Professional Documents
Culture Documents
February 2009
SSU
UBBSSTTA
ATTIIO
ONNA
AUUTTO
OMMA ATTIIO
ONN SSY
YSSTTEEM
M FFO
ORR EEH
HVV
SSU
UBBSSTTA
ATTIIO
ONNSS
I. SCOPE
This technical description covers PPC’s technical, functional, configuration and testing
requirements for a substation automation system for extra high voltage (ehv) substations
with three (3) 400kV and 150kV buses respectively.
The substation automation system shall be digital and shall include control, protection,
monitoring, measurement functions and teletransmission of data and commands.
III. STANDARDS
The applicable standards for this automated digital control and protection system for
switching station are the following:
• IEC – 60870 – 5 – 101
• IEC – 60870 – 5 – 103
• IEC – 60870 – 5 – 104
• IEC – 60255 – 5
• IEC – 60255 – 22 – 1
• IEC – 60255 – 22 – 2
• IEC – 60255 – 22 – 3
• IEC – 60255 – 22 – 4
• IEC – 60068 – 2 – 6
• IEC – 61850
IV. USE
The Substation Automation System (S.A.S) for ehv substations, which is SCADA like, is
to be used for the control, protection and supervision of PPC’s Air insulated (AIS) 400
/150/30KV ehv substations and for the 150/20KV substations if it happens to be installed
inside the ehv substations.
-1-
V. CLIMATIC CONDITIONS
This automated digital control and protection system for ehv substations, shall be capable
of withstanding the following climatic conditions:
a. Ambient temperature during operation : -5 0 C to +50 0C
b. Ambient temperature during storage : -25 0C to +55 0C
c. Relative humidity : 5% - 90%
d. Altitude level : Up to 1000m above sea level
-2-
• Short circuit level of the 30KV side : 20KΑ
• Basic Insulation level of the 30KV side : 250KV
• Nominal voltage for the 20KV : 20KV
• Maximum voltage for the 20KV : 24KV
• Maximum short circuit level of 20KV : 10KA
• Basic Insulation level at 20KV : 125KV
• Nominal frequency : 50Hz
• Frequency tolerance : ± 0,2 Hz
• Available auxiliary Voltage for control and signalling :220V DC for the 400KV and
30KV side and 110V DC for
the 150KV and 20 KV (if
applicable) side
• Available AC auxiliary Voltage :3Φ,380V AC and 1Φ,220V AC
b. From the bay control unit, - bay level (located in relay kiosks)
c. From the HMI, - station level (Control building of the EHV Substation)
d. The 400KV, 150KV and 30KV equipment shall be controlled and remotely
from the transmission’s system control center (TCC) and the 20KV equipment
along with the 150/20KV transformer bays (if required) shall be remotely
controlled and from the distribution’s system control center (DCC).
e. The commands will be issued each time only from one control place excluding
at the same time the other three. The priority (switching authority) of commands
shall be in the order indicated above and shall be carried out either via software
-3-
or hardware. Each control level shall have proper indication indicating the
selected position.
f. The control for the 400KV, 150KV, 30KV and the 150/20KV transformer bays
(if required) shall be as per bay while for the 20KV side (if required) as per
transformer bay including all of its corresponding feeders.
7. At table 1 of the attached appendix, the necessary commands from the Substation
Automation System (S.A.S) to the ehv substation equipment are presented, as well
as the commands that required to be received from TCC and DCC remote control
centers.
-4-
b. The supervision shall include the following:
1. The position of each 400KV, 150KV, 30KV and 20KV(if required) ehv
substation circuit breakers on a continuous basis
2. The position of each 400KV, 150KV and 30KV, ehv substation
disconnectors (isolators) on a continuous basis.
3. The position of each 400KV and 150KV ehv substation earthing switch on
a continuous basis
4. Every detected change shall cause a change in the single-line diagram
displayed on the operator’s terminal (HMI unit) located in the ehv
substation control building, notation in the event list and a print-out
5. Alarms shall be issued, in the form of lists and print-out, in case the
position changes are not caused by a command.
6. At the operator’s terminal and specifically at the colour visual display, the
single-line diagram of the ehv substation (including the future bays of the
switching station with dotted-lines), details of the status of breakers and
disconnectors (isolators) and measurements shall be depicted.
7. The naming of the equipment shall be as indicated in the single-line
diagram of the ehv substation which is provided by T/NPRD of PPC S.A.
8. The substation automation system for ehv substation shall also allow
supervision of all ehv substation 400KV and 150KV circuit breaker and
motor driven (electrically operated) disconnectors and earthing switches
from the transmission system’s control center (TCC).
10. The naming of the equipment shall be as indicated in the single line
diagram of the ehv substation provided by T/NPRD/PPC S.A.
2. Switchgear Interlocking
-5-
e. As it is indicated in paragraph 2-b above, the interlockings for the 400kV side shall
be and as per the schematic diagrams, however for reasons of further assistance to
the procedure, a complete description of the 400kV side interlockings also follows.
Attention The following interlockings are valid for a ehv substation with
three (3) 400KV buses.
The operation of a 400kV power unit line disconnector is allowed providing that
same conditions as those of a transmission line disconnector are present and in
addition, the interlocking requirements of the power unit are also met.
2. The operation of a 400KV transmission line disconnector’s earthing switch is
allowed providing that the following conditions are met:
The disconnector of the transmission line in question is open and
The transmission line in question is out of service.
3. The operation of a disconnector of the bus bars associated with a 400kV
transmission line, a 400kV power unit line or a line feeding an autotransformer,
which are happen to be located between the bus bars tie circuit breaker and bus
bars section, is allowed providing that the following conditions are met.
• The bus bars disconnector’s earthing switch of the corresponding 400kV
transmission line is open and
• The circuit breaker of the corresponding 400kV transmission line is open
and
• The disconnectors of the other bus bars of the same 400kV line are open
and
• The bus bar to be free of any earthing switches (Earthing switches located at
the end of the bus bar to be open) and
• The disconnector of the bus section is open or the earthing switch at the
other side of bus section disconnector is open.
In excess of the previous procedure and with the aim of transferring a 400kV
line to another bus under load conditions (this operation is allowed only from
the ehv substation’s control building) the operation of a bus-bar disconnector
associated with o 400kV transmission line, a 400kV power unit line or a line
feeding an autotransformer is allowed providing that the following conditions
are met
-6-
• The earthing switches of bus-bars disconnectors of the 400kV line in
question is open and
• The disconnector of one of the other buses of the same 400kV line is closed
and
• The buses of the two bus disconnectors in question are tied together (For the
400kV lines between bus-tie and bus-section : The 400kV bus-coupling
circuit breaker closed and also closed the 400kV disconnectors located at
both sides of the bus tie of the buses in question. For the 400kV lines
beyond the bus-section: The bus-tie 400kV circuit breaker closed and also
closed the disconnectors located at both sides of the bus-tie of the buses in
question and in addition closed the 400kV disconnectors of the bus section
of the buses in question) and
• The bus is free of any earthing switches (earthing switches open at the ends
of the bus) and
• The disconnector of the bus section is open or the earthing switch at the
other end of the disconnector of the bus section is open.
4. The operation of the earthing switch of a power unit line disconnector is allowed
when the same conditions with that of the corresponding earthing switch of the
transmission line disconnector are met and in addition the interlocking
requirements originated from the power unit are also met.
The operation of an earthing switch of the bus disconnectors of the 400kV
transmission line and 400kV power unit line is allowed when the following
conditions are met:
• The disconnector of the line in question is open and
• The bus disconnectors of the same line are also open
5. The operation of the 400KV bus coupling disconnector of bus I or bus III is
allowed providing that the following conditions are met:
The 400kV bus coupling circuit breaker is open and
The 400kV bus coupling disconnector of bus II which is towards to the
disconnector to be operated is open and
The earthing switch which grounds the section of bus between the
disconnector which is to be operated and the 400kV bus coupling circuit
breaker is open and
The earthing switch which grounds the section of the bus which is right after
the 400kV bus coupling circuit breaker is open and
The bus is free of any earthing switches (earthing switches are open at the
end of the bus) and
The section bus disconnector is open or the earthing switch at the other end
of the bus section disconnector is open.
The operation of one (1) of the 400kV bus-tie disconnectors associated with bus
II is allowed providing that same conditions exist as those of the disconnectors
of buses I and III.
-7-
In excess of the previous procedure the operation of the one (1) of the 400kV
bus-tie disconnectors associated with bus II is allowed when bus II is tied to
some other bus, that is when the following conditions exist:
• The 400kV bus tie circuit breaker is closed and
• The other disconnector of bus II is closed and
• The bus-tie disconnector of the other bus which is located however on the
same side of the 400kV bus-tie circuit breaker with the disconnector to be
operated, is closed
6. The operation of an earthing switch of a 400KV bus-tie disconnector which
grounds the buses (I or II or III) is allowed when the bus in question is free of
voltage, which means:
• The bus tie disconnector associated with the earthing switch which is about
to be operated is open and
• The bus section disconnector of the bus in question is open and
• All bus disconnectors of the 400kV lines which happens to be between bus
tie and bus section are open
or
• The bus tie disconnector associated with the earthing switch which is about
to be operated is open and
• All the bus disconnectors (of the bus in question at both side of the bus-
section) of the 400kV lines are open and providing that the bus section
disconnector is closed
7. The operation of a disconnector of the bus section is allowed providing that the
following conditions exist:
• Both earthing switches of the bus section disconnector are open and
• The earthing switch of the bus tie disconnector which grounds the bus under
question (towards the bus section) is open and
• Is deenergized at least one of the two sections of the bus section (all bus
disconnectors of the 400kV lines and, on situation, the disconnectors of the
bus tie of the bus in question are all open).
8. The operation of the one of the earthing switches of the bus section
disconnectors is allowed providing the following conditions exist:
• The bus section disconnector associated with the earthing switch which is
about to be operated is open and
• The bus in question in the section in which is to be grounded is free of
voltage (All the disconnectors of the bus in question are open)
-8-
B. 150KV side Interlockings
-9-
C. Interlockings of the 30KV side
D. Interlockings of 20KV side (if required, that is if the ehv substation includes a
150/20KV substation).
No schematic diagrams are provided for this voltage level.
1. The operation of any circuit breaker of a medium voltage bay (TM, BSM, OLM,
CM, IPPM) is allowed providing the circuit breaker’s carriage is in the operating
position or in the test position (metal-clad panels).
2. The circuit breaker’s carriage of the medium voltage bays (TM, OLM, CM,
IPPM) can be moved from the test position to the operating position only if the
grounding (earthing) switch of the medium voltage bay is opened.
3. The circuit breaker of the medium voltage bays (TM, OLM, CM, IPPM) can be
closed in the operating position only if a grounding (earthing) switch of the
medium voltage bay is opened.
4. The circuit breaker of the medium voltage bay TM (transformer incoming bay)
can be closed only if the corresponding high voltage (150KV) transformer
circuit breaker is closed.
5. The operation of the grounding (earthing) switch of the medium voltage bays
(TM, OLM, CM, IPPM) is allowed only if the circuit breaker carriage is in the
test position.
6. The operation of the grounding switch of the “TM” (transformer incoming)
medium voltage bay is allowed only if the corresponding high voltage side
(150KV) transformer bay circuit breaker is open.
a. The phasing function is to be carried out when two asynchronous systems are
going to be connected, so that stress is avoided on the network and its
components. The phasing function shall compensate for measured slip
frequency as well as circuit breaker closing times.
- 10 -
b. Synchro-check function shall involve the 400KV and 150KV transmission lines
at 150KV autotransformer bays and bus coupling 400KV and 150KV circuit
breakers.
d. The signals for the synchro-check function will be provided via VTs, which
have secondaries of 100 V A.C. for the 400KV and 120 V A.C. for the
3 3
150KV.
1. For the 150KV buses and lines, the 120 V shall correspond to
3
160KV
2. For the 400KV buses and lines, the 100 V shall correspond 400KV
3
3. The synchro-check function will be fed three (3) line-to-line voltages for
the 400KV side and line-to-neutral (ΦΒ) voltage for the 150KV side and
the substation automation system for the ehv substation shall calculate
phase angles and frequency.
f. The synchro-check with phasing shall be carried out from the bay control units
and from the operator’s terminal located in the ehv substation’s control
building.(HMI center)
g. It is noted that the specified closing time of the 400KV and 150KV breakers is
110ms and 100ms respectively.
h. For the control of the synchro-check function, on the HMI center PC will be
displayed:
• The six measured magnitudes (V1, φ1, f1, V2, φ2, f2) and the
corresponding differences (∆V, ∆φ, ∆f), related to the permissible
synchro-check limits.
• The voltage comparison figure (from the above mentioned four) applied
• In case of synchro-check operation failure, the reasons of failure (out of
range voltage or/and angle or/and frequency).
• Notification message “closing command of the circuit breaker” in case
of successful synchro-check function.
- 11 -
i. The substation automation system for the ehv substation shall also allow
synchro-check with phasing from the system’s control centers (transmission’s
and distribution’s) with the same features as those described above.
a. The substation automation system for the ehv substation shall control the taps of
all autotransformers, if any, of the ehv substation. The number of taps and the
corresponding voltage level of each tap is indicated below:
H. V. (400KV) M. V. (150KV)
180120
178055
175950
173805
171615
169380
167105
164785
162415
160000 +10 steps
400KV 157535 Principal tap
155020 -8 steps
152450
149825
147145
144405
141605
138745
135820
b. For all autotransformers a voltage regulator relay shall be provided for the
automatic tap changer control function if the tap changer control function can
not be accomplished by other means.
c. Tap changer control will be carried out from the following points:
1. Locally, on the autotransformer itself
2. The bay control unit (relay kiosk)
3. The HMI center (ehv substation’s control building)
4. The transmission system’s control center
- 12 -
d. Furthermore, tap changer position shall be displayed on the visual display unit
located in the ehv substation’s control building (HMI center) and also in the
transmission system’s control center console.
e. It should also be noted that the system shall contain capability for emergency
stop of the tap changing procedure.
5. Transformer Tap changer Control (if required, that is if the ehv substation
includes and a 150/20KV substation)
The substation automation system for ehv substation shall control the taps of all
transformers, of the substation.
a. The number of taps and the corresponding voltage level of each tap is indicated below:
1 161250
2 159375
3 157500
Voltage variation 4 155625
+ 7.5% 5 153750
150KV 6 151875
-12.5% 7 150000
in steps of 1.25% 8 148125
9 146250
10 144375
11 142500
12 140625
13 138750
14 136875 21.000 V
15 135000 or
16 133125 15.750 V
17 131250
b. For all transformers, a voltage regulator shall be provided for the automatic tap changer
control function if the tap changer control function can not be accomplished by other
means.
c. Tap changer control will be carried out from the following points:
1. Locally, on the transformer itself
2. The bay control unit (relay kiosk)
3. The HMI center (ehv substation’s control building)
4. The distribution’s system control center
d. Furthermore, tap changer position shall be displayed on the visual display unit located in
the ehv substation’s control building (HMI center) and also in the distribution system’s
control center console.
e. It should also be noted that the system shall contain capability for emergency stop of the
tap changing procedure.
- 13 -
6. Measurements
6.1 The substation automation system for the ehv substation, after receiving analog
signals from VTs and CTs and after calculating certain parameters, shall display on
the visual display unit, located in the ehv substation’s control building, and transmit
to the TCC and DCC the values of measurements that are presented on table 4. It
should be pointed out, that the ratios and classes of the voltage and current
transformers, appear at the single-line diagrams of the ehv substation which are
included in the inquiry.
a. Events and alarms generated by the equipment of the ehv substation shall be
displayed in an event list in the visual display unit at the operator’s terminal in
the ehv substation’s control room (HMI)
c. The events and alarms shall also be printed on a printer located in the ehv
substation’s control room.
d. The number of digital signals (events and alarms) will vary from ehv substation
to ehv substation. The (total) number will be estimated every time from tables 2
and 3 of this hereby technical description.
e. All digital input signals whether are events or alarms shall be suitable for 220V
DC for the 400KV and 30KV side and 110V DC for the 150KV side.
f. Characterization of all events and alarms will be curried out via software after
the awarding of the contract by the supplier with the assistance of PPC’s
engineers.
h. The events shall be registered in a chronological event list in which the type of
event and its time of occurrence are indicated. All events shall be stored in the
computer. Printouts shall also be possible.
i. The operator shall be able to call up the chronological event list on the visual
display unit at any time for the entire ehv substation or sections of it.
j. The operator shall be able to call up for viewing, a certain type or group of
events based on.
• Date and time
• Bay
• Device.
- 14 -
k. All events and alarms shall be displayed in English. A list, however must be
provided where all events and alarms shall be translated in Greek.
l. All events and alarms shall be automatically recorded on the Mass Storage Unit
of the system.
n. All digital signal inputs must be decoupled from the plant by the use of opto –
isolators or similar which will give input isolation of at least 2KV.
o. The event and alarm recording function shall be designed for reliable long-term
operation in a hostile environment where electrical / mechanical noise and
disturbances are present as well as high electromagnetic fields. It shall process
and record valid event and alarm information and not be adversely affected by
its environment.
p. The alarm list shall contain a summary display of the present alarm situation.
Each alarm shall be reported on one line which shall contains the following:
• The alarm date and time
• The name of the device that the alarm is generated from
• A descriptive text
• The acknowledgement state
t. Every alarm shall be announced and by the sound of a horn. This means that the
system must be equipped and with a horn.
Disabling of the horn shall be achieved, if desired, via keyboard/mouse from the
HMI center.
Acknowledgement of the horn shall be carried from the HMI center via
keyboard / mouse and then the horn shall be deactivated.
- Supply voltage of the horn: 220V D.C.
- 15 -
150/20KV substation. The list of events and alarms is indicated in the attached
Tables 2 and 3.
