Professional Documents
Culture Documents
Rev.0
1. TABLE OF CONTENTS
Part B: Commercial
4. Key Concerns.................................................................................5
5. Subcontracts (Financial)................................................................6
Appendices
1. Overall Cost Summary Report
2. Schedule of Price
a. Cash In Data
c. Cash Flow
1.1 General
This project is a District Cooling Plant for Rihan Heights; it is a fast track
project to be Completed within 10 Months.
• Type of Contract Lump Sum Fixed Price
• Total Lump Sum Value AED 53,166,016.00
• Provisional Sum ( Temporary
Generator) AED 2,504,439.00
By Client
• Construction All Risk Insurance & Third Party Liabilities.
By Kharafi National
• Workmen’s Compensation Insurance, Third Party Liability, Employer’s Liability Insurance
USD 5 million, Motor Vehicles Insurance, Contractor’s Plant & Equipment Insurance.
• Marine Cargo Insurance.
• Professional Indemnity in an amount of AED 10 million from the commencement date until
the date which is twelve (12) years after the date of Taking Over Certificate.
• The Performance Security shall be for an amount equivalent to ten (10) percent.
4.0 Key
4.1 Material and Equipment Delivery
• Material approvals and early procurement is critical to avoid further material
delays whereas such delays will clear the way to have a risk of liquidated
damages.
• Material Submittal & Procurement log to be monitored closely.
4.3 Overruns
• Overrun is expected in the subcontracts for Hydrostatic test- Flushing and
Chemical Cleaning as the estimated budget was found to be low.
5.0 Subcontracts
Potential
Task No. Expenditure Type SUBCONTRACT Value (AED)
Subcontractors
Mechanical
4.15.07 Subcontracts Testing HVAC Initial Start-up Under process 115,017
4.15.07 Subcontracts Testing HVAC Testing, Balancing Under process 80,018
4.15.10 Subcontracts Special Systems Fire Fighting System Under process 122,425
4.15.11 Subcontracts Special Systems Fire Fighting System Under process 826,767
4.15.12 Subcontracts Construction Electric Chain Hoist Under process 40,843
4.15.07 Subcontracts Construction Flushing /Chemical Flushing Under process 35,000
4.15.07 Subcontracts Construction Testing & Commissioning Under process 25,000
Modular District Cooling Plant
4.15.13 Subcontracts Construction Stellar 21,253,000
(Stellar)
Electrical
4.15.08 Subcontracts Construction HV Cable Laying & Termination NCI 45,500
4.15.09 Subcontracts Special Systems Fire Alarm System Under process 19,941
4.15.09 Subcontracts Special Systems Telecommunication System Under process 2,000
4.15.08 Subcontracts Construction Cabling Under process 76,500
Special System - SCADA Control &
4.15.14 Subcontracts Special Systems Stellar 1,026,596
Automation (Stellar)
Civil Works
4.15.02 Subcontracts Construction Waterproofing Beam Engineering 132,831
4.15.04 Subcontracts Construction Steel Doors Under process 89,676
4.15.04 Subcontracts Construction Wooden Doors Under process 12,805
4.15.04 Subcontracts Construction Aluminum Windows, louver windows Under process 40,200
4.15.05 Subcontracts Construction Metal Works Under process 5,250
4.15.05 Subcontracts Construction Suspended Ceiling Under process 11,197
4.15.02 Subcontracts Construction Epoxy Floor Coating Under process 15,235
4.15.04 Subcontracts Construction Steel Gates Under process 38,750
4.15.02 Subcontracts Construction GRP Lining Under process 182,280
4.15.06 Subcontracts Construction Geotechnical Report Matrix Laboratory 13,529
4.15.07 Subcontracts Construction Material Testing Under process 31,000
4.15.05 Subcontracts Construction GRP Ladder Under process 10,712
4.15.05 Subcontracts Construction Kitchen Equipments Under process 15,804
Misc.
4.15.06 Subcontracts Engineering Environment Assessment Study Under process 30,000
Services during Defect Liability
4.15.15 Subcontracts Services Under process 210,675
Period
4.15.06 Subcontracts Engineering Design (Stamping Purpose Only) DC PRO 125,000
Operation & Maintenance for 12
4.15.15 Subcontracts Services Under process 1,396,524
Months