Professional Documents
Culture Documents
Struktur: Rencana Anggaran Biaya Lantai 1
Struktur: Rencana Anggaran Biaya Lantai 1
Balok 40/70
as 5 (A-G) 24 0.5 0.7
Balok 40/70 as 5 (J-R) 32 0.5 0.7
as 4 64 0.5 0.7
as 3 (B-Q) 56 0.5 0.7
as 2 (B-I) 25.5 0.5 0.7
as 2 (M-Q) 16.7 0.5 0.7
as A-I 29.5 0.5 0.5
Balok 35/50
as M-R 20.7 0.5 0.5
Kolom K1 0.6 0.6 4
SW1 4 0.4 4
SW2 4 0.4 4
Shear Wall SW3 4 0.4 4
SW4 4 0.4 4
SW5 8 0.4 4
Arah X 2.85 0.4 4
Core Wall
Arah Y 6 0.4 4
Total
Anggaran Biaya Lantai 1 Rencana Angga
Struktur
Harga Beton K-400 Total Dana
Jumlah Komponen Beban Ketengan
(1 m3) Rp
1 1310000 IDR 110,138,250 Segmen 1
1 1310000 IDR 51,522,300 Pelat Lantai Segmen 2
1 1310000 IDR 77,283,450 Segmen 3
1 1310000 IDR 1,048,000 as A (1-2)
1 1310000 IDR 5,764,000 as A (3-6)
1 1310000 IDR 1,048,000 as A (7-8)
1 1310000 IDR 12,052,000 as B
1 1310000 IDR 12,052,000 as C
1 1310000 IDR 12,052,000 as D
1 1310000 IDR 12,052,000 as E
1 1310000 IDR 12,052,000 as F
1 1310000 IDR 12,052,000 as G
1 1310000 IDR 1,021,800 as I to Core
1 1310000 IDR 5,764,000 as I (2-5)
Balok B50/80 (Y)
1 1310000 IDR 9,956,000 as J (2-7)
1 1310000 IDR 9,956,000 as K (2-7)
1 1310000 IDR 9,956,000 as L (2-7)
1 1310000 IDR 12,052,000 as M
1 1310000 IDR 12,052,000 as N
1 1310000 IDR 12,052,000 as O
1 1310000 IDR 12,052,000 as P
1 1310000 IDR 12,052,000 as Q
1 1310000 IDR 1,048,000 as R (1-2)
1 1310000 IDR 5,764,000 as R (3-6)
1 1310000 IDR 1,048,000 as R (7-8)
1 1310000 IDR 2,096,000 SW X
Balok B50/80 X
1 1310000 IDR 2,882,000 CORE
1 1310000 IDR 25,676,000 as 7 (B-Q)
1 1310000 IDR 9,170,000 as 6 (B-G)
1 1310000 IDR 12,838,000 as 6 (J-Q)
1 1310000 IDR 11,004,000 as 5 (A-G)
1 1310000 IDR 14,672,000 Balok 40/70 as 5 (J-R)
1 1310000 IDR 29,344,000 as 4
1 1310000 IDR 25,676,000 as 3 (B-Q)
1 1310000 IDR 11,691,750 as 2 (B-I)
1 1310000 IDR 7,656,950 as 2 (M-Q)
2 1310000 IDR 19,322,500 as A-I
Balok 35/50
2 1310000 IDR 13,558,500 as M-R
92 1310000 IDR 173,548,800 Kolom K1
1 1310000 IDR 8,384,000 SW1
1 1310000 IDR 8,384,000 SW2
1 1310000 IDR 8,384,000 Shear Wall SW3
1 1310000 IDR 8,384,000 SW4
1 1310000 IDR 16,768,000 SW5
3 1310000 IDR 17,920,800 Arah X
Core Wall
1 1310000 IDR 12,576,000 Arah Y
IDR 863,827,100 Total
Balok B50/80 X
Balok 40/70
Balok 35/50
Total
Total Keseluruhan Balok 12 L
Rencana Anggaran Biaya 1 Lantai
ur Balok
Panjang Lebar Tinggi Tulangan Longitudinal Harga Tulangan 1 Batang 12 Meter
Ketengan Jumlah
(m) (m) (m) Buah Rp
as A (1-2) 2 0.5 0.8 1 11 253000
as A (3-6) 11 0.5 0.8 1 11 253000
as A (7-8) 2 0.5 0.8 1 11 253000
as B 23 0.5 0.8 1 11 253000
