You are on page 1of 138

Data Rencana Anggaran Biaya La

b 600 mm 0.6 m Struktur


Kolom K1
h 600 mm 0.6 m Panjang Lebar Tinggi
Komponen Beban Ketengan
b 600 mm 0.6 m (m) (m) (m)
Kolom K2
h 600 mm 0.6 m Segmen 1 29.5 19 0.15
b 500 mm 0.5 m Pelat Lantai Segmen 2 13.8 19 0.15
Balok B50/80
h 800 mm 0.8 m Segmen 3 20.7 19 0.15
b 400 mm 0.4 m as A (1-2) 2 0.5 0.8
Balok B40/70
h 700 mm 0.7 m as A (3-6) 11 0.5 0.8
b 350 mm 0.35 m as A (7-8) 2 0.5 0.8
Balok B35/50
h 500 mm 0.5 m as B 23 0.5 0.8
Lantai h 150 mm 0.15 m as C 23 0.5 0.8
Atap h 130 mm 0.13 m as D 23 0.5 0.8
b 400 mm 0.4 m as E 23 0.5 0.8
Shear Wall
h 400 mm 0.4 m as F 23 0.5 0.8
b 400 mm 0.4 m as G 23 0.5 0.8
Core Wall
h 400 mm 0.4 m as I to Core 1.95 0.5 0.8
as I (2-5) 11 0.5 0.8
Balok B50/80 (Y)
as J (2-7) 19 0.5 0.8
as K (2-7) 19 0.5 0.8
as L (2-7) 19 0.5 0.8
as M 23 0.5 0.8
as N 23 0.5 0.8
as O 23 0.5 0.8
as P 23 0.5 0.8
as Q 23 0.5 0.8
as R (1-2) 2 0.5 0.8
as R (3-6) 11 0.5 0.8
as R (7-8) 2 0.5 0.8
SW X 4 0.5 0.8
Balok B50/80 X
CORE 5.5 0.5 0.8
as 7 (B-Q) 56 0.5 0.7
as 6 (B-G) 20 0.5 0.7
as 6 (J-Q) 28 0.5 0.7
as 5 (A-G) 24 0.5 0.7
Balok 40/70 as 5 (J-R) 32 0.5 0.7
as 4 64 0.5 0.7
as 3 (B-Q) 56 0.5 0.7
as 2 (B-I) 25.5 0.5 0.7
as 2 (M-Q) 16.7 0.5 0.7
as A-I 29.5 0.5 0.5
Balok 35/50
as M-R 20.7 0.5 0.5
Kolom K1 0.6 0.6 4
SW1 4 0.4 4
SW2 4 0.4 4
Shear Wall SW3 4 0.4 4
SW4 4 0.4 4
SW5 8 0.4 4
Arah X 2.85 0.4 4
Core Wall
Arah Y 6 0.4 4
Total

Rencana Anggaran Biaya La


Struktur
Panjang Lebar Tinggi
Komponen Beban Ketengan
(m) (m) (m)
Segmen 1 29.5 19 0.15
Pelat Lantai Segmen 2 13.8 19 0.15
Segmen 3 20.7 19 0.15
as A (1-2) 2 0.5 0.8
as A (3-6) 11 0.5 0.8
as A (7-8) 2 0.5 0.8
as B 23 0.5 0.8
as C 23 0.5 0.8
as D 23 0.5 0.8
as E 23 0.5 0.8
as F 23 0.5 0.8
as G 23 0.5 0.8
as I to Core 1.95 0.5 0.8
as I (2-5) 11 0.5 0.8
Balok B50/80 (Y)
as J (2-7) 19 0.5 0.8
as K (2-7) 19 0.5 0.8
as L (2-7) 19 0.5 0.8
as M 23 0.5 0.8
as N 23 0.5 0.8
as O 23 0.5 0.8
as P 23 0.5 0.8
as Q 23 0.5 0.8
as R (1-2) 2 0.5 0.8
as R (3-6) 11 0.5 0.8
as R (7-8) 2 0.5 0.8
SW X 4 0.5 0.8
Balok B50/80 X
CORE 5.5 0.5 0.8
as 7 (B-Q) 56 0.5 0.7
as 6 (B-G) 20 0.5 0.7
as 6 (J-Q) 28 0.5 0.7

Balok 40/70
as 5 (A-G) 24 0.5 0.7
Balok 40/70 as 5 (J-R) 32 0.5 0.7
as 4 64 0.5 0.7
as 3 (B-Q) 56 0.5 0.7
as 2 (B-I) 25.5 0.5 0.7
as 2 (M-Q) 16.7 0.5 0.7
as A-I 29.5 0.5 0.5
Balok 35/50
as M-R 20.7 0.5 0.5
Kolom K1 0.6 0.6 4
SW1 4 0.4 4
SW2 4 0.4 4
Shear Wall SW3 4 0.4 4
SW4 4 0.4 4
SW5 8 0.4 4
Arah X 2.85 0.4 4
Core Wall
Arah Y 6 0.4 4
Total
Anggaran Biaya Lantai 1 Rencana Angga
Struktur
Harga Beton K-400 Total Dana
Jumlah Komponen Beban Ketengan
(1 m3) Rp
1 1310000 IDR 110,138,250 Segmen 1
1 1310000 IDR 51,522,300 Pelat Lantai Segmen 2
1 1310000 IDR 77,283,450 Segmen 3
1 1310000 IDR 1,048,000 as A (1-2)
1 1310000 IDR 5,764,000 as A (3-6)
1 1310000 IDR 1,048,000 as A (7-8)
1 1310000 IDR 12,052,000 as B
1 1310000 IDR 12,052,000 as C
1 1310000 IDR 12,052,000 as D
1 1310000 IDR 12,052,000 as E
1 1310000 IDR 12,052,000 as F
1 1310000 IDR 12,052,000 as G
1 1310000 IDR 1,021,800 as I to Core
1 1310000 IDR 5,764,000 as I (2-5)
Balok B50/80 (Y)
1 1310000 IDR 9,956,000 as J (2-7)
1 1310000 IDR 9,956,000 as K (2-7)
1 1310000 IDR 9,956,000 as L (2-7)
1 1310000 IDR 12,052,000 as M
1 1310000 IDR 12,052,000 as N
1 1310000 IDR 12,052,000 as O
1 1310000 IDR 12,052,000 as P
1 1310000 IDR 12,052,000 as Q
1 1310000 IDR 1,048,000 as R (1-2)
1 1310000 IDR 5,764,000 as R (3-6)
1 1310000 IDR 1,048,000 as R (7-8)
1 1310000 IDR 2,096,000 SW X
Balok B50/80 X
1 1310000 IDR 2,882,000 CORE
1 1310000 IDR 25,676,000 as 7 (B-Q)
1 1310000 IDR 9,170,000 as 6 (B-G)
1 1310000 IDR 12,838,000 as 6 (J-Q)
1 1310000 IDR 11,004,000 as 5 (A-G)
1 1310000 IDR 14,672,000 Balok 40/70 as 5 (J-R)
1 1310000 IDR 29,344,000 as 4
1 1310000 IDR 25,676,000 as 3 (B-Q)
1 1310000 IDR 11,691,750 as 2 (B-I)
1 1310000 IDR 7,656,950 as 2 (M-Q)
2 1310000 IDR 19,322,500 as A-I
Balok 35/50
2 1310000 IDR 13,558,500 as M-R
92 1310000 IDR 173,548,800 Kolom K1
1 1310000 IDR 8,384,000 SW1
1 1310000 IDR 8,384,000 SW2
1 1310000 IDR 8,384,000 Shear Wall SW3
1 1310000 IDR 8,384,000 SW4
1 1310000 IDR 16,768,000 SW5
3 1310000 IDR 17,920,800 Arah X
Core Wall
1 1310000 IDR 12,576,000 Arah Y
IDR 863,827,100 Total

Anggaran Biaya Lantai 1


Harga Beton K-400 Total Dana
Jumlah
(1 m3) Rp
1 1310000 IDR 110,138,250
1 1310000 IDR 51,522,300
1 1310000 IDR 77,283,450
1 1310000 IDR 1,048,000
1 1310000 IDR 5,764,000
1 1310000 IDR 1,048,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 1,021,800
1 1310000 IDR 5,764,000
1 1310000 IDR 9,956,000
1 1310000 IDR 9,956,000
1 1310000 IDR 9,956,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 12,052,000
1 1310000 IDR 1,048,000
1 1310000 IDR 5,764,000
1 1310000 IDR 1,048,000
1 1310000 IDR 2,096,000
1 1310000 IDR 2,882,000
1 1310000 IDR 25,676,000
1 1310000 IDR 9,170,000
1 1310000 IDR 12,838,000
1 1310000 IDR 11,004,000
1 1310000 IDR 14,672,000
1 1310000 IDR 29,344,000
1 1310000 IDR 25,676,000
1 1310000 IDR 11,691,750
1 1310000 IDR 7,656,950
2 1310000 IDR 19,322,500
2 1310000 IDR 13,558,500
92 1310000 IDR 173,548,800
1 1310000 IDR 8,384,000
1 1310000 IDR 8,384,000
1 1310000 IDR 8,384,000
1 1310000 IDR 8,384,000
1 1310000 IDR 16,768,000
3 1310000 IDR 17,920,800
1 1310000 IDR 12,576,000
IDR 863,827,100
Rencana Anggaran Biaya Lantai 2-11