Note
By an event is meant for example the opening or closing of a circuit breaker, the
operation of a relay, etc. By alarm is meant for example low SF6 of a circuit breaker, etc.
8. Protection
Protection relays of the numerical type shall be included in the supply of the substation
automation system for ehv substation.
The relays to be provided are the following:
b. For the 150KV side of the ehv substation and for the 150KV TL.
• 150KV distance protection relay in accordance with technical description TD-16.
• Phase and ground overcurrent directional relay for the 150KV lines in accordance
with specification SS-131
• Bus-bar differential protection in accordance with specification SS-55
• Phase and ground overcurrent relay in accordance with technical description TD-
48 for the protection of the autotransformer’s 150kV winding.
- 16 -
e. For the transformer 150/20 KV bay if a 150/20KV substation is included in the
ehv substation.
• Transformer differential relay in accordance with specification SS-100.
It should be noted that the transformer differential relay will cover and include
in its protection zone and the 20KV bus of the substation.
• One (1) phase earth overcurrent relay, as per TD-31B technical description
• One (1) definite time overcurrent relay suitable for the detection of small earth
fault currents, as per specification SS-94
b. The automatic switching sequence function will be used in conjunction with the
HMI center and bay control units and execution shall be carried out form the
operator’s terminal (HMI center) and bay control units.
a. The fault recording function shall be used to sense and record data related to
faults (prior to, during and after the faults). The fault recording function shall
record eight (8) analog signals per 400KV and 150KV line related to :
1. Three (3) phase-to-phase voltages
2. One (1) open-delta voltage (100V) (residual voltage)
3. Three (3) phase-to-phase currents
4. One (1) phase-to-neutral current
b. The fault recording function will be used in conjunction with the HMI center
c. The voltage and current input signals will either be transmitted to the HMI
center from the bay control units or be input via analog transformers or directly
from CTs and VTs if the proposed system allows such a transmission.
- 17 -
d. Voltage of analog inputs
− For the 400KV : 100 V rms.
3
− For the 150KV : 120 V rms.
3
e. Current of analog inputs for
both 400KV and 150KV : 1A rms.
f. Sampling rate : 1 – 9,3 KHz
g. Pre – fault recording time : ≥ 60ms
h. Post – fault recording time : ≥ 2sec
i. Total recording time : ≥ 5 sec
1. The structure of the substation automation system shall be of the distributed type with
star arrangement and shall be divided into a two (2) levels with capability for
communication with two (2) system’s control centers, if the ehv substation includes a
150/20KV substation. Whether the ehv substation includes a 150/20KV substation, it
will always be indicated in the inquiry.
The required structure is indicated on Fig No1 below:
- 18 -
NOTES:
1. Station Level equipment is located in the ehv substation’s control building
2. Bay level equipment is located in the various relay kiosks of the ehv substation.
3. Capability shall exist for GPS signal and for internal time signal.
4. Protection relays include distance relays, Autotransformer / transformer (if
required) differential relays, overcurrent relays and voltage relays.
5. For the above serial communication structure there shall be redundancy for each
connection shown.
6. The bay control units and the protection relays will be connected in a single fiber
optic cable (f.o.c) loop (network redundancy). In case of large number of bay
control units, the above scheme can be implemented by the use of more than one
loop.
7. Bay control units and protection relays, can be connected in the loop directly or
within appropriate devices (e.g. Ethernet switches, functionally based on
IEC-61850-3). The direct connection of each device in the loop and the connection
between loops will be implemented based on IEC-61850 communication protocol
and with bidirectional information transfer.
8. The Ethernet loops will communicate with central units-servers or industrial PCs,
within IEC-61850 protocol, at station level.
9. Central units can be connected with the above mentioned loops or with a different
loop, in accordance with the conditions mentioned above.
- 19 -
l. Switchgear interlocking in accordance with paragraph VIII-2 of this hereby
technical description
m. Automatic switching sequences in accordance with paragraph VIII-9
n. The bay control units shall be autonomous devices and can not be embodied in
relays.
a. Location
The bay control units will be located inside the relay kiosks, which are located
throughout the ehv substation’s.
b. Interfacing
All bay control units shall contain an optical-fiber serial interface for connection
to the HMI center and a RS 232 serial interface for connection to a PC.
All optical-fiber cables will be part of the supply as well.
g. Mounting
The bay control units shall be suitable for panel flash mounting or ½ flash panel
mounting.
- 20 -
4. Human-Machine Interface center (HMI) functions and other requirements
The HMI center manages the bay control units and indirectly or directly the protection
relays, controls the interaction between the station level and HMI center, processes
information for the entire ehv substation and archives data in accordance with the
parameterized (setting) requirements of the user. Specifically the HMI center shall
perform the following:
a. Coordinate communication
− To the transmission’s system control center for the 400KV, 150KV and 30KV
− To the distribution’s system control center for the 20KV for the 150/20KV
transformers bays and 150KV transmission line bays if the ehv substation includes
a 150/20KV substation.
− To an evaluation center connected remotely via a telephone line using a modem
− To the bay control units and via the bay control units to the protection relays or to
the protection relays directly.
The above is for the purpose of controlling and monitoring activities at the ehv
substation and at system’s control centers as well as to provide data for use and
analysis.
b. Event recording and alarm handling in accordance with paragraph VIII – 7 of this
hereby technical description
c. Archiving of events
d. Time synchronization
Time synchronization shall be achieved by using GPS signal and by internal clock. In
other words, the HMI center shall be capable of been synchronized by GPS and to
switch automatically to an internal clock if the GPS satellites can not be located by the
ehv substation’s antenna.
e. Switchgear Interlocking
Switchgear interlocking in accordance with paragraph VIII – 2 of this hereby technical
description.
f. Displaying via the ehv substation’s visual display unit all measured and calculated
metering data, ehv substation’s one line diagram with real time circuit breaker,
disconnector and earthing switch status.
- 21 -
i. Location and mounting
All the equipment required for communication and coordination reasons, except for the
equipment mentioned in paragraph IX-6a÷f, will be provided installed inside a metallic panel.
j. Fault Recording
Fault recording in accordance with the requirements of paragraph VIII-10 of this
hereby technical description.
k. Interfacing with the bay control units and relays and transmission’s system and
distribution’s system control centers (if required).
5. Mass Storage
It shall be possible to store historic event data and alarms on hard disks.
The system will be equipped with dual hard disks that will utilize “raid mirroring” for
storing event, alarm and fault data. This way the uninterrupted function of the HMI is
achieved, eliminating any risk of data loss.
The mass storage will be part of the HMI, capable of recording data of up to six (6)
months.
The operator’s terminal (HMI), located in the ehv substation’s control building, shall
include the following equipment;
a. Two (2) duplicate industrial PCs, Pentium of the latest series, with related
software package, preferably based on a professional edition of “WINDOWS”,
for displaying
− ehv substation’s overview (single-line diagram)
− Detailed diagrams of substation
− Event and alarm list
− Alarm information
− Fault data and fault graphical representation
− Measurement data
− Autotransformer / transformer (if required) tap changer position
The two PCs are on hot redundancy (backup) allowing the concurrent access to the
same application (master-slave connection). In case of malfunction of the master, the
processing of all the system functions is automatically transferred to the slave.
b. Two (2) 21” colour monitors (VDU), TFT, of resolution of 1280X1024 pixels
and refresh frequency of 75Hz.
- One VDU, to be used for displaying detailed diagrams of the ehv substation.
- VDUs supply voltage : 220 V AC
c. A dot matrix printer with 24 pins for printing events and alarms.
- Printer supply voltage : 220V AC
- 22 -
d. A laser printer for screen shot printing, measurements and fault data printing
- Printer supply voltage : 220V AC
f. A UPS System for the uninterruptible supply of the PCs, and VDUs and printers
which shall consist of the following:
1. A DC/AC inverter which shall be equipped with an electrical transfer
switch (AC-input)
2. The DC input will be supplied from the ehv substation’s batteries
3. DC input voltage : 220V DC ±15%
4. AC output : 220V AC, 50Hz, 2000VA, 6 sockets
5. AC output tolerances : For voltage ±1%, For frequency ±0,75%
6. The DC/AC inverter with its accessories shall be supplied in a panel
suitable for floor standing of class protection of IP52
g. All the equipment required for the communication and coordination with the
system bay level.
7. System Safety
All programs and parameters of the substation automation system, must be securely
stored in flash EPROMS so that the system to be capable of starting automatically after
a power interruption.
X. TIME SYNCHRONIZATION
2. For the GPS time signal distribution to all relevant units within the ehv substation, a
master clock must be provided with no more than eight (8) units per branch.
- 23 -
4. Signal strength at the input of the antenna : ~ 1X10 E-16 Watt, i.e. below the general
noise level.
- 24 -
b. It is noted that the provided IEDs of the 20kV bays will be capable of the
following:
i. Transmission of all indications, alarms and analog signals to and commands
from HMI/DCC, within Ethernet port (FOC) by IEC-61850 communication
protocol, in accordance with the attached Tables 1, 2, 3 of this hereby
technical description.
ii. Control of the corresponding 20kV bay equipment with embedded
appropriate control switches and mimic diagram.
iii. Digital inputs (DI) for the indications and alarms transfer from the 20kV
equipment or auxiliary equipment of the panel, according to the
corresponding attached Tables.
In case that IEDs will receive commands from not embedded control
switches, additional digital inputs will be provided.
iv. Digital outputs (DO) for the commands transfer from the 20kV equipment or
auxiliary equipment of the panel as well as for the transmission of signals
derived from the IED’s protection functions operation.
v. The functions of IEDs will be in accordance with the relevant technical
descriptions, as follows:
1. OLM panel: One (1) IED with functions according to the technical
description TD-50 and also with a number of Digital Inputs DI=18 and
Digital outputs DO=11, in total.
2. TM panel: One (1) IED with functions according to the technical
description TD-51 and also with a number of Digital Inputs DI=11 and
Digital outputs DO=7, in total.
Also one (1) IED with protection functions according to specification
SS-100 and also with a number of Digital Inputs DI=6 and Digital
outputs DO=4, in total
3. CM panel: One (1) three-phase IED with functions according to the
technical description TD-41 and also with a number of Digital Inputs
DI=17 and Digital outputs DO=6, in total.
Three (3) single-phase IEDs with protection functions according to the
technical description TD-40 and also with a number of Digital Inputs
DI=4 and Digital outputs DO=4, in total
4. ULM panel: One (1) IED with functions according to the technical
description TD-51 and also with a number of Digital Inputs DI=16 and
Digital outputs DO=9, in total.
5. BSM panel: One (1) IED with functions according to the technical
description TD-51 and also with a number of Digital Inputs DI=13 and
Digital outputs DO=4, in total.
6. IPPM panel:
- For underground 20kV feeder bay
One (1) IED with functions according to the technical description TD-
51 and also with a number of Digital Inputs DI=16 and Digital outputs
DO=9, in total.
- For overhead 20kV feeder bay
One (1) IED with functions according to the technical description TD-
50 and also with a number of Digital Inputs DI= 18 and Digital outputs
DO=11, in total.
- 25 -
c. Characteristics of the signals of alarms, measurements and commands
• Voltage : 100V AC
• Current : 5A
• Voltage : 110V DC
a. The fiber optic cables which will be used to connect bay control units with the
HMI center will be about 400 m long (the exact length will be derived from the
ehv substation’s layout drawings) and shall consist of glass fibre.
b. The fiber optic cables which will be used to connect bay control units with
protection relays with distances up to 3-6 m will be glass fibre. In the case
which the protections relays are connected directly to the HMI center with a
distance of about 400m long, the connection shall be with glass fibre.
c. The fiber optic cable which will be used to connect bus-bar differential relays to
the HMI center will be about 50 meters long and will consist of glass fibre.
d. If the structure of the substation automation system is of a double loop, this loop
shall be of glass fibre.
e. The glass fiber optic cables shall be equipped with rodent protection.
f. Temperature range withstand of the glass fiber optic cables shall be as follows:
g. Fibers in all other aspects will be as per IEC 60794-1 and IEC 60794-2
- 26 -
XIV. COMMUNICATION PROTOCOLS AND OTHER COMMUNICATIONS.
The following protocols are acceptable for the communications within the ehv
substation and also for the communication of the substation automation system
(S.A.S) with the system’s control centers.
1. Between bay level control units and HMI center, the acceptable communication
protocol is IEC-61850.
5. Between bay level control units and protection relays the acceptable protocol is
IEC-61850
6. Between HMI center and IEDs of 20KV bays, the acceptable protocol is
IEC-61850
XV. CERTIFICATION
The offered system and its devices shall be certified by conformance test performed in
accordance with IEC 61850-10. The certificate must be of level A (level A means
independent Lab., e.g. KEMA).
The certificate can be of level B (manufacturer’s Lab) if the manufacturer’s Lab has
been qualified by the UCA International Users Group.
In the first case the certificate (level A) must be submitted along with technical offer.
In the second case the certificate (level B), along with the UCA International Users
Group certification to the manufacturer must be submitted in the technical offer.
- 27 -
XVI. COMMUNICATION OF THE SUBSTATION AUTOMATION SYSTEM
WITH THE TRANSMISSION’S SYSTEM CONTROL CENTER WITH
CONVENTIONAL MEANS
Because the transmission’s system control center is not capable yet to communicate
via IEC-60870-5-101 protocol, a panel must be provided with an IEC-60870-5-101
protocol converter system. The inputs (events and alarms) to the protocol converter
system will be from the substation automation system (IEC-60870-5-101) and the
outputs will either be from free contacts suitable for 48V DC or digital signals of 48V
DC. The commands which originate from the transmission’s system control center
will be received by the protocol convert system in the form of free contacts. The
required auxiliary relays of 48V DC (coil voltage) for the commands will be part of
the supply.
This panel, besides the IEC-60870-5-101 protocol converter system, must contain and
the following:
a. Terminal blocks and miniature circuit breakers.
b. The converter system must accommodate the signals mentioned in previous
paragraphs and which are included at the attached Tables 1, 2, 3 and 4 of this
thereby technical description.
c. The transducers for the conversion of the analog measurements from the
substation automation system to current signals of -20….+20mA.
Because the distribution’s system control center is not capable to communicate via
IEC-60870-5-101 protocol, a panel must be provided with an IEC-60870-5-101
protocol converter. The inputs (events and alarms) to the protocol converter system
will be from the substation automation system (IEC-60870-5-101) and the outputs
will either be from free contacts suitable for 24V DC or digital signals of 24V DC.
The commands which originate from the distribution’s system control center will be
received by the protocol convert system in the form of free contacts. The required
auxiliary relays of 24V DC (coil voltage) for the commands will be part of the supply.
This panel, besides the IEC-60870-5-101 protocol converter system, must contain and
the following:
a. Terminal blocks and miniature circuit breakers.
b. The converter system must accommodate the signals mentioned in previous
paragraphs and which are included at the attached Tables 1, 2, 3 and 4 of this
thereby technical description.
c. The transducers for the conversion of the analog measurements from the
substation automation system to current signals of -5….+5mA.
- 28 -
XVIII. SOFTWARE
Any software needed for the configuration setting, parameterizing, documentation
and displaying of the system or of the devices which is composed of (bay control
units, protection relays, bus bar differential protection relays and GPS) shall be
professional “windows” based and shall be provided on the basis of a royalty free,
non-exclusive with irrevocable license to use by PPC.
Software for the analysis of fault data shall also be provided with the same terms as
above.
XIX. TESTS
The following routine and type tests concern the bay control units.
Only one (1) routine test concerns the panels of the system.
The tests required for the protection relays are specified in the relative specifications.
1. Routine tests
a. Power frequency voltage test as per
IEC-60255-5 : 2KV, 5Hz, 1minute
2. Type Tests
a. Impulse voltage test as per IEC-60255-5,
all circuits, class III : 5KV peak, 1.2 / 50 µs, 0.5 J,
3 positive and 3 negative shots at
intervals of 5 sec.
- 29 -
f. Radiated electromagnetic field
disturbance test as per
IEC-60255-22-3 class III : 10V/m, 27 to 500MHz
3. Acceptance Test
This concerns the entire system after its installation, and shall be performed in
accordance with the supplier’s standard in the presence of T/NPRD personnel.
1. All wording appearing on the VDU with regard the single line diagrams of the ehv
substation shall be in Greek language.
2. Care shall be taken so that the system can be expanded in the future, if needed.
4.1 For all “functions” within the substation, an object oriented data model will be
provided grouping the data into the smallest possible independent functions named
Logical Nodes (LN). Entire functionality of S.A.S split into LNs.
The LNs and all data attributes contained therein will be named according to
standardised “semantic”. The Substation Configuration Language used to configure
the S.A.S and individual IEDs is the SCL language.
4.2 Complete S.A.S will be formally documented within SCL especially through SCD
(Substation Configuration Description) files.
The SCD files will ensure that all system engineering work has been recorded for
re-use in future adaptations, extensions and refurbishment of the S.A.S. The SCD
files is part of the documentation that PPC will receive with the delivery of the
System.
XXI. COMMISSIONING
The commissioning of the system shall be carried out by the supplier of the system,
therefore the cost of the commissioning of the system must be included in the economic
offer.
XXII. TRAINING
1. In the scope of supply, a training of at least six (6) PPC engineers shall be included.
Training shall take place at the facilities of the supplier for at least seven (7) days and
- 30 -
shall include but not limited to the following.
a. System parameterization
b. System configuration
c. System documentation
d. Test run of the system (to the extend that it is possible)
2. In addition along with entire system, two (2) Laptops must be supplied with he
following characteristics:
Pentium IV : 2,5MHz
Hard Disk : 40GB at least
Central unit : 512MB
Screen cart : VCA, 64MB
Network cart : 10/100
Modem cart : 56K
Drive : DVD/RW
Drive : FD/3,5”
Screen :15” TFT with resolution 1024X768pixels/75Hz pixels
The above laptops must be loaded with all parameterizing, setting and documentation
programs of the substation automation system, protections relays and GPS system.
