You are on page 1of 7

Delays in Construction Projects:

Causes and Mitigation

Aleksander Srdić, Ph.D. Assoc. Prof. Jana Šelih, Ph.D.


University of Ljubljana, Faculty of University of Ljubljana, Faculty of
Civil and Geodetic Engineering, Civil and Geodetic Engineering,
Slovenia Slovenia
aleksander.srdic@fgg.uni-lj.si jana.selih@fgg.uni-lj.si

DOI 10.5592/otmcj.2015.3.5 During execution of construction projects, the works proceed


Research paper at a slower pace than planned, and delays frequently appear.
Their appearance leads to additional cost generation, conflicts
among project participants and, in worst-case scenario, litiga-
tion. The presented study uses online survey as the research tool in
order to determine the current level of use of time management tech-
niques and tools in Slovenian construction industry. The obtained
results show that the construction companies could use the available
contemporary time management tools in larger extent, as well as more
efficiently in order to manage their projects more efficiently.

Keywords
Delays; Construction
Project; Responsibility;
Empirical study

a. srdić · j. šelih · delays in construction projects: causes and mitigation · pp 1383-1389 1383
INTRODUCTION of delays in previous phases. Special parison between the as-planned and
Construction projects are complex en- attention should be therefore placed to as-built schedule, since this informa-
deavours, associated with large costs the preparation stage, and ensure that tion form the basis for resolving claims
and long duration. A large number of adequately detailed documentation is and disputes among the stakeholders
interconnected activities carried out available at the start of the project. involved. Yang & Kao [6] reviewed 18
by different project participants need When dealing with the delays, it is delay analysis methods. On this basis,
to be carried out during execution of not only important to identify delays they proposed 6 suggestions to be
a construction project. Even when the and quantify the delay impacts on used in development an ideal delay
plans are prepared with due diligence, project performance but also to iden- method. Application of window analy-
uncertainties and unexpected events tify and quantify the impacts of delays sis, where the critical path is split into
appear during project execution. Often, already occurred upon further project timeframes, and only partial as-built
such events lead to delays that have an development. In order to determine critical paths are modelled, was pre-
adverse effect upon the execution and responsibility and enable to learning sented in this work as well.
performance of the project [1-3], all from these undesirable events, the in their work, Sun & Meng [7] con-
construction project stakeholders (in- primary causes and origin of delays ducted a comprehensive survey of
cluding final users) may suffer when a should be identified as well. literature. The obtained results show
delay occurs [4]. The responsibility for the occur- that the identification of delays is pre-
Delays occur due to a variety of rea- rence of a particular delay can be al- dominantly carried out on the basis of
sons (or, in other words, have various located to one (or several) project existing documentation of the com-
origins); con be compensated or not; stakeholders. If these responsibilities pleted projects; more precisely, this
and they may appear concurrently are not identified before the onset of method was used in 49 papers out of
or subsequently. Further, the impact the project, there is a risk of conflicts 101 surveyed articles. In 36 papers, the
caused on the project performance among project stakeholders regarding delays were studied by obtaining the
may be direct or indirect. Their ap- the responsibility allocation that may response through the use of stand-
pearance leads to additional cost gen- lead even to litigation. Responsibility ardized questionnaires that included
eration, conflicts among project par- allocation matrix defined prior to the questions of ranking the importance
ticipants and, in worst-case scenario, project can therefore be an extremely of individual causes. Case study ap-
litigation where additional costs may useful conflict management tool as it proach and interviews were used in 28
be generated. clarifies the roles and responsibilities and 13 articles, respectively. The clas-
Often, delays appear already in the in projects. On this basis, the financial sification of delays that can be found in
initial stages of the construction proj- compensation for harmful events can the relevant professional and scientific
ects, such as the stage of the prepara- be determined. literature is most often based on iden-
tion of the general plans, or conceptual tification of the delay origin, or, in oth-
design, obtaining the building permit Literature survey er words, responsibility for the delay.
etc. As a consequence, the construction Delays have been systematically ana- Kartam [8] classified the delays with
process itself is frequently delayed al- lyzed by several researchers. Sweis et respect to their timing, compensability
ready at its start, due to the occurrence al [5] used, as the baseline, the com- and impact, as presented in Figure 1.