Panjang Lebar Tinggi Harga Beton K-400 Total Dana


Jumlah
(m) (m) (m) (1 m3) Rp
29.5 19 0.15 1 1310000 IDR 110,138,250
13.8 19 0.15 1 1310000 IDR 51,522,300
20.7 19 0.15 1 1310000 IDR 77,283,450
2 0.5 0.8 1 1310000 IDR 1,048,000
11 0.5 0.8 1 1310000 IDR 5,764,000
2 0.5 0.8 1 1310000 IDR 1,048,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
1.95 0.5 0.8 1 1310000 IDR 1,021,800
11 0.5 0.8 1 1310000 IDR 5,764,000
19 0.5 0.8 1 1310000 IDR 9,956,000
19 0.5 0.8 1 1310000 IDR 9,956,000
19 0.5 0.8 1 1310000 IDR 9,956,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
23 0.5 0.8 1 1310000 IDR 12,052,000
2 0.5 0.8 1 1310000 IDR 1,048,000
11 0.5 0.8 1 1310000 IDR 5,764,000
2 0.5 0.8 1 1310000 IDR 1,048,000
4 0.5 0.8 1 1310000 IDR 2,096,000
5.5 0.5 0.8 1 1310000 IDR 2,882,000
56 0.5 0.7 1 1310000 IDR 25,676,000
20 0.5 0.7 1 1310000 IDR 9,170,000
28 0.5 0.7 1 1310000 IDR 12,838,000
24 0.5 0.7 1 1310000 IDR 11,004,000
32 0.5 0.7 1 1310000 IDR 14,672,000
64 0.5 0.7 1 1310000 IDR 29,344,000
56 0.5 0.7 1 1310000 IDR 25,676,000
25.5 0.5 0.7 1 1310000 IDR 11,691,750
16.7 0.5 0.7 1 1310000 IDR 7,656,950
29.5 0.5 0.5 2 1310000 IDR 19,322,500
20.7 0.5 0.5 2 1310000 IDR 13,558,500
0.6 0.6 4 92 1310000 IDR 173,548,800
4 0.4 4 1 1310000 IDR 8,384,000
4 0.4 4 1 1310000 IDR 8,384,000
4 0.4 4 1 1310000 IDR 8,384,000
4 0.4 4 1 1310000 IDR 8,384,000
8 0.4 4 1 1310000 IDR 16,768,000
2.85 0.4 4 3 1310000 IDR 17,920,800
6 0.4 4 1 1310000 IDR 12,576,000
IDR 863,827,100
Rencana Anggaran Biaya Lantai 2-11
Struktur
Panjang Lebar Tinggi Harga Beton K-400
Komponen Beban Ketengan Jumlah
(m) (m) (m) (1 m3)
Segmen 1 29.5 19 0.15 1 1310000
Pelat Lantai Segmen 2 13.8 19 0.15 1 1310000
Segmen 3 20.7 19 0.15 1 1310000
as A (1-2) 2 0.5 0.8 1 1310000
as A (3-6) 11 0.5 0.8 1 1310000
as A (7-8) 2 0.5 0.8 1 1310000
as B 23 0.5 0.8 1 1310000
as C 23 0.5 0.8 1 1310000
as D 23 0.5 0.8 1 1310000
as E 23 0.5 0.8 1 1310000
as F 23 0.5 0.8 1 1310000
as G 23 0.5 0.8 1 1310000
as I to Core 1.95 0.5 0.8 1 1310000
as I (2-5) 11 0.5 0.8 1 1310000
Balok B50/80 (Y)
as J (2-7) 19 0.5 0.8 1 1310000
as K (2-7) 19 0.5 0.8 1 1310000
as L (2-7) 19 0.5 0.8 1 1310000
as M 23 0.5 0.8 1 1310000
as N 23 0.5 0.8 1 1310000
as O 23 0.5 0.8 1 1310000
as P 23 0.5 0.8 1 1310000
as Q 23 0.5 0.8 1 1310000
as R (1-2) 2 0.5 0.8 1 1310000
as R (3-6) 11 0.5 0.8 1 1310000
as R (7-8) 2 0.5 0.8 1 1310000
SW X 4 0.5 0.8 1 1310000
Balok B50/80 X
CORE 5.5 0.5 0.8 1 1310000
as 7 (B-Q) 56 0.5 0.7 1 1310000
as 6 (B-G) 20 0.5 0.7 1 1310000
as 6 (J-Q) 28 0.5 0.7 1 1310000
as 5 (A-G) 24 0.5 0.7 1 1310000
Balok 40/70 as 5 (J-R) 32 0.5 0.7 1 1310000
as 4 64 0.5 0.7 1 1310000
as 3 (B-Q) 56 0.5 0.7 1 1310000
as 2 (B-I) 25.5 0.5 0.7 1 1310000
as 2 (M-Q) 16.7 0.5 0.7 1 1310000
as A-I 29.5 0.5 0.5 2 1310000
Balok 35/50
as M-R 20.7 0.5 0.5 2 1310000
Kolom K1 0.6 0.6 4 92 1310000
SW1 4 0.4 4 1 1310000
SW2 4 0.4 4 1 1310000
Shear Wall SW3 4 0.4 4 1 1310000
SW4 4 0.4 4 1 1310000
SW5 8 0.4 4 1 1310000
Arah X 2.85 0.4 4 3 1310000
Core Wall
Arah Y 6 0.4 4 1 1310000
Total
11 REKAPITULASI RENCANA ANGGARAN
Total Dan
Level
Total Dana Rp
Rp Lantai 12 IDR 863,827
IDR 110,138,250 Lantai 11 IDR 863,827
IDR 51,522,300 Lantai 10 IDR 863,827
IDR 77,283,450 Lantai 9 IDR 863,827
IDR 1,048,000 Lantai 8 IDR 863,827
IDR 5,764,000 Lantai 7 IDR 863,827
IDR 1,048,000 Lantai 6 IDR 863,827
IDR 12,052,000 Lantai 5 IDR 863,827
IDR 12,052,000 Lantai 4 IDR 863,827
IDR 12,052,000 Lantai 3 IDR 863,827
IDR 12,052,000 Lantai 2 IDR 863,827
IDR 12,052,000 Lantai 1 IDR 863,827
IDR 12,052,000 JUMLAH IDR 10,365,92
IDR 1,021,800
IDR 5,764,000
IDR 9,956,000
IDR 9,956,000
IDR 9,956,000
IDR 12,052,000
IDR 12,052,000
IDR 12,052,000
IDR 12,052,000
IDR 12,052,000
IDR 1,048,000
IDR 5,764,000
IDR 1,048,000
IDR 2,096,000
IDR 2,882,000
IDR 25,676,000
IDR 9,170,000
IDR 12,838,000
IDR 11,004,000
IDR 14,672,000
IDR 29,344,000
IDR 25,676,000
IDR 11,691,750
IDR 7,656,950
IDR 19,322,500
IDR 13,558,500
IDR 173,548,800
IDR 8,384,000
IDR 8,384,000
IDR 8,384,000
IDR 8,384,000
IDR 16,768,000
IDR 17,920,800
IDR 12,576,000
IDR 863,827,100
ANA ANGGARAN BETON READY MIX K-400
Total Dana
Rp
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 863,827,100
IDR 10,365,925,200
Data Tulangan Longitudinal
b 600 mm 0.6 m Struktur Balok
Kolom K1 D22 10 Buah
h 600 mm 0.6 m
Komponen Beban
b 500 mm 0.5 m
Balok B50/80 D19 11 Buah
h 800 mm 0.8 m
b 400 mm 0.4 m
Balok B40/70 D19 9 Buah
h 700 mm 0.7 m
b 350 mm 0.35 m
Balok B35/50 D19 6 Buah
h 500 mm 0.5 m

Balok B50/80 (Y)

Balok B50/80 X

Balok 40/70

Balok 35/50

Total
Total Keseluruhan Balok 12 L
Rencana Anggaran Biaya 1 Lantai
ur Balok
Panjang Lebar Tinggi Tulangan Longitudinal Harga Tulangan 1 Batang 12 Meter
Ketengan Jumlah
(m) (m) (m) Buah Rp
as A (1-2) 2 0.5 0.8 1 11 253000
as A (3-6) 11 0.5 0.8 1 11 253000
as A (7-8) 2 0.5 0.8 1 11 253000
as B 23 0.5 0.8 1 11 253000
as C 23 0.5 0.8 1 11 253000
as D 23 0.5 0.8 1 11 253000
as E 23 0.5 0.8 1 11 253000
as F 23 0.5 0.8 1 11 253000
as G 23 0.5 0.8 1 11 253000
as I to Core 1.95 0.5 0.8 1 11 253000
as I (2-5) 11 0.5 0.8 1 11 253000
as J (2-7) 19 0.5 0.8 1 11 253000
as K (2-7) 19 0.5 0.8 1 11 253000
as L (2-7) 19 0.5 0.8 1 11 253000
as M 23 0.5 0.8 1 11 253000
as N 23 0.5 0.8 1 11 253000
as O 23 0.5 0.8 1 11 253000
as P 23 0.5 0.8 1 11 253000
as Q 23 0.5 0.8 1 11 253000
as R (1-2) 2 0.5 0.8 1 11 253000
as R (3-6) 11 0.5 0.8 1 11 253000
as R (7-8) 2 0.5 0.8 1 11 253000
SW X 4 0.5 0.8 1 11 253000
CORE 5.5 0.5 0.8 1 11 253000
as 7 (B-Q) 56 0.5 0.7 1 9 253000
as 6 (B-G) 20 0.5 0.7 1 9 253000
as 6 (J-Q) 28 0.5 0.7 1 9 253000
as 5 (A-G) 24 0.5 0.7 1 9 253000
as 5 (J-R) 32 0.5 0.7 1 9 253000
as 4 64 0.5 0.7 1 9 253000
as 3 (B-Q) 56 0.5 0.7 1 9 253000
as 2 (B-I) 25.5 0.5 0.7 1 9 253000
as 2 (M-Q) 16.7 0.5 0.7 1 9 253000
as A-I 29.5 0.5 0.5 2 6 253000
as M-R 20.7 0.5 0.5 2 6 253000

Keseluruhan Balok 12 Lantai


Biaya 1 Lantai

Total Panjang Balok Kebutuhan Besi Balok 12 meter Kebutuhan Total Harga
m Buah Buah Rp

