1 2. When designating an injection point circuit for the purpose of inspection, the
recommended upstream limit of the injection point circuit is__________?
0 A. Minimum 12 inches
1 B. Maximum 12 inches
2 C. Three pipe diameters
3 D. Both A and C
1 3. A piping circuit, 300’long, operates at 500°F. What is the linear thermal expansion
of the circuit if the circuit was constructed using A 106-B piping?
0 A. 3.62 inches
0 B. 7.24 inches
1 C. 10.86 inches
2 D. 14.48 inches
0
4. In Guided bend specimens for welder qualifications corner discontinuities are
allowed :
0 A. if they are not related to weld
1 B. under no circumstances
2 C. if there is no evidence that they are due to slag inclusion
3 D. if they are not greater than 5/8”
1 9. CUI can be minimized by selecting insulation material. Which of the following can
2 be the solution
1 10. CMLs can be eliminated for piping systems with which of the following
2 characteristics:
0 A. high potential for creating an emergency in the event of a leak
1 B. extremely corrosive systems
2 C. low potential for creating an emergency in the event of a leak
3 D. piping systems in cyclic conditions at high pressures and temperatures
11. When evaluating a radiograph of 2 ” thick carbon steel piping, what is the
maximum geometric unsharpness?
0 A. 0.020
1 B. 0.030
2 C. 0.040
3 D. 0.070
0
1 12. A welder is tested on ½ inch thick pipe in the 5G position. How many face bends
2 are required for this test?
0 A. 1
1 B. 2
2 C. 3
3 D. 4
1 13. During the final four hours of buried piping test, which was re pressurized to
2 125psi , the gauge fell by 5psi
0 A. The piping system failed
1 B. The piping system passed
2 C. The test must be repeated
3 D. The piping system must be visually inspected
0
1 16. The cracks produced as the result of mechanical loading on a shaft at change in
crossection is called as
0 A. Mechanical fatigue
1 B. Vibration fatigue
2 C. Thermal fatigue
3 D. Brittle fracture
0
17. Determine the MAWP, at the next inspection, of the following piping system
based on the following
Pipe description NPS 10, A 106 B, operates at 100 0F
Thickness determined from inspection 0.30 in.,
Observed corrosion rate 0.02 in/year, Next planned inspection 5 years
0 A. 372 PSIG
1 B. 744 PSIG
2 C. 1041 PSIG
3 D. 1116 PSIG
1 18. Wet magnetic particle examination shall not be performed if the surface
temperature of the part exceeds _____________
0 A. 100°C
1 B. 40°F
2 C. Manufacturer’s temperature limitations
3 D. 135°F
1 19. Who shall provide the materials, equipment, quality control, and workmanship
necessary to maintain and repair the piping systems in accordance with the
requirements of API 570?
0 A. Piping engineer
1 B. Repair organization
2 C. inspector
3 D. operator
1 20. The owner of buried piping should conduct surveys of the surface conditions on
and adjacent to each pipeline path every _________________.
0 A. 6 months
1 B. 12 months
2 C. yearly
3 D. 5 years
1 24. What percentage of the areas of damaged insulation should be inspected for a
Class 1 system that is observed with damaged insulation not in susceptible
temperature area?
0 A. 100%
1 B. 75%
2 C. 50%
3 D. 0%
1 25. When reviewing a group of radiographs all of the information must be available
except :
0 A. minimum source to film distance
1 B. geometric unsharpness
2 C. material type
3 D. exposure technique
26. What would be the maximum operating pressure of a flange A182 Gr.F2 400# at
500°F
A. 900 psi
B. 970 psi
C. 885 psi
D. 950 psi
1 28. Calculate the short term corrosion rate of the system , based on the following
t initial = 1.125’’ t previous = 1.112” , t actual = 0.997” and 5 year interval:
0 A. 0.023” per year
1 B. 0.021” per year
2 C. 0.112” per year
3 D. 0.997” per year
2
29. A piping circuit has got mixed grades of material with A53 Gr.B and Al06 Gr.B
used in sulphur environment. It was decided to increase the operating
temperature to 550°F
3 A. Increase the number of CML on the system
4 B. The system should be monitored for two months and establish the
5 number of TML
6 C. The number of CML need not be changed
7 D. Carry out visual inspection frequently
8
30. Out of the patch mentioned which one is not allowed on a NPS 12 piping repair
9 A. 8” dia circular patch
10 B. 6” dia circular patch
11 C. 6” X 6” patch with 1” round corner
12 D. 6” X 6” patch with 2” round corner
31. A normal fluid service system piping of 10 mm thick what is the maximum under
cut permissible on a girth weld
A. 1.5 mm
B. 3.0 mm
C. 4.5 mm
D. No under cut is permitted for this thickness
32. What is the temperature range for PWHT of a P-6 base material ?
A. 500 0 F to 700 0 F
B. 1000 0 F to 1100 0 F
C. 1400 0 F to 1475 0 F
D. not specified
37 What is the size of a test point on a piping system with OD greater than 10"
A. 3" dia
B. 4" dia
C. 2" dia
D. 2" or 3" dia
Please answer the following questions using WPS (PR /ASME / 035) and
PQR (02/ASME/2003) supplied with the paper