Delays classification

Origin Compensability Timing Impact

Contractor
Third
Owner / Subcon- Excusable Inexcusable Nonconcurrent Concurrent Direct Indirect
party
tractor

Excusable Noncompensable

Figure 1: Classification of delays. [8]

1384 organ ization , techno logy and management i n construc ti on · a n i nte rnati ona l journa l · 7( 3)2 015
A delay is compensable to the con- their impact upon time performance of built, immediate schedules) can be
tractor when it is caused by the owner, the project can be described. employed,
e.g. incomplete drawing and specifi- XX identification of root causes,
cation, changes in scope or late pos- Research goals and methodology XX classification of the delays and their
session of site. The conditions of con- The aim of the research presented in impact, and
tract should allow the contractor to this paper is first to establish, on the XX assigning responsibility and deter-
be entitled to a time extension and to basis of literature survey, classifica- mination of compensation.
monetary recompense for extra costs tion of delays. The second research
caused by the delay. Excusable delays goal is to determine the attitudes of 2.1 Classification of delay causes
are occurrences over which neither the different construction project stake- Within research presented in this pa-
owner nor the contractor have any con- holders regarding the occurrence, type per, the framework of the classification
trol, e.g. extreme weather conditions, and allocation of responsibility for the of delay causes was adopted from the
acts of God and other unforeseen fu- delays in Slovenia. An on-line survey pioneer work of [14].
ture events. In this case, the contractor among the stakeholders was used as Three categories of the delay causes
should declare an excusable delay and the research tool. In order to formulate were identified as relevant in Slove-
can thus be entitled to time extension. the content of the questionnaire used nian construction practice, and as
Non-excusable delays caused by the in the survey, an extensive literature such, they were added to the list of de-
general contractor lead to the position survey was carried out by which the lays. The first category relates to com-
where the contractor is entitled nei- key problems of time management dur- plicated and lengthy procedure of ob-
ther to time extension nor to monetary ing execution of construction projects taining the building permit. National
recompense from the owner. In addi- were identified. spatial planning legislature demands
tion, the contractor may pay liquidated that the spatial plans identify, for each
damages according to the contract. Fundamentals of Delay plot, special regimes such as cultural
Empirical evidence was analysed Analysis or biodiversity preservation. Relevant
as well; for example, Sweis & al [5] Determination of delay causes has to institutions provide conditions that
have found, by conducting an empiri- be based on objective delay analysis; need to be respected during construc-
cal study among construction project therefore, analysing construction de- tion and use of the structure. Al illus-
stakeholders in Jordan, that change lays has become an integral part of a trative example is construction of the
orders by the client and financial dif- project’s construction life. Even with new ski jump facility in Planica valley
ficulties of the contractor are the lead- today’s technology and understand- that is located in protected area. In or-
ing causes of construction delays. Re- ing of project management techniques, der to ensure uninterrupted nesting of
search where 79 legal cases in Taiwan construction projects continue to suf- the local (protected) birds, the build-
(that relate to schedule delays in con- fer delays, and project completion ing permit specifically stated that the
struction projects) were analysed was dates still get pushed back. A number contractor was not allowed to execute
carried out by Yang & al [9]. He found of solution methods and delay analysis works during their nesting period. As
that the main causes of schedule de- techniques were developed and their a consequence, the works were inter-
lays were changes orders, changed usefulness and selection of proper rupted during the nesting period, and
scope of work, delayed site handover method are based on available project deviations from original schedule oc-
and weather. date and its quality. curred. Sometimes, additional stake-
Recent research in the area of de- The most comprehensive taxonomy holders are identified, after submitting
lays in construction include the work of and classification is presented in Rec- the permit request, e.g. renovation of
Mahamid et al [10] and Pourrostam & ommended practice published by the an old building where elements that
Ismail [11], where the delays were stud- Association AACE International [12]. have cultural heritage value are found
ied from the consultants’ perspective. Schematically, it is presented in Fig. 2. only after the onset of works. This cat-
The authors identify bid award for the Regardless of the selected method, egory can be labelled »legal issues«.
lowest price, changes in specifications the delay analysis procedure should The second cause of delays that
and materials types during construc- be carried out as a sequence of the fol- became extremely important with the
tion as top delay causes. Furthermore, lowing activities [13]: onset of the economic crisis is the
Gonzales & al [1] analyzed the causes XX data gathering and collection rel- financial structure of the project, es-
of delay and time performance in con- evant information, pecially when there is a long chain of
struction projects on the basis of 2 in- XX data analysis, where use of dif- subcontractors. Slovenian legislature
dicators, by which both the causes and ferent schedules (as planned, as demands that the payment of works