362.45 30 332 IDR 84,058,196

322.2 27 242 IDR 61,137,450

100.4 8 50 IDR 12,700,600

IDR 157,896,246
IDR 1,894,754,950
Rencana Anggaran
Panjang Lebar Tinggi
Komponen Beban Ketengan Jumlah
(m) (m) (m)
Kolom K1 0.6 0.6 4 92
as A (1-2) 2 0.5 0.8 12
as A (3-6) 11 0.5 0.8 12
as A (7-8) 2 0.5 0.8 12
as B 23 0.5 0.8 12
as C 23 0.5 0.8 12
as D 23 0.5 0.8 12
as E 23 0.5 0.8 12
as F 23 0.5 0.8 12
as G 23 0.5 0.8 12
as I to Core 1.95 0.5 0.8 12
as I (2-5) 11 0.5 0.8 12
Balok B50/80 (Y)
as J (2-7) 19 0.5 0.8 12
as K (2-7) 19 0.5 0.8 12
as L (2-7) 19 0.5 0.8 12
as M 23 0.5 0.8 12
as N 23 0.5 0.8 12
as O 23 0.5 0.8 12
as P 23 0.5 0.8 12
as Q 23 0.5 0.8 12
as R (1-2) 2 0.5 0.8 12
as R (3-6) 11 0.5 0.8 12
as R (7-8) 2 0.5 0.8 12
SW X 4 0.5 0.8 12
Balok B50/80 X
CORE 5.5 0.5 0.8 12
as 7 (B-Q) 56 0.5 0.7 12
as 6 (B-G) 20 0.5 0.7 12
as 6 (J-Q) 28 0.5 0.7 12
as 5 (A-G) 24 0.5 0.7 12
Balok 40/70 as 5 (J-R) 32 0.5 0.7 12
as 4 64 0.5 0.7 12
as 3 (B-Q) 56 0.5 0.7 12
as 2 (B-I) 25.5 0.5 0.7 12
as 2 (M-Q) 16.7 0.5 0.7 12
as A-I 29.5 0.5 0.5 24
Balok 35/50
as M-R 20.7 0.5 0.5 24
SW1 4 0.4 4 1
SW2 4 0.4 4 1
Shear Wall
Shear Wall SW3 4 0.4 4 1
SW4 4 0.4 4 1
SW5 8 0.4 4 1
Arah X 2.85 2.85 4 3
Core Wall
Arah Y 6 6 4 1
Total
Rencana Anggaran Biaya Tulangan Longitudinal Seluruh
Tulangan Longitudinal Harga Tulangan 1 Batang 12 Meter Total Panjang
Buah Rp m
10 338000 48
11 338000 24
11 338000 132
11 338000 24
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 23
11 338000 132
11 338000 228
11 338000 228
11 338000 228
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 24
11 338000 132
11 338000 24
11 338000 48
11 338000 66
9 338000 672
9 338000 240
9 338000 336
9 338000 288
9 338000 384
9 338000 768
9 338000 672
9 338000 306
9 338000 200
6 338000 708
6 338000 497
40 338000 48
40 338000 48
40 338000 48
40 338000 48
74 338000 48
116 338000 48
nal Seluruh
Kebutuhan Besi Balok 12 meter Kebutuhan Total Harga
Buah Buah Rp
4 3680 IDR 1,243,840,000
2 22 IDR 7,436,000
11 121 IDR 40,898,000
2 22 IDR 7,436,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
2 21 IDR 7,250,100
11 121 IDR 40,898,000
19 209 IDR 70,642,000
19 209 IDR 70,642,000
19 209 IDR 70,642,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
2 22 IDR 7,436,000
11 121 IDR 40,898,000
2 22 IDR 7,436,000
4 44 IDR 14,872,000
6 61 IDR 20,449,000
56 504 IDR 170,352,000
20 180 IDR 60,840,000
28 252 IDR 85,176,000
24 216 IDR 73,008,000
32 288 IDR 97,344,000
64 576 IDR 194,688,000
56 504 IDR 170,352,000
26 230 IDR 77,571,000
17 150 IDR 50,801,400
59 354 IDR 119,652,000
41 248 IDR 83,959,200
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 296 IDR 100,048,000
4 1392 IDR 470,496,000

IDR 4,562,036,700
Rencana Anggaran Biaya Tulangan Transversal Seluruh
Struktur Kolom
Sengkang
Total Panjang Kolom
Total Sengkang 1 Kolom/4 meter
Total Sengkang Hingga Atas
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-13/Batang
Rencana Anggaran Biaya 1 Kolom
Total Keseluruhan Kolom
Confinement
Total confinement 1 Kolom/4 meter
Total confinement Hingga Atas
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-13/Batang
Rencana Anggaran Biaya 1 Kolom
Total Keseluruhan Kolom
Struktur Balok B1
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Struktur Balok B2
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Struktur Balok B3
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Total
sal Seluruh
Tulangan Tumpuan
Kebutuhan Tulangan per 4 Meter
48 Segmen 1 Arah X
57 Total Segmen 1 X
684 Kebutuhan Tulangan Segmen 1 Arah X
1.04 Kebutuhan Tulangan per 4 Meter
711 Segmen 1 Arah Y
59 Total Segmen 1 Y
IDR 118,000 Kebutuhan Tulangan Segmen 1 Arah X
IDR 6,995,040 Harga Tulangan D-13/Batang
IDR 643,543,680 Kebutuhan Tulangan/batang X
Kebutuhan Tulangan/batang Y
114 Rencana Anggaran Biaya 1 Lantai X
1368 Rencana Anggaran Biaya 1 Lantai Y
1.04 Total Rencana Anggaran Biaya X
1423 Total Rencana Anggaran Biaya Y
119 Tulangan Lapangan
IDR 118,000 Kebutuhan Tulangan per 4 Meter
IDR 13,990,080 Segmen 1 Arah X
IDR 1,287,087,360 Total Segmen 1 X
Kebutuhan Tulangan Segmen 1 Arah X
363 Kebutuhan Tulangan per 4 Meter
27 Segmen 1 Arah Y
2451 Total Segmen 1 Y
1.14 Kebutuhan Tulangan Segmen 1 Arah X
2794 Harga Tulangan D-13/Batang
233 Kebutuhan Tulangan/batang X
IDR 69,000 Kebutuhan Tulangan/batang Y
IDR 16,063,601 Rencana Anggaran Biaya 1 Lantai X
IDR 192,763,213 Rencana Anggaran Biaya 1 Lantai Y
Total Rencana Anggaran Biaya X
322 Total Rencana Anggaran Biaya Y
23 Tulangan Bagi
1853 Kebutuhan Tulangan per 4 Meter
0.94 Segmen 1 Arah X
1741 Total Segmen 1 X
145 Kebutuhan Tulangan Segmen 1 Arah X
IDR 69,000 Kebutuhan Tulangan per 4 Meter
IDR 10,013,573 Segmen 1 Arah Y
IDR 120,162,879 Total Segmen 1 Y
Kebutuhan Tulangan Segmen 1 Arah X
100 Harga Tulangan D-13/Batang
25 Kebutuhan Tulangan/batang X
628 Kebutuhan Tulangan/batang Y
0.69 Rencana Anggaran Biaya 1 Lantai X
433 Rencana Anggaran Biaya 1 Lantai Y
36 Total Rencana Anggaran Biaya X
IDR 69,000 Total Rencana Anggaran Biaya Y
IDR 2,489,606 Total
IDR 29,875,275
IDR 2,273,432,407
Struktur Pelat Lantai
Tulangan Tumpuan
27 Kebutuhan Tulangan per 4 Meter 27
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
197 Kebutuhan Tulangan Segmen 2 Arah X 92
27 Kebutuhan Tulangan per 4 Meter 27
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
127 Kebutuhan Tulangan Segmen 2 Arah X 127
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
16 Kebutuhan Tulangan/batang X 8
11 Kebutuhan Tulangan/batang Y 11
IDR 1,933,889 Rencana Anggaran Biaya 1 Lantai X IDR 904,667
IDR 1,245,556 Rencana Anggaran Biaya 1 Lantai Y IDR 1,245,556
IDR 23,206,667 Total Rencana Anggaran Biaya X IDR 10,856,000
IDR 14,946,667 Total Rencana Anggaran Biaya Y IDR 14,946,667
Tulangan Lapangan
13 Kebutuhan Tulangan per 4 Meter 13
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
98 Kebutuhan Tulangan Segmen 2 Arah X 46
13 Kebutuhan Tulangan per 4 Meter 13
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
63 Kebutuhan Tulangan Segmen 1 Arah X 63
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
8 Kebutuhan Tulangan/batang X 4
5 Kebutuhan Tulangan/batang Y 5
IDR 966,944 Rencana Anggaran Biaya 1 Lantai X IDR 452,333
IDR 622,778 Rencana Anggaran Biaya 1 Lantai Y IDR 622,778
IDR 11,603,333 Total Rencana Anggaran Biaya X IDR 5,428,000
IDR 7,473,333 Total Rencana Anggaran Biaya Y IDR 7,473,333
Tulangan Bagi
10 Kebutuhan Tulangan per 4 Meter 10
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
74 Kebutuhan Tulangan Segmen 2 Arah X 35
10 Kebutuhan Tulangan per 4 Meter 10
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
48 Kebutuhan Tulangan Segmen 1 Arah X 48
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
6 Kebutuhan Tulangan/batang X 3
4 Kebutuhan Tulangan/batang Y 4
IDR 725,208 Rencana Anggaran Biaya 1 Lantai X IDR 339,250
IDR 467,083 Rencana Anggaran Biaya 1 Lantai Y IDR 467,083
IDR 8,702,500 Total Rencana Anggaran Biaya X IDR 4,071,000
IDR 5,605,000 Total Rencana Anggaran Biaya Y IDR 5,605,000
Tulangan Tumpuan
Kebutuhan Tulangan per 4 Meter 27
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 138
Kebutuhan Tulangan per 4 Meter 27
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 127
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 12
Kebutuhan Tulangan/batang Y 11
Rencana Anggaran Biaya 1 Lantai X IDR 1,357,000
Rencana Anggaran Biaya 1 Lantai Y IDR 1,245,556
Total Rencana Anggaran Biaya X IDR 16,284,000
Total Rencana Anggaran Biaya Y IDR 14,946,667
Tulangan Lapangan
Kebutuhan Tulangan per 4 Meter 13
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 69
Kebutuhan Tulangan per 4 Meter 13
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 63
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 6
Kebutuhan Tulangan/batang Y 5
Rencana Anggaran Biaya 1 Lantai X IDR 678,500
Rencana Anggaran Biaya 1 Lantai Y IDR 622,778
Total Rencana Anggaran Biaya X IDR 8,142,000
Total Rencana Anggaran Biaya Y IDR 7,473,333
Tulangan Bagi
Kebutuhan Tulangan per 4 Meter 10
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 52
Kebutuhan Tulangan per 4 Meter 10
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 48
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 4
Kebutuhan Tulangan/batang Y 4
Rencana Anggaran Biaya 1 Lantai X IDR 508,875
Rencana Anggaran Biaya 1 Lantai Y IDR 467,083
Total Rencana Anggaran Biaya X IDR 6,106,500
Total Rencana Anggaran Biaya Y IDR 5,605,000
IDR 178,475,000
Data AHSP 1M3 BETON READY
b 600 mm 0.6 m
Kolom K1 NO URAIAN KODE SATUAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2 3 4
Kolom K2
h 600 mm 0.6 m A Tenaga Kerja
b 500 mm 0.5 m 1 Pekerja L.01 OH
Balok B50/80
h 800 mm 0.8 m 2 Tukang Batu L.02 OH
b 400 mm 0.4 m 3 Kepala Tukang L.03 OH
Balok B40/70
h 700 mm 0.7 m 4 Mandor L.04 OH
b 350 mm 0.35 m JUMLAH HARGA TENAGA KERJA
Balok B35/50
h 500 mm 0.5 m B Bahan Campuran Beton
Lantai h 150 mm 0.15 m 1 Ready Mixed M.09.x m3
Atap h 130 mm 0.13 m JUMLAH HARGA HARGA BAHAN
b 400 mm 0.4 m C Pompa dan Conveyor Beton E.35 m3
Shear Wall
h 400 mm 0.4 m JUMLAH HARGA HARGA PERALATAN
b 400 mm 0.4 m D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
Core Wall
h 400 mm 0.4 m E Overhead + Profit
F Harga Satuan Pekerjaan per-m3 (D+E)
P 1M3 BETON READY MIXED Renc
HARGA SATUAN JUMLAH HARGA Struktur
KOEFISIEN
Rp Rp
Komponen Struktur Ketengan
5 6 7
Segmen 1
1 IDR 135,500 IDR 135,500 Pelat Lantai Segmen 2
0.25 IDR 155,800 IDR 38,950 Segmen 3
0.025 IDR 164,052 IDR 4,101 as A (1-2)
0.1 IDR 183,200 IDR 18,320 as A (3-6)
A TENAGA KERJA IDR 196,871 as A (7-8)
as B
1.02 IDR 1,310,000 IDR 1,336,200 as C
IDR 1,336,200 as D
0.12 IDR 10,400 IDR 1,248 as E
IDR 1,248 as F
eralatan (A+B+C) IDR 1,534,319 as G
15% x D IDR 230,147.90 as I to Core
IDR 1,764,467.20 as I (2-5)
Balok B50/80 (Y)
as J (2-7)
as K (2-7)
as L (2-7)
as M
as N
as O
as P
as Q
as R (1-2)
as R (3-6)
as R (7-8)
SW X
Balok B50/80 X
CORE
as 7 (B-Q)
as 6 (B-G)
as 6 (J-Q)
as 5 (A-G)
Balok 40/70 as 5 (J-R)
as 4
as 3 (B-Q)
as 2 (B-I)
as 2 (M-Q)
as A-I
Balok 35/50
as M-R
Kolom K1
SW1
SW2
Shear Wall SW3
SW4
SW5
Arah X
Core Wall
Arah Y
Total 1 Lantai
Total Rencana Anggaran Biaya Pekerjaan B
Rencana Anggaran Pekerjaan Beton