With the delivery of all system components and providing that all schematic and wiring
drawings of the system have been submitted and approved by PPC, a payment order
will be issued to the amount of 70% of the worth of the delivered system. An additional
20% of the total of the delivered system will be paid after the precommissioning of the
system and the remaining 10% of the worth of the system will be paid after he final
commissioning and acceptance testing of the system. The time between delivery of the
system and final commissioning can be from three (3) months to eight (8) months.
All bidders are required, in their technical offer, to provide the following:
2. Point by point description of the system offered against this hereby technical
description.
3. Point by point compliance, differences or any deviations from this hereby technical
description must be clearly indicated.
4. A drawing with the structure (configuration) of the offered system and with all
communication protocols indicated on it.
5. Failure to comply with requirements of 2, 3 and 4 above, will result in rejection of the
offer.
- 31 -
In other words, a technical offer comprised of some technical brochures and generalities
without addressing all technical points raised by this hereby technical description will
be rejected.
6. Outline drawings with over-all dimensions and wiring drawings of all the system’s
devices.
7. Any available test certificates for all specified type tests in this hereby technical
description may be submitted along with the technical offer.
Acceptance or not of the submitted test certificates will be subject to the purchaser’s
approval.
8. A reference list for the offered system shall be submitted and in which the following
shall be included:
− Country and buyer
− Number of systems sold
− Year of sale.
2. Complete outline and wiring drawings (four (4) copies of each drawing) for all the
equipment of the system and the system itself, for approval before the shipment of the
entire system.
1. The HMI equipment mentioned in paragraph IX-6g shall be placed on a separate panel.
2. Each panel for 400KV transmission line bays shall contain, besides other equipment,
the following:
a. Two (2) digital distance protection relays of the same manufacturer but with
different settings and algorithms, as per SS-108.
b. One (1) bay control unit
c. Furthermore, one (1) of the panels for the 400KV transmission line bays shall
include one (1) bay control unit for the bus section bay. This panel will be
designated during the implementation of the contract.
3. Each panel for the 400KV line bays of power plants shall contain, besides other
equipment, the following:
a. One (1) numerical phase and earth overcurrent protection relay, as per TD-31B
technical description.
b. One (1) bay control unit
- 32 -
4. Each panel for the 400KV autotransformer bays shall contain, besides other equipment,
the following:
a. One (1) autotransformer differential protection relay as per SS-68
b. Three (3), 3-phase and earth fault overcurrent relays that will be connected with
the corresponding voltage transformers of the 400KV, 150KV and 30KV
autotransformer bushings, as per TD-48
c. One (1) single phase overcurrent mass protection relay as per TD-49
d. One (1) voltage regulation relay
e. One (1) bay control unit
5. Each panel for 400KV bus coupler shall contain, besides other equipment, the
following:
a. One (1) bay control unit
6. Each panel for the 150 KV transmission line bays shall contain, besides other
equipment, the following:
a. One (1) distance protection relay as per TD-16
b. One (1) directional and earth(ground) overcurrent relay as per SS-131
c. One (1) bay control unit
d. Furthermore, one (1) of the panels for the 150KV transmission line bays shall
include a bay control unit which, however, shall not have control functions on it.
It will be used for indication purposes only and for transmitting the required
signals to the HMI center (e.g. for indications of manually operated
disconnectors' status for the manually operated 150KV bus section bay). That
panel will be designated during the implementation of the contract.
7. Each panel for the 150KV autotransformer bays shall contain, besides other equipment,
the following :
a. One (1) distance protection relay without automatic reclosing as per TD-16
b. One (1) bay control unit
8. Each panel for the 150KV capacitor bays (if required) shall contain, besides other
equipment, the following:
a. One (1) bay control unit
b. Three (3) current unbalance relays as per TD-38
c. One (1) Numerical overcurrent plus overload relay in accordance with TD-37
d. One (1) voltage relay as per TD-39
9. Each panel for the 150KV bus coupler bays shall contain, besides other equipment, the
following:
a. One bay control unit
10. Each panel for the 150KV power unit line bays shall contain, besides other equipment,
the following:
- 33 -
a. One (1) numerical phase and earth overcurrent protection relay, as per TD-31B
technical description.
b. One (1) bay control unit
11. Εach panel for the 30KV autotransformer bay shall contain, besides other equipment,
the following:
a. One (1) 3-phase and earth fault overcurrent relay as per TD-48 that will be
connected to the current transformers of the 30KV shunt reactor bushings.
b. One (1) voltage relay supplied from VTs connected in broken delta for the
protection of 30KV, 50MVAR shunt reactors against earth faults as per TD-52
c. One (1) voltage relay supplied from single – phase VT, located in the neutral of
a 30KV, 50MVAR shunt reactor for the detection of overvoltage conditions as
per TD-46.
12. Each panel for the (150/20KV) transformer bay (if required) shall contain, besides other
equipment, the following:
a. One (1) transformer differential protection relay as per SS-100
b. One (1) phase earth overcurrent relay, as per TD-31B technical description
c. One (1) definite time overcurrent relay suitable for the detection of small earth
fault currents, as per specification SS-94
d. One (1) bay control unit
13. The 400KV and 150KV busbar differential protection systems as per SS-55 will be
installed:
a. In uniform panels if the protection systems are of centralized structure, the number
of panels to be determined by the supplier depending on the system offered.
All panels for the above system will be located inside the corresponding bus
coupler bay relay kiosk.
b. If the protection system is of distributed structure, the peripheral units will be
installed in the protection panel inside the relay kiosk of the corresponding bay and
the central unit inside the corresponding bus coupler relay kiosk.
14. Each communication panel for the conventional communication with the transmission’s
system control center shall contain all equipment described in paragraph XVI.
15. Each communication panel for the conventional communication with the distribution’s
system control center (if applicable) shall contain all equipment described in paragraph
XVI.
16. By this term <<other equipment >> is mentioned basically the following: microcircuit
breakers, auxiliary relays, terminal blocks etc.
- 34 -
17. All fiber optic cables necessary for the connection of bay control units, protection relays
to the HMI center and also the 20KV IEDs to HMI center must be supplied.
18. All panels shall be equipped with 25% spare terminals blocks which will be used for the
wiring of signals and commands from the outdoor primary equipment.
In the wiring drawings the points of the terminal blocks on where the signals or
commands are to be wired, shall be clearly indicated.
All terminal blocks shall be suitable for conductors of 8mm2 in cross section.
19. All panels, which shall bear protection relays, shall be equipped with test sockets
(current, voltage and trip circuits) used for the testing of relays. A number of the
corresponding male plugs must also be supplied. The test sockets shall be the same with
regard the design and function as those of ENTRELEC make.
It should be noted that test terminal blocks are not acceptable.
20. All incoming voltage feeds for each panel must be run through voltage sockets of type
omega (Ω) for isolation purposes.
21. All panels of the system must be wired with 1.5mm2 control cables and all control
cables must be equipped with copper strip of 0.1mm2 in thickness and must also bear
protection against rodents.
22. All panels which are to be provided for the entire system shall be of the IP52 protection
class as per IEC-60529.
23. All panels of the system must bear doors of plexiglass.
24. The protection and control panels of the 400KV and 150KV bays, will be installed
inside the relay kiosks of the corresponding bays.
The protection and control panels of the 30KV bays, will be installed inside the relay
kiosks of the corresponding 400KV bays.
The 20KV metal-clad panels (not included in the supply), will be located inside the
control building of the ehv substation
The colours used for the mimic diagrams appearing on the VDUs (screens) of the HMI
shall be as follows:
1. 400KV Buses and Equipment : Green colour
2. 150KV Buses and Equipment : Red colour
3. 20KV Buses and Equipment : Black colour
4. 30KV Buses and Equipment : Blue colour
5. 380V AC Buses and Equipment : Orange colour
6. 220V AC Buses and Equipment : Brown colour
7. 220V DC Buses and Equipment : Purple colour
8. 110V DC Buses and Equipment : White colour
9. Earthing (grounding) : Yellow colour
10. Equipment status : In accordance with IEC 60073, latest revision
11. VDU background colour : Light Grey / Blue colour
- 35 -
XXVIII. PACKING
All panels, covered with nylon, shall be packed inside robust wooden boxes.
VDUs, PCs, printer, UPS, GPS antenna and its accessories, fiber optic cables and any
other components of the system shall all be packed separately inside robust boxes and
each box besides been labelled properly, it shall bear indication as to what it contains.
- 36 -
APPENDIX
TABLE 1 : CONTROL
TABLE 2 : INDICATIONS
TABLE 3 : ALARMS
TABLE 4 : MEASUREMENTS
- 37 -
TABLE 1 : CONTROL
CONTENTS
- 38 -
TABLE 1.1
EHV
400KV OVERHEAD T.L. BAY TCC**
Substation
Note
- 39 -
TABLE 1.2
EHV
400 KV OVERHEAD T.L. BAY FOR INTERNATIONAL LINKS TCC
Substation
Auto-reclosing 1 - OFF ● ●
Auto-reclosing 2 - ON ● ●
Auto-reclosing 2 - OFF ● ●
Note
- 40 -
TABLE 1.3
TABLE 1.4
EHV
400 KV AUTOTRANSFORMER BAY TCC
Substation
C.B 400 KV, C.B 150 KV, C.B 30 KV of the same autotransformer bay ● ●
emergency opening (common command)
- 41 -
TABLE 1.5
EHV
400 KV BUS COUPLER BAY - BUS SECTION BAY TCC
Substation
C.B 400 KV (Ρ805) -opening C.B ● ●
C.B 400 KV (Ρ805) – C.B selection (for closing) ●
- 42 -
TABLE 1.5 (continues)
Note
TABLE 1.6
Note
- 43 -
TABLE 1.7
EHV Power
150 KV OVERHEAD T.L. BAY FOR POWER PLANT TCC
Substation plant
- 44 -
TABLE 1.8
EHV
150 KV AUTOTRANSFORMER BAY TCC
Substation
Note
* common command for all C.Bs
- 45 -
TABLE 1.9
EHV
150 KV TRANSFORMER BAY TCC DCC
Substation
C.B 150 KV -opening C.B ● ●
C.B 150 KV – C.B selection (for closing) ●
TABLE 1.10
EHV
150 KV BUS COUPLER BAY TCC
Substation
Note
- 46 -
TABLE 1.11
EHV
30 KV AUTOTRANSFORMER BAY TCC
Substation
TABLE 1.12
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
● ●
Overcurrent instantaneous elements ON
● ●
Overcurrent instantaneous elements OFF
● ●
CB auto-reclosing operation - ON (only for overhead T.L. feeder bay)
● ●
CB auto-reclosing operation - OFF (only for overhead T.L. feeder bay)
● ●
Panel in "remote" control
- 47 -
20 KV BUS COUPLER BAY (BSM panel) PANEL HMI / DCC
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
PANEL / DCC
20 KV CAPACITORS BANKS BAY (CM panel) TCC
HMI (* )
For every protection relay of 20 kV bays or transformers, it is required that after operation of its ''reset"
command, the corresponding telecontrol will be ensured.
(*)& (●) Will be designated during the implementation of the contract
TCC or DCC
20 KV FEEDER BAY FOR INDEPENDENT PRODUCER (IPPM) PANEL / HMI
(* )
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
CB auto-reclosing operation - OFF (only for overhead T.L. feeder bay) ● (●)
(*) & (●) Will be designated during the implementation of the contract
- 48 -
TABLE 2 : INDICATIONS
CONTENTS
TABLE 2.12
20 KV BUS COUPLER BAY (BSM panel)
- 49 -
TABLE 2.1
EHV
400KV OVERHEAD T.L. BAY TCC
SUBSTATION
Note
- 50 -
TABLE 2.2
EHV
400 KV OVERHEAD T.L. BAY FOR INTERNATIONAL LINKS TCC
SUBSTATION
Note
- 51 -
TABLE 2.3
EHV POWER
400 KV BAY FOR CONNECTION WITH POWER PLANT TCC PLANT
SUBSTATION
Bay controlled by "ehv substation" ● ●
Bay controlled by "TCC" ● ●
TABLE 2.4
- 52 -
TABLE 2.5
EHV
400 KV BUS COUPLER BAY - BUS SECTION BAY TCC
SUBSTATION
- 53 -
TABLE 2.5 (continues)
EHV
400 KV BUS COUPLER BAY - BUS SECTION BAY TCC
SUBSTATION
Note
- 54 -
TABLE 2.6
EHV
150 KV OVERHEAD T.L. BAY TCC
SUBSTATION
Note
- 55 -
TABLE 2.7
EHV Power
150 KV OVERHEAD T.L. BAY FOR POWER PLANT TCC
SUBSTATION Plant
Bay controlled by "ehv substation" ● ●
- 56 -
TABLE 2.8
EHV
150 KV AUTOTRANSFORMER BAY TCC
SUBSTATION
Bay controlled by "ehv substation" ● ●
On Load Tap Changer - control on "voltage step " (25 steps) ● ● (2)
Note
- 57 -
TABLE 2.9
EHV
150 KV TRANSFORMER BAY (TM panel) TCC DCC
SUBSTATION
- 58 -
TABLE 2.10
EHV
150 KV BUS COUPLER BAY TCC
SUBSTATION
Bay controlled by "ehv substation" ● ●
EHV
150 KV BUS SECTION BAY TCC
SUBSTATION
Note
- 59 -
TABLE 2.11
EHV
30 KV AUTOTRANSFORMER BAY TCC
SUBSTATION
C.B 30 KV – open ● ●
C.B 30 KV – closed ● ●
D.S 30 KV – open ● ●
D.S 30 KV – closed ● ●
- 60 -
TABLE 2.12
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
C.B 20 KV – opening ● ●
C.B 20 KV – closing ● ●
- 61 -
PANEL / DCC
20 KV CAPACITORS BANKS BAY (CM panel) TCC
HMI (*)
(*) & (●) Will be designated during the implementation of the contract
C.B 20 KV - opening ● ●
C.B 20 KV – closing ● ●
- 62 -
TABLE 3 : ALARMS
CONTENTS
- 63 -
TABLE 3.1
EHV
GENERAL ALARMS OF EHV SUBSTATION - ACOUSTIC
SUBSTATION
110V DC panels – DC supply loss
110V DC panels – DC supply loss for general alarms (supervising will be
performed by the use of auxiliary A.C. relays that will excite an AC alarm bell)
220V DC panels – DC supply loss
220V DC panels – DC supply loss for general alarms (supervising will be
performed by the use of auxiliary A.C. relays that will excite an AC alarm bell)
AC panels. AC supply loss. Supervising per phase (supervising will be
performed by the use of auxiliary DC relays that will excite an DC alarm bell)
EHV substation entrance bell
Alarm Ι - excitation of the substation control building security system
Alarm ΙΙ - excitation of the substation control building fire detection system
- 64 -
TABLE 3.2
EHV
GENERAL ALARMS OF EHV SUBSTATION - VISUAL TCC DCC
SUBSTATION
400 ΚV SIDE
Synchro-check voltage comparison scheme: "Live line"-"live
bus"
Synchro-check voltage comparison scheme: "Dead line"-"live
bus"
Synchro-check voltage comparison scheme: "Live line"-"dead
bus"
Synchro-check voltage comparison scheme: "Dead line"-"dead
bus"
Synchro-check operation failure (due to) – "voltage magnitude
difference"
Synchro-check operation failure (due to) – "frequency difference"
Synchro-check operation failure (due to) – "phase difference"
400KV bus-bars differential protection – blocking
400KV bus-bars differential protection – excitation
400KV bus-bars differential protection – one (1) trip alarm per
zone
400KV bus-bars differential protection – overall trip alarm
150 KV SIDE
Synchro-check voltage comparison scheme: "Live line"-"live
bus"
Synchro-check voltage comparison scheme: "Dead line"-"live
bus"
Synchro-check voltage comparison scheme: "Live line"-"dead
bus"
Synchro-check voltage comparison scheme: "Dead line"-"dead
bus"
Synchro-check operation failure (due to) – "voltage magnitude
difference"
Synchro-check operation failure (due to) – "frequency difference"
Synchro-check operation failure (due to) – "phase difference"
150KV bus-bars differential protection – blocking
150KV bus-bars differential protection – excitation
150KV bus-bars differential protection – one (1) trip alarm per
zone
150KV bus-bars differential protection – overall trip alarm
220V D.C. SUPPLY NETWORK
Battery charger 1 of 220V batteries – overvoltage / undervoltage
at the output
Battery charger 1 of 220V batteries – malfunction / damage
Battery charger 2 (back-up) of 220V batteries – overvoltage /
undervoltage at the output
- 65 -
EHV
220V D.C. SUPPLY NETWORK (continues) SUBSTATION
TCC DCC
Battery charger 2 (back-up) of 220V batteries – malfunction /
damage
Battery charger of 48V batteries – malfunction / damage
For every 220V DC supply panel
Supervision relay of DC current leakage
DC supply loss at the panel’s busbars (supervising by auxiliary
undervoltage relay)
DC supply loss of general alarms (supervising by auxiliary AC
relay)
Trip of panel’s supply auto-circuit breaker (*)
For every 220V DC supply
Tripping of auto-C.B. for power line carrier (400KV side)
Tripping of auto-C.B. for central control unit
Tripping of auto-C.B. for PC display
Tripping of auto-C.B. for 400 KV busbars differential protection
Tripping of auto-C.B. for transmission SCADA interface
Tripping of auto-C.B. 1, for protection and control D.C. loop (±1)
Tripping of auto-C.B. 1, for protection and control D.C. loop (±2)
Tripping of auto-C.B. 1, for D.S motors D.C. loop (±Ι)
Tripping of auto-C.B. 1, for alarms D.C. loop (±3)
Tripping of auto-C.B. 1, for interlockings
Tripping of auto-C.B. 2, for protection and control D.C. loop (±1)
Tripping of auto-C.B. 2, for protection and control D.C. loop (±2)
Tripping of auto-C.B. 2, for D.S motors D.C. loop (±Ι)
Tripping of auto-C.B. 2, for alarms D.C. loop (±3)
Tripping of auto-C.B. 2, for interlockings
Tripping of auto-C.B. for general signals
Collectively (one common signal for similar supplies)
- 66 -
TABLE 3.2 (continues)
EHV
110V D.C. SUPPLY NETWORK SUBSTATION
TCC DCC
Battery charger 1 of 110V batteries – overvoltage / undervoltage
at the output
Battery charger 1 of 110V batteries – malfunction / damage
Battery charger 2 (back-up) of 110V batteries – overvoltage /
undervoltage at the output
Battery charger 2 (back-up) of 110V batteries – malfunction /
damage
For every 110V DC supply panel
- 67 -
TABLE 3.2 (continues)
EHV
A.C. SUPPLY NETWORK TCC DCC
SUBSTATION
- 68 -
TABLE 3.3
EHV
400KV OVERHEAD T.L. BAY TCC
SUBSTATION
400 KV C.B. - low SF6 pressure – level 1
400 KV C.B. - low SF6 pressure - level 2
400 KV C.B. – spring uncharged
Distance protection relay 1 - malfunction
Distance protection relay 1 - excitation of phase Α
Distance protection relay 1 - excitation of phase B
Distance protection relay 1 - excitation of phase C
Distance protection relay 1 – general excitation
Distance protection relay 1 – trip command to C.B of the bay
Distance protection relay 1 – fault detection at zone 1
Distance protection relay 1 - fault detection at zone 2
Distance protection relay 1 - fault detection at zone 3
Distance protection relay 1 - fault detection backward
Distance protection relay 1 – remote trip command via power line
carrier, from the C.B. of the S/S connecting at the opposite end of the
Transmission line
Distance protection relay 1 – autoreclosing blocked
Distance protection relay 2 - malfunction
Distance protection relay 2 - excitation of phase Α
Distance protection relay 2 - excitation of phase B
Distance protection relay 2 - excitation of phase C
Distance protection relay 2 - general excitation
Distance protection relay 2 – trip command to C.B of the bay
Distance protection relay 2 – fault detection at zone 1
Distance protection relay 2 - fault detection at zone 2
Distance protection relay 2 - fault detection at zone 3
Distance protection relay 2 - fault detection backward
Distance protection relay 2 – remote trip command via power line
carrier, from the C.B. of the S/S connecting at the opposite end of the
Transmission line
Distance protection relay 2 – autoreclosing blocked
400kV busbar differential protection relay - trip
mcb (*) of transmission line voltage control for distance protection
relay - trip
mcb of transmission line voltage control for synchro-check - trip
mcb of busbar voltage control for synchro-check - trip
- 69 -
TABLE 3.3 (continues)
- 70 -
TABLE 3.4
EHV
400 KV OVERHEAD T.L. BAY FOR INTERNATIONAL LINKS
SUBSTATION TCC
400 KV C.B. - low SF6 pressure - level 1
400 KV C.B. - low SF6 pressure - level 2
400 KV C.B. – spring uncharged
Distance protection relay 1 - malfunction
Distance protection relay 1 - excitation of phase Α
Distance protection relay 1 - excitation of phase B
Distance protection relay 1 - excitation of phase C
Distance protection relay 1 – general excitation
Distance protection relay 1 – trip command to C.B of the bay
Distance protection relay 1 – fault detection at zone 1
Distance protection relay 1 - fault detection at zone 2
Distance protection relay 1 - fault detection at zone 3
Distance protection relay 1 - fault detection backward
Distance protection relay 1 – remote trip command via power line carrier,
from the C.B. of the S/S connecting at the opposite end of the T.L.
