D U 1200 1850

Unit No. L B D Qty.


Excavation
Abutment 2 8.100 16.200 3.650 957.906
Pier
4 5.300 5.300 2.400 269.664

Return Wall 4 8.100 8.100 3.650 957.906

Total for Excavation 2185.476


Foundation
PCC
Abutment 2 8.100 16.200 0.150 39.366
Pier 0.000
Pile CAP 4 5.300 5.300 0.100 11.236
Ded. Of Pile -16 3.142 0.360 0.100 -1.810
Return Wall 4 8.100 8.100 0.150 39.366

Total For PCC in Foundation 88.158

Pile 1200 Dia Rm. 16 20.000 320.000

RCC M35 in Foundation


Abutment 2 7.9 16 0.6 151.680 2
2 6.1 16 0.5 97.600 2
2 1.8 16 1 57.600
Pile CAP 4 5.1 5.1 1.8 187.272
Ded. Of Pile -16 3.142 0.360 0.050 -0.905
Return Wall 4 8.100 7.9 0.6 153.576
4 8.100 6.1 0.5 98.820
4 8.100 1.8 1 58.320

Total For PCC in Foundation 803.963

Sub-Structure

RCC M35 in Sub Structure


Abutment & Return Wall
Abutment Wall 2 16 1.25 6.205 248.200
Return Wall 4 10.5 1.05 8.85 390.285
Return Wall 4 2.3 1.6 0.5 7.360
Abutment CAP 2 16 1.3 1 41.600
Dirt Wall 2 15 0.3 1.62 14.580
Bracket 2 15 0.2 0.24 1.440
Pedestal 12 0.7 0.8 0.5 3.360
Pier
Pier Shaft 4 3.141593 1 4.305 54.098
Pier CAP 4 14 2.2 0.5 61.600
Pier CAP 4 11 2.2 1 96.800
Pedestal 48 0.7 0.8 0.5 13.440

Total for RCC M-30 in Sub-Structure 932.763


RCC M30 in Sub Structure
Approach Slab 2 15 3.5 0.3 31.500

Total for RCC M-30 in Sub-Structure 31.500

Super-Structure

RCC/PSC M35 in Super Structure


RCC Solid Slab 5 11.98 16 1 958.400
RCC Railing Kerb 10 11.98 0.5 0.3 17.970

Total for RCC/PSC M35 in Super Structure 976.370

RCC/PSC M40 in Super Structure


Crash Barrier 2 60 0.32 Area 38.400

Total for RCC/PSC M35 in Super Structure 38.400

Misc.
Filter Media Behind Abutment & Return
Behind Abutment 2 15 0.6 6.55 117.900
Behind Return Wall 4 9.9 0.6 6.55 155.628
Stone Pitching 4 188.6468 0.3 226.376
Filter Materail below Pitching 4 188.6468 0.15 113.188
Weep Hole
In Abutment Rmt. 2 1.069 56 119.752
In Return Rmt. 4 1.069 44 188.182

Toe Wall
Excavation Cum 4 16.49336 1.4 1.5 138.544
PCC Cum 4 16.49336 1.4 0.1 9.236
Raft Cum 4 16.49336 1.2 0.4 31.667
Wall Cum 4 16.49336 0.51 Area 33.646
Drainage Spout Nos. 2 13 26.000
Painting of Structure Rm 2 60 120.000
Initial Load Test Tonne 2
Lateral Load Test Tonne
Testing on Span Tonne 5
HT
FRL 100
GL 93
FDN 89.5
WC 0.075
Slb+Grdr 1
Bearing 0.12
Pedestal 0.5
Abt. CAP 1
FDN Rft 1.6
Pier CAP 1.5
Abt. Wall HT. 6.205
Pier Shaft HT. 4.305
Return Wall 8.85

Ret. Wall Length 10.5


Total Viduct Length 60
A CAP BTM -OGL 3
ABT WL Top 0.9
ABT WL Base 1.6
Avg Length of Weep Hole 1.069