Panjang Lebar Tinggi Volume Total Biaya


Jumlah Harga Satuan Pekerjaan m3
(m) (m) (m) (m3) Rp
29.5 19 0.15 1 84.075 IDR 1,764,467.20 IDR 148,347,579
13.8 19 0.15 1 39.33 IDR 1,764,467.20 IDR 69,396,495
20.7 19 0.15 1 58.995 IDR 1,764,467.20 IDR 104,094,742
2 0.5 0.8 1 0.8 IDR 1,764,467.20 IDR 1,411,574
11 0.5 0.8 1 4.4 IDR 1,764,467.20 IDR 7,763,656
2 0.5 0.8 1 0.8 IDR 1,764,467.20 IDR 1,411,574
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
1.95 0.5 0.8 1 0.78 IDR 1,764,467.20 IDR 1,376,284
11 0.5 0.8 1 4.4 IDR 1,764,467.20 IDR 7,763,656
19 0.5 0.8 1 7.6 IDR 1,764,467.20 IDR 13,409,951
19 0.5 0.8 1 7.6 IDR 1,764,467.20 IDR 13,409,951
19 0.5 0.8 1 7.6 IDR 1,764,467.20 IDR 13,409,951
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
23 0.5 0.8 1 9.2 IDR 1,764,467.20 IDR 16,233,098
2 0.5 0.8 1 0.8 IDR 1,764,467.20 IDR 1,411,574
11 0.5 0.8 1 4.4 IDR 1,764,467.20 IDR 7,763,656
2 0.5 0.8 1 0.8 IDR 1,764,467.20 IDR 1,411,574
4 0.5 0.8 1 1.6 IDR 1,764,467.20 IDR 2,823,148
5.5 0.5 0.8 1 2.2 IDR 1,764,467.20 IDR 3,881,828
56 0.4 0.7 1 15.68 IDR 1,764,467.20 IDR 27,666,846
20 0.4 0.7 1 5.6 IDR 1,764,467.20 IDR 9,881,016
28 0.4 0.7 1 7.84 IDR 1,764,467.20 IDR 13,833,423
24 0.4 0.7 1 6.72 IDR 1,764,467.20 IDR 11,857,220
32 0.4 0.7 1 8.96 IDR 1,764,467.20 IDR 15,809,626
64 0.4 0.7 1 17.92 IDR 1,764,467.20 IDR 31,619,252
56 0.4 0.7 1 15.68 IDR 1,764,467.20 IDR 27,666,846
25.5 0.4 0.7 1 7.14 IDR 1,764,467.20 IDR 12,598,296
16.7 0.4 0.7 1 4.676 IDR 1,764,467.20 IDR 8,250,649
29.5 0.35 0.5 2 5.1625 IDR 1,764,467.20 IDR 18,218,124
20.7 0.35 0.5 2 3.6225 IDR 1,764,467.20 IDR 12,783,565
0.6 0.6 4 92 1.44 IDR 1,764,467.20 IDR 233,756,614
4 0.4 4 1 6.4 IDR 1,764,467.20 IDR 11,292,590
4 0.4 4 1 6.4 IDR 1,764,467.20 IDR 11,292,590
4 0.4 4 1 6.4 IDR 1,764,467.20 IDR 11,292,590
4 0.4 4 1 6.4 IDR 1,764,467.20 IDR 11,292,590
8 0.4 4 1 12.8 IDR 1,764,467.20 IDR 22,585,180
2.85 0.4 4 3 4.56 IDR 1,764,467.20 IDR 24,137,911
6 0.4 4 1 9.6 IDR 1,764,467.20 IDR 16,938,885
IDR 1,110,425,082
ran Biaya Pekerjaan Beton IDR 13,325,100,984
Data LIST TULANGAN
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN P

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KER
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)

KEBUTUHAN TULANGA
Tulangan Tumpuan
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
Tulangan Lapangan
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
Tulangan Bagi
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 338000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-19 2.23 26.76 253000
D-10 0.617 7.404 100000
D-13 1.04 12.48 118000
D-25 3.85 46.2 439000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-13 2.23 26.76 118000

AHSP PEMBESIAN PELAT 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 0.7 IDR 135,500 IDR 94,850


OH 0.7 IDR 170,500 IDR 119,350
OH 0.07 IDR 170,500 IDR 11,935
OH 0.07 IDR 183,200 IDR 12,824
AH HARGA TENAGA KERJA IDR 238,959

Kg 105 IDR 118,000 IDR 12,390,000


Kg 1.5 IDR 26,000 IDR 39,000
IDR 12,390,000
an Peralatan (A+B) IDR 12,628,959
15% x D IDR 1,894,344
g (D+E) IDR 14,523,303

KEBUTUHAN TULANGAN PELAT LANTAI

7
7

3
3
3
3
BERAT BESI TULANGAN
Diameter Polos Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Struktur
Panjang Jenis Tulangan Arah Kebutuhan Tulangan
Komponen Struktur Ketengan
(m) (Buah)
29.5 Tumpuan X 6.667
19 Tumpuan Y 6.667
29.5 Lapangan X 3.333
Segmen 1
19 Lapangan Y 3.333
29.5 Bagi X 2.500
19 Bagi Y 2.500
13.8 Tumpuan X 6.667
19 Tumpuan Y 6.667
13.8 Lapangan X 3.333
Pelat Lantai Segmen 2
19 Lapangan Y 3.333
13.8 Bagi X 2.500
19 Bagi Y 2.500
20.7 Tumpuan X 6.667
19 Tumpuan Y 6.667
20.7 Lapangan X 3.333
Segmen 3
19 Lapangan Y 3.333
20.7 Bagi X 2.500
19 Bagi Y 2.500
Total 1 Lantai
Total Keseluruhan
Polos