Distance protection relay 1 – autoreclosing blocked
Distance protection relay 2 - malfunction
Distance protection relay 2 - excitation of phase Α
Distance protection relay 2 - excitation of phase B
Distance protection relay 2 - excitation of phase C
Distance protection relay 2 - general excitation
Distance protection relay 2 – trip command to C.B of the bay
Distance protection relay 2 – fault detection at zone 1
Distance protection relay 2 - fault detection at zone 2
Distance protection relay 2 - fault detection at zone 3
Distance protection relay 2 - fault detection backward
Distance protection relay 2 – remote trip command via power line carrier,
from the C.B. of the S/S connecting at the opposite end of the T.L.
Distance protection relay 2 – autoreclosing blocked
400kV busbar differential protection relay - trip
mcb of transmission line voltage control for distance protection relay - trip
mcb of transmission line voltage control for synchro-check - trip
mcb of busbar voltage control for synchro-check - trip
- 71 -
TABLE 3.4 (continues)
- 72 -
TABLE 3.5
EHV POWER
400 KV OVERHEAD T.L. BAY FOR POWER PLANT TCC PLANT
SUBSTATION
Alarms of protection units which are to be sent to the Power Plant, as well as alarms of the Power Plant
protection units to EHV Substation, will be designated during the stage of studies submission.
- 73 -
TABLE 3.6
EHV
400 KV AUTOTRANSFORMER BAY TCC
SUBSTATION
400 KV C.B. - low SF6 pressure - level 1
400 KV C.B. - low SF6 pressure - level 2
400 KV C.B. – spring uncharged
Overcurrent protection relay - malfunction (3)
Overcurrent protection relay - alarm
Overcurrent protection relay - trip
Bus-bar differential protection relay - trip
Protection and control panel of the bay – trip of DC supply mcb for
control and protection (+01)
Protection and control panel of the bay – trip of DC supply mcb for
control and protection (+02)
Protection and control panel of the bay – trip of DC supply mcb for
control and protection (+12)
Protection and control panel of the bay – trip of DC supply mcb for
alarms (+03)
Protection and control panel of the bay – trip of DC supply mcb for
interlockings (+04)
Protection and control panel of the bay – trip of DC supply mcb for
D.S motors (+)
DC supply loss for operation, control, protection and alarms of the
bay
Autotransformer’s alarms
- 74 -
TABLE 3.6 (continues)
EHV
400 KV AUTOTRANSFORMER BAY (continues) TCC
SUBSTATION
Autotransformer – oil low level - alarm (2)
Autotransformer - OLTC oil low level - alarm (2)
Autotransformer - oil high level - alarm (2)
Autotransformer - OLTC oil high level - alarm (2)
Autotransformer – Buchholz relay - trip (4)
Autotransformer – OLTC Buchholz relay - trip (4)
Autotransformer – oil temperature - trip (5)
Autotransformer - winding (H2) temperature - trip (5)
Autotransformer - winding (Y2) temperature - trip (5)
Autotransformer - winding (X2) temperature - trip (5)
Autotransformer - pressure relief valve - trip (5)
Autotransformer – deferential protection relay - malfunction (3)
Autotransformer – deferential protection relay - excitation
Autotransformer – deferential protection relay - trip
Autotransformer – mass protection relay - malfunction (3)
Autotransformer – mass protection relay – excitation
Autotransformer – mass protection relay - trip
Activation of fire extinguishing system
Note :
(x) Alarms to TCC, having the same numbering will be a common signal
- 75 -
TABLE 3.7
EHV
400 KV BUS COUPLER BAY TCC
SUBSTATION
- 76 -
TABLE 3.8
EHV
150 KV OVERHEAD T.L. BAY TCC
SUBSTATION
Note :
(x) Alarms to TCC, having the same numbering will be a common signal
- 77 -
TABLE 3.9
EHV POWER
150 KV OVERHEAD T.L. BAY FOR POWER PLANT TCC PLANT
SUBSTATION
Alarms of protection units which are to be sent to the Power Plant, as well as alarms of the Power Plant
protection units to EHV Substation, will be designated during the stage of studies submission.
- 78 -
TABLE 3.10
EHV
150 KV AUTOTRANSFORMER BAY TCC
SUBSTATION
150 KV C.B. - low SF6 pressure - level 1
150 KV C.B. - low SF6 pressure - level 2
150 KV C.B. – spring uncharged
Distance protection relay - malfunction (1)
Distance protection relay - excitation of phase Α
Distance protection relay - excitation of phase B
Distance protection relay - excitation of phase C
Distance protection relay – general excitation
Distance protection relay – trip command to C.B of the bay
Distance protection relay – fault detection at zone 1
Distance protection relay - fault detection at zone 2
Distance protection relay - fault detection at zone 3
Distance protection relay - fault detection backward
Overcurrent protection relay - malfunction (1)
Overcurrent protection relay - excitation
Overcurrent protection relay – trip command to C.B of the bay
mcb of transmission line voltage control for distance protection relay -
trip
mcb of T.L voltage control for synchro-check - trip
mcb of busbar voltage control for synchro-check - trip
Busbar differential protection relay - trip
Cable protection relay (if applicable) - trip
Protection and control panel of the bay – trip of DC supply mcb for
control and protection (+QL)
Protection and control panel of the bay – trip of DC supply mcb for
alarms (+SL)
Protection and control panel of the bay – trip of DC supply mcb for
interlockings (+04)
Protection and control panel of the bay – trip of DC supply mcb for D.S
motors (+)
DC supply loss for operation, control, protection and alarms of the bay
Note :
(x) Alarms to TCC, having the same numbering will be a common signal
- 79 -
TABLE 3.11
EHV
150 KV TRANSFORMER BAY DCC
SUBSTATION
150 KV C.B. - low SF6 pressure - level 1
150 KV C.B. - low SF6 pressure - level 2
150 KV C.B. – spring uncharged
Busbar differential protection relay - trip
Protection and control panel of the bay – trip of DC supply mcb for control
and protection (+QL)
Protection and control panel of the bay – trip of DC supply mcb for alarms
(+SL)
Protection and control panel of the bay – trip of DC supply mcb for
interlockings (+04)
Protection and control panel of the bay – trip of DC supply mcb for D.S
motors (+)
Transformer – Buchholz relay - alarm
Transformer – OLTC Buchholz relay - alarm
Transformer – oil temperature - alarm
Transformer - winding (Χ1) temperature - alarm
Transformer - winding (Χ3) temperature - alarm
Transformer – oil low level - alarm
Transformer – OLTC oil low level - alarm
Overcurrent protection relay of transformer neutral - malfunction
Transformer neutral - overcurrent protection relay – alarm due to earth
fault
Transformer neutral earthing resistance – high temperature alarm
Transformer – trip from Buchholz relay to the bay C.B.
Transformer – trip from OLTC Buchholz relay to the bay C.B.
Transformer – trip due to oil temperature to the bay C.B.
- 80 -
TABLE 3.11 (continues)
EHV
150 KV TRANSFORMER BAY (continues) DCC
SUBSTATION
TABLE 3.12
EHV
150 KV BUS COUPLER BAY TCC
SUBSTATION
150 KV C.B. - low SF6 pressure - level 1
150 KV C.B. - low SF6 pressure - level 2
150 KV C.B. – spring uncharged
Busbar differential protection relay - trip
mcb of busbar 1 voltage control for synchro-check - trip
mcb of busbar 2 voltage control for synchro-check - trip
Protection and control panel of the bay – trip of DC supply mcb for control
and protection (+QL)
Protection and control panel of the bay – trip of DC supply mcb for alarms
(+SL)
Protection and control panel of the bay – trip of DC supply mcb for
interlockings (+04)
Protection and control panel of the bay – trip of DC supply mcb for D.S
motors (+)
DC supply loss for operation, control, protection and alarms of the bay
- 81 -
TABLE 3.13
EHV
30 KV AUTOTRANSFORMER BAY TCC
SUBSTATION
30 KV C.B. - low SF6 pressure - level 1
30 KV C.B. - low SF6 pressure - level 2
30 KV C.B. – spring uncharged (1)
30 KV C.B. – motor protection (1)
Autotransformer – overcurrent protection relay - excitation
Autotransformer – overcurrent protection relay – trip alarm
Protection and control panel of the bay – trip of DC supply mcb for control
and protection (+ 01) (2)
Protection and control panel of the bay – trip of DC supply mcb for alarms
(+03) (2)
Reactor – trip from Buchholz relay to the bay C.B.
Reactor – reactor’s own protections (BUCHHOLZ, GASS)
Reactor - oil temperature - alarm
Reactor – trip due to oil temperature to the bay C.B.
Reactor – neutral voltage transformer
Reactor – oil level (min)
Reactor – thermostat - alarm
Reactor – overcurrent protection relay - alarm
Reactor - overcurrent protection relay - trip
30KV voltage transformer –unbalance protection relay
Note :
Alarms to TCC, having the same numbering (x) will be a common signal
- 82 -
TABLE 3.14
- 83 -
TABLE 3.15
- 84 -
TABLE 3.15 (continues)
PANEL TCC or
20 KV FEEDER BAY FOR INDEPENDENT PRODUCER (IPPM)
/ΗΜΙ DCC (*)
IPPM panel - trip of DC supply mcb for bay protection () (3)
IPPM panel - trip of DC supply mcb for bay alarms () (3)
C.B. opening or closing - malfunction () (1)
Note :
Alarms to TCC, having the same numbering (x) will be a common signal
(*) & (●) Will be designated during the implementation of the contract
- 85 -
TABLE 3.16
PANEL/
20 KV CAPACITORS BANKS BAY (CM panel)
HMI
TCC DCC (*)
CM panel - low SF6 pressure - level 1 ()
CM panel - low SF6 pressure - level 2 ()
CM panel - C.B. spring uncharged ()
CM panel - 20 KV incoming cable - live ()
CM panel - overcurrent protection relay - failure ()
CM panel – arc detection relay - failure ()
CM panel - unbalance protection relay - failure ()
CM panel - arc detection relay – trip to the C.B. of the bay ()
CM panel - instantaneous elements of overcurrent (phase)
protection– trip to the C.B. of the bay
CM panel - time elements of overcurrent (phase) protection– trip to
()
the C.B. of the bay
CM panel - instantaneous elements of overcurrent (earth)
protection– trip to the C.B. of the bay
CM panel - time elements of overcurrent (earth) protection– trip to
()
the C.B. of the bay
st
CM panel – instantaneous elements of overcurrent protection of 1
capacitor bank neutral – trip to the C.B. of the bay ()
st
CM panel – time elements of overcurrent protection of 1 capacitor
bank neutral – trip to the C.B. of the bay ()
CM panel – instantaneous elements of overcurrent protection of
nd
2 capacitor bank neutral – trip to the C.B. of the bay ()
nd
CM panel – time elements of overcurrent protection of 2
capacitor bank neutral – trip to the C.B. of the bay ()
rd
CM panel – instantaneous elements of overcurrent protection of 3
capacitor bank neutral – trip to the C.B. of the bay ()
rd
CM panel – time elements of overcurrent protection of 3 capacitor
bank neutral – trip to the C.B. of the bay ()
CM panel - trip of DC supply mcb for bay control ()
CM panel - trip of DC supply mcb for bay protection ()
CM panel - trip of DC supply mcb for bay alarm ()
st
Loss of 1 capacitor bank (4,3 Μvar) ()
nd
Loss of 2 capacitor bank (4,3 Μvar) ()
rd
Loss of 3 capacitor bank (4,3 Μvar) ()
20kV C.B. opening or closing - malfunction ()
- 86 -
TABLE 3.16 (continues)
TABLE 3.17
- 87 -
TABLE 4 : MEASUREMENTS
CONTENTS
TABLE 4.5
20 KV BUS COUPLER BAY (BSM panel)
- 88 -
TABLE 4.1
EHV
110V DC PANELS (for each panel) TCC DCC
SUBSTATION
Current ●
Voltage ●
EHV
220V DC PANELS (for each panel) TCC DCC
SUBSTATION
Current ●
Voltage ●
EHV
400/230V AC PANEL - SUBSTATION TCC DCC
SUBSTATION
Current ●
Voltage ●
Energy ●
- 89 -
TABLE 4.2
EHV POWER
400KV OVERHEAD T.L. BAY TCC
SUBSTATION PLANT
Note
- 90 -
TABLE 4.3
EHV POWER
150 KV OVERHEAD T.L. BAY TCC DCC
SUBSTATION PLANT
Current of three phases ● ●
Voltage of three phases (the 3 phase and 3 polar voltages
● ● (1)
are presented)
Active power (3ph) ● ●
Reactive power (3ph) ● ●
EHV POWER
150 KV OVERHEAD T.L. BAY FOR POWER PLANT SUBSTATION
TCC DCC
PLANT
Current of three phases ● ● (2)
Voltage of three phases (the 3 phase and 3 polar voltages
● ● (1)
are presented) (2)
Active power (3ph) ● ● (2)
Reactive power (3ph) ● ● (2)
Active energy (3ph) ● (2)
Reactive energy (3ph) ● (2)
EHV POWER
150 KV TRANSFORMER BAY TCC DCC
SUBSTATION PLANT
Note
(1) Only the three (3) polar
(2) The measurements of 400KV bay to Power Plant, will be designated during the execution of the
Project
- 91 -
TABLE 4.4
EHV
30 KV AUTOTRANSFORMER BAY TCC DCC
SUBSTATION
Note
(1) Only the three (3) polar voltages
TABLE 4.5
Frequency ● ●
Current of phase B ● ●
Maximum current ● ●
Current of phase B ● ●
- 92 -
TCC
20 KV CAPACITORS BANKS BAY (CM panel) PANEL HMI / DCC
(* )
TCC
20 KV FEEDER BAY FOR INDEPENDENT PRODUCER (IPPM) PANEL HMI / DCC
(* )
(*) & (●) Will be designated during the implementation of the contract
- 93 -
PUBLIC POWER CORPORATION
TRANSMISSION SYSTEM DEPARTMENT MARCH 2009
PROTECTION SECTION
Technical description for digital phase overcurrent relays for 400 KV, 150KV,
30 KV sides of ATR and reactors
3. Operating environment.
5. Additional functions.
8. Software.
9. Tests.
10.Additional requirements.