as C 23 0.5 0.8 1 11 253000
as D 23 0.5 0.8 1 11 253000
as E 23 0.5 0.8 1 11 253000
as F 23 0.5 0.8 1 11 253000
as G 23 0.5 0.8 1 11 253000
as I to Core 1.95 0.5 0.8 1 11 253000
as I (2-5) 11 0.5 0.8 1 11 253000
as J (2-7) 19 0.5 0.8 1 11 253000
as K (2-7) 19 0.5 0.8 1 11 253000
as L (2-7) 19 0.5 0.8 1 11 253000
as M 23 0.5 0.8 1 11 253000
as N 23 0.5 0.8 1 11 253000
as O 23 0.5 0.8 1 11 253000
as P 23 0.5 0.8 1 11 253000
as Q 23 0.5 0.8 1 11 253000
as R (1-2) 2 0.5 0.8 1 11 253000
as R (3-6) 11 0.5 0.8 1 11 253000
as R (7-8) 2 0.5 0.8 1 11 253000
SW X 4 0.5 0.8 1 11 253000
CORE 5.5 0.5 0.8 1 11 253000
as 7 (B-Q) 56 0.5 0.7 1 9 253000
as 6 (B-G) 20 0.5 0.7 1 9 253000
as 6 (J-Q) 28 0.5 0.7 1 9 253000
as 5 (A-G) 24 0.5 0.7 1 9 253000
as 5 (J-R) 32 0.5 0.7 1 9 253000
as 4 64 0.5 0.7 1 9 253000
as 3 (B-Q) 56 0.5 0.7 1 9 253000
as 2 (B-I) 25.5 0.5 0.7 1 9 253000
as 2 (M-Q) 16.7 0.5 0.7 1 9 253000
as A-I 29.5 0.5 0.5 2 6 253000
as M-R 20.7 0.5 0.5 2 6 253000
Total Panjang Balok Kebutuhan Besi Balok 12 meter Kebutuhan Total Harga
m Buah Buah Rp
IDR 157,896,246
IDR 1,894,754,950
Rencana Anggaran
Panjang Lebar Tinggi
Komponen Beban Ketengan Jumlah
(m) (m) (m)
Kolom K1 0.6 0.6 4 92
as A (1-2) 2 0.5 0.8 12
as A (3-6) 11 0.5 0.8 12
as A (7-8) 2 0.5 0.8 12
as B 23 0.5 0.8 12
as C 23 0.5 0.8 12
as D 23 0.5 0.8 12
as E 23 0.5 0.8 12
as F 23 0.5 0.8 12
as G 23 0.5 0.8 12
as I to Core 1.95 0.5 0.8 12
as I (2-5) 11 0.5 0.8 12
Balok B50/80 (Y)
as J (2-7) 19 0.5 0.8 12
as K (2-7) 19 0.5 0.8 12
as L (2-7) 19 0.5 0.8 12
as M 23 0.5 0.8 12
as N 23 0.5 0.8 12
as O 23 0.5 0.8 12
as P 23 0.5 0.8 12
as Q 23 0.5 0.8 12
as R (1-2) 2 0.5 0.8 12
as R (3-6) 11 0.5 0.8 12
as R (7-8) 2 0.5 0.8 12
SW X 4 0.5 0.8 12
Balok B50/80 X
CORE 5.5 0.5 0.8 12
as 7 (B-Q) 56 0.5 0.7 12
as 6 (B-G) 20 0.5 0.7 12
as 6 (J-Q) 28 0.5 0.7 12
as 5 (A-G) 24 0.5 0.7 12
Balok 40/70 as 5 (J-R) 32 0.5 0.7 12
as 4 64 0.5 0.7 12
as 3 (B-Q) 56 0.5 0.7 12
as 2 (B-I) 25.5 0.5 0.7 12
as 2 (M-Q) 16.7 0.5 0.7 12
as A-I 29.5 0.5 0.5 24
Balok 35/50
as M-R 20.7 0.5 0.5 24
SW1 4 0.4 4 1
SW2 4 0.4 4 1
Shear Wall
Shear Wall SW3 4 0.4 4 1
SW4 4 0.4 4 1
SW5 8 0.4 4 1
Arah X 2.85 2.85 4 3
Core Wall
Arah Y 6 6 4 1
Total
Rencana Anggaran Biaya Tulangan Longitudinal Seluruh
Tulangan Longitudinal Harga Tulangan 1 Batang 12 Meter Total Panjang
Buah Rp m
10 338000 48
11 338000 24
11 338000 132
11 338000 24
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 23
11 338000 132
11 338000 228
11 338000 228
11 338000 228
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 276
11 338000 24
11 338000 132