0.222
0.395
0.617
0.888
-
1.58
2.23
2.98
3.85
5.18
6.31
7.99
9.88

Detail Pekerjaan Struktur Pelat Lantai

Kebutuhan Tulangan per meter Berat 1 Batang Tulangan Kebutuhan Tulangan Segmen
(Aktual) (Kg) (Buah)
7 1.04 206.500
7 1.04 133.000
4 1.04 118.000
4 1.04 76.000
3 1.04 88.500
3 1.04 57.000
7 1.04 96.600
7 1.04 133.000
4 1.04 55.200
4 1.04 76.000
3 1.04 41.400
3 1.04 57.000
7 1.04 144.900
7 1.04 133.000
4 1.04 82.800
4 1.04 76.000
3 1.04 62.100
3 1.04 57.000
ur Pelat Lantai

Kebutuhan Tulangan Segmen Kebutuhan Tulangan Total Kebutuhan Tulangan Total


(Aktual) (buah) (Aktual)
207 17.250 18
133 11.083 12
118 9.833 10
76 6.333 7
89 7.417 8
57 4.750 5
98 8.167 9
133 11.083 12
56 4.667 5
76 6.333 7
42 3.500 4
57 4.750 5
145 12.083 13
133 11.083 12
83 6.917 7
76 6.333 7
63 5.250 6
57 4.750 5
Berat Total Berat Aktual Rencana Anggaran Biaya
(Kg) (Kg) (Rp)
18.720 19 IDR 2,759,428
12.480 13 IDR 1,888,029
10.400 11 IDR 1,597,563
7.280 8 IDR 1,161,864
8.320 9 IDR 1,307,097
5.200 6 IDR 871,398
9.360 10 IDR 1,452,330
12.480 13 IDR 1,888,029
5.200 6 IDR 871,398
7.280 8 IDR 1,161,864
4.160 5 IDR 726,165
5.200 6 IDR 871,398
13.520 14 IDR 2,033,262
12.480 13 IDR 1,888,029
7.280 8 IDR 1,161,864
7.280 8 IDR 1,161,864
6.240 7 IDR 1,016,631
5.200 6 IDR 871,398
IDR 24,689,615
IDR 296,275,378
Data LIST TULANGAN
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LON

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KER
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Kolom

AHSP PEMBESIAN TULANGAN TRANSVERSA


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KER
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Kolom
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

BESIAN TULANGAN LONGITUDINAL KOLOM 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 338,000 IDR 35,490,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 35,490,000
an Peralatan (A+B) IDR 36,075,592
15% x D IDR 5,411,339
g (D+E) IDR 41,486,931
m 10

ULANGAN TRANSVERSAL DAN CONFINEMENT KOLOM 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
an Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
g (D+E) IDR 14,921,931
m 10
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulang


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) Lantai (Kg)
Kolom Longitudinal 0.6 0.6 12 92 2.98

Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Kolom Transversal 0.6 0.6 48 92 1.04
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Kolom Transversal 0.6 0.6 48 92 1.04
Rencana Anggaran Tulangan Longitudinal Kolom

Kebutuhan Tulangan 1 Lantai Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
0.833 10 29.8

Rencana Anggaran Tulangan Transversal Kolom


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
1.240 480 595.2

Rencana Anggaran Tulangan Confinement Kolom


Panjang Total Confinement Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
2.880 480 1382.4
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
30 IDR 1,145,039,290

ansversal Kolom
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
596 49.667 50 52

finement Kolom
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
1383 115.250 116 120.64
Rencana Anggaran Biaya
(Rp)
IDR 713,865,169
Rencana Anggaran Biaya
(Rp)
IDR 1,656,167,193
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LON

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
AHSP PEMBESIAN TULANGAN TRA
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1

AHSP PEMBESIAN TULANGAN

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

BESIAN TULANGAN LONGITUDINAL BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 253,000 IDR 26,565,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 26,565,000
n Peralatan (A+B) IDR 27,150,592
15% x D IDR 4,072,589
(D+E) IDR 31,223,181
B1 11
2
BESIAN TULANGAN TRANSVERSAL BALOK 100 Kg
HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 100,000 IDR 10,500,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 10,500,000
n Peralatan (A+B) IDR 11,085,592
15% x D IDR 1,662,839
(D+E) IDR 12,748,431
B1 11
2

PEMBESIAN TULANGAN TORSI BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931
B1 11
2
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulan


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A (1-2) 2 0.5 0.8 1 2.23
as A (3-6) 11 0.5 0.8 1 2.23
as A (7-8) 2 0.5 0.8 1 2.23
as B 23 0.5 0.8 1 2.23
as C 23 0.5 0.8 1 2.23
as D 23 0.5 0.8 1 2.23
as E 23 0.5 0.8 1 2.23
as F 23 0.5 0.8 1 2.23
as G 23 0.5 0.8 1 2.23
as I to Core 1.95 0.5 0.8 1 2.23
as I (2-5) 11 0.5 0.8 1 2.23
as J (2-7) 19 0.5 0.8 1 2.23
Balok B1
as K (2-7) 19 0.5 0.8 1 2.23
as L (2-7) 19 0.5 0.8 1 2.23
as M 23 0.5 0.8 1 2.23
as N 23 0.5 0.8 1 2.23
as O 23 0.5 0.8 1 2.23
as P 23 0.5 0.8 1 2.23
as Q 23 0.5 0.8 1 2.23
as R (1-2) 2 0.5 0.8 1 2.23
as R (3-6) 11 0.5 0.8 1 2.23
as R (7-8) 2 0.5 0.8 1 2.23
SW X 4 0.5 0.8 1 2.23
CORE 5.5 0.5 0.8 1 2.23
Total 1 Lantai
Total Keseluruhan

Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A (1-2) 2 0.5 0.8 1 0.617
as A (3-6) 11 0.5 0.8 1 0.617
as A (7-8) 2 0.5 0.8 1 0.617
as B 23 0.5 0.8 1 0.617
as C 23 0.5 0.8 1 0.617
as D 23 0.5 0.8 1 0.617
as E 23 0.5 0.8 1 0.617
as F 23 0.5 0.8 1 0.617
as G 23 0.5 0.8 1 0.617
as I to Core 1.95 0.5 0.8 1 0.617
as I (2-5) 11 0.5 0.8 1 0.617
as J (2-7) 19 0.5 0.8 1 0.617
Balok B1
as K (2-7) 19 0.5 0.8 1 0.617
as L (2-7) 19 0.5 0.8 1 0.617
as M 23 0.5 0.8 1 0.617
as N 23 0.5 0.8 1 0.617
as O 23 0.5 0.8 1 0.617
as P 23 0.5 0.8 1 0.617
as Q 23 0.5 0.8 1 0.617
as R (1-2) 2 0.5 0.8 1 0.617
as R (3-6) 11 0.5 0.8 1 0.617
as R (7-8) 2 0.5 0.8 1 0.617
SW X 4 0.5 0.8 1 0.617
CORE 5.5 0.5 0.8 1 0.617
Total 1 Lantai
Total Keseluruhan

Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A (1-2) 2 0.5 0.8 1 1.04
as A (3-6) 11 0.5 0.8 1 1.04
as A (7-8) 2 0.5 0.8 1 1.04
as B 23 0.5 0.8 1 1.04
as C 23 0.5 0.8 1 1.04
as D 23 0.5 0.8 1 1.04
as E 23 0.5 0.8 1 1.04
as F 23 0.5 0.8 1 1.04
as G 23 0.5 0.8 1 1.04
as I to Core 1.95 0.5 0.8 1 1.04
as I (2-5) 11 0.5 0.8 1 1.04
as J (2-7) 19 0.5 0.8 1 1.04
Balok B1
as K (2-7) 19 0.5 0.8 1 1.04
as L (2-7) 19 0.5 0.8 1 1.04
as M 23 0.5 0.8 1 1.04
as N 23 0.5 0.8 1 1.04
as O 23 0.5 0.8 1 1.04
as P 23 0.5 0.8 1 1.04
as Q 23 0.5 0.8 1 1.04
as R (1-2) 2 0.5 0.8 1 1.04
as R (3-6) 11 0.5 0.8 1 1.04
as R (7-8) 2 0.5 0.8 1 1.04
SW X 4 0.5 0.8 1 1.04
CORE 5.5 0.5 0.8 1 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok

Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
0.917 1.833 4.088
0.917 10.083 22.486
0.917 1.833 4.088
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 1.788 3.986
0.917 10.083 22.486
0.917 17.417 38.839
0.917 17.417 38.839
0.917 17.417 38.839
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 21.083 47.016
0.917 1.833 4.088
0.917 10.083 22.486
0.917 1.833 4.088
0.917 3.667 8.177
0.917 5.042 11.243

Rencana Anggaran Tulangan Transversal Balok


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
1.340 23.529 31.529
1.340 129.412 173.412
1.340 23.529 31.529
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 22.941 30.741
1.340 129.412 173.412
1.340 223.529 299.529
1.340 223.529 299.529
1.340 223.529 299.529
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 270.588 362.588
1.340 23.529 31.529
1.340 129.412 173.412
1.340 23.529 31.529
1.340 47.059 63.059
1.340 64.706 86.706