1
1. Introductory remarks – range of application.
3. Operating environment.
• Network data
The relays will be installed in transmission network of PPC.
Rated voltage : 400, 150, 30 KV
System neutral : earthed
Nominal frequency : 50 Ηz (in emergency conditions frequency could be between
47.5 Hz και 51 Hz)
The secondary nominal current of CTs is 1A or 5A.
• Power supply
In PPC substation for the supply of the control equipment is available a battery
system providing DC voltage of a level 220V DC / 110V DC.
2
• Ambient conditions
The relays will be designed for indoor operation over a temperature range from
-5° to +55ºC and a humidity range from 10% to 90%.
5. Additional functions.
Signaling contacts
- Continuous current carrying capacity : 5 Α
- Making capacity : 10 Α
- Breaking capacity : 0.1 Α στα 220V DC
The relay must be equipped with the following ports and interfaces:
- User interface (keyboard & displays) on the front plate of the relay ensuring dialog
with the relay permitting setting, operation, metering and fault reporting.
- The relay shall be capable for communicating via an Ethernet port via IEC-61850
protocol.
- Serial interface (standard type serial port) RS232 for connection of a personal
computer and for data transfer to the control centre via modem.
The communication protocols will be compatible with the standard public
communication networks according to the recommendation of the international
regulations.
Together with the relay, the supplier must provide twenty (20) cables at least for the
communication of the relay with PC.
4
8. Software.
Software for the operation of the offered devices will be provided on the basis of a
royalty free, non-exclusive, with irrevocable license to use for the operation of the
relays. This term is applicable for the software covering all issues: Settings, setting
transmission, fault reporting, communication relay-PC and communication relay –
remote station.
The software shall be menu-driven, friendly to the user and easy to be followed even
by an inexperienced operator (three (3) copies at least).
9. Tests.
5
TECHNICAL DESCRIPTION 31/B
ATTACHMENT “A”
7
PUBLIC POWER CORPORATION S.A.
DECEMBER 2008
ATHENS
1
1. Introductory remarks - range of application.
This technical description concerns digital distance protection relays to be installed in PPC
transmission power system of a nominal vo1tage of 150 KV. It establishes requirements for
the performance, design, testing and operation οf the relevant equipment and related
software. The relays are primarily intended to provide fast, selective and reliable clearance of
faults in high voltage network.
Ιn addition to the fundamental distance protection function supplementary οr optional
functions are required covering the needs for operation in a modem working environment.
The items to be offered (hardware/software) will conform to the international standards and
codes of practice, mainly:
- Currently valid IEC standards applicable for such devices covering performance, insulation
and disturbance requirements, indicately :
Withstand voltage : (IEC 255-5)
3. Operating environment.
• Network data
The relays will be installed in the 150KV transmission network of PPC.
The main data of this network are shown below.
Rated voltage : 150KV rms
System neutral :solidly earthed
Nominal frequency : 50 Ηz (in emergency conditions frequency could be
between 47.5 Ηz to 51 Ηz)
Short-circuit level : 6500 MVΑ (nominal)
2
• VT, CT characteristics
The secondary nominal voltage of the inductive or capacitive potential transformers is
typically 120 / 3 or 100 / 3 and their class 3P/0.5.
Nominal secondary current of the CTs is 1A and their class 5P20 and burden 60VA.
• Power supply
In 150KV PPC substation for the supply of the control/recording equipment is available a
battery system providing DC voltage of a level of 110V or 220V (+10%, -10%).
• Electromagnetic interference
The relays will be installed in high voltage installation and it is the manufacturer’s
responsibility to provide all necessary measures (grounding, shielding) to assure reliable
operation.
• Ambient conditions
The relays will be designed for indoor operation over a temperature range from –5 oC to 55oC
and humidity range from 5% to 90%.
Distance relay will be numerical type and will ensure clearance of all types of phase or
ground faults in the protected zone and direction providing selective three phase tripping.
Fault detection will include impedance excitation and eventually underimpedance, earth -
fault and overcurrent excitation.
The impedance characteristics of the relay will be quadrilateral (or mho only for faults
between phases) ensuring enhanced stability in case of load encroachment.
At least 3-distrance zones will be provided (two zones forward and one zone reverse)
The reach of the distance zones can be selectable within the range 80 Ohm secondary in X-
axis and 30 Ohm secondary in R-axis.
The relay will be fast with a maximum permissible operating time 30 msec for all types of
faults.
At least four groups of settings have to be stored in the relay which must be selectable by the
user during operation either locally by on-the-relay interface or remotely via external signal.
Marshalling of binary inputs, binary output indicators on the relay front panel must be
possible by means of the interface on the front or remotely.
The assignments of inputs, outputs can be easily restructured for adaptation to the on site
conditions.
The contacts assignment can be performed by selection from an existing library in the
memory of the relay and/or by establishment of equations based on the Boolean logic.
3
In addition to the basic distance protection function, a package of extra functions is requested
to meet the needs for the efficient operation of the network. Analytically :
- Switch-on-to fault feature (SOTF) : by monitoring the manual close command
over a defined period, SOTF will ensure instantaneous tripping without
autoreclosing when the circuit breaker is closed onto a fault.
- Back-up overcurrent - time protection function : it will be activated in case of
failure of voltage measurement circuit.
- Teleprotection: typically the permissive underreach scheme is used.
Optionally other schemes will be provided (direct transfer zone extension,
overreach or blocking scheme)
- Autoreclosing: fast three pole autoreclose.
- Synchrocheck: feature related to the autoreclosure function (for remote
control). It ensures circuit breaker closure only in synchronize conditions
(selectable by the user).
- Fault locator.
- Fault recording : in the event of a fault and/or excitation the fault data will be
stored in the relay for analysis. The fault data can be read remotely via
modem. Ιn the offer it must be clearly stated the memory capacity and the
number/time length of the faults which can be stored. The capacity of the
memory will permit the storage of at least four faults. It must be underlined
that the fault report will include digital events and analog waveforms.
- Metering: it enables real time measurements of all analog quantities (U,I,P,Q)
either locally or remotely via modem.
- Directional earth fault (DEF) function it is used for achievement of
discriminative clearance of high resistance earth fault.
- Self-monitoring: During operation self-monitoring tests will be performed and
in case of an internal fault or loss of dc supply a signal is issued for protection
blocking and/or warning.
- Circuit Breaker Failure Protection : by monitoring the circuit breaker status
after an issue of a trip command over a time period while the relay excitation
is yet active a circuit breaker failure is issued.
Αll functions will be included in a housing providing degree of protection ΙΡ51 according to
IEC.
The construction preferably will be of modular design with plug-in units facilitating repairs
and providing self-diagnostic (fault tracing) for each module.
The installation will be flush mounting.
Αll the appropriate specia1 accessories (special cables/ plugs interfaces, adaptors etc.) for
communication and testing have to be included in the offer.
4
Automatic short-circuit of current contacts must to be foreseen, in the case where the current
input unit is of draw out type.
The dc/dc converter accommodated in the relay housing will provide uninterrupted operation
and it must have an input voltage of 110 V DC or 220 V DC.
The analog to digital converter will digitize the input signal with a resolution of 12 bits (min
requirements) for reliable wareform operation. .
The heavy duty trip output contacts will be of heavy duty with the following ratings
(minimum requirements) : .
a. Current carrying capacity :5Α
b. Making capacity (L/R=40ms) : 1000W/VA
c. Breaking capacity : 30W/VA
d. Number of contacts :6
The switching/breaking capacity of the contacts must be mentioned in the offer. The function
of the alarm contacts will be assignable and their configuration can be done easily by the
software locally or remotely. Signal contacts will provide information for the status of the
relay in case of maloperation.
Twelve (12) digital inputs and sixteen (16) digital outputs at least are required.
The relay shall be fitted with two (2) serial ports for reasons of interfacing and specifically
with:
5
2. One serial port suitable for system interface (fiber optic) shall be available for
connection to a digital computerized substation control system. The communication
protocol shall be as per IEC 61850.
4. A number of 20 cables for the communication of the relay with PC must be included
in the offer.
5. The relay must be equipped with an integral keyboard and display for parameter
setting
7. Software.
Software for the operation (3 copies at least, included in the price of the offered devices) will
be provided on the basis of a royalty free, non-exclusive, with irrevocable license to use for
the operation of the relays. This term is applicable for the software covering all issues:
Setting transmission, calibration, fault analysis, communication relay-PC and communication
relay -remote station.
The software will be menu-driven, friendly to the user and easy to be followed even by an
inexperienced operator. The fault analysis software will be capable of displaying on a VGA
all analog waveforms and binary signals.
8. Tests
The package to be offered will be in compliance with the standards mentioned in §2 above.
Tests certificates, issued by official laboratories, will be provided covering type and routine
tests.
Existing certificates and test reports will be accepted providing that they will be found
satisfactory by the purchaser. Conformity to the relevant EU directives and guidelines is also
required.
9. Additional requirements
6
Also references and documentation will be provided which demonstrate that the offered
hardware/software packages have been used in commercial scale and that the offered material
is part of the manufacturer’s standard production.
In the references a list of users of the offered products, in the area of the power transmission
networks, will be provided. The purchaser can request certifications of users concerning the
good performance of the products.
After the assignment of the contract the contractor has to provide full technical
documentation in Greek or English language covering all relevant issues on
the/operation/testing/troubleshooting ensuring an unobstacle operation by the PPC personnel
without any intervention of the manufacturer/contractor.
The contractor will undertake the cost of training in the premises of the supplier of three
engineers covering the cost of transportation and accommodation.
All hardware/software features will be according to this specification. Any deviation has to
be clearly described and identified in the offer.
10. Certification
The offered devices shall be certified by conformance test performed in accordance with IEC
61850-10. The certificate must be of level A (level A means independent Lab, e.g. KEMA).
The certificate can be of level B (manufacturer’s Lab) if the manufacturer’s Lab has been
qualified by the UCA International Users Group.
In the first case the certificate (level A) must be submitted along with technical offer. In the
second case the certificate (level B), along with the UCA International Users Group
certification to the manufacturer must be submitted in the technical offer.
7
A
ATTTTA
ACCH
HMMEEN
NTT ““A
A””
8
16. Are the relays equipped with back-up
overcurrent - time protection function ? : ……………………………………………
9
28. Is the offered relay of the modular design
type? : ……………………………………………
10
39. Is the offered relay equipped with internal
synchronization clock? : ……………………………………………
..……………………………………………
11
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION AND EHV SUBSTATION SPECIFICATIONS AND
EQUIPMENT SECTION
January 2006
I. SCOPE
This hereby technical description covers PPC’s requirements regarding
functional features, technical characteristics and testing of numerical
overcurrent and overload protection relays.
II. KEYWORDS
Numerical overcurrent and overload relays, overcurrent protection relays.
III. STANDARDS
The relays shall conform to IEC standards. Relays as per ANSI/IEEE standard
can be offered, subject, however to PPC approval.
IV. USE
The relay with separate overload (overcurrent) and short-circuit protection
(overcurrent) will be used to protect 155 KV, 26.7 MVAR shunt capacitor
banks against overloading and all types of short circuits. (3-phase and phase-
to-ground faults)
V. OPERATING CONDITIONS
1. Installation : Indoors, inside a relay kiosk.
1
VI. PPC’s 150 KV ELECTRIC SYSTEM CHARACTERISTICS
3. Number of phases : 3
4. Nominal Frequency : 50 Hz
1. Inverse time overcurrent protection for all phase and ground faults.
The short-circuit protection shall be set above 3×IN, where IN≈100 A
IN = Shunt Capacitor bank current.
The time relay shall be set at 5 to 7 cycles. Given the fact that the capacitors shall
be switched via control switching relays, the expected inrush current shall be of
the order of (35-45)×IN where IN≈100 A.
3. The characteristic curves of the inverse time for overcurrent and overload
protection shall be in accordance with IEC 60255-3, which are inverse time, very
inverse time, extremely inverse time and long inverse time.
Since the capacitor bank is solidly grounded, the total current (phases and ground)
will be derived from the phase currents by means of the Holmgreen circuit indicated
below in Fig. No 1.
2
BR
Fig. No 1
2. Rated frequency : 50 Hz
4. Setting ranges
a. Definite time overload protection (phase and earth, I> and IE>)
Overcurrent element range (I)
(for phase and earth) : (0.5 to 4)×In in steps
of 0.1A
Delay time (for phase and earth) : 0.01 to 20 seconds in steps
of 0.1 sec.
b. Inverse time overcurrent protection (phase and earth, I>> and IE>>)
1. Phases setting range : (0.5 to 4)×In in steps of 0.1A
2. Earth setting range : (0.5 to 4)×In in steps of 0.1A
3. Time multiplier : 0.05 – 1 sec
4. Reset ratio : >95%.
1. Type of relay: Numerical of definite and inverse time with four (4) overcurrent
stages (Two for overcurrent (I>> and IE>>) and two for overload (I> and IE>)).
2. The relay terminals shall be of the screw type and they must be suitable to be wired
with 2.5 mm2 size conductors.
3
4. The relay shall be equipped with event and fault recording capability.
6. The relay will be equipped with a port RS485 for system interfacing via
IEC 61850 protocol or IEC 60870-5-103 or Profibus-fms or Modbus/Rtu or
DNP3.0
7. Binary Outputs
The relay shall be equipped with the following programmable outputs:
XI. TESTS
A. Routine Tests
B. Type Tests
4
3. Fast Transient interference test :
4 KV, 5/50 ns, 5 KHz, burst length = 15 ms,
repetition rate 300 ms : both polarities,
duration = 1 min as per IEC 60255 – 22 – 4
and IEC 61000-4-4, class IV.
2. Technical pamphlets and brochures which will help the evaluation process.
4. Any type test certificates for the type tests specified in this hereby technical
description.
XIII. PACKING
The relays shall be packed inside robust paper boxes, proper for this type of
equipment.
5
“ATTACHMENT A”
Data which must be provided by all bidders. Failure to comply will result in rejection of the
offer.
6
14. Binary Outputs
IIa/AG/ia/Technical 2/8.10.2002
ΙΙδ/pm/AG/March 2005
IΙδ/σ.π/Α.G/April 2005
ΙΙδ/Revision No. 5/pm/AG/January2006
7
PPC S.A.
T/NPRD / Substation and ehv substation specifications and equipment Section
January 2006
I. SCOPE
III. STANDARDS
The relays shall conform to IEC standards. Relays as per ANSI/IEEE can be offered,
subject, however to PPC approval.
IV. USE
The relay will be used to detect capacitor element failure or failures anywhere in the
two branches of each phase of a 150KV, 26.7MVAR internally fused shunt capacitor
banks and to provide either alarm or tripping depending on the number of failed
elements.
-1-
V. OPERATING CONDITIONS
2. Limits of ambient
temperature during service : -10oC to +45oC
Unbalance Protection
The relay is going to be used in conjunction with a CT of ratio 1/1A which is connected
midpoint between the two branches of each phase (H-bridge connection) of a 155KV,
26.7MVAR internally fused capacitor banks (16 units of 556.2KVAR at each phase, at
11,186KV).
The relay shall provide an alarm signal after the failure of any two (2) capacitor
elements (about 0,23A) and a trip signal after the failure of four (4) capacitor elements
(about 0,5A)
1. Type: Numerical, single-phase, overcurrent of definite time with two stages (low and
high)
-2-
2. The relay must be of reduced sensitivity for frequencies other than the fundamental
so as to prevent undesired operations.
3. Both the output trip contacts and the output alarm contacts of the relay must be
programmable so that some can be assigned to the low stage element and some to the
high stage element. (At least one trip and one alarm to the low stage and one trip and
one alarm to the high stage).
5. The relay terminals shall be of the screw type and they must be suitable to be wired
with 2,5mm2 size conductors.
-3-
X. TESTS
A. Routine Tests
1. Power frequency voltage withstand test: 2KV rms, 50Hz, 1 minute as per IEC 60255-5.
B. Type Tests
XI. COMMUNICATIONS
2. The relay shall be equipped with a port for communicating via IEC 61850 protocol
or IEC 60870-5-103 or Profibus-fms or Modbus/Rtu or DNP3.0
2. Technical pamphlets and brochures that will help the evaluation process.
3. Outline and wiring drawings of the offered relay including mounting instructions.
4. Any type test certificates for the type test specified in this hereby technical
description.
XIII. PACKING
The relays shall be packed inside robust paper boxes proper for this type of equipment.
-4-
“ATTACHMENT A”
CURRENT UNBALANCE RELAYS TO BE USED IN CONJUNCTION WITH 155KV
SHUNT CAPACITOR BANKS
12. Continuous current rating of the output contacts for alarm : ..................................
-5-
18. Are the relay terminals of the screw type and suitable to be wired
with 2,5mm2 size conductors? : ...................................
19. Weight of the relay : ..................................
21. Is the relay equipped with a RS232 port for interfacing with a
PC? : .................................
-6-
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION AND EHV SUBSTATION SPECIFICATIONS AND
EQUIPMENT SECTION
January 2006
I. SCOPE
II. KEYWORDS
III. STANDARDS
IV. USE
The relay will be used to protect 155 KV, 26.7 MVAR internally fused shunt
capacitor banks against overvoltages.
V. OPERATING CONDITIONS
-1-
VI. ELECTRICAL CHARACTERISTICS OF PPC’s 150 KV SYSTEM
3. Number of phases :3
4. Nominal Frequency : 50 Hz
The overvoltage element of the relay shall be set at the value of 1.1xVn, where
Vn=100V, with a time delay of about 30 sec.
1. Type : Numerical
3. Rated frequency : 50 Hz
-2-
6. Inputs : The relay shall be supplied
via three (3) single phase
VT with nominal ratio of
160000/ 3 /100/ 3 V
as shown in Fig. No 1. below.
