prasannayapalli, earth levelling has been done. New PF & two storeyed railway Prasannayapalli-Anatapur 4 4 station building is coming up in Prasannayapalli Anantapur-Taticherla 4 4 Earthwork complete. Taticherla-Garladinne 8 8 Earthwork complete. Garladinne-Kalluru 9 9 Bridge construction on Pennar river in progress Kalluru-Pamidi 8 8 Earthwork complete. Pamidi-Ramarjupalli 7 7 Earthwork complete. Ramarjupalli-Turkapalli 5 5 Earthwork complete. Turkapalli-Gooty 9 9 Earthwork complete. Kalluru-Khaderpet 8 8 Khaderpet-Venkatampalle 11 11 11 Venkatampalle-Gulapalyamu 10 10 10 Gulapalyamu-Hanuman Circle 8 8 8 Hanuman Circle-Guntakal 3 3 3 Total 337 66 337 % Complete 20% 100%