Drill 24" RBit to 12m TECBM#P02-P Time-Depth Plot

171/2" Rbit Days from spud


0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00
0
Hole condition, RIH
casing
Drill 24" RBit 20",cementing,WOC,
preparing OH 17-1/2"
100
13 3/8" casing, Drill of formation with
cement, WOC, BHA TCB 17-1/2",
N/U Diverter from12 mMD to
200 83mMD

Drill 12 1/4" Rbit Well condition, RIH 13-


3/8" casing,cementing
& WOC
300
Nipple up 13-5/8" BOP;pressure test
choke & manual valve.Pressure test
Depth (M)

9 400
5/8" casing, annular 13-5/8" x3000psi
cement,
WOC,N/U BOP 7" Casing, Cement, WOC,
N/D 13 5/8" BOP, N/U 7 1/16" BOP
500 Run GR - CBL
Drill 8 1/2" Rbit
Perfo-DFit-Frac Simulation)
Completion Job
600

TD Prognosis = 610m
700

800

Prognosis Actual