a. srdić · j. šelih · delays in construction projects: causes and mitigation · pp 1383-1389 1385
Retrospective

Observational Modeled

Static Logic Dinamic Logic Additive Subtractive

Modified/
Periodic Contemporaneous
Gross Reconstructed Single Base Multi Base Single Base Multi Base
(fixed/variable) Updates
Updates

Figure 2: Taxonomy of Retrospective Schedule Analysis. [12]

is carried out after the works are com- lay cause is related to the project par- ing methods and associated software
pleted, with due date specified in the ticipants who are contractually bound within project planning and monitoring
construction contract. This means that to the general contractor or to the cli- The core part of the survey is fo-
the subcontractors are often paid even ent, such as the Engineer (who is, on cused to the delay analysis. The clas-
later than the contractor, which, in one hand, the representative of the cli- sification used in the survey was ad-
some cases, may lead to the insolven- ent, and on the other hand, required by opted as proposed by [14]. Frequency
cy or even to bankruptcy of the subcon- the legislature), or the subcontractors; of the following causes of delays was
tractor who is not able to continue the in other words, there is no contractual investigated:
works due to his financial problems. As relation between project participant XX general causes (e.g. slow process
a consequence, a delay appears. and the client. They are labelled as of relevant spatial act acceptance;
The third additionally identified de- “Auxilliary project participants”). administrative causes; land own-
The resulting list of delay causes in ership consolidation; acquirement
Cause presented in Table 1. We assume that of relevant consents, e.g. from
not all listed causes of delay are per- the neighbours, or various other
1 Project causes ceived as equally important. stakeholders);
XX project financing (delayed payments,
2 Client Survey execution financing difficulties);
The content of the questionnaire to XX poor project management (e.g. inad-
Incomplete design
3 be used in the survey was divided equate communication among project
documentation
into several sections. In the first part, participants, poor scheduling, project
4 Execution of works general data, such as the role of the manager is appointed too late etc.)
company answering the survey in the XX client (e.g. orders changes after
5 Material construction process, type and extent the project is initiated; making
of experience, number of performed decisions too late; conflicts among
6 Rework projects within the last year, and pro- co-owners);
fessional background and experience XX various causes taking place during
7 Equipment and tools
of the respondent were collected. execution of works (e.g. poor manage-
8 Acts of God (Force Majeure)
In the second part, the questions ment of the contractor, inadequate
were focused to the construction ac- operational planning, poor manage-
9 Legal issues tivities carried out in the responding ment of conflicts with subcontractors,
company. In particular, we assume executed works are not compliant to
10 Project financing that the type of the facility to be con- the project documentation, ...);
structed, i.e. buildings vs engineering XX inadequate Engineering (late checks
11 Auxiliary project participants
works, has an influence upon the oc- and approvals of the executed works,
currence, extent and causes of delay. conflicts between Engineer and the
Table 1: Causes of delays appearing We also wanted to obtain information contractor, rigidity of the Engineer, ...);
in construction projects regarding the level of use of schedul- XX project documentation (e.g.

