You are on page 1of 6

MOMBASA PORT - AREA DEVELOPMENT PROJECT

PACKAGE 3: CONSTRUCTION OF MTEZA - KIBUNDANI SECTION
GRADUATE TRAINEE WEEKLY REPORT
MWONGA MICHAEL MWENDWA
st
AS AT 31  AUGUST 2019
Location/
Date Activity Remarks
Chainage
th  Km 16+560-660 & 
Monday 26
9th fill layer fill levels
August 2019 Km16+740-16+840
th
6  fill layer fill levels Km 14+340-14+420
th  Layer thickness analysis  Km 16+420-16+540
Tuesday 27
th
August 2019 9  fill layer fill levels Km 16+400-540
th
10  fill layer fill levels Km 16+560-660
Culvert excavation levels Km 16+860
Wenesday 28th  7th fill layer fill levels Km 14+340-420
August 2019 10th fill layer fill levels Km 16+740-860
Km 16+400-660 & 
Layer thickness analysis
Km 16+740-16+880
Stockpile quantity calculations Contractor's camp
th Km 16+400-540 & 
Thursday 29   Layer thickness analysis
August 2019 Km 16+740-880
10th fill layer fill levels Km 16+400-560
11th fill layer fill levels Km 16+560-660
th
8  fill layer fill levels Km 14+340-420
th
11  fill layer fill levels Km 16+740-840
th
Friday 30   Topsoil stripping levels Km 13+600-710
August 2019 Culvert excavation levels Km 14+430
Km 16+580-660 & 
Layer thickness analysis
Km 14+320-420
11th fill layer fill levels Km 16+400-540
th
st 9  fill layer fill levels Km 14+340-420
Saturday 31   th
August 2019 12  fill layer fill levels Km 16+560-660
Km 16+400-560 & 
Layer thickness analysis
Km 16+740-880
Rise and Fall Method
Back Sight  Intermediate  Fore Sight  Reduced 
Rise Fall
(BS) Sight (IS) (FS) Level
Height of Collimation Method
Back Sight  Intermediat Fore  Height of  Reduced  Remark
Remark
(BS) e Sight (IS) Sight (FS) Collimation Level

You might also like