The secondaries of the three (3)
CTs will be connected in star
(wye)-grounded connection.
L1 L2 L3
VTs
3-phase
voltage
relay
Fig. No 1
2. The relay terminals shall be of the screw type and they must be suitable to be wired
with 2.5 mm size conductors.
-3-
XI. TESTS
A. Routine Tests
B. Type Tests
2. Technical pamphlets and brochures which will help the evaluation process.
4. Any type test certificates for the type tests specified in this hereby technical
description.
XIII. PACKING
The relays shall be packed inside robust paper boxes proper for this type of
equipment.
-4-
“ATTACHMENT A”
VOLTAGE RELAYS
TO BE USED IN CONJUNCTION WITH 155 KV SHUNT CAPACITORS
BANKS
-5-
15. Is the relay equip with fault
disturbance recording capability? : …………………………………
Revision/pm/AG/October 2004
Revision No.2/pm/AG/March 2005
Revision No.3/pm/AG/January 2006
-6-
PPC S.A.
T/NPRD / Substation Design and Specifications Section
March 2006
I. SCOPE
III. STANDARDS
The relays shall conform to IEC standards. Relays as per ANSI/IEEE can be offered,
subject, however to PPC approval.
IV. USE
The relay will be used to detect capacitor unit failure or failures anywhere in the two
stars (wyes) of 20KV, 4MVAR externally fused shunt capacitor banks and to provide
either alarm or tripping depending on the number of failed units (alarm for one unit
failure, tripping for two unit failures).
-1-
V. OPERATING CONDITIONS
2. Limits of ambient
temperature during service : -10oC to +45oC
Unbalance Protection
2. The relay must be of reduced sensitivity for frequencies other than the fundamental
so as to prevent undesired operations.
3. The relay shall be equipped with at least two(2) trip output contacts one associated
with the low stage (IE>) and one with the high stage (IE>>) and two output alarm
contacts one for the low stage (IE>) and one associated with the high stage (IE>>)
-2-
4. The relay shall be suitable for flush panel mounting.
5. The relay terminals shall be suitable to be wired with 2,5mm2 size conductors and
preferably be of the screw type.
7. The relay shall be capable of communicating via IEC – 60870 – 5 – 103 protocol or
IEC-61850 or Profibus-fms or Modbus/RTU or DNP3.0.
-3-
15. Thermal current withstand
a. 2xIn continuous :
b. 40xIn for one (1) second :
X. TESTS
A. Routine Tests
1. Power frequency voltage withstand test: 2KV rms, 50Hz, 1 minute as per IEC
60255-5
B. Type Tests
2. Technical pamphlets and brochures that will help the evaluation process.
3. Outline and wiring drawings of the offered relay including mounting instructions.
4. Any type test certificates for the type test specified in this hereby technical
description.
XII. PACKING
The relays shall be packed inside robust paper boxes proper for this type of equipment.
One relay per box.
-4-
“ATTACHMENT A”
CURRENT UNBALANCE RELAYS TO BE USED IN CONJUNCTION WITH 20KV
SHUNT CAPACITOR BANKS
a. In steps of : ..................................
a. In steps of : ..................................
10. Current rating of the output tripping contacts for 1 second : ..................................
13. Continuous current rating of the output contacts for alarm : ..................................
-5-
14. Switching making capacity of the output contacts for alarm at
110V D.C. : ..................................
19. Are the relay terminals of the screw type and suitable to be wired
with 2,5mm2 size conductors? : ..................................
24. Does one output trip contact and one output alarm contact
correspond to the low stage of the relay; : ..................................
25. Does one output trip contact and one output alarm contact
correspond to the high stage of the relay; : ..................................
26. Thermal current withstand capability
a. continuous : ..................................
b. For one (1) second : ..................................
Mt/AG/October 2002
Revision No.1/pm/AG/May 2004
ΙΙδ/pm/AG/June 2005
ΙΙδ/pm/AG/August 2005
ΙΙδ/pm/AG/March 2006
-6-
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION DESIGN AND SPECIFICATIONS
SECTION
March 2006
I. SCOPE
II. KEYWORDS
III. STANDARDS
The relays shall conform to IEC standards. Relays as per ANSI/IEEE standard
can be offered, subject, however to PPC approval.
IV. USE
The relay with separate overload and short-circuit protection will be used to
protect 20 KV, 3 X 4 MVAR shunt capacitor banks against overloading and all
types of short circuits.
V. OPERATING CONDITIONS
1
VI. PPC’s 20 KV ELECTRIC SYSTEM CHARACTERISTICS
3. Number of phases : 3
4. Nominal Frequency : 50 Hz
1. Inverse – time overcurrent protection for all phase and ground faults.
The short – circuit protection shall be set above 3 X IN, where IN ~ 350 A
IN = Shunt Capacitor bank current.
The time relay shall be set at 5 to 7 cycles. Given the fact that the capacitors shall
be switched via control switching relays, the expected inrush current shall be of
the order of (35-45)XIN where IN ~ 350 A.
3. The characteristic curves of the inverse time for overcurrent protection shall be in
accordance with IEC 60255 – 3, which are inverse time, very inverse time,
extremely inverse time and long inverse time.
Since the capacitor bank is solidly grounded, the total current (phases and ground)
will be derived from the phase currents by means of the Holmgreen circuit indicated
below in Fig. No 1.
2
BR
Fig. No 1
2. Rated frequency : 50 Hz
4. Setting ranges
a. Definite – time overloading protection
- phase currents IA, IB, IC (I>)
- earth (ground) current IE.(IE>)
b. Inverse time overcurrent protection (for phases + earth, I>> & IE>>)
Setting ranges
1. Phases : (0,5 to 4) x In in steps of 0.1A
2. Earth : (0,1 to 3) x In in steps of 0.1A
3. Time multiplier
(for phases + earth) : 0.05 – 1,0 sec (IEC) or
0,5-15sec (ANSI)
3
X. ADDITIONAL REQUIRED FEATURES OF THE RELAY
1. Type of relay : Numerical with definite and inverse time overcurrent with two
overcurrent stages for phase (I> and I>>) and two for earth (IE> and IE>>).
3. The relay terminals must be suitable to be wired with 2.5 mm2 size conductors and
of the screw type.
5. The relay shall be equipped with event and fault recording capability.
6. The relay shall will be preferably equipped with a port for PC connection.
7. The relay will be equipped with port for system interfacing via IEC
60870 – 5 – 103 protocol or IEC-61850 or Profibus-Fms, or Modbus/RTU or
DNP3.0.
8. Binary Outputs
The relay shall be equipped with the following outputs :
XI. TESTS
A. Routine Tests
4
B. Type Tests
2. Technical pamphlets and brochures which will help the evaluation process.
4. Any type test certificates for the type tests specified in this hereby technical
description.
XIII. PACKING
The relays shall be packed inside robust paper boxes, proper for this type of
equipment.
One relay per box.
5
“ATTACHMENT A”
Data which must be provided by all bidders. Failure to comply will result in rejection of the
offer.
6
system interfacing via IEC 60870-5-
103 protocol or IEC-61850 or
Profibus-Fms or Modbus/RTU or DNP3.0? : ………………………………...
a. continuous : ...................................................
7
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION & SWITCHING STATION
SPECIFICATIONS AND EQUIPMENT SECTION
September 2004
VOLTAGE RELAYS
SUPPLIED FROM SINGLE-PHASE VT LOCATED IN THE NEUTRAL OF
A 30KV, 50MVAR SHUNT REACTOR FOR THE DETECTION OF
OVERVOLTAGE CONDITIONS
I. SCOPE
II. KEYWORDS
III. STANDARDS
IV. USE
The voltage relays are used for the detection of overvoltage conditions in the
neutral of a 30KV, 50MVAR shunt reactors and thus protecting the shunt
reactors against earth faults.
The single phase voltage transformer which feeds the voltage relay is of
30KV/ 3 /100/ 3 V ratio, and of rated burden of 200VA.
V. OPERATING CONDITIONS
1
VI. ELECTRICAL CHARACTERISTICS OF PPC’s 30 KV SYSTEM
3. Number of phases : 3
4. Nominal Frequency : 50 Hz
The relay shall be equipped with overvoltage protection function and with the
following characteristics:
1. The overvoltage element of the relay shall be set at a value little below of
the value of 100 / 3 V with the time delay being set at a value of about 0,3
– 1sec.
2. Rated frequency : 50 Hz
2
3. Setting range : 50 – 130 V in steps of I V
XI. TESTS
A. Routine Tests
3
B. Type Tests
2. Technical pamphlets and brochures which will help the evaluation process.
4. If the offered type of voltage relay is equipped with more than one (1) inputs
from VTs, then a drawing must de submitted in which the relay wiring must
be indicated for the supply of the relay from one single-phase VT.
5. Any type test certificates for the type tests specified in this hereby technical
description. Acceptance or not lies on PPC’s judgment.
XIII. PACKING
The relays shall be packed inside robust paper boxes proper for this type of
equipment.
4
“ATTACHMENT A”
VOLTAGE RELAYS
SUPPLIED FROM SINGLE PHASE VT LOCATED IN THE NEUTRAL OF
A 30KV, 50MVAR SHUNT REACTOR
FOR DETECTION OF OVERVOLTAGE CONDITIONS
5
14. Are the relay terminals of the screw type
and suitable to be wired with 2.5 mm2
size conductors ? : …………………………………..
IIδ/pm/AG/17.9.2004
6
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION AND SWITCHING STATION
SPECIFICATIONS AND EQUIPMENT SECTION
November 2003
I. SCOPE
II. KEYWORDS
III. STANDARDS
IV. USE
V. OPERATING CONDITIONS
1
VI. PPC’s ELECTRIC SYSTEM CHARACTERISTICS
1. Nominal Voltage (phase to phase) : 400/150/30 KV
3. Number of phases : 3
4. Nominal Frequency : 50 Hz
Overcurrent protection phase + earth of definite time with two (2) stages of
overcurrent.
Since the CTs which are used for the protection of the autotransformer windings
(400, 150 & 30KV) are connected star(wye)-grounded, the earth fault current,
beyond that of the phases, could be measured by means of the Holmgreen circuit,
indicated below in Fig. No 1.
BR relay
Fig. No 1
3. Rated frequency : 50 Hz
2
4. Rated auxiliary supply voltage : 220 V DC
a. Definite – time
2. The relay terminals shall be preferably of the screw type and they must be
suitable to be wired with 2.5 mm2 size conductors.
3
XI. TESTS
A. Routine Tests
B. Type Tests
XII. COMMUNICATIONS
The function of the Fault recording shall be used for recording of phase and
ground (earth) currents during fault conditions.
The recording will be initiated either by tripping signal or by pick up.
Total recording time : 3sec at least.
4
XIV. DATA TO BE SUBMITTED BY BIDDERS
2. Technical pamphlets and brochures which will help the evaluation process.
4. Any type test certificates for the type tests specified in this hereby technical
description.
XV. PACKING
The relays shall be delivered packed properly inside robust paper boxes,
proper for this type of equipment.
One relay per box.
5
“ATTACHMENT A”
Data which must be provided by all bidders. Failure to comply will result in rejection of the
offer.
6
other protocols? : ………………………………...
7
PPC S.A.
T/NPRD / Substation & Switching station Specifications
and Equipment Section
November 2003
I. SCOPE
III. STANDARDS
The relays shall conform to IEC standards. Relays as per ANSI/IEEE can be offered,
subject, however to PPC approval.
IV. USE
The relays will be used to protect against short circuit currents which can be developed
between autotransformer mass(tank) and earth.
The protected autotransformer is of ratio of 400/150/30KV, of apparent power of
280MVA and of connection of star-grounded/star-grounded/delta .
The relays are to be used in conjunction with CTs of ratio 200/5A.
-1-
V. OPERATING CONDITIONS
2. Limits of ambient
temperature during service : -5oC to +45oC
Earth overcurrent Protection with definite time with two levels of overcurrent
(I Ε > and I Ε >>).
-2-
delay time : 0-20 sec
4. Rated auxiliary supply voltage : 220V D.C. ± 10%
5. Number of output contacts for : Two (2) CO or NO for stage IE >
tripping and for stage I E >>.
6. Continuous current rating of the
output tripping contacts : 5A
7. Current rating of the output
tripping contacts for 0,5sec. : 30A
8. Switching breaking capacity of
the output tripping contacts at
220V D.C. : 0,15A
9. Number of output contacts for
alarm : 2 NO associated one with I Ε > and
one with I Ε >>
10. Continuous current rating of the
output contacts for alarm : 1A
11. Switching breaking capacity of
the output contacts for alarm at
220V DC : 0,15A
1. Type : Digital
2. Single-phase. A three phase relay can be accepted providing that it can be wired so
as to be excited by a phase to earth current.
3. The relay must be of reduced sensitivity for frequencies other than the fundamental
so as to prevent undesired operations.
5. The relay terminals shall be suitable to be wired with 2,5mm2 size conductors.
X. COMMUNICATIONS
a. The relay shall be capable for communicating with an automated substation control
and protection system, via IEC protocol 60870-5-103, and also preferably via one
of the following protocols : Profibus-fms, Lon, Mobus/RTU or DNP.3 .
b. The relay shall be equipped with a port for PC connection.
-3-
c. The relay shall be capable of being connected either with fiber optic cable or
special communication cable for the purposes of communication with an automated
substation control and protection system.
The function of the fault recording shall be used for recording of phase and ground
(earth) currents during fault conditions.
The recording will be initiated either by tripping signal or by pick up.
Total recording time : 3sec at least
XII. TESTS
A. Routine Tests
1. Power frequency voltage withstand test: 2KV rms, 50Hz, 1 minute as per IEC
60255-5
B. Type Tests
2. Technical pamphlets and brochures that will help the evaluation process.
-4-
3. Outline and wiring drawings of the offered relay including mounting instructions.
5. Any type test certificates for the type test specified in this hereby technical
description. Acceptance or not of these certificates lies on PPC’s judgment.
XII. PACKING
The relays shall be delivered packed properly inside robust paper boxes, proper for this
type of equipment.
One relay per box.
-5-
“ATTACHMENT A”
OVERCURRENT RELAYS TO BE USED FOR AUTOTRANSFORMER MASS
PROTECTION
4. Setting range
A. stage 1, I Ε > : ..................................
In steps of : ..................................
Delay time : ..................................
B. stage 2, I Ε >> : ..................................
In steps of : ..................................
Delay time : ..................................
5. Rated Input : ..................................
9. Current rating of the output tripping contacts for 0,5 second : ..................................
12. Continuous current rating of the output contacts for alarm : ..................................
13. Switching breaking capacity of the output contacts for alarm at : ..................................
220V D.C.
14. Rated frequency : ..................................
-6-
17. Is the relay suitable for surface panel mounting? : ..................................
18. Are the relay terminals suitable to be wired with 2,5mm2 size
conductors? : ..................................
-7-
PUBLIC POWER CORPORATION S.A.
NPRD/SUBSTATION-SWITCHING STATION
SPECIFICATIONS & EQUIPMENT SECTION
January 2006
Ι. SCOPE
This hereby technical description covers PPC’s requirements regarding
technical and operating features and also testing of phase and earth overcurrent
relays of definite and inverse time with auto-reclosing function. The relays
should be equipped with phase and earth overcurrent protection and auto-
reclosing function suitable for one rapid auto-reclosing and at least two
sequential adjustable time delayed reclosings.
ΙV. USE
The relays will be used for the protection of medium voltage (20kV) overhead
distribution lines against phase and ground faults in conjunction with 3-pole
multiple-shot auto-reclosing.
1. Type of relay
Numerical
2. Construction-Installation
The relay shall be in a case and must be suitable for flush panel mounting.
4. Operating Conditions
a. Installation : Inside the control building of the substation
b. Ambient temperature : Minimum (-5οC)
Maximum (+40οC)
c. Altitude : Up to 1000m above sea level
d. Humidity : 5% - 85%
C. Auto-reclosing
e. The relay shall be equipped with a timer of range 0-10sec, for blocking the
auto-reclosing function wherever the circuit breaker is manually closed.
f. The relay shall be equipped with operation counter for counting the rapid
and delayed reclosings.
The relay must have at least five (5) additional binary inputs at 110V D.C. for
inputs like the following:
a. Input from circuit breaker malfunction, for example loss of SF6 or
uncharged spring,
b. Input from control switch contact used for opening of the breaker,
c. Input from control switch contact used for closing the breaker,
d. Input for blocking of reclosing function from a remote place,
e. Input for blocking the phase and earth (ground) overcurrent definite time
instantaneous elements (I>> and ΙΕ>>) from remote place. In other words, the
disabling of the definite time overcurrent stage (I>> or IE>>), for all the time
that the auto-reclosing function is in operation.
The relay shall be equipped with the following number of control (command)
contacts and with the following technical characteristics.
a. Number of contacts with regard the phase and earth stages of the definite
time and inverse time overcurrent functions shall be as follows:
One (1) NO contact and
One (1) NO contact for making through the autoreclosing function
The relay shall be equipped with the following number of alarm contacts:
a. Number of contacts with regard the definite time and inverse time
overcurrent function shall be as follows:
The following dimensions are valid only when the inquiry concerns
individual relays. The dimensions are not of importance when the inquiry
concerns metalclad switchgear panels.
• For width smaller than 12cm, the maximum height shall be 40cm.
• For width between 12cm and 19cm, the maximum height shall be
25cm.
• The width and depth of the relay shall not exceed in any case 19cm and
30cm respectively.
• All the terminals of the relay must be located at its rear side.
IX. TESTS
Α. Routine Tests (as per IEC 60255-5)
1. Power frequency voltage test : 2 kV rms, 50 Hz
Β. Type Tests
1. Impulse voltage test : 5 kV crest, 1.2/50µs,0.5J
(as per IEC 60255-5) 3 positive and 3 negative
pulses in 5 sec intervals
c. Any type test certificates for the type test specified in this hereby technical
description. Acceptance or not of these certificates lies on PPC’s judgment.
