The data center's power, cooling and standby power supply must be able to adequately support current and future needs.
building, refreshing, or moving the data center, it is important to understand these requirements. Accurate estimates of faci
are a critical input to the project’s final budget. Once the load estimate has been determined, IT should seek professional e
center construction requires specialized skills.
This tool can be used to determine a high level estimation for the data center's power, cooling, and standby power requirem
of 10%-15% accuracy. Complete the white cells with required information and follow the arrows to determine final results.
Note: Some calculations in this tool are adapted from APC information.
Info-Tech Research Group tools and template documents are provided for the free and unrestricted use of subscribers to In
Group services. These documents are intended to supply general information only, not specific professional or personal ad
intended to be used as a substitute for any kind of professional advice. Use this document either in whole or in part as a ba
document creation. To customize this document with corporate marks and titles, simply replace the Info-Tech Information in
Footer fields of this document.
Start Calculator
s Calculator
y support current and future needs. Whether IT is
irements. Accurate estimates of facility requirements
mined, IT should seek professional expertise as data
Input Table
Item Number
Total floor area in the data center (sq. ft)
1200
List each server located in the data center in the table below. Use nameplate ratings to collect amps and volts for each dev
determine the kW required. Be sure to include the device name for tracking purposes.
Inputs
Outputs
WATTS
(Enter if volts Total Existing Server Load
VOLTS WATTS kW
and amps are (kW)
not available)
240 192.96 0.19
78.793
48 160.8 0.16
684 684 0.68
684 684 0.68
684 684 0.68 Average Server Load (kW)
336 336 0.34
0.906
251 251 0.25
251 251 0.25
251 251 0.25
251 251 0.25
251 251 0.25
171 171 0.17
251 251 0.25
194 194 0.19
267 267 0.27
267 267 0.27
267 267 0.27
267 267 0.27
373 373 0.37
481 481 0.48
371 371 0.37
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
481 481 0.48
481 481 0.48
481 481 0.48
715 715 0.72
715 715 0.72
572 572 0.57
715 715 0.72
513 513 0.51
572 572 0.57
336 336 0.34
590 590 0.59
572 572 0.57
564 564 0.56
564 564 0.56
658 658 0.66
998 998 1
481 481 0.48
613 613 0.61
183 183 0.18
336 336 0.34
336 336 0.34
336 336 0.34
478 478 0.48
564 564 0.56
9120 9120 9.12
9120 9120 9.12
9120 9120 9.12
9120 9120 9.12
610 610 0.61
610 610 0.61
1664 1664 1.66
267 267 0.27
1860 1860 1.86
481 481 0.48
481 481 0.48
481 481 0.48
481 481 0.48
715 715 0.72
564 564 0.56
564 564 0.56
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
336 336 0.34
409 409 0.41
409 409 0.41
564 564 0.56
564 564 0.56
564 564 0.56
564 564 0.56
564 564 0.56
564 564 0.56
564 564 0.56
3198 3198 3.2
481 481 0.48
481 481 0.48
481 481 0.48
Next Step >>>
Other Existing Equipment Load Calculations
Enter equipment information, along with Amps and Volts into the table below to calculate the total equipment load in kW fo
Where a power utility or calculation tool is not available from the vendor to express power requirements as kW, nameplate
List each equipment device located in the data center in the table below (other equipment includes switches, routers, etc.).
and volts for each device to determine the kW required. Be sure to include the device name for tracking purposes.
Inputs
her equipment includes switches, routers, etc.). Use nameplate ratings to collect amps
he device name for tracking purposes.
Outputs
WATTS
(Enter if volts and Total Existing Equipment Load
WATTS kW
amps are not (kW)
available)
257 257 0.26
13.66
360 0.36
1608 1608 1.61
150 150 0.15
360 0.36 Average Equipment Load (kW)
1608 1608 1.61
0.141
75 75 0.08
49 49 0.05
49 49 0.05
658 658 0.66
29 29 0.03
29 29 0.03
29 29 0.03
29 29 0.03
29 29 0.03
29 29 0.03
29 29 0.03
25 25 0.03
257 257 0.26
150 150 0.15
360 0.36
1608 1608 1.61
5880 5880 5.88
Next Step >>>
Server Room Power and Load Requirements Estimates
The following table summarizes the power load requirements for the organization's data center environment based on the i
Item Description
92.450
Size of generator
45.283 needed (estimated in
kW)
144.620 535.064
44.075
N/A
191.094
191.094
382.188
477.735
240.000
1150.615
)
248.422
286.641
535.064
Cooling Requirements Estimation
The following table summarizes the cooling load requirements for the organization's data center environment.
Item Description
Total heat given off from server and storage
Total existing server and storage load
devices in the data center.
Total heat given off from other equipment located
Total existing equipment load
in the data center.
The amount of heat given off from expected future
Estimated future loads
devices to be added in the data center.
Total heat given off from the UPS or backup
UPS inefficiency and battery charging
battery located in the data center.
Total heat given off from the power distribution unit
Power Distribution (PDU)
located in the data center.
Amount of heat given off from lighting in the data
Lighting center. Based on the total amount of floor area in
the data center. (2.0 x Floor Area in sq. ft.)
Amount of heat given off from the maximum
People
number of employees working in the data center.
The total size of cooling load required to cool the
Total Estimated Cooling Load
data center.
78792.76 268683.31
13657.00 46570.37
45283.20 154415.70
44074.55 150294.20
2756.57 9399.90
2400.00 8184.00
500.00 1705.00
187464.07 639252.48
53.27 TONS
Standby Power Requirements Estimation
The following table summarizes the standby power load requirements for the organizations' data center environment.
Item
Server load power requirements
Description kW
Total estimated power requirements for servers
78.793
and storage devices located in the data center.
Total estimated power requirements for other
equipment (routers, computers, switches, 13.657
convenience plugs etc.) located in the data center.
Based on the average server load and anticipated
45.283
number of future servers to be added.
Total size of cooling load required to cool the data
187.464
center based on the total heat output.
Total load required to power emergency lighting in
2.400
response to an outage.
Total load that will require a standby power supply
327.597
in the event of an outage.
Data Center Requirements Estimates Results Summary
The following table summarizes the complete results from Tabs 1 - 4 that estimate the organization's critical power, cooling, and standby power requirements for the data center.