ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

6/24/2020 19:44
No. Particular Unit Quantity Rate Per Amount

1 Cement concrete with stone ballast


1-1/2" gauge 1:3:6 cft. 100

Cement 16 cft. lbs. 1440 lbs.


Stone ballast 1-1/2" gauge cft. 96 cft.
Sand cft. 48 cft.

Masons no. 1 no.


Workers no. 8 no.

2 Cement concrete 1:2:4 with 1/4" to 3/4"


stone chipping or river shingle aggregate cft. 100

Cement 23 cft. lbs. 2070 lbs.


Stone cft. 92 cft.
Sand cft. 46 cft.

Masons no. 1 no.


Workers no. 10 no.

3 Mixing only cement concrete 1:2:4 with 1/2"


to 3/4" gauge stone chipping or river shingle
or river shingle aggregate cft. 100

Masons no. 1 no.


Workers no. 5 no.

4 Cement concrete with 3/4" stone ballast or


river shingle aggregate 1:2-1/2:5 cft. 100

Cement 19 cft. lbs. 1710 lbs.


Stone ballast 3/4" gauge cft. 94 cft.
Sand cft. 47 cft.

Masons no. 1 no.


Workers no. 10 no.

5 Cement concrete 1:1-1/2:3 with 1/4" to 3/4"


stone or river shingle aggregate cft. 100

Cement 19 cft. lbs. 2790 lbs.


Stone or river shingle 1/4" to 3/4" gauge cft. 92 cft.
Sand cft. 46 cft.

Masons no. 1 no.


Workers no. 10 no.

6 1-1/2" Thick cement concrete 1:2:4 with


5% pudlo to the weight of cement for damp
proof course cft. 100

Cement 2-3/4 cft. lbs. 248 lbs.


pudlo lbs. 12 lbs.
Stone ballast 1/4" to 3/4" gauge cft. 12 cft.
Sand cft. 6 cft.

Masons no. 1 no.


Workers no. 1 no.

7 Cement concrete 1:2:4 with ironite 10% to


the weight of cement cft. 100

Cement 21 cft. lbs. 1890 lbs.


Ironite lbs. 189 lbs.
Stone ballast 1/4" to 3/4" gauge cft. 92 cft.
Sand cft. 46 cft.

Masons no. 1 no.


Workers no. 10 no.

8 1" Thick cement concrete 1:2:4 with 10%


pudlo to the weight of cement for damp
proof course cft. 100

Cement lbs. 173 lbs.


pudlo lbs. 8.75 lbs.
Stone ballast 1/4" to 3/4" gauge cft. 8 cft.
Sand cft. 4 cft.

Masons no. 0.75 no.


Workers no. 0.75 no.

9 Cement concrete 1:6:12 using 3/4" to stone


or rivre shingle aggregate in foundation cft. 100

Cement lbs. 765 lbs.


Sand cft. 51 cft.
Stone or river shingle Aggregate 1/4" to 3/4" cft. 102 cft.

Masons no. 1 no.


Workers no. 10 no.

10 Cement concrete 1:4:8 using 3/4" to stone


or rivre shingle aggregate cft. 100
Cement lbs. 1170 lbs.
Sand cft. 52 cft.
Stone or river shingle Aggregate 1/4" to 3/4" cft. 104 cft.

Masons no. 1 no.


Workers no. 10 no.

11 Lime concrete ( 1:1:1:6 ) with gravel


aggerate cft. 100

Gravel cft. 100 cft.


Lime motar 1:1:1 cft. 38 cft.

Masons no. 0.5 no.


Workers no. 7 no.
Sundries L-s L-s

12 Lime concrete 1:1:4 in foundation using


medium brick aggregate cft. 100

Lime mortar cft. 34 cft.


Brick bat aggragate cft. 100 cft.

Masons no. 0.5 no.


Workers no. 7 no.
Sundries L-s L-s

13 Lime concrete 1:2:6 with gravel or broken


brick aggregate cft. 100

Gravel cft. 100 cft.


Lime cft. 17.5 cft.
Sand cft. 35 cft.

Masons no. 0.5 no.


Workers no. 10 no.

14 Lime concrete ( 1:1:1:6 ) with broken brick


or stone ballast cft. 100

Stone or brick ballast 1-1/2" gauge cft. 100 cft.


Lime motar 1:1:1 cft. 34 cft.

Masons no. 0.5 no.


Workers no. 7 no.
Sundries L-s L-s

15 Composite concrete with stone ballast,river


shingle or hill gravel 1:2:5:10 cft. 100

Cement 9 cft. lbs. 810 lbs.


Stone ballast 3/4"gauge river shingle or cft. 90 cft.
hill gravel
Lime cft. 18 cft.
Sand cft. 45 cft.

Masons no. 1 no.


Workers no. 10 no.

16 Cement concrete ( 1:3:5 ) using medium


fine stone or river shingle aggreate cft. 100

Cement cft. 17.9 cft.


Sand cft. 53.7 cft.
Stone or river shingle aggregate 3/4" to 1/2" cft. 89.5 cft.

Masons no. 1 no.


Workers no. 10 no.

17 Mixing only granolithic mix( 1:2-1/2 ) with


1/4" down granite chipping with ordinary
cement cft. 100

Cement lbs. 3568 lbs.


Sand cft. 7.5 cft.
1/4" Granite chipping cft. 104 cft.

Masons no. 1 no.


Workers no. 5 no.

18 Mixing only granolithic mix( 1:2 ) with


1/4" down granite chipping with ordinary
cement cft. 100

Cement lbs. 4320 lbs.


Sand cft. 9 cft.
1/4" Granite chipping cft. 96 cft.

Masons no. 1 no.


Workers no. 5 no.

19 Mixing only Terrazo mix( 1:3 ) with 1/4"


chipping with coloured cement cft. 100

Colour crete lbs. 3240 lbs.


1/4" Marble chipping cft. 108 cft.

Masons no. 1 no.


Workers no. 5 no.

20 Mixing only Terrazo mix( 1:2 ) with 1/4"


chipping with coloured cement cft. 100
Colour crete lbs. 4320 lbs.
1/4" Marble chipping cft. 96 cft.

Masons no. 1 no.


Workers no. 5 no.

21 Timber shuttering ( form work ) sft. 100

Timber scantling cft. 15 cft.


Tinber planks 1" sft. 110 sft.
Nails and spikes lbs. 3 lbs.
M-S bolts & washer if required

Carpenters no. 4 no.


Workers no. 2 no.
Remark
+ 1 Carp;
for Beam,
lintel &
Walls.

+ 2 Cap;
for Stairs &
Columns

+ 2 Cap;
for T&G

+ 1 Cap;
for Each
additional
Story high.

Shuttering
can be use
min; of 3
times

Add timber
planks 10
sft. For T&
G work.

You might also like