XIII. PACKING
The relays shall be delivered packed properly inside robust paper boxes,
proper for this type of equipment.
One relay per box.
Information by the Bidders. Failure to comply will result in rejection of the offer.
3. Is the auto-reclosing function suitable for one rapid reclosing and : ..................................
at least two sequential delayed reclosings?
6. Altitude : ..................................
7. Humidity : ..................................
9. Are the terminals of the relay suitable to be wired with 2,5 mm2
size copper conductors? : ..................................
C. Auto-reclosing
a. Setting range of the dead time : ..................................
during the first rapid reclosing
b. Setting range of the dead time
during the first delayed reclosing : ..................................
c. Setting range of the dead time
during the second delayed reclosing : ..................................
d. Setting range of the reclaim (reset) time of
the relay after a successful reclosing cycle : ..................................
25. Is the relay equipped with a key pad and RS232 port for setting
and parameterization purposes? : …...............................
27. Does the offered relay comply in full with the requirements of
paragraphs VI-12 of this technical description? : …...............................
…...............................
…...............................
…...............................
…...............................
28. Is the required software for the relay settings and communication
provided? : …...............................
…...............................
…...............................
…...............................
…...............................
29. Αre five (5) cables for the communication of the relay with PC
provided? : …...............................
…...............................
…...............................
…...............................
…...............................
js/AG/October 2003
Rev. No.1/ pm/ AG/ March 2005
Rev. No.2/ pm/ AG/ July 2005
Rev. No.3/ bk/ AG/ August 2005
Rev. No.4/ sp/ AG/ September 2005
Rev. No.5/ sp/ AG/ October 2005
Rev. No.6/ pm/ AG/ November 2005
Rev. No.7/ pm/ AG/ January 2006
January 2006
Ι. SCOPE
ΙV. USE
The relays will be used for the back-up protection of medium voltage (20kV)
overhead distribution lines and the 20KV bus bars of the substation against
phase and earth (ground) faults. The relays can also be used as main protection
for underground distribution feeders (20kV) against phase and earth faults.
1 TD-51
222
V. STANDARDS
The phase and earth overcurrent protection relays of definite and inverse time,
shall comply to the IEC 60255-3, 60255-5 and 60255-22 Standards. Relays as
per ANSI/IEEE can be offered, subject, however to PPC’s approval.
1. Type of relay
Numerical
2. Construction-Installation
The relay shall be in a case and must be suitable for flush panel mounting.
4. Operating Conditions
a. Installation : Inside the control building of the substation
b. Ambient temperature : Minimum (-5οC)
Maximum (+40οC)
c. Altitude : Up to 1000m above sea level
d. Humidity : 5% - 85%
a. Definite time Phase and earth overcurrent protection with two (2) stages for
phase and earth Ι>, Ι>> and ΙΕ>, ΙΕ >>.
b. Inverse time Phase and earth overcurrent protection with characteristic curves
as per IEC 60255-3, which are inverse time, very inverse time, extremely
inverse time and long inverse time with one overcurrent stage for phase (Ip)
and one for earth (IpΕ).
2 TD-51
333
The relay shall be equipped with the following number of heavy duty contacts
which shall be used for command purposes, with the following technical
characteristics.
a. The number of contacts with regard the phase and earth stages of the definite
time and inverse time overcurrent functions shall be as follows
One (1) NO contact
The relay shall be equipped with the following number of alarm contacts:
a. The number of contacts with regard the definite time and inverse time
overcurrent function shall be as follows
3 TD-51
444
VIII. TESTS
Α. Routine Tests (κατά IEC 60255-5)
1. Power frequency voltage test : 2 kV rms, 50 Hz
Β. Type Tests
1. Impulse voltage test : 5 kV crest, 1.2/50µs,0.5J
(as per IEC 60255-5) 3 positive and 3 negative
pulses in 5 sec intervals
IΧ. COMMUNICATION
a. The relay shall be capable for communicating via a RS485 port with a
substation automation system , via IEC protocol 61850, and or via one of the
following protocols : Profibus-fms,, Modbus/RTU or DNP 3.0 or IEC-60870
-5-103.
b. The relay shall be equipped with an RS232 port for PC interfacing.
Χ. FAULT RECORDING
4 TD-51
555
The function of the fault recording, event and oscillographic, shall be used for
recording of phase and ground (earth) currents during fault conditions.
- The recording will be initiated either by tripping signal or by pick up.
- Total recording time: 3sec at least
- Resolution for events: 1ms
The following dimensions are valid only when the inquiry concerns individual
relays. The dimensions are not of importance when the inquiry concerns
metalclad switchgear panels.
The dimensions of the relay shall be as follows:
• For width smaller than 12cm, the maximum height shall be 40cm
• For width between 12cm and 20cm, the maximum height shall be 30cm
• The width and depth of the relay shall not exceed in any case 20cm and
30cm respectively
• All the terminals of the relay must be located at its rear side
c. Any type test certificates for the type test specified in this hereby technical
description. Acceptance or not of these certificates lies on PPC’s judgment.
XIII. PACKING
The relays shall be delivered packed properly inside robust paper boxes, proper
for this type of equipment.
One relay per box.
5 TD-51
666
ATTACHMENT ‘Α’
Information by the Bidders. Failure to fill or partial filling of the attachment shall
constitute sufficient reason for rejection of the offer.
8. Are the terminals of the relay suitable to be wired with 2,5 mm2
size copper conductors? : ..................................
6 TD-51
777
7 TD-51
PUBLIC POWER CORPORATION S.A.
T/NPRD/SUBSTATION & SWITCHING STATION
SPECIFICATIONS AND EQUIPMENT SECTION
February 2004
VOLTAGE RELAYS
SUPPLIED FROM VTs CONNECTED IN “BROKEN (OPEN) DELTA”
FOR PROTECTION OF 30KV, 50 MVAR SHUNT REACTORS AGAINST
EARTH FAULTS
I. SCOPE
II. KEYWORDS
III. STANDARDS
IV. USE
The voltage relays are used for the detection of earth faults for 30KV,
50MVAR shunt reactors of star (wye) connection and earthed not solidly but
via VT. The input of the voltage relay will be connected to the opening of the
΄΄ broken delta΄΄ which is crated by connecting the secondaries of the three
VTs in ΄΄ broken delta΄΄ .With this way, the residual voltage is detected and as
result of it, the conditions of the earth faults.
The VTs whose secondaries are connected in open delta are of ratio of
30KV/ 3 /100/3 V and their primaries are connected in star (wye) earthed
connection.
V. OPERATING CONDITIONS
1
VI. ELECTRICAL CHARACTERISTICS OF PPC’s 30 KV SYSTEM
3. Number of phases : 3
4. Nominal Frequency : 50 Hz
The relay shall be equipped with overvoltage protection function and with the
following characteristics:
1. The overvoltage element of the relay shall be set at a value little below of
the value of 100 /3V with the time delay being set at a value of about 0,3 –
1sec.
2. Rated frequency : 50 Hz
2
4. Rated auxiliary supply voltage : 220V DC
3
XI. TESTS
A. Routine Tests
B. Type Tests
2. Technical pamphlets and brochures which will help the evaluation process.
4. If the offered type of voltage relay is equipped with more than one (1) inputs
from VTs, then a drawing must de submitted in which the relay wiring must
be indicated for the detection of the residual voltage
5. Any type test certificates for the type tests specified in this hereby technical
description. Acceptance or not lies on PPC’s judgment.
XIII. PACKING
The relays shall be packed inside robust paper boxes proper for this type of
equipment.
4
“ATTACHMENT A”
VOLTAGE RELAYS
SUPPLIED FROM VTS CONNECTED IN BROKEN DELTA
FOR PROTECTION OF 30 KV, 50MVAR STUNT REACTORS AGAINST
EARTH FAULTS
5
14. Are the relay terminals of the screw type
and suitable to be wired with 2.5 mm2
size conductors ? : …………………………………..
IIδ/pm/AG/5.3.2004
6
PUBLIC POWER CORPORATION
TNPRD/SUBSTATION AND EHV SUBSTATION
SPECIFICATIONS & EQUIPMENT SECTION
December 2008
SPECIFICATION SS-55 / 8
NUMERICAL
BUSBAR DIFFERENTIAL PROTECTION SYSTEM
I. SCOPE
This Specification covers the requirements concerning the general and
operating characteristics of a numerical busbar differential protection
system for installation in a busbar system consisting of one, two, or three
operating busbars, with or without bus coupler and bus sectionalizing
isolators or circuit breakers and as shown specifically on the single line
diagram for each substation (attached each time to the inquiry).
II. KEYWORDS
Protection, busbar protection, busbar differential protection.
III. USE
The busbar differential protection system shall be used to detect all kinds
of faults between phases and between phases and ground for 400kV or
150kV busbars.
I V. OPERATING CONDITIONS
2. Tripping time.
Tripping time from occurrence of fault to energizing of circuit
breaker trip coil shall be ≤15msec for all kind of internal faults.
3. Stability - Selectivity.
The busbar differential protection system must be extreme stable
against external faults even in case of saturated CTs.
The protection system shall not respond at all to faults outside the
protected zone and shall only disconnect those busbars that are
affected by the fault.
ss-055/8a
-3-
4. Sensitivity.
High sensitivity for internal faults, adjustable and closely adapted to
the existing exploitation conditions. The sensitivity must be
basically unaffected by the number of feeders included in the
protective scheme.
6. Reliability.
The protection system must provide maximum security against
false tripping and decide positively whether the fault is within or
outside the protected zone.
7. Operational criteria.
At least two independent criteria of different nature and principle,
both simultaneously present, must be fulfilled in order to achieve
tripping.
8. Flexibility in operation.
Execution of all necessary switching operations (transfer of a
feeder from one bus to another, switching “off” and “on” of the bus
coupler etc) must be possible without restrictions due to the
protection system which shall remain in operation. Protection
should adjust itself automatically to changing exploitation
conditions without the least interruption.
ss-055/8a
-4-
This capability should overcome the blind spot between the current
transformers and the circuit breaker, which arises when the current
transformers are positioned on one side only of the circuit breaker.
14. Interference.
The busbar differential protection system shall be immune against
any external interference, coming either from the D.C. supply or
from the measuring circuits or any other cause.
ss-055/8a
-5-
18. Interfacing
The busbar differential protection system shall be fitted with two
serial ports, one for connection to a PC and another for interfacing
with HMI center of a digital computerized substation control system.
The communication protocol should be in accordance with
IEC – 61850 and relevant test certificates of UCA level A or level B
must be submitted.
ss-055/8a
-6-
X. STANDARDS
All testing of the busbar differential protection system shall conform to IEC
standards unless, herein, otherwise indicated.
XI. TESTS
A. Type tests.
1. Insulation tests as per IEC 255-5.
a. High voltage test (dielectric) 2kV rms, 50Hz for 1 min.
between all terminals and case earth.
b. High voltage impulse test.
Three (3) positive and three (3) negative impulses of
5kV peak, 1.2 / 50µsec, 0.5J between all terminals
and all terminals and case earth.
B. Routine Tests.
Insulation test (dielectric).
2kV rms, 50Hz for 1 minute between all terminals and case earth.
NOTE : Bidders are required to submit, if available, any official
test reports for all of the above tests along with their
technical offer.
ss-055/8a
-7-
2. Spare parts.
The Manufacturer shall submit a complete list of recommended
spare parts, with unit prices, that - according to his opinion - should
be purchased for a period of five years operation. PPC S.A
maintains the right to purchase or not these spare parts.
3. Drawings - Pamphlets.
Bidders are requested to submit attached to their offers, outline
drawings, over-all dimensions of the complete equipment for
erection purposes as well as any information, sketches and data
necessary for the complete description of the busbar differential
protection system offered by them.
2. Maintenance Instructions.
Maintenance Instructions for the busbar differential protection
system.
ss-055/8a
-8-
“ATTACHMENT A”
NUMERICAL
BUSBAR DIFFERENTIAL PROTECTION SYSTEM
1. Type :………...…………………………
2. Manufacturer :………...…………………………
ss-055/8a
-9-
ss-055/8a
-10-
ss-055/8a
PUBLIC POWER CORPORAΤIΟΝ S.A.
TRANSMISSION NEW PROJECTS DEPT.
July 2008
SPECIFICATION SS - 68/3
Ι. SCOPE
This hereby specification covers the requirements concerning the technical and operational
characteristics and also testing requirements for digital differential relays used for the protection of
3-phase, 280ΜVΑ autotransformers with delta tertiary and of voltage ratio of 400/150/30KV and of
wye - wye - delta connection.
Digital autotransformer differential relays, digital differential relays for three - winding transformers.
III. USE
The digital differential relays are to be used for the protection of 3 - phase 280MVA, 400/150/30KV
autotransformers of wye - wye - delta (tertiary) connection.
IV. STANDARDS
The relays shall conform to the latest IEC standards. Relays based on ANSI / ΙΕΕΕ or DIN / VDE
standards can be offered, subject however, to the Purchaser's approval.
V. OPERATlNG CONDITIONS
1. Installation : Indoors
2. Temperature range : -5°C to 55° C
3. Relative Humidity : 5% to 85%
1
VI. CHARACTERISTICS OF ΤΗΕ ELECTRICAL SYSTEM
3. Rated frequency : 50 Ηz
The digital differential relays will be used in conjunction with current transformers which have the
following characteristics.
- 400 KV side : Ratio = 400/ 1Α, Burden = 60VA, Accuracy class = 5Ρ20
- 150 KV side : Ratio = 1000/ 1Α, Burden = 30VA, Accuracy class = 5Ρ20
2
2. Operating Characteristic : Dual slope percentage operating
characteristic which shall prevent operation
unless the differential current is greater than a
certain percentage of the through fault
current.
This percentage shall be adjustable either
continuously or by steps.
5. Output Contacts
a. Trip contacts
- Number : at least two (2)
3
- Continuous current rating : 5 Α.
- Switching making capacity : 1000 W.
- Switching breaking capacity : 30W.
- Current rating for 0.5 sec : 30A.
b. Alarm contacts :
- Number of alarm contacts : at least four (4)
selectable contacts, plus two ΝΟ
contacts all free of voltage.
4
X. DIGITΑL DIFFERENTIAL RELAY REQUIRED ADDITIONAL FEATURES
4. External Wiring of the relay : The relay shall be equipped with screw type
terminals suitable for 2.5 mm2 conductors.
ΧI. COMMUNICATIONS
The relay shall be fitted with two (2) serial ports for reasons of interfacing and specifically with :
2. One serial port suitable for system interface (fiber optic) shall be available for connection to a
digital computerized substation control and protection system. The communication protocol
shall be as per IEC-61850 or IEC 60870 - 5-103, or Profibus-fms, or Modbus/RTU or DNP 3.0
3. One serial port suitable for connection to a digital computerized substation control and
protection system via the same protocol used by the substation control and protection system.
5
XII. SOFTWARE
Software, preferably WINOOWS based, for the parameter setting analysis of fault data and records
and commissioning shall be provided on a basis of a royalty free, non exclusive with irrevocable
License to use by PPC S.A.
The software shall be user friendly and capable of displaying on VDU (screen) all analog wave
forms and digital signals. The software shall be menu - driven.
XIII. TESTS
2. Type tests.
a. Impulse Voltage test as
Per IEC-60255 - 5. : 5 KV peak, 1.2/50 µs, 0.5j
ΝΟΤΕ: Ιn case of lack of IEC testing standards, the only other standards that could be considered are
VDE and ANSI/IEEE, subject, however to the purchaser's approval.
6
XIV. INFORMATION WHICH MUST BE PROVIDED BV ΑLL BIDDERS
1. All necessary technical pamphlets and technical information so that the technical evaluation of
the offered differential relay can be carried out.
2. Outline drawings with over-all dimensions and wiring diagrams of the offered differential relays.
3. Any test certificates for all specified type tests in this hereby specification may be submitted along
with the technical offer.
Acceptance or not of the submitted test certificates will be subject to the purchaser's approval.
4. Α reference list shall be submitted and in which the following shall be included :
- Country and buyer
- Type of the relay
- Number of units sold
- Year of sale.
5. All bidders are required to complete attachment 'Ά". Failure to comply with this request or
submission of attachment 'Ά" incomplete shall constitute sufficient reason for rejection of the
offer.
1. Complete functional and wiring drawings for approval before shipment of the relays.
2. Complete outline dimensional drawings for approval before shipment of the relays.
4. Complete instructions for the operation and application of the related software.
XVI. PACKING
Each relay with all of its units (if any) shall be packaged separately inside a robust box properly
labelled.
7
ATTACHMENT "Α"
4. Digital Inputs
a. Rated Voltage : ………………………
b. Rated Voltage tolerance : ………………………
5. Trip contacts
a. Number of trip contacts : ………………………
b. Continuous current rating : ………………………
c. Switching making capacity : ………………………
d. Switching breaking capacity : ………………………
e. Current rating for 0.5 sec : ………………………
f. Rated Voltage : ………………………220V DC
6. Alarm contacts
a. Number of alarm contacts : ………………………
b. Are they selectable? : ………………………
c. Rated Voltage : ………………………220V DC
: ………………………
8
: ………………………
13. Is restrain provided against external faults with
current transformer saturation? : ………………………
: ………………………
: ………………………
9
substation control system? : ………………………
: ………………………
Α. G./me/20.3.2002
A.G./mm/4.7.2003
PK/pm/16.7.2008
10
PUBLIC POWER CORPORATION S.A January 2006
ATHENS - GREECE
I. SCOPE
This specification covers the requirements with regard the technical characteristics,
design characteristics and testing of a single phase earth fault numerical relay for the
detection of high impedance earth faults and of a suitable current transformer which
shall be used in connection with the above relay.