7.9 16 0.6 151.680


4.85 16 1 155.200
CH-78+450
Unit No. L B D Qty.
Excavation
Abutment 2 5.900 33.000 3.650 1421.310
Pier
4 5.300 5.300 2.400 269.664

Return Wall 4 4.200 5.700 3.650 349.524

Total for Excavation 2040.498


Foundation
PCC
Abutment 2 5.900 33.000 0.150 58.410
Pier 0.000
Pile CAP 4 5.300 5.300 0.100 11.236
Ded. Of Pile -16 3.142 0.360 0.100 -1.810
Return Wall 4 4.200 5.700 0.150 14.364

Total For PCC in Foundation 82.200

Pile 1200 Dia Rm. 16 20.000 320.000

RCC M35 in Foundation


Abutment 2 5.7 33 0.6 225.720 2
2 4.25 33 0.3 84.150 2
2 1.45 16 0.6 27.840
Pile CAP 4 5.1 5.1 1.8 187.272
Ded. Of Pile -16 3.142 0.360 0.050 -0.905
Return Wall 4 3.600 5.7 0.6 49.248
4 3.600 4.2 0.3 18.144
4 3.600 1.5 0.6 12.960

Total For PCC in Foundation 604.429

Sub-Structure

RCC M35 in Sub Structure


Abutment & Return Wall
Abutment Wall 2 33 1.1 3.605 261.723
Return Wall 4 6 0.9 6.25 135.000
Return Wall 4 2.1 1.3 0.3 3.276
Abutment CAP 2 33 1.3 1 85.800
Dirt Wall 2 32 0.3 1.62 31.104
Bracket 2 32 0.2 0.24 3.072
Pedestal 12 0.7 0.8 0.5 3.360
Pier
Pier Shaft 4 3.141593 1 1.305 16.399
Pier CAP 4 14 2.2 0.5 61.600
Pier CAP 4 11 2.2 1 96.800
Pedestal 48 0.7 0.8 0.5 13.440

Total for RCC M-30 in Sub-Structure 711.574


RCC M30 in Sub Structure
Approach Slab 2 31 3.5 0.3 65.100

Total for RCC M-30 in Sub-Structure 65.100

Super-Structure

RCC/PSC M35 in Super Structure


RCC Solid Slab 6 11.98 32 1 2300.160
RCC Railing Kerb 12 11.98 0.5 0.3 21.564

Total for RCC/PSC M35 in Super Structure 2321.724

RCC/PSC M40 in Super Structure


Crash Barrier 2 36 0.32 Area 23.040

Total for RCC/PSC M35 in Super Structure 23.040

Misc.
Filter Media Behind Abutment & Return
Behind Abutment 2 32 0.6 3.55 136.320
Behind Return Wall 4 5.4 0.6 3.55 46.008
Stone Pitching 4 70.13311 0.3 84.160
Filter Materail below Pitching 4 70.13311 0.15 42.080
Weep Hole
In Abutment Rmt. 2 0.900 30 54.000
In Return Rmt. 4 0.900 6 21.600

Toe Wall
Excavation Cum 4 9.424778 1.4 1.5 79.168
PCC Cum 4 9.424778 1.4 0.1 5.278
Raft Cum 4 9.424778 1.2 0.4 18.096
Wall Cum 4 9.424778 0.51 Area 19.227
Drainage Spout Nos. 2 8.2 16.400
Painting of Structure Rm 2 36 72.000
Initial Load Test Tonne 2
Lateral Load Test Tonne
Testing on Span Tonne 6
HT
FRL 100
GL 96
FDN 92.5
WC 0.075
Slb+Grdr 1
Bearing 0.12
Pedestal 0.5
Abt. CAP 1
FDN Rft 1.2
Pier CAP 1.5
Abt. Wall HT. 3.605
Pier Shaft HT. 1.305
Return Wall 6.25

Ret. Wall Length 6


Total Viduct Length 36
A CAP BTM -OGL 0
ABT WL Top 0.9
ABT WL Base 1.25
Avg Length of Weep Hole 0.900

7.9 16 0.6 151.680


4.85 16 1 155.200