11 338000 24
11 338000 48
11 338000 66
9 338000 672
9 338000 240
9 338000 336
9 338000 288
9 338000 384
9 338000 768
9 338000 672
9 338000 306
9 338000 200
6 338000 708
6 338000 497
40 338000 48
40 338000 48
40 338000 48
40 338000 48
74 338000 48
116 338000 48
nal Seluruh
Kebutuhan Besi Balok 12 meter Kebutuhan Total Harga
Buah Buah Rp
4 3680 IDR 1,243,840,000
2 22 IDR 7,436,000
11 121 IDR 40,898,000
2 22 IDR 7,436,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
2 21 IDR 7,250,100
11 121 IDR 40,898,000
19 209 IDR 70,642,000
19 209 IDR 70,642,000
19 209 IDR 70,642,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
23 253 IDR 85,514,000
2 22 IDR 7,436,000
11 121 IDR 40,898,000
2 22 IDR 7,436,000
4 44 IDR 14,872,000
6 61 IDR 20,449,000
56 504 IDR 170,352,000
20 180 IDR 60,840,000
28 252 IDR 85,176,000
24 216 IDR 73,008,000
32 288 IDR 97,344,000
64 576 IDR 194,688,000
56 504 IDR 170,352,000
26 230 IDR 77,571,000
17 150 IDR 50,801,400
59 354 IDR 119,652,000
41 248 IDR 83,959,200
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 160 IDR 54,080,000
4 296 IDR 100,048,000
4 1392 IDR 470,496,000
IDR 4,562,036,700
Rencana Anggaran Biaya Tulangan Transversal Seluruh
Struktur Kolom
Sengkang
Total Panjang Kolom
Total Sengkang 1 Kolom/4 meter
Total Sengkang Hingga Atas
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-13/Batang
Rencana Anggaran Biaya 1 Kolom
Total Keseluruhan Kolom
Confinement
Total confinement 1 Kolom/4 meter
Total confinement Hingga Atas
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-13/Batang
Rencana Anggaran Biaya 1 Kolom
Total Keseluruhan Kolom
Struktur Balok B1
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Struktur Balok B2
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Struktur Balok B3
Total Panjang Balok
Total Sengkang Balok 4 meter
Kebutuhan Sengkang total
Keliling Sengkang
Kebutuhan Sengkang/Batang
Kebutuhan Tulangan/batang
Harga Tulangan D-10/Batang
Rencana Anggaran Biaya 1 Lantai
Total Rencana Anggaran Biaya
Total
sal Seluruh
Tulangan Tumpuan
Kebutuhan Tulangan per 4 Meter
48 Segmen 1 Arah X
57 Total Segmen 1 X
684 Kebutuhan Tulangan Segmen 1 Arah X
1.04 Kebutuhan Tulangan per 4 Meter
711 Segmen 1 Arah Y
59 Total Segmen 1 Y
IDR 118,000 Kebutuhan Tulangan Segmen 1 Arah X
IDR 6,995,040 Harga Tulangan D-13/Batang
IDR 643,543,680 Kebutuhan Tulangan/batang X
Kebutuhan Tulangan/batang Y
114 Rencana Anggaran Biaya 1 Lantai X
1368 Rencana Anggaran Biaya 1 Lantai Y
1.04 Total Rencana Anggaran Biaya X
1423 Total Rencana Anggaran Biaya Y
119 Tulangan Lapangan