Rencana Anggaran Tulangan Torsi Balok

Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
0.167 0.333 0.347
0.167 1.833 1.907
0.167 0.333 0.347
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 0.325 0.338
0.167 1.833 1.907
0.167 3.167 3.293
0.167 3.167 3.293
0.167 3.167 3.293
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 3.833 3.987
0.167 0.333 0.347
0.167 1.833 1.907
0.167 0.333 0.347
0.167 0.667 0.693
0.167 0.917 0.953
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
6 IDR 1,873,391
31 IDR 9,679,186
6 IDR 1,873,391
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
6 IDR 1,873,391
31 IDR 9,679,186
52 IDR 16,236,054
52 IDR 16,236,054
52 IDR 16,236,054
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
63 IDR 19,670,604
6 IDR 1,873,391
31 IDR 9,679,186
6 IDR 1,873,391
11 IDR 3,434,550
16 IDR 4,995,709
IDR 311,919,576
IDR 3,743,034,914

ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
32 2.667 3 1.851
174 14.500 15 9.255
32 2.667 3 1.851
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
31 2.583 3 1.851
174 14.500 15 9.255
300 25.000 25 15.425
300 25.000 25 15.425
300 25.000 25 15.425
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
32 2.667 3 1.851
174 14.500 15 9.255
32 2.667 3 1.851
64 5.333 6 3.702
87 7.250 8 4.936

Berat Aktual Rencana Anggaran Biaya


(Kg) (Rp)
1 IDR 312,232
2 IDR 624,464
1 IDR 312,232
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
1 IDR 312,232
2 IDR 624,464
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
4 IDR 1,248,927
1 IDR 312,232
2 IDR 624,464
1 IDR 312,232
1 IDR 312,232
1 IDR 312,232
IDR 21,543,995
IDR 258,527,937
Rencana Anggaran Biaya
(Rp)
IDR 235,973
IDR 1,179,867
IDR 235,973
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 235,973
IDR 1,179,867
IDR 1,966,445
IDR 1,966,445
IDR 1,966,445
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 2,438,392
IDR 235,973
IDR 1,179,867
IDR 235,973
IDR 471,947
IDR 629,263
IDR 38,542,331
IDR 462,507,970
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LON

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1

AHSP PEMBESIAN TULANGAN TRA


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1

AHSP PEMBESIAN TULANGAN


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

BESIAN TULANGAN LONGITUDINAL BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 253,000 IDR 26,565,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 26,565,000
n Peralatan (A+B) IDR 27,150,592
15% x D IDR 4,072,589
(D+E) IDR 31,223,181
B1 9
2

BESIAN TULANGAN TRANSVERSAL BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 100,000 IDR 10,500,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 10,500,000
n Peralatan (A+B) IDR 11,085,592
15% x D IDR 1,662,839
(D+E) IDR 12,748,431
B1 11
2

PEMBESIAN TULANGAN TORSI BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931
B1 11
2
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulan


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as 7 (B-Q) 56 0.4 0.7 1 2.23
as 6 (B-G) 20 0.4 0.7 1 2.23
as 6 (J-Q) 28 0.4 0.7 1 2.23
as 5 (A-G) 24 0.4 0.7 1 2.23
Balok B2 as 5 (J-R) 32 0.4 0.7 1 2.23
as 4 64 0.4 0.7 1 2.23
as 3 (B-Q) 56 0.4 0.7 1 2.23
as 2 (B-I) 25.5 0.4 0.7 1 2.23
as 2 (M-Q) 16.7 0.4 0.7 1 2.23
Total 1 Lantai
Total Keseluruhan

Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as 7 (B-Q) 56 0.4 0.7 1 0.617
as 6 (B-G) 20 0.4 0.7 1 0.617

Balok B2
as 6 (J-Q) 28 0.4 0.7 1 0.617
as 5 (A-G) 24 0.4 0.7 1 0.617
Balok B2 as 5 (J-R) 32 0.4 0.7 1 0.617
as 4 64 0.4 0.7 1 0.617
as 3 (B-Q) 56 0.4 0.7 1 0.617
as 2 (B-I) 25.5 0.4 0.7 1 0.617
as 2 (M-Q) 16.7 0.4 0.7 1 0.617
Total 1 Lantai
Total Keseluruhan

Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Balok B2 as 7 (B-Q) 56 0.4 0.7 1 1.04
as 6 (B-G) 20 0.4 0.7 1 1.04
as 6 (J-Q) 28 0.4 0.7 1 1.04
as 5 (A-G) 24 0.4 0.7 1 1.04
as 5 (J-R) 32 0.4 0.7 1 1.04
as 4 64 0.4 0.7 1 1.04
as 3 (B-Q) 56 0.4 0.7 1 1.04
as 2 (B-I) 25.5 0.4 0.7 1 1.04
as 2 (M-Q) 16.7 0.4 0.7 1 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok

Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
0.750 42.000 93.660
0.750 15.000 33.450
0.750 21.000 46.830
0.750 18.000 40.140
0.750 24.000 53.520
0.750 48.000 107.040
0.750 42.000 93.660
0.750 19.125 42.649
0.750 12.525 27.931

Rencana Anggaran Tulangan Transversal Balok


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
1.140 560.000 638.400
1.140 200.000 228.000
1.140 280.000 319.200
1.140 240.000 273.600
1.140 320.000 364.800
1.140 640.000 729.600
1.140 560.000 638.400
1.140 255.000 290.700
1.140 167.000 190.380

Rencana Anggaran Tulangan Torsi Balok


Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total
(Buah) (Buah) (Kg)
0.167 9.333 9.707
0.167 3.333 3.467
0.167 4.667 4.853
0.167 4.000 4.160
0.167 5.333 5.547
0.167 10.667 11.093
0.167 9.333 9.707
0.167 4.250 4.420
0.167 2.783 2.895
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
94 IDR 29,349,790
34 IDR 10,615,881
47 IDR 14,674,895
41 IDR 12,801,504
54 IDR 16,860,518
108 IDR 33,721,035
94 IDR 29,349,790
43 IDR 13,425,968
28 IDR 8,742,491
IDR 169,541,872
IDR 2,034,502,461

ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
639 53.250 54 33.318
228 19.000 19 11.723
320 26.667 27 16.659
274 22.833 23 14.191
365 30.417 31 19.127
730 60.833 61 37.637
639 53.250 54 33.318
291 24.250 25 15.425
191 15.917 16 9.872

Berat Aktual Rencana Anggaran Biaya


(Kg) (Rp)
10 IDR 3,122,318
4 IDR 1,248,927
5 IDR 1,561,159
5 IDR 1,561,159
6 IDR 1,873,391
12 IDR 3,746,782
10 IDR 3,122,318
5 IDR 1,561,159
3 IDR 936,695
IDR 18,733,908
IDR 224,806,902
Rencana Anggaran Biaya
(Rp)
IDR 4,247,522
IDR 1,494,499
IDR 2,123,761
IDR 1,809,130
IDR 2,438,392
IDR 4,798,127
IDR 4,247,522
IDR 1,966,445
IDR 1,258,525
IDR 24,383,924
IDR 292,607,083
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LON

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1

AHSP PEMBESIAN TULANGAN TRA


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1

AHSP PEMBESIAN TULANGAN


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

BESIAN TULANGAN LONGITUDINAL BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 253,000 IDR 26,565,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 26,565,000
n Peralatan (A+B) IDR 27,150,592
15% x D IDR 4,072,589
(D+E) IDR 31,223,181
B1 7
2

BESIAN TULANGAN TRANSVERSAL BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 100,000 IDR 10,500,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 10,500,000
n Peralatan (A+B) IDR 11,085,592
15% x D IDR 1,662,839
(D+E) IDR 12,748,431
B1 11
2

PEMBESIAN TULANGAN TORSI BALOK 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931
B1 11
2
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulan


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A-I 29.5 0.35 0.5 2 2.23
Balok B3
as M-R 20.7 0.35 0.5 2 2.23
Total 1 Lantai
Total Keseluruhan

Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A-I 29.5 0.35 0.5 2 0.617
Balok B3
as M-R 20.7 0.35 0.5 2 0.617
Total 1 Lantai
Total Keseluruhan

Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A-I 29.5 0.35 0.5 2 1.04
Balok B3
as M-R 20.7 0.35 0.5 2 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok

Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
0.583 17.208 38.375
0.583 12.075 26.927

Rencana Anggaran Tulangan Transversal Balok


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
0.890 295.000 262.550
0.890 207.000 184.230
Rencana Anggaran Tulangan Torsi Balok
Kebutuhan Tulangan 1 Balok Kebutuhan Tulangan Total Berat Total
(Buah) (Buah) (Kg)
0.167 4.917 5.113
0.167 3.450 3.588
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
39 IDR 24,354,081
27 IDR 16,860,518
IDR 41,214,599
IDR 494,575,184

ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
263 21.917 22 13.574
185 15.417 16 9.872
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
6 IDR 3,746,782
4 IDR 2,497,854
IDR 6,244,636
IDR 74,935,634
Rencana Anggaran Biaya
(Rp)
IDR 3,460,944
IDR 2,517,050
IDR 5,977,994
IDR 71,735,930
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LONGI

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Shear Wall

AHSP PEMBESIAN TULANGAN TRANS


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)

AHSP PEMBESIAN TULANGAN TRANSVERSAL D


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

IAN TULANGAN LONGITUDINAL SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 439,000 IDR 46,095,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 46,095,000
n Peralatan (A+B) IDR 46,680,592
15% x D IDR 7,002,089
(D+E) IDR 53,682,681
Wall 40

SIAN TULANGAN TRANSVERSAL SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931

NGAN TRANSVERSAL DAN CONFINEMENT SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulanga


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) Lantai (Kg)
Shear Wall Arah Y SW Y 4 0.4 12 4 3.85

R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah Y SW Y 4 0.4 48 4 1.04
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah Y SW Y 4 0.4 48 4 1.04
ncana Anggaran Tulangan Longitudinal Shear Wall

Kebutuhan Tulangan 1 Dinding Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
3.333 40.000 154.000