II. KEYWORDS
Numerical single-phase relay for the detection of earth fault, earth
fault relay, overcurrent relay, current transformers, instrument transformers.
III. USE
The relay will be used for the detection of small earth fault currents, which by
design are not being detected by the overcurrent protection relays of the MV
distribution lines. The indoor type CT shall be connected to the earthing terminal of the
neutral earthing resistor of the power transformer.
IV. STANDARDS
The numerical relays shall be in accordance with the following IEC standards:
-IEC – 60255-5
-IEC – 60255-22
-IEC – 61000-4
Prospective bidders are required to subunit separate technical and economic offers for
the two equipment of this hereby speciations. Furthermore they can submit offers only
for one of the two equipment or both, but separately, if the desire so.
1. The relay shall be of reduced sensitivity with regard to 3rd harmonics currents.
3. The relay shall be equipped with an RS485 port for communication purposes via
IEC-61850 protocol or IEC – 60870 –5-103 or Profibus-fms or Moddbus/Rtu or
DNP 3.0.
4. The relay terminals shall be of the screw type and must be suitable to be wired with
control cable of cross section of 2.5mm ².
1. Rated Voltage : 12 KV
2. Rated Frequency : 50 Hz
3. Ratio : 25/5-5A
4. Primary rated current : 25 A
5. Number of secondary windings : Two (2). One for protection purposes and
one for metering
6. Protection winding characteristics
2. The secondary windings terminals of the CT must be suitable for connection with
control cables with cross section of 4mm2
1. Routine Tests
a. Power frequency voltage withstand test : 2KV,
50Hz for one (1) minute in accordance
with IEC-60255-5 standard
2. Type Tests
a. Impulse voltage withstand: 5KV peak value
In accordance with IEC – 600255-5 standard
1. Routine Tests
a. Verification of terminal markings
b. Power-frequency withstand test on primary
winding: 28KV, 50Hz, 1 minute
c. Power-frequency withstand test on the secondary
winding: 3KV, 50Hz, 1 minute
d. Partial discharge measurement (≤20pC at 14.4KV)
e. Determination of errors
2. Type Tests
a. Temperature rise test
b. Lightning impulse test for the primary
winding: 75KV peak value of shape 1.2/50µs
c. Short-time current test
d. Power frequency voltage wet
test: 28KV, 50Hz for 1 minute
The relays and the CT’s shall be delivered packaged separately inside a robust paper
box suitable for this type of equipment.
1. Final drawings indicating dimensions, cross view and top view and
supporting strips of the CT.
2. Setting instructions, maintenance instructions for the relay and any software
needed for its setting and parameterization.
Failure to answer all following questions will result in rejection of the offer.
A. RELAY
20. Is the relay equipped with an RS232 port for interfacing with a
PC? : …..............................
21. Are the relay terminals of the screw type and suitable to be wired
with control cables of 2.5mm² in cross section? : …..............................
…..............................
…..............................
1. Manufacturer : ..................................
..................................
2. Type : ..................................
..................................
..................................
5. Ratio : ..................................
21. Does the CT bear at its base four (4) hot-dip galvanized steel
strips for supporting purposes? : ..................................
..................................
22. Are the necessary bolts, nuts, and washers for the support
(mounting) of the CT part of the supply? : ..................................
June 2006
SPECIFICATION SS – 100/4
DIGITAL DIFFERENTIAL RELAY FOR
TRANSFORMER PROTECTION.
I. SCOPE
Τhis hereby specification covers the requirements concerning the technical and
operational characteristics and also testing requirements for digital differential relays used
for the protection of 3-phase, power transformers of 40/50 MVA, 150/15.75 – 21 KV and
of delta - wye connection.
Digital transformer differential relays, digital differential relays for two – winding
transformers.
III. USE
The digital differential relays are to be used for the protection of 3 – phase 40/50 MVA,
150/15.75 – 21 KV transformers of delta – wye connection. The zone of protection shall
include and the 20KV bus of the substation (Transformer +20Kv-bus differential
protection).
IV. STANDARDS
The relays shall conform to the latest IEC standards. Relays based on ANSI / ΙEEE or
DIN / VDE standards can be offered, subject however, to the Purchaser’s approval.
V. OPERATING CONDITIONS
1. Installation : Indoors
2. Temperature range : -5oC to 55o C
3. Relative Humidity : 5% to 85%
2
3. Rated frequency : 50 Hz
The digital differential relays will be used in conjunction with current transformers which
have the following characteristics.
- 150 KV side : Ratio = 200/ 1A, Burden = 25VA, Accuracy class = 5P20
- 15.75 - 20 KV side : Ratio = 950–720 / 0.58Α, Burden = 30VA, Accuracy class = 5P20
for a substation with the 20KV side installed outdoors.
- 20KV side: Ratio = 600/0.5A, Burden = 15VA and Accuracy class = 5P10 for a
substation with the 20KV side installed inside the control building of the substation.
1. Protection capability :a. Against all three and two phase internal faults.
b. Against all interturn faults
c. Against all phase to ground internal faults.
a. Trip contacts
- Number : at least two (2)
- Continuous current rating : 5 A.
- Switching making capacity : 1000 W at 110V DC
- Switching breaking capacity : 30 W at 110V DC
- Current rating for 0.5 sec : 30 Α.
4
b. Alarm contacts
- Number of alarm contacts : at least two (2) selectable contacts, plus
two NO contacts all free of voltage.
4. External wiring of the relay : The relay shall be equipped with screw
type terminals suitable for 2.5 mm2
conductors.
XI. COMMUNICATIONS
The relay shall be fitted with two (2) serial ports for reasons of interfacing
and specifically with :
2. One serial port suitable for system interface (fiber optic) shall be available for
connection to a digital computerized substation control system. The communication
protocol shall be as per IEC 60870 – 5 – 103 or Profibus, or Lon or Modbus RTU or
DNP3.0 or IEC – 61850.
XII. SOFTWARE
Software, preferably WINDOWS based, for the parameter setting analysis of fault
data and records and commissioning shall be provided on a basis of a royalty free,
non exclusive with irrevocable license to use by PPC S.A.
The software shall be user friendly and capable of displaying on VDU (screen) all
analog wave forms and digital signals. The software shall be menu – driven.
6
XIII. TESTS
2. Type tests.
a. Impulse Voltage test as per IEC - 60255 - 5. : 5 KV peak, 1.2/ 50 µs, 0.5j
b. High Frequency test as per IEC –60255-22-1. : 2.5 KV peak, 1MHz, t = 15 µs,
400 shoots/sec, duration = 2 sec.
NOTE: In case of lack of IEC testing standards, the only other standards that could be
considered are VDE and ANSI/IEEE, subject, however to the purchaser’s approval.
1. All necessary technical pamphlets and technical information so that the technical
evaluation of the offered differential relay can be carried out.
2. Outline drawings with over-all dimensions and wiring diagrams of the offered
differential relays.
3. Any test certificates for all specified type tests in this hereby specification may be
submitted along with the technical offer.
Acceptance or not of the submitted test certificates will be subject to the purchaser’s
approval.
7
4. A reference list shall be submitted and in which the following shall be included :
- Country and buyer
- Type of the relay
- Number of units sold
- Year of sale.
5. All bidders are required to complete attachment ‘’A’’. Failure to comply with this
request or submission of attachment ‘’A’’ incomplete shall constitute sufficient reason
for rejection of the offer.
1. Complete functional and wiring drawings for approval before shipment of the relays.
2. Complete outline dimensional drawings for approval before shipment of the relays.
4. Complete instructions for the operation and application of the related software.
XVI. PACKING
Each relay with all of its units (if any) shall be packaged separately inside a robust box
properly labeled.
8
ATTACHMENT “A”
4. Digital Inputs
a. Rated Voltage : ..................................................
b. Rated Voltage tolerance : ..................................................
5. Trip contacts
a. Number of trip contacts : ..................................................
b. Continuous current rating : ..................................................
c. Switching making capacity : ..................................................
d. Switching breaking capacity : ..................................................
e. Current rating for 0.5 sec : ..................................................
f. Rated Voltage : ..................................................
6. Alarm contacts
a. Number of alarm contacts : ..................................................
b. Are they selectable? : ..................................................
c. Rated Voltage : ..................................................
me/AG/26/3/2002
Revision No.2/IIδ/pm/AG/October 2004
Revision No.3/IΙδ/nn/AG/Apri/2006
Revision No.4/IΙδ/πµ/AG/June/2006
PUBLIC POWER CORPORATION OF GREECE S.A.
TRANSMISSION NEW PROJECTS DEPARTMENT September 2005
SPECIFICATION SS – 108/3
N
NUUM
MEER
RIIC
CAAL
LDDIISSTTA
ANNCCEE PPR
ROOT
TE ECCT TIIO
ONNR REEL
LA AY
YSS FFO
ORRT
THHE
E
440000K
KVVTTRRAANNSSM
MIISSSSIIO
ON NLLIIN
NEESS
I. SCOPE
This specification covers the required technical, operational and constructional
characteristics and testing of numerical distance protection relays for 400KV
transmission lines.
III. USE
The distance protection relays are to be used for the protection of each 400KV
transmission line of the 400KV double circuit against phase to phase and phase to ground
faults.
It should be noted that for reasons of increased reliability, two (2) redundant distance
relays of the same type but of different manufacturer are employed for the protection of
each transmission line. One used as back-up.
IV. STANDARDS
The relays shall conform to the latest IEC standards. Relays based on ANSI / IEEE or
DIN / VDE standards can be offered, subject however, to the Purchaser’s approval.
V. OPERATING CONDITIONS
1. Installation : Indoors
2. Temperature range : -5 0 C to 550 C
3. Relative Humidity : 5% to 85 %
No of circuits :2
Cross Section, MCM : 954 MCM*
R1, Ohms / Km : 0.03293*
X1, Ohms / Km : 0.3184*
Ro, Ohms / Km : 0.2587*
Xo, Ohms / Km : 1.1740*
Rom, Ohms / Km : 0.2262**
Xom, Ohms / Km : 0.7568**
B1, µmhos / Km : 3.57*
Bo, µmhos / Km : 2.168*
Bom, µmhos / Km : -0.5762**
Length Range : 10 to 180 Km
1. Voltage Transformers
− Type : Single-phase, oil immersed of the inductive
type
− Connection : Wye grounded
− Number of secondary windings :3
− Rated output per secondary
winding and class:
Windings 1 and 2 (for metering) : 150 VA, class 0.5
Windings 3 (protection) : 100 VA, class 3P / 0.5
400 100 100 100
Rated transformation ratio : KV − − V
3 3 3 3
1. Analog inputs
a. Rated Current : 1A AC
b. Rated Voltage : 100 3 V AC
2. Binary (Digital) Inputs
a. Rated Voltage : 220V DC
b. Rated Voltage tolerance : +10%, -15%
c. Number of digital inputs : 12
3. Output Contacts
a. Heavy duty contacts (for breaker operation)
Six (6) N.O., heavy duty contacts with the following characteristics:
− Maximum rated voltage : 250 V DC
− Continuous Current : 5A
− Short-time current, for 0.5 sec : 30A
− Switching making capability : 4A at 250 V DC
− Switching breaking capability
(for DC with L/R <40 msec) : 0.15A at 250V DC
b. Signalling (indication) configurable contacts.
Ten (10) (NO.) contacts with the following characteristics:
− Maximum rated voltage : 250 V DC
− Continuous Current : 1A
− Switching making capability : 0.10A at 250 V DC
− Switching breaking capability
(for DC with L/R <40 msec) : 0.10A at 250V DC
6. Operating Characteristic.
The operating characteristic shall be quadrilateral (polygonal) for all types of faults or
mho only for phase-to-phase faults.
7. Zones
The distance relay shall have at least three (3) distance zones, two (2) in the forward
direction and one (1) in the forward-reverse direction for all type of faults (phase to
phase and phase to earth).
The reach of the distance zones shall be selectable within the range of 0-90: Ω
secondary in the X axis and within the range of 0-30 Ω secondary in the R-axis.
In addition to the basic distance protection features, the distance relay shall have the
following additional features:
4. Auto reclosure
The range of operational modes shall, be as follows:
a. Fast single-pole auto reclosing for single-phase faults
b. Fast three-pole auto reclosing for multi-phase faults
c. Fast three-pole autoreclosing for all fault types
d. Single or multi shot autoreclosing, up to 3 shots.
5. Synchrocheck
7. Fault locator
XI. COMMUNICATIONS
The relay shall be fitted with two serial ports for reasons of interfacing and specifically
with:
XII. SOFTWARE
Software, WINDOWS based, for the parameter setting, analysis of fault data and records
and commissioning shall be provided on the basis of a royalty free, non exclusive with
irrevocable license to use by PPC.
The software shall be user friendly and displaying on VDU (screen) all analog
waveforms and digital signals. The software shall be menu-driven.
XIII. TESTS
2. Type tests.
a. Impulse Voltage test as
per IEC-60255-5 : 5KV peak, 1.2 / 50µs, 0.5J
e. Vibration test as per IEC-60068-2-6: 60Hz to 150Hz, 0.5 acceleration, sweep rate =
10 octaves / min, 20 cycles in 3 orthogonal axes
NOTE: In case of lack of IEC testing standards, the only other standards that could be
considered are VDE and ANSI / IEEE, subject, however to the purchaser’s approval.
1. All necessary technical pamphlets and technical information so that the technical
evaluation of the offered distance relay can be carried out.
2. Outline drawings with over-all dimensions and wiring diagrams of the offered distance
relays.
3. Any test certificates for all specified type tests in this hereby specification may be
submitted along with the technical offer.
Acceptance or not of the submitted test certificates will be subject to the purchaser’s
approval.
4. A list of recommended spare parts shall be submitted and prices must be indicated in
the economic offer. Purchaser maintains the right to purchase all or some or none of the
proposed spare parts.
5. A reference list shall be submitted and in which the following shall be included:
− Country and buyer
− Type of the relay
− Number of units sold
− Year of sale.
6. All bidders are required to complete attachment “A”. Failure to comply with this request
or submission of attachment “A” incomplete shall constitute sufficient reason for
rejection of the offer.
1. Complete functional and wiring drawings for approval before shipment of the relays.
2. Complete outline dimensional drawings for approval before shipment of the relays.
4. Complete instructions for the operation and application of the related software.
XVI. PACKING
Each relay with all of its units (if any) shall be packaged separately inside a robust box
properly labeled.
4. Digital Inputs:
a. Rated voltage : ……………………………………………
b. Rated voltage tolerance : ……………………………………………
c. Number of inputs : ……………………………………………
6. Signaling contacts
a. Are they configurable? : ……………………………………………
b. Number of signaling contacts : ……………………………………………
c. Rated voltage : ……………………………………………
d. Continuous current : ……………………………………………
e. Switching making capability : ……………………………………………
f. Switching breaking capability
SPECIFICATION SS-131 / 6
ATHENS - GREECE
---*---
November 2008
-2-
SPECIFICATION SS-131 / 6
PHASE AND EARTH
DEFINITE AND INVERSE TIME
OVERCURRENT RELAYS
WITH DIRECTIONAL CAPABILITY FOR BOTH PHASE
AND EARTH
FOR 150kV TRANSMISSION LINE TRANSFORMER
BAYS & PROTECTION.
I. SCOPE
This specification covers the requirements concerning the technical
and operational characteristics of definite time and inverse time 3-
phase and earth overcurrent relays with directional capability for both
phase and earth.
The relays are to be used as back-up protection for the 150 kV
Transmission Lines and 150kV Transformers bays.
II. KEYWORDS
Overcurrent relays, phase and earth (ground).
I>>, IΕ> and IΕ>>) and with directional capability for both phase
and earth.
b. Inverse time overcurrent phase and earth protection with
overcurrents stage, for both phase and earth (I>, IΕ>) and with
directional capability for both phase and earth.
per per
IEEE / ANSI IEC
a.2.
X. ADDITIONAL REQUIREMENTS
The relay must be :
XII. SOFTWARE
Any software need for the parameterization and setting of the relay
must be supplied
XIII. TESTS
a. Routine tests.
b. Type tests.
b.1. Impulse test as per IEC 60255-5 : 5 kV peak, 1.2/50 µs, 0.5 J
NOTE :
Bidders are required to submit, if available, any official test reports for
all of the above tests along with their technical offer. Acceptance or not
lies on the judgment of PPC S.A.
-6-
2. Drawings pamphlets
Bidders are requested to submit along with their technical offers,
outline drawings, wiring diagrams and any information and data
which will attributed to the compete description of the offered
relay.
2. One serial port suitable for system interface shall be available for
connection to a digital computerized substation control system. The
communication protocol shall be as per IEC 61850. The relevant
certificates, in accordance with IEC 61850-10, must be submitted.
The certificates must be of level A (level A means independent
Lab, e.g. KEMA).
The certificates can be of level B (manufacturer’s Lab), if the
manufacturer’s Lab has been qualified by the UCA International
Users Group.
In the first case the certificates (level A) must be submitted along
with technical offer. In the second case the certificates (level B)
along with the UCA International Users Group certification to the
manufacturer must be submitted in the technical offer.
XVI. GUARANTEE
Guarantee of good operation for a period of at least five (5) years
must be provided.
-7-
SPECIFICATION SS-131 / 6
PHASE AND EARTH
DEFINITE AND INVERSE TIME
OVERCURRENT RELAYS
WITH DIRECTIONAL CAPABILITY FOR BOTH PHASE
AND EARTH
FOR 150 kV TRANSMISSION LINE PROTECTION
ATTACHMENT “A”
9.a.2.
II/AG/a.k/SS-131e/18.07.2000
ΙΙδ/pm/AG/JUNE 2004
IIδ/GS/August 2006
ΙΙδ/pm/IA/July 2008
ΙΙδ/pt/IA/November 2008