IDR 118,000 Kebutuhan Tulangan per 4 Meter
IDR 13,990,080 Segmen 1 Arah X
IDR 1,287,087,360 Total Segmen 1 X
Kebutuhan Tulangan Segmen 1 Arah X
363 Kebutuhan Tulangan per 4 Meter
27 Segmen 1 Arah Y
2451 Total Segmen 1 Y
1.14 Kebutuhan Tulangan Segmen 1 Arah X
2794 Harga Tulangan D-13/Batang
233 Kebutuhan Tulangan/batang X
IDR 69,000 Kebutuhan Tulangan/batang Y
IDR 16,063,601 Rencana Anggaran Biaya 1 Lantai X
IDR 192,763,213 Rencana Anggaran Biaya 1 Lantai Y
Total Rencana Anggaran Biaya X
322 Total Rencana Anggaran Biaya Y
23 Tulangan Bagi
1853 Kebutuhan Tulangan per 4 Meter
0.94 Segmen 1 Arah X
1741 Total Segmen 1 X
145 Kebutuhan Tulangan Segmen 1 Arah X
IDR 69,000 Kebutuhan Tulangan per 4 Meter
IDR 10,013,573 Segmen 1 Arah Y
IDR 120,162,879 Total Segmen 1 Y
Kebutuhan Tulangan Segmen 1 Arah X
100 Harga Tulangan D-13/Batang
25 Kebutuhan Tulangan/batang X
628 Kebutuhan Tulangan/batang Y
0.69 Rencana Anggaran Biaya 1 Lantai X
433 Rencana Anggaran Biaya 1 Lantai Y
36 Total Rencana Anggaran Biaya X
IDR 69,000 Total Rencana Anggaran Biaya Y
IDR 2,489,606 Total
IDR 29,875,275
IDR 2,273,432,407
Struktur Pelat Lantai
Tulangan Tumpuan
27 Kebutuhan Tulangan per 4 Meter 27
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
197 Kebutuhan Tulangan Segmen 2 Arah X 92
27 Kebutuhan Tulangan per 4 Meter 27
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
127 Kebutuhan Tulangan Segmen 2 Arah X 127
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
16 Kebutuhan Tulangan/batang X 8
11 Kebutuhan Tulangan/batang Y 11
IDR 1,933,889 Rencana Anggaran Biaya 1 Lantai X IDR 904,667
IDR 1,245,556 Rencana Anggaran Biaya 1 Lantai Y IDR 1,245,556
IDR 23,206,667 Total Rencana Anggaran Biaya X IDR 10,856,000
IDR 14,946,667 Total Rencana Anggaran Biaya Y IDR 14,946,667
Tulangan Lapangan
13 Kebutuhan Tulangan per 4 Meter 13
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
98 Kebutuhan Tulangan Segmen 2 Arah X 46
13 Kebutuhan Tulangan per 4 Meter 13
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
63 Kebutuhan Tulangan Segmen 1 Arah X 63
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
8 Kebutuhan Tulangan/batang X 4
5 Kebutuhan Tulangan/batang Y 5
IDR 966,944 Rencana Anggaran Biaya 1 Lantai X IDR 452,333
IDR 622,778 Rencana Anggaran Biaya 1 Lantai Y IDR 622,778
IDR 11,603,333 Total Rencana Anggaran Biaya X IDR 5,428,000
IDR 7,473,333 Total Rencana Anggaran Biaya Y IDR 7,473,333
Tulangan Bagi
10 Kebutuhan Tulangan per 4 Meter 10
29.5 Segmen 2 Arah X 13.8
7.375 Total Segmen 2 X 3.45
74 Kebutuhan Tulangan Segmen 2 Arah X 35
