BALAGTAS STATION

CONSTRUCTION ACTIVITY AT PILE CAP


As of 2021-05 (May)
LEGEND:

CONSTRUCTION: COMPLETED
Pile Cap and Tie Beams

CONSTRUCTION: UNSTARTED
Pile Cap and Tie Beams

NOTES:
1. COMPLETED CONCRETE WORKS DATED AS PER ACTUAL FINISH OF CONCRETE POURING.
2. INFORMATION APPLIED IN THE MODEL ARE GATHERED FROM THE ACTUAL SITE ACTIVITY.
3. INFORMATION APPLIED IN THE MODEL ARE REFERENCED TO SHOP DRAWINGS APPROVED
BY THE ENGINEER; IN LINE WITH SHOP DRAWINGS FOR APPROVAL.
4. INFORMATION OF THE MODEL SHOWN INDICATED AS PER DATE OF PREPARATION.

DATE PREPARED: MAY 14, 2021

BALAGTAS STATION - PILE CAP & TIE BEAMS (TOP OF PILE @ EL. +1.200M)
1 SCALE(A1):
BALAGTAS STATION
CONSTRUCTION ACTIVITY AT PILE CAP
As of 2021-05 (May)
LEGEND:

CONSTRUCTION: COMPLETED
Pile Cap and Tie Beams PILE CAP: PC2
Date of Actual Finish
Aug. 08, 2020
COMPLETED

CONSTRUCTION: UNSTARTED
Pile Cap and Tie Beams

PILE CAP: PC1


NOTES: Date of Actual Finish
Aug. 11, 2020
1. COMPLETED CONCRETE WORKS DATED AS PER ACTUAL FINISH OF CONCRETE POURING. COMPLETED TIE BEAM: TB1
2. INFORMATION APPLIED IN THE MODEL ARE GATHERED FROM THE ACTUAL SITE ACTIVITY. Date of Actual Finish
3. INFORMATION APPLIED IN THE MODEL ARE REFERENCED TO SHOP DRAWINGS APPROVED Aug. 11, 2020
BY THE ENGINEER; IN LINE WITH SHOP DRAWINGS FOR APPROVAL. COMPLETED
4. INFORMATION OF THE MODEL SHOWN INDICATED AS PER DATE OF PREPARATION.

DATE PREPARED: MAY 14, 2021 PILE CAP: PC1 TIE BEAM: TB1
Date of Actual Finish Date of Actual Finish
Aug. 13, 2020 Aug. 13, 2020 PILE CAP: PC1 PILE CAP: PC1A
COMPLETED COMPLETED Date of Actual Finish Date of Actual Finish
Aug. 11, 2020 Oct. 03, 2020
COMPLETED COMPLETED

PILE CAP: PC1 TIE BEAM: TB1


Date of Actual Finish Date of Actual Finish PILE CAP: PC1
Aug. 17, 2020 Aug. 17, 2020 PILE CAP: PC1 Date of Actual Finish
COMPLETED COMPLETED Date of Actual Finish TIE BEAM: TB1
Oct. 07, 2020
Aug. 13, 2020 Date of Actual Finish
COMPLETED
COMPLETED Oct. 07, 2020
COMPLETED

PILE CAP: PC1 TIE BEAM: TB1


Date of Actual Finish Date of Actual Finish PILE CAP: PC1 TIE BEAM: TB1
Aug. 19, 2020 Aug. 19, 2020 PILE CAP: PC1 Date of Actual Finish Date of Actual Finish
COMPLETED COMPLETED Date of Actual Finish PILE CAP: PC1
Oct. 08, 2020 Oct. 08, 2020
Aug. 17, 2020 Date of Actual Finish
COMPLETED COMPLETED
COMPLETED Oct. 07, 2020
COMPLETED

PILE CAP: PC1 TIE BEAM: TB1


Date of Actual Finish Date of Actual Finish PILE CAP: PC1 TIE BEAM: TB1
Aug. 22, 2020 Aug. 22, 2020 PILE CAP: PC1 Date of Actual Finish Date of Actual Finish
COMPLETED COMPLETED Date of Actual Finish PILE CAP: PC1
Mar. 22, 2021 Mar. 22, 2021
Aug. 19, 2020 Date of Actual Finish
COMPLETED COMPLETED
COMPLETED Oct. 08, 2020
COMPLETED