Rencana Anggaran Tulangan Transversal Shear Wall


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
4.440 480.000 2131.200
Rencana Anggaran Tulangan Confinement Shear Wall
Panjang Total Confinement Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
4.160 480 1996.8
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
154 IDR 330,685,314

versal Shear Wall


Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
2132 177.667 178 185.12
ement Shear Wall
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
1383 115.250 116 120.64
Rencana Anggaran Biaya
(Rp)
IDR 110,493,913
Rencana Anggaran Biaya
(Rp)
IDR 72,007,269
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LONGI

NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Shear Wall

AHSP PEMBESIAN TULANGAN TRANS


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)

AHSP PEMBESIAN TULANGAN TRANSVERSAL D


NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000

IAN TULANGAN LONGITUDINAL SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 439,000 IDR 46,095,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 46,095,000
n Peralatan (A+B) IDR 46,680,592
15% x D IDR 7,002,089
(D+E) IDR 53,682,681
Wall 74

SIAN TULANGAN TRANSVERSAL SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931

NGAN TRANSVERSAL DAN CONFINEMENT SHEAR WALL 100 Kg


HARGA SATUAN JUMLAH HARGA
SATUAN KOEFISIEN
Rp Rp
4 5 6 7

OH 2.1 IDR 135,500 IDR 284,550


OH 1.4 IDR 170,500 IDR 238,700
OH 0.14 IDR 170,500 IDR 23,870
OH 0.21 IDR 183,200 IDR 38,472
AH HARGA TENAGA KERJA IDR 585,592

Kg 105 IDR 118,000 IDR 12,390,000


Kg 2.1 IDR 26,000 IDR 54,600
IDR 12,390,000
n Peralatan (A+B) IDR 12,975,592
15% x D IDR 1,946,339
(D+E) IDR 14,921,931
BERAT BESI TULANGAN
Diameter Ulir Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88

Rencana Anggaran Tulanga


Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) Lantai (Kg)
Shear Wall Arah X SW X 8 0.4 12 1 3.85

R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah X SW X 8 0.4 48 1 1.04
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah X SW X 8 0.4 48 1 1.04
ncana Anggaran Tulangan Longitudinal Shear Wall

Kebutuhan Tulangan 1 Dinding Kebutuhan Tulangan Total Berat Total


(Buah) (Buah) (Kg)
6.167 74.000 284.900

Rencana Anggaran Tulangan Transversal Shear Wall


Keliling Sengkang Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
8.440 480.000 4051.200
Rencana Anggaran Tulangan Confinement Shear Wall
Panjang Total Confinement Kebutuhan Sengkang Total Panjang Tulangan
(m) (Buah) (Buah)
5.200 480 2496
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
285 IDR 152,995,640

versal Shear Wall


Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
4052 337.667 338 351.52
ement Shear Wall
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
2496 208.000 208 216.32
Rencana Anggaran Biaya
(Rp)
IDR 52,453,571
Rencana Anggaran Biaya
(Rp)
IDR 32,279,121
Rekapitulasi Perhitungan Rencana Anggaran Biaya Struktur
No Struktur Jenis Pekerjaan Biaya
Pekerjaan Beton IDR 3,862,065,796
1 Pelat Lantai
Pekerjaan Pembesian IDR 296,275,378
Pekerjaan Beton IDR 2,805,079,368
Pekerjaan Pembesian
2 Kolom Longitudinal IDR 1,145,039,290
Transversal IDR 713,865,169
Confinement IDR 1,656,167,193
Balok B1
Pekerjaan Beton IDR 3,069,749,447
Pekerjaan Pembesian
Longitudinal IDR 3,743,034,914
Transversal IDR 462,507,970
Torsi IDR 258,527,937
Balok B2
Pekerjaan Beton IDR 1,910,198,070
Pekerjaan Pembesian
3 Balok
Longitudinal IDR 2,034,502,461
Transversal IDR 292,607,083
Torsi IDR 224,806,902
Balok B3
Pekerjaan Beton IDR 372,020,263
Pekerjaan Pembesian
Longitudinal IDR 494,575,184
Transversal IDR 71,735,930
Torsi 74935634
SW arah Y
Pekerjaan Beton IDR 542,044,322
Pekerjaan Pembesian
Longitudinal IDR 330,685,314
Transversal IDR 110,493,913
Confinement IDR 72,007,269
4 Shear Wall
SW arah X
Pekerjaan Beton IDR 492,921,556
Pekerjaan Pembesian
Longitudinal IDR 152,995,640
Transversal IDR 52,453,571
Confinement IDR 32,279,121
Total IDR 25,198,639,063
Data AHSP PEMASA
b 600 mm 0.6 m
Kolom K1 NO URAIAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2
Kolom K2
h 600 mm 0.6 m A Tenaga Kerja
b 500 mm 0.5 m 1 Pekerja
Balok B50/80
h 800 mm 0.8 m 2 Tukang Kayu
b 400 mm 0.4 m 3 Kepala Tukang
Balok B40/70
h 700 mm 0.7 m 4 Mandor
b 350 mm 0.35 m JUMLAH HARGA T
Balok B35/50
h 500 mm 0.5 m B Bahan
Lantai h 150 mm 0.15 m 1 Kayu Kelas III
Atap h 130 mm 0.13 m 2 Paku 5-12 Cm
b 400 mm 0.4 m 3 Minyak Bekisting
Shear Wall
h 400 mm 0.4 m 4 Balok Kayu Kelas II
b 400 mm 0.4 m 5 Plywood Tebal 9 mm
Core Wall
h 400 mm 0.4 m 6 Dolken Kayu Galam, 8-10 Cm Panjang 4 m
JUMLAH HARGA HARGA BAHAN
C Julah Harga Tenaga Kerja dan Bahan(A+B)
D Overhead + Profit
E Harga Satuan Pemasangan 1m3 Bekisting Lantai (D+E)
AHSP PEMASANGAN 1 M2 BEKISTING LANTAI
HARGA SATUAN
KODE SATUAN KOEFISIEN
Rp
3 4 5 6

L.01 OH 0.66 IDR 135,500


L.02 OH 0.33 IDR 155,800
L.03 OH 0.033 IDR 170,500
L.04 OH 0.033 IDR 183,200
JUMLAH HARGA TENAGA KERJA

m3 0.04 IDR 2,719,600


Kg 0.4 IDR 36,000
Liter 0.2 IDR 6,000
m3 0.015 IDR 2,719,600
Lbr 0.35 IDR 98,000
Batang 6 IDR 33,300

an(A+B)
15% x C
kisting Lantai (D+E)
Detail Pekerjaan Struktur Pelat Lantai
JUMLAH HARGA Struktur
Rp Panjang Luas
Komponen Struktur Ketengan Arah
7 (m) (m2)
29.5 X
Segmen 1 560.5
IDR 89,430 19 Y
IDR 51,414 13.8 X
Pelat Lantai Segmen 2 262.2
IDR 5,627 19 Y
IDR 6,046 20.7 X
Segmen 3 393.3
IDR 152,516 19 Y
Total
IDR 108,784 Total Keseluruhan
IDR 14,400
IDR 1,200
IDR 40,794
IDR 34,300
IDR 199,800
IDR 399,278
IDR 551,794
IDR 82,769
IDR 634,563
uktur Pelat Lantai