10 Kebutuhan Tulangan per 4 Meter 10
19 Segmen 2 Arah Y 19
4.75 Total Segmen 2 Y 4.75
48 Kebutuhan Tulangan Segmen 1 Arah X 48
IDR 118,000 Harga Tulangan D-13/Batang IDR 118,000
6 Kebutuhan Tulangan/batang X 3
4 Kebutuhan Tulangan/batang Y 4
IDR 725,208 Rencana Anggaran Biaya 1 Lantai X IDR 339,250
IDR 467,083 Rencana Anggaran Biaya 1 Lantai Y IDR 467,083
IDR 8,702,500 Total Rencana Anggaran Biaya X IDR 4,071,000
IDR 5,605,000 Total Rencana Anggaran Biaya Y IDR 5,605,000
Tulangan Tumpuan
Kebutuhan Tulangan per 4 Meter 27
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 138
Kebutuhan Tulangan per 4 Meter 27
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 127
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 12
Kebutuhan Tulangan/batang Y 11
Rencana Anggaran Biaya 1 Lantai X IDR 1,357,000
Rencana Anggaran Biaya 1 Lantai Y IDR 1,245,556
Total Rencana Anggaran Biaya X IDR 16,284,000
Total Rencana Anggaran Biaya Y IDR 14,946,667
Tulangan Lapangan
Kebutuhan Tulangan per 4 Meter 13
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 69
Kebutuhan Tulangan per 4 Meter 13
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 63
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 6
Kebutuhan Tulangan/batang Y 5
Rencana Anggaran Biaya 1 Lantai X IDR 678,500
Rencana Anggaran Biaya 1 Lantai Y IDR 622,778
Total Rencana Anggaran Biaya X IDR 8,142,000
Total Rencana Anggaran Biaya Y IDR 7,473,333
Tulangan Bagi
Kebutuhan Tulangan per 4 Meter 10
Segmen 3 Arah X 20.7
Total Segmen 3 X 5.175
Kebutuhan Tulangan Segmen 3 Arah X 52
Kebutuhan Tulangan per 4 Meter 10
Segmen 3 Arah Y 19
Total Segmen 3 Y 4.75
Kebutuhan Tulangan Segmen 3 Arah X 48
Harga Tulangan D-13/Batang IDR 118,000
Kebutuhan Tulangan/batang X 4
Kebutuhan Tulangan/batang Y 4
Rencana Anggaran Biaya 1 Lantai X IDR 508,875
Rencana Anggaran Biaya 1 Lantai Y IDR 467,083
Total Rencana Anggaran Biaya X IDR 6,106,500
Total Rencana Anggaran Biaya Y IDR 5,605,000
IDR 178,475,000
Data AHSP 1M3 BETON READY
b 600 mm 0.6 m
Kolom K1 NO URAIAN KODE SATUAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2 3 4
Kolom K2
h 600 mm 0.6 m A Tenaga Kerja
b 500 mm 0.5 m 1 Pekerja L.01 OH
Balok B50/80
h 800 mm 0.8 m 2 Tukang Batu L.02 OH
b 400 mm 0.4 m 3 Kepala Tukang L.03 OH
Balok B40/70
h 700 mm 0.7 m 4 Mandor L.04 OH
b 350 mm 0.35 m JUMLAH HARGA TENAGA KERJA
Balok B35/50
h 500 mm 0.5 m B Bahan Campuran Beton
Lantai h 150 mm 0.15 m 1 Ready Mixed M.09.x m3
Atap h 130 mm 0.13 m JUMLAH HARGA HARGA BAHAN
b 400 mm 0.4 m C Pompa dan Conveyor Beton E.35 m3
Shear Wall
h 400 mm 0.4 m JUMLAH HARGA HARGA PERALATAN
