ARMOUR ENERGY LTD
Level 27, 111 Eagle Street - Brisbane 4000
DATE : 9/15/2013
REPORT No : 3
D.F.S. : 3
Page 1 of 3
ARMOUR ENERGY DAILY DRILL
Level 27, 111 Eagle Street - Brisbane 4000 Armour Site Repres
Rig : (07)3999-842
FROM TO HOURS
0:00 1:00 1.0 clean out cement from cellar
1:00 3:30 2.5 Slack off casing and remove
3:30 4:30 1.0 Break out casing drive sub and set up for drilling
4:30 5:00 0.5 RIH 8 1/2" PDC and add diverter rubber
5:30 7:30 2.5 Drill out cement plug and shoe.WOB#4000.
5:00 8:00 1.0 PJSM/Pull out Lay out BHA
7:30 8:30 0.5 POOH and lay out pipe
8:00 14:30 6.0 Repair Rod Handler(Nitro Fitter on Location)-Rig Repair
8:30 18:00 3.5 Drill 8 1/2" hole with hammer to 17.8m to 79m
14:30 18:30 0.5 Crew change/PJSM
18:00 0:00 5.5 Drill 8 1/2" hole with Hammer to 152m
18:30
24.5
OPERATIONS at 06:00 HRS : Break down 8 1/2" BHA
DATE : 9/15/2013
REPORT No : 3
D.F.S. : 3
up for drilling
bber
B#4000.
Location)-Rig Repair
.8m to 79m
52m
PERMITS ISSUED 3
PRE TOUR MEETING 2
INCIDENTS REPORTED
SCD INTRUCTIONS
JSA
HAZOBS
Page 2 of 3
WELL : Myrtle Basin 1
Report # 7
Report For 10/2/2013
Report Date : 10/2/2013
WEATHER :
Summary of Ops Past 24 hrs Drilled 8 1/2" hole with hammer to 152m (24:00hrs)
CH Inductions 0
5 day Forecast
Monday, 16 september 2013 Drill 8.5" hole/nipple down riser assy?nipple up "A" section
Tuesday, 17 september 2013 Rig up & Run casing and cement nipple up and test bop
Wednesday, 18 september 2013 Drill out and FIT Trip BHA M/up 6.25" assy
Thrysday, 19 september 2013 Drill 6,25 hole
Friday, 20 september 2013 Drill 6,25 hole