PILE CAP: PC1 TIE BEAM: TB1


Date of Actual Finish Date of Actual Finish PILE CAP: PC1 TIE BEAM: TB1
Aug. 25, 2020 Aug. 25, 2020 PILE CAP: PC1
Date of Actual Finish Date of Actual Finish Date of Actual Finish
COMPLETED COMPLETED Oct. 10, 2020 Oct. 10, 2020 PILE CAP: PC1
Aug. 22, 2020 Date of Actual Finish
COMPLETED COMPLETED COMPLETED
Mar. 22, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish PILE CAP: PC1 TIE BEAM: TB1
Aug. 28, 2020 PILE CAP: PC1
Date of Actual Finish Date of Actual Finish Date of Actual Finish
COMPLETED Oct. 14, 2020 Oct. 14, 2020 PILE CAP: PC1
Aug. 25, 2020 Date of Actual Finish
COMPLETED COMPLETED COMPLETED
Oct. 10, 2020
COMPLETED

TIE BEAM: TB1


Date of Actual Finish PILE CAP: PC1 TIE BEAM: TB1
PILE CAP: PC1
Aug. 18, 2020 Date of Actual Finish Date of Actual Finish
Date of Actual Finish PILE CAP: PC1
COMPLETED Apr. 07, 2021 Apr. 07, 2021
Aug. 28, 2020 Date of Actual Finish
COMPLETED COMPLETED
COMPLETED Oct. 14, 2020
COMPLETED
BALAGTAS STATION - PILE CAP & TIE BEAMS @ GRID LINE 1 - 8 / A - D
1 SCALE(A1):

PILE CAP: PC1


Date of Actual Finish
Apr. 07, 2021 PILE CAP: PC1
COMPLETED Date of Actual Finish
Apr. 07, 2021
COMPLETED

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
TIE BEAM: TB1
Date of Actual Finish PILE CAP: PC1
Apr. 07, 2021 Date of Actual Finish A
COMPLETED Apr. 07, 2021
COMPLETED
B

C
D

8' 8" 14' 14"


BALAGTAS STATION
KEYPLAN
BALAGTAS STATION
CONSTRUCTION ACTIVITY AT PILE CAP
As of 2021-05 (May)
LEGEND:

CONSTRUCTION: COMPLETED
Pile Cap and Tie Beams

CONSTRUCTION: UNSTARTED
Pile Cap and Tie Beams
PILE CAP: PC1A
Date of Actual Finish
Mar. 13, 2020
COMPLETED

NOTES:
1. COMPLETED CONCRETE WORKS DATED AS PER ACTUAL FINISH OF CONCRETE POURING.
2. INFORMATION APPLIED IN THE MODEL ARE GATHERED FROM THE ACTUAL SITE ACTIVITY.
3. INFORMATION APPLIED IN THE MODEL ARE REFERENCED TO SHOP DRAWINGS APPROVED
BY THE ENGINEER; IN LINE WITH SHOP DRAWINGS FOR APPROVAL. PILE CAP: PC1
4. INFORMATION OF THE MODEL SHOWN INDICATED AS PER DATE OF PREPARATION. Date of Actual Finish TIE BEAM: TB1
Mar. 07, 2020 Date of Actual Finish
COMPLETED Mar. 07, 2020
DATE PREPARED: MAY 14, 2021 COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
Mar. 07, 2020 Date of Actual Finish
COMPLETED Mar. 07, 2020 PILE CAP: PC1
COMPLETED Date of Actual Finish
Mar. 07, 2020
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1 PILE CAP: PC1
Mar. 11, 2020 Date of Actual Finish Date of Actual Finish TIE BEAM: TB1
COMPLETED Mar. 11, 2020 PILE CAP: PC1 Sep. 04, 2020 Date of Actual Finish
COMPLETED Date of Actual Finish PILE CAP: PC1A
COMPLETED Sep. 04, 2020 Date of Actual Finish
Mar. 07, 2020 COMPLETED
COMPLETED Feb. 16, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1 PILE CAP: PC1
Mar. 13, 2020 Date of Actual Finish Date of Actual Finish TIE BEAM: TB1
COMPLETED Mar. 13, 2020 PILE CAP: PC1 Sep. 11, 2020 Date of Actual Finish
COMPLETED Date of Actual Finish Sep. 11, 2020 PILE CAP: PC1
COMPLETED
Mar. 11, 2020 COMPLETED Date of Actual Finish
COMPLETED Sep. 04, 2020
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1 PILE CAP: PC1
Mar. 16, 2020 Date of Actual Finish Date of Actual Finish TIE BEAM: TB1
COMPLETED Mar. 16, 2020 PILE CAP: PC1 Sep. 29, 2020 Date of Actual Finish
COMPLETED Date of Actual Finish Sep. 29, 2020 PILE CAP: PC1
COMPLETED
Mar. 13, 2020 COMPLETED Date of Actual Finish
COMPLETED Sep. 11, 2020
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1 Sep. 30, 2020 Date of Actual Finish
Date of Actual Finish COMPLETED Sep. 30, 2020
Mar. 16, 2020 COMPLETED
COMPLETED PILE CAP: PC3
Date of Actual Finish
Sep. 29, 2020
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
Mar. 06, 2021 Date of Actual Finish
COMPLETED Mar. 06, 2021
COMPLETED PILE CAP: PC1
Date of Actual Finish
Sep. 30, 2020
COMPLETED