1386 organ ization , techno logy and management i n construc ti on · a n i nte rnati ona l journa l · 7( 3)2 015
incompatibility of drawings, lack
No. of resp. No. of resp. (%)
of details, poor drawings, late
incorporation of changes that were
Engineers 44 71,0
executed, into the drawings; late
incorporation of changes into the Architects 10 16,1
project documents etc.;
XX construction products (e.g. lack of Economists 6 9,7
certain materials and products on
the market, damaged materials, late Others 2 3.2

supply of construction products, …);


Total 62 100,0
XX construction machinery and equip-
ment (e.g. lack of machinery and
Table 2: Professional background of the respondents.
equipment on contractor’s side;
non-skilled operators, unavailability
of up-to-date machinery etc) No. of resp. No. of resp. (%)
XX workforce (poorly skilled workers,
low productivity, conflicts among No scheduling is used 16 25,8
foremen and workers, injuries, ...);
XX Force Majeure (e.g. different ground MS Project, Primavera 25 40,3

conditions as anticipated, unfavour-


MS Excel, Word 18 29,0
able weather, fire, strikes ....).
An on-line survey containing the Other 3 4,8
questions described above was pre-
pared. The target group of respondents Total 62 100,0
consisted of professionals, either rep-
resentatives of clients, or contractors. Table 3: Scheduling tools used by the respondents.
The survey was sent to the represen-
tatives of different stakeholders in education, and the majority (61,3%) ing of works that have been executed
construction process who were asked has the B.Sc. degree. Their education- against the schedule. The results are
to answer the questions. In order to al background varies, but the majority presented in Table 4. Weekly monitor-
obtain more answers, these respon- of the respondents are Civil Engineer- ing of works is most often (43,5%) en-
dents we asked to forward the survey ing professionals (Table 2). countered; however it is alarming that
to competent individuals who also par- We assume that companies that 7 (11,3%) respondents claim that they
ticipated in the construction projects use contemporary tools for project don’t monitor the progress of actual
(“rolling snowball principle”). scheduling are more efficient in time works at all.
management; therefore, one ques- Next important issue is the identifi-
Results tion addressed the issue of schedule cation of the actual causes of delay. The
62 responses were obtained; however, preparation and monitoring. The an- types of delay causes were formulated in
it should be noted that some of them swers regarding the scheduling tools’ accordance with the classification of de-
were only partially completed. use show that approximately a quarter lays presented in Section 2. Three possi-
The majority of respondents were of respondents do not use scheduling ble answers indicating the frequency of
representatives of clients (14,5%), tools at all. Standard software pack- delay occurrence (always; often; never)
contractors (22,6%) and professional ages for time management, MS Project were offered to the respondents. The re-
engineers (project managers, design and Primavera, are used by approxi- sults are presented in Table 5.
engineers and surveying engineers) mately 40% of the respondents (Table It can be seen that legal obstacles
(35,5%). Overall, the results show that 3). It is clear that the use of integrated (building permit issues etc.), lack of
they are well experienced, as the re- software packages that enable simul- design details and specifications, slow
ported work experience of 47% respon- taneous time, scope and cost control decision making process on the side of
dents ranges from 5 to 15 years, while are not yet a part of daily routine of the owner and design documentation
the work experience of 32% respon- Slovenian construction industry. delays; and change orders form the
dents ranges from 15 to 25 years. All re- The core part of the survey was fo- client’s side are perceived as the lead
spondents have completed secondary cused to the issues related to monitor- causes of delays.

a. srdić · j. šelih · delays in construction projects: causes and mitigation · pp 1383-1389 1387
The results presented in Table 5
How often do you monitor the
show that the causes of the majority
executed works against the No. of resp. No. of resp. (%)
schedule? of delays can be attributed to the legal
issues, slow decisions of the owner or
We do not monitor the execution of his representative, and to design that
7 11,3
works in terms of time lacks details important for the contrac-
tor. Many of the issues within these
Daily 9 14,5 categories appear in the very begin-
ning of the project, and can be miti-
Weekly 27 43,5
gated (partially or fully) by the owner;
Monthly 17 27,4 while their costs are far away from be-
ing excessive.
Bi-annualy 2 3,2
Discussion and Conclusions
Total 62 100,0 Delays are a part of the construction
projects. In this paper, we wanted to
Table 4: Frequency of executed works’ monitoring. identify the current state in this field
within the Slovenian construction in-
Cause of delay Always Always & often Category of delay dustry by carrying out a survey among
various construction project stake-
Legal obstacles with
1 9,7% 53,2% Legal holders. Results show that delays are
building permit issues
a part of the daily routine during con-
Lack of design details struction project execution. It can be
2 14,5% 50,0% Design
and specifications concluded that more attention should
be paid to the processes that are tak-
Slow decision making ing place prior to construction, such as
3 6,5% 46,8% Owner
process issued by owner
producing adequate design drawings
Design documentation
and documents.
4 8,1% 45,2% Design The results of the presented re-
delays
search identify the needs of the con-
Change orders and ad- struction industry from the viewpoint
5 ditional request issued 4,8% 45,1% Owner of time management and delays that
by owner
occur in projects, and could be used
as the baseline for the preparation of
Design documentation
6 6,5% 43,6% Design guidelines for time management for all
error and discrepancy
construction stakeholders.
Inappropriate design
7 3,2% 35,5% Design
solution

