All sections of this form must be filled in prior to completion of the risk assessment
Title: Olympic Dam EP6 Permanent Works CRAW
After the risk assessment is completed and approved, the owner of the assessment is to:
a) Upload the completed assessment to the Project Risk/ HSEC folder, then issue final copy to all relevant stakeholders
b) Enter actions into the relevant system to track to completion
c) Notify and gain approval from the OD Area Owner of any newly identified fatality risks or deviations from nominated OD Material Risk Critical Controls
Scope / Objectives:
Second CRAW for EP6 covering the execution of the SMPE&I components
M Collingwood
James Marner
A Hazelton
M Ferris
D Henze
B Jones
D Wilford
G Smith
A Thompson
G Thompson
R Brandt
S Goddard
P Dyson
S Chalmers
M Tirol
M Pakula
A Halliday
Brad Morice
Trevor Aldersea
Vicki Penhall
I have reviewed this risk assessment and am satisfied that the hazards have been identified and the risk will be managed by existing controls and implementation of the
action plan.
Department: Date:
1 Mobilisation of Personnel
1. Social Distancing
2. Cleaning and Decontamination Practices
3. Personal Protective Equipment (PPE)
4. Isolation and Self Monitoring Practices
1.4 Mobilisation of personnel to site Physical health Health & Safety COVID-19 NA NA 5. Workplace Entry and Travel Restrictions 2 Unlikely 3 2 Unlikely 3
6. Personal Hygiene Practices
7. Appropriate Site Medical Response Resources & Equipment
8. Field Leadership CCOs to check for implementation and compliance with the above (COVID-19 CCO)
Project HSEMP;
Inexperienced drivers / unlicensed 1. Vehicle design and specification Valid Australian licence;
drivers; 2. Vehicle maintenance Vehicles registered, site compliant & maintained in a roadworthy condition;
Failure to adhere to road traffic rules; 3. Operator competency Daily vehicle pre-start checks completed;
Vehicle pre-start checks not 4. Positive Communications and Accessing Vehicle maintenance inspections and repairs done regularly;
5.1. Vechicle incident - Light vehicle incident (including off-
1.8 Travel to / from work Vehicles / Transport Interaction with public and site vehicles Health & Safety completed; Construction Work Area or Active Mining Area Defective vehicles tagged out and removed for service; 3 Highly Unlikely 3 3 Highly Unlikely 3
site driving)
Not driving to environmental 5. Road design and maintenance Wear seat belts at all times when vehicle is in motion;
conditions (visibility, road surface, 6. Traffic management plan Drive to conditions;
weather); 7. Journey management (off-site and/or Reverse Parking only;
remote driving) Limited driving on public roads to be managed by Supervision;
Journey Management Plan
Portable wind monitor to be used for task, no go / stop if wind gusts excessive;
Competent & trained crane operator & rigger (VOC);
Daily weather report made available at pre-start to all crews;
Check crane specifications and correct assessment of load size and type;
Ineffective or absent suitable lift plan; Pre-lift checklist (simple lifts only) assessment and TTTC are required;
Personal injury during crane lifts due No lifts over 75% of any cranes indicated load chart SWL without lift study;
to wind conditions; 1. Task planning and execution Use of load charts;
Non competent crane operator / 2. Load inspection and documentation Assess ground conditions;
Loss of control of buildings during crane
2.2 Loading / unloading materials and buildings from transport truck Rigging & Lifting
operation loading / unloading
Health & Safety dogman; 9. Loading and unloading cargo from truck incident 3. Designated & controlled loading area Daily pre-start inspections; 3 Highly Unlikely 3 3 Highly Unlikely 3
Non compliance to project 4. Fit for purpose equipment In-date annual crane inspection;
requirements (crane lifts); 5. Operator competency Evidence of service records and maintenance regime;
Wrong size crane for lift and lifting Itinerant Classified Lifting P&E Procedure followed;
gear Check for services in area overhead & below ground;
De-rate if on slope or articulated as per requirements;
Tag lines 16mm rope
At Risk' proximity of unloading to 1. Task planning and execution Use of Lifting Plant and Equipment Procedure
existing structures, building or plant; 2. Load inspection and documentation VOC / Competent Riggers / Crane Operators / Forklift Operators
2.5 Loading / unloading materials and buildings from transport truck Rigging & Lifting Plant on Plant interface Health & Safety No spotter in place 9. Loading and unloading cargo from truck incident 3. Designated & controlled loading area Pre Start inspections of Lifting Gear Crane / Forklift 3 Unlikely 10 3 Unlikely 10
Property damage due to contact with 4. Fit for purpose equipment Tag Lines
forklift / transport equipment 5. Operator competency Spotters
Personnel not inducted / authorised All intended personnel will go through G&S mobilisation process;
2.7 Transport materials, plant, equipment and buildings to site Procedures Site Access Health & Safety
for site
NA NA
All personnel to complete the Client and G&S site induction
2 Unlikely 3 2 Unlikely 3
1SAP
Item Task/Activity Step Actions Required Responsibility Due Date
Work Number
example Pedestrian crossing the road on site Install lighting at all established pedestrian crossings on site to assist with visibility Joe Bloggs 1/1/2010 1234567
G&S Emergency Response Plan to be aligned with Teneo ERP and OD Review of site and plan.
1 4.6 Emergency Procedures
Also include tailings dam wall failure as scenario under ERP.
Daniel Wilford (Chris Ryan) 5/30/2020
2 5.1 Operating Mobile Plant Maintenance protocols to be developed and implemented for Mobile Plant/equipment breakdown in field. Daniel Wilford (Matt Ferris) 5/30/2020
These prompts provides some key words to assist with hazard identification.
The list is not exhaustive but provides examples that cover a variety of situations.