MOMBASA PORT - AREA DEVELOPMENT PROJECT

PACKAGE 3: CONSTRUCTION OF MTEZA - KIBUNDANI SECTION


GRADUATE TRAINEE WEEKLY REPORT
MWONGA MICHAEL MWENDWA
th
AS AT 24 AUGUST 2019
Location/
Date Activity Remarks
Chainage
th
Monday 19 Km 16+400-560 &
5th fill layer joint cross-sections
August 2019 Km 16+740-860
th Layer thickness analysis
Tuesday 20
rd
August 2019 3 fill layer joint cross-sections Km 14+340-420
th
6 Fill Layer joint cross-sections Km 16+740-880
st th
Wenesday 21 4 Fill Layer joint cross-sections Km 14+340-420
August 2019 th
6 Fill Layer joint cross-sections Km 16+400-540
th
7 Fill Layer joint cross-sections Km 16+560-660
nd Layer thickness analysis
Thursday 22
August 2019 7th Fill Layer joint cross-sections Km 16+740-860
th
rd 7 Fill Layer joint cross-sections Km 16+400-540
Friday 23 th
5 fill layer joint cross-sections Km 14+340-420
August 2019 th
8 Fill Layer joint cross-sections Km 16+740-860
th
6 fill layer joint cross-sections Km 14+340-420
th
8 Fill Layer joint cross-sections Km 16+560-660
Saturday 24th
August 2019 Topo of the stockpiled materials in
the contractor's camp with the aim Contractor's camp
of calculating their quantities