Rencana Anggaran Biaya


(Rp)
IDR 355,672,682

IDR 166,382,475

IDR 249,573,712

IDR 771,628,869
IDR 9,259,546,433
Data AHSP PEMASA
b 600 mm 0.6 m
Kolom K1 NO URAIAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2
Kolom K2
h 600 mm 0.6 m A
b 500 mm 0.5 m 1 Pekerja
Balok B50/80
h 800 mm 0.8 m 2 Tukang Kayu
b 400 mm 0.4 m 3 Kepala Tukang
Balok B40/70
h 700 mm 0.7 m 4 Mandor
b 350 mm 0.35 m JUMLAH HARGA T
Balok B35/50
h 500 mm 0.5 m B
Lantai h 150 mm 0.15 m 1 Kayu Kelas III
Atap h 130 mm 0.13 m 2 Paku 5-12 Cm
b 400 mm 0.4 m 3 Minyak Bekisting
Shear Wall
h 400 mm 0.4 m 4 Balok Kayu Kelas II
b 400 mm 0.4 m 5 Plywood Tebal 9 mm
Core Wall
h 400 mm 0.4 m 6 Dolken Kayu Galam, 8-10 Cm Panjang 4 m
JUMLAH HARGA
C Julah Harga Tenaga
D Overhead + Profit
E Harga Satuan Pemasangan
AHSP PEMASANGAN 1 M2 BEKISTING BALOK
HARGA SATUAN
KODE SATUAN KOEFISIEN
Rp
3 4 5 6
Tenaga Kerja
L.01 OH 0.66 IDR 135,500
L.02 OH 0.33 IDR 155,800
L.03 OH 0.033 IDR 170,500
L.04 OH 0.033 IDR 183,200
JUMLAH HARGA TENAGA KERJA
Bahan
m3 0.04 IDR 2,719,600
Kg 0.4 IDR 36,000
Liter 0.2 IDR 6,000
m3 0.015 IDR 2,719,600
Lbr 0.35 IDR 98,000
Batang 6 IDR 33,300
JUMLAH HARGA HARGA BAHAN
Julah Harga Tenaga Kerja dan Bahan(A+B)
Overhead + Profit 15% x C
Harga Satuan Pemasangan 1m3 Bekisting Lantai (D+E)
Rencana Anggaran Tulangan Bekisting Balok B1
JUMLAH HARGA Struktur
Rp Panjang Lebar Tinggi Luas
Komponen Struktur Ketengan
7 (m) (m) (m) (m2)
as A (1-2) 2 0.5 0.8 1
IDR 89,430 as A (3-6) 11 0.5 0.8 5.5
IDR 51,414 as A (7-8) 2 0.5 0.8 1
IDR 5,627 as B 23 0.5 0.8 11.5
IDR 6,046 as C 23 0.5 0.8 11.5
IDR 152,516 as D 23 0.5 0.8 11.5
as E 23 0.5 0.8 11.5
IDR 108,784 as F 23 0.5 0.8 11.5
IDR 14,400 as G 23 0.5 0.8 11.5
IDR 1,200 as I to Core 1.95 0.5 0.8 0.98
IDR 40,794 as I (2-5) 11 0.5 0.8 5.5
IDR 34,300 as J (2-7) 19 0.5 0.8 9.5
Balok B1
IDR 199,800 as K (2-7) 19 0.5 0.8 9.5
IDR 399,278 as L (2-7) 19 0.5 0.8 9.5
IDR 551,794 as M 23 0.5 0.8 11.5
IDR 82,769 as N 23 0.5 0.8 11.5
IDR 634,563 as O 23 0.5 0.8 11.5
as P 23 0.5 0.8 11.5
as Q 23 0.5 0.8 11.5
as R (1-2) 2 0.5 0.8 1
as R (3-6) 11 0.5 0.8 5.5
as R (7-8) 2 0.5 0.8 1
SW X 4 0.5 0.8 2
CORE 5.5 0.5 0.8 2.75
Total
Total Keseluruhan
an Bekisting Balok B1 Rencana Anggaran Tulangan
ur Struktur
Rencana Anggaran Biaya
Komponen Struktur Ketengan
(Rp)
IDR 634,563 as 7 (B-Q)
IDR 3,490,098 as 6 (B-G)
IDR 634,563 as 6 (J-Q)
IDR 7,297,477 as 5 (A-G)
IDR 7,297,477 Balok B2 as 5 (J-R)
IDR 7,297,477 as 4
IDR 7,297,477 as 3 (B-Q)
IDR 7,297,477 as 2 (B-I)
IDR 7,297,477 as 2 (M-Q)
IDR 618,699 Total 1 Lantai
IDR 3,490,098 Total Keseluruhan
IDR 6,028,351
IDR 6,028,351 Rencana Anggaran
IDR 6,028,351
IDR 7,297,477
Komponen Struktur Ketengan
IDR 7,297,477
IDR 7,297,477 as A-I
Balok B3
IDR 7,297,477 as M-R
IDR 7,297,477 Total
IDR 634,563 Total Keseluruhan
IDR 3,490,098
IDR 634,563
IDR 1,269,126
IDR 1,745,049
IDR 114,998,719
IDR 1,379,984,624
Anggaran Tulangan Bekisting Balok B2
Struktur
Panjang Lebar Tinggi Luas Rencana Anggaran Biaya
(m) (m) (m) (m2) (Rp)
56 0.4 0.7 22.4 IDR 14,214,216
20 0.4 0.7 8 IDR 5,076,506
28 0.4 0.7 11.2 IDR 7,107,108
24 0.4 0.7 9.6 IDR 6,091,807
32 0.4 0.7 12.8 IDR 8,122,409
64 0.4 0.7 25.6 IDR 16,244,818
56 0.4 0.7 22.4 IDR 14,214,216
25.5 0.4 0.7 10.2 IDR 6,472,545
16.7 0.4 0.7 6.68 IDR 4,238,882
IDR 81,782,507
IDR 981,390,086

Rencana Anggaran Tulangan Bekisting Balok B3


Struktur
Panjang Lebar Tinggi Luas Rencana Anggaran Biaya
Jumlah
(m) (m) (m) (m2) (Rp)
29.5 0.35 0.5 2 10.325 IDR 13,103,730
20.7 0.35 0.5 2 7.245 IDR 9,194,821
IDR 22,298,551
IDR 267,582,617
Data AHSP PEMASA
b 600 mm 0.6 m
Kolom K1 NO URAIAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2
Kolom K2
h 600 mm 0.6 m A
b 500 mm 0.5 m 1 Pekerja
Balok B50/80
h 800 mm 0.8 m 2 Tukang Kayu
b 400 mm 0.4 m 3 Kepala Tukang
Balok B40/70
h 700 mm 0.7 m 4 Mandor
b 350 mm 0.35 m JUMLAH HARGA T
Balok B35/50
h 500 mm 0.5 m B
Lantai h 150 mm 0.15 m 1 Kayu Kelas III
Atap h 130 mm 0.13 m 2 Paku 5-12 Cm
b 400 mm 0.4 m 3 Minyak Bekisting
Shear Wall
h 400 mm 0.4 m 4 Balok Kayu Kelas II
b 400 mm 0.4 m 5 Plywood Tebal 9 mm
Core Wall
h 400 mm 0.4 m 6 Dolken Kayu Galam, 8-10 Cm Panjang 4 m
JUMLAH HARGA
C Julah Harga Tenaga
D Overhead + Profit
E Harga Satuan Pemasangan
AHSP PEMASANGAN 1 M2 BEKISTING KOLOM
HARGA SATUAN
KODE SATUAN KOEFISIEN
Rp
3 4 5 6
Tenaga Kerja
L.01 OH 0.66 IDR 135,500
L.02 OH 0.33 IDR 155,800
L.03 OH 0.033 IDR 170,500
L.04 OH 0.033 IDR 183,200
JUMLAH HARGA TENAGA KERJA
Bahan
m3 0.04 IDR 2,719,600
Kg 0.4 IDR 36,000
Liter 0.2 IDR 6,000
m3 0.015 IDR 2,719,600
Lbr 0.35 IDR 98,000
Batang 6 IDR 33,300
JUMLAH HARGA HARGA BAHAN
Julah Harga Tenaga Kerja dan Bahan(A+B)
Overhead + Profit 15% x C
Harga Satuan Pemasangan 1m3 Bekisting Lantai (D+E)
Rencana Anggaran Tulangan Bekisting Kolom K1
JUMLAH HARGA Struktur
Rp Panjang Lebar Tinggi Jumlah
Komponen Struktur Ketengan
7 (m) (m) (m) n
Kolom Longitudinal 0.6 0.6 48 92
IDR 89,430
IDR 51,414
IDR 5,627
IDR 6,046
IDR 152,516

IDR 108,784
IDR 14,400
IDR 1,200
IDR 40,794
IDR 34,300
IDR 199,800
IDR 399,278
IDR 551,794
IDR 82,769
IDR 634,563
g Kolom K1

Luas Rencana Anggaran Biaya


(m2) (Rp)
0.36 IDR 1,008,803,217
Data AHSP PEMASA
b 600 mm 0.6 m
Kolom K1 NO URAIAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2
Kolom K2
h 600 mm 0.6 m A
b 500 mm 0.5 m 1 Pekerja
Balok B50/80
h 800 mm 0.8 m 2 Tukang Kayu
b 400 mm 0.4 m 3 Kepala Tukang
Balok B40/70
h 700 mm 0.7 m 4 Mandor
b 350 mm 0.35 m JUMLAH HARGA T
Balok B35/50
h 500 mm 0.5 m B
Lantai h 150 mm 0.15 m 1 Kayu Kelas III
Atap h 130 mm 0.13 m 2 Paku 5-12 Cm
b 400 mm 0.4 m 3 Minyak Bekisting
Shear Wall
h 400 mm 0.4 m 4 Balok Kayu Kelas II
b 400 mm 0.4 m 5 Plywood Tebal 9 mm
Core Wall
h 400 mm 0.4 m 6 Dolken Kayu Galam, 8-10 Cm Panjang 4 m
JUMLAH HARGA
C Julah Harga Tenaga
D Overhead + Profit
E Harga Satuan Pemasangan
AHSP PEMASANGAN 1 M2 BEKISTING KOLOM
HARGA SATUAN
KODE SATUAN KOEFISIEN
Rp
3 4 5 6
Tenaga Kerja
L.01 OH 0.66 IDR 135,500
L.02 OH 0.33 IDR 155,800
L.03 OH 0.033 IDR 170,500
L.04 OH 0.033 IDR 183,200
JUMLAH HARGA TENAGA KERJA
Bahan
m3 0.04 IDR 2,719,600
Kg 0.4 IDR 36,000
Liter 0.2 IDR 6,000
m3 0.015 IDR 2,719,600
Lbr 0.35 IDR 98,000
Batang 6 IDR 33,300
JUMLAH HARGA HARGA BAHAN
Julah Harga Tenaga Kerja dan Bahan(A+B)
Overhead + Profit 15% x C
Harga Satuan Pemasangan 1m3 Bekisting Lantai (D+E)
Rencana Anggaran Bekisting Shea
JUMLAH HARGA Struktur
Rp Panjang Lebar Tinggi
Komponen Struktur Ketengan Jumlah
7 (m) (m) (m)
Shear Wall Arah Y SW Y 4 0.4 48 4
IDR 89,430
IDR 51,414
IDR 5,627
IDR 6,046 Rencana Anggaran Bekisting Shea
IDR 152,516 Struktur
Panjang Lebar Tinggi
Komponen Struktur Ketengan Jumlah
IDR 108,784 (m) (m) (m)
IDR 14,400 Shear Wall Arah X 8 0.4 12 48 1
IDR 1,200
IDR 40,794
IDR 34,300
IDR 199,800
IDR 399,278
IDR 551,794
IDR 82,769
IDR 634,563
garan Bekisting Shear Wall Y

Luas Rencana Anggaran Biaya


(m2) (Rp)
1.6 IDR 194,937,820

garan Bekisting Shear Wall X


Luas Rencana Anggaran Biaya
(m2) (Rp)
4.8 IDR 146,203,365
Rekapitulasi Perhitungan Rencana Anggaran Biaya Bekisting
No Struktur Jenis Pekerjaan Biaya
1 Pelat Lantai Bekisting IDR 771,628,869
Bekisting B1 IDR 114,998,719
2 Balok Bekisting B2 IDR 81,782,507
Bekisting B3 IDR 22,298,551
3 Kolom Bekisting K1 IDR 1,008,803,217
SW X IDR 146,203,365
4 Shear Wall
SW Y IDR 194,937,820
Total IDR 2,340,653,048

You might also like