Lack of information
8 gathered before design 3,2% 35,5% Design
stage

Delay with spatial plan-


9 8,1% 32,3% Legal
ning documentation

10 Unqualified workforce 6,5% 30,7% Client

11 No project risk analysis 4,8% 30,6% Management

Inappropriate project
12 3,2% 30,6% Management
management

Table 4: Causes of delays as perceived by the respondents.

1388 organ ization , techno logy and management i n construc ti on · a n i nte rnati ona l journa l · 7( 3)2 015
References
1. González, P., González, V., Molenaar, K., & 9. Yang, J.B., Chu, M.Y. & Huang, K.M. (2013),
Orozco, F. (2014), Analysis of Causes of Delay An Empirical study of schedule delay causes
and Time Performance in Construction Proj- based on Taiwan’s litigation cases, Project
ects, Journal of Construction Engineering and Management Journal, Vol.44, p.21-3.
Management, Vol.140(1), 04013027 10. Mahamid, I., Al-Ghonamy, A., & Aichouni, M.
2. Majid, M. Z. A., & McCaffer, R. (1998), Factors (2015), Risk matrix for delay causes in con-
of Non-Excusable Delays That Influence Con- struction projects in Saudi Arabia, Research J.
tractors’ Performance, Journal of Management of Applied Sciences, Engineering and Technol-
in Engineering, Vol.14(3), p.42–49. ogy, Vol. 9(8), p. 665-670.
3. AlSehaimi, A., Tzortzopoulos, P. & Koskela, L. 11. Pourrostam, T., & Ismail, A. (2011), Study of
(2013), Improving construction management Methods for Minimizing Construction Delays:
practice with the Last Planner System: a case Evidences from a Developing Country, Ad-
study, Engineering, Construction and Architec- vanced Materials Research, Vols. 201-2013, p.
tural Management , Vol.21(1), p. 51-64. 2939-2942.
4. Faridi, A. S., & El‐Sayegh, S. M. (2006), Sig- 12. AACE-International. (2011). Forensic schedule
nificant factors causing delay in the UAE con- analysis - Recommended Practice No. 29R-03.
struction industry, Construction Management 13. Saggaf, H. A. (1998), The Five Commandments
and Economics, Vol.24(11), p.1167-1176. of Construction Project Delay Analysis, Cost
5. Sweis, G., Sweis, R., Abu Hammad, A. & Shbo- Engineering, Vol.40(4), pp.37-41.
ul, A. (2008), Delays in construction projects: 14. Kumaraswamy, M.M., & Chan, D. W. M. (1998),
The case of Jordan, Int.J. of Project Man., Vol Contributors to construction delays, Construc-
26(6), p.665-674. tion Management and Economics, Vol.16(1),
6. Yang, Y.-B., & Kao, C.-K. (2009), Review of p.17-29
Delay Analysis Methods: A Process-Based
Comparison, Open Construction & Building
Technology Journal, Vol.3. Retrieved from:
http://connection.ebscohost.com/c/arti-
cles/51409426/review-delay-analysis-meth-
ods-process-based-comparison (Nov.15, 2015)
7. Sun, M., & Meng, X. (2009), Taxonomy for
change causes and effects in construction
projects. International Journal of Project Man-
agement, Vol.27(6), p.560–572.
8. Kartam, S. (1999), Generic methodology for
analyzing delay claims, Journal of Construc-
tion Engineering Management, Vol.125(6),
p.409-419.

a. srdić · j. šelih · delays in construction projects: causes and mitigation · pp 1383-1389 1389

You might also like