BALAGTAS STATION - PILE CAP & TIE BEAMS @ GRID LINE 8 - 14 / A - D


1 SCALE(A1):

PILE CAP: PC1


Date of Actual Finish
Mar. 06, 2020
COMPLETED

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

A
B

C
D

8' 8" 14' 14"


BALAGTAS STATION
KEYPLAN
BALAGTAS STATION
CONSTRUCTION ACTIVITY AT PILE CAP
As of 2021-05 (May)
LEGEND:

CONSTRUCTION: COMPLETED
Pile Cap and Tie Beams

CONSTRUCTION: UNSTARTED
Pile Cap and Tie Beams

PILE CAP: PC1


TIE BEAM: TB1
NOTES: Date of Actual Finish
Mar. 01, 2020 Date of Actual Finish
COMPLETED Mar. 01, 2020
1. COMPLETED CONCRETE WORKS DATED AS PER ACTUAL FINISH OF CONCRETE POURING. COMPLETED
2. INFORMATION APPLIED IN THE MODEL ARE GATHERED FROM THE ACTUAL SITE ACTIVITY.
3. INFORMATION APPLIED IN THE MODEL ARE REFERENCED TO SHOP DRAWINGS APPROVED
BY THE ENGINEER; IN LINE WITH SHOP DRAWINGS FOR APPROVAL.
4. INFORMATION OF THE MODEL SHOWN INDICATED AS PER DATE OF PREPARATION.

PILE CAP: PC1


DATE PREPARED: MAY 14, 2021 Date of Actual Finish TIE BEAM: TB1
Mar. 01, 2020 Date of Actual Finish
COMPLETED Mar. 01, 2020 PILE CAP: PC1
COMPLETED Date of Actual Finish
Mar. 01, 2020
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1
Mar. 01, 2020 Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1 Date of Actual Finish
COMPLETED Mar. 01, 2020 Date of Actual Finish
Date of Actual Finish Feb. 17, 2021
COMPLETED Feb. 17, 2021
Mar. 01, 2020 COMPLETED
COMPLETED
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1
Mar. 05, 2020 Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1 Date of Actual Finish
COMPLETED Mar. 05, 2020 Date of Actual Finish
Date of Actual Finish Feb. 17, 2021
COMPLETED Feb. 17, 2021 PILE CAP: PC1
Mar. 01, 2020 COMPLETED
COMPLETED Date of Actual Finish
COMPLETED Feb. 17, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1
Mar. 05, 2020 Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1 Date of Actual Finish
COMPLETED Mar. 05, 2020 Date of Actual Finish
Date of Actual Finish Mar. 23, 2021
COMPLETED Mar. 23, 2021 PILE CAP: PC1
Mar. 05, 2020 COMPLETED
COMPLETED Date of Actual Finish
COMPLETED Feb. 17, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
PILE CAP: PC1 Date of Actual Finish
Date of Actual Finish Mar. 02, 2021
COMPLETED Mar. 02, 2021 PILE CAP: PC1
Mar. 05, 2020 COMPLETED Date of Actual Finish
COMPLETED Mar. 23, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish TIE BEAM: TB1
Feb. 26, 2021 Date of Actual Finish
COMPLETED Feb. 26, 2021 PILE CAP: PC1
COMPLETED Date of Actual Finish
Mar. 02, 2021
COMPLETED

PILE CAP: PC1


Date of Actual Finish
Feb. 26, 2021
COMPLETED BALAGTAS STATION - PILE CAP & TIE BEAMS @ GRID LINE 14 - 19 / A - D
1 SCALE(A1):

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

A
B

C
D

8' 8" 14' 14"

BALAGTAS STATION
KEYPLAN