b 400 mm 0.4 m D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
Core Wall
h 400 mm 0.4 m E Overhead + Profit
F Harga Satuan Pekerjaan per-m3 (D+E)
P 1M3 BETON READY MIXED Renc
HARGA SATUAN JUMLAH HARGA Struktur
KOEFISIEN
Rp Rp
Komponen Struktur Ketengan
5 6 7
Segmen 1
1 IDR 135,500 IDR 135,500 Pelat Lantai Segmen 2
0.25 IDR 155,800 IDR 38,950 Segmen 3
0.025 IDR 164,052 IDR 4,101 as A (1-2)
0.1 IDR 183,200 IDR 18,320 as A (3-6)
A TENAGA KERJA IDR 196,871 as A (7-8)
as B
1.02 IDR 1,310,000 IDR 1,336,200 as C
IDR 1,336,200 as D
0.12 IDR 10,400 IDR 1,248 as E
IDR 1,248 as F
eralatan (A+B+C) IDR 1,534,319 as G
15% x D IDR 230,147.90 as I to Core
IDR 1,764,467.20 as I (2-5)
Balok B50/80 (Y)
as J (2-7)
as K (2-7)
as L (2-7)
as M
as N
as O
as P
as Q
as R (1-2)
as R (3-6)
as R (7-8)
SW X
Balok B50/80 X
CORE
as 7 (B-Q)
as 6 (B-G)
as 6 (J-Q)
as 5 (A-G)
Balok 40/70 as 5 (J-R)
as 4
as 3 (B-Q)
as 2 (B-I)
as 2 (M-Q)
as A-I
Balok 35/50
as M-R
Kolom K1
SW1
SW2
Shear Wall SW3
SW4
SW5
Arah X
Core Wall
Arah Y
Total 1 Lantai
Total Rencana Anggaran Biaya Pekerjaan B
Rencana Anggaran Pekerjaan Beton
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KER
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
KEBUTUHAN TULANGA
Tulangan Tumpuan
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
Tulangan Lapangan
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
Tulangan Bagi
Kebutuhan Tulangan per Meter
Kebutuhan Tulangan per Meter
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 338000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-19 2.23 26.76 253000
D-10 0.617 7.404 100000
D-13 1.04 12.48 118000
D-25 3.85 46.2 439000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-13 1.04 12.48 118000
D-13 1.58 18.96 118000
D-13 2.23 26.76 118000
7
7
3
3
3
3
BERAT BESI TULANGAN
Diameter Polos Polos
(mm) (Kg/m)
6 0.222 0.222
8 0.395 0.395
10 0.617 0.617
12 - 0.888
13 1.04 -
16 1.58 1.58
19 2.23 2.23
22 2.98 2.98
25 3.85 3.85
29 - 5.18
32 - 6.31
36 - 7.99
40 - 9.88
Struktur
Panjang Jenis Tulangan Arah Kebutuhan Tulangan
Komponen Struktur Ketengan
(m) (Buah)
29.5 Tumpuan X 6.667
19 Tumpuan Y 6.667
29.5 Lapangan X 3.333
Segmen 1
19 Lapangan Y 3.333
29.5 Bagi X 2.500
19 Bagi Y 2.500
13.8 Tumpuan X 6.667
19 Tumpuan Y 6.667
13.8 Lapangan X 3.333
Pelat Lantai Segmen 2
19 Lapangan Y 3.333
13.8 Bagi X 2.500
19 Bagi Y 2.500
20.7 Tumpuan X 6.667
19 Tumpuan Y 6.667
20.7 Lapangan X 3.333
Segmen 3
19 Lapangan Y 3.333
20.7 Bagi X 2.500
19 Bagi Y 2.500
Total 1 Lantai
Total Keseluruhan
Polos
0.222
0.395
0.617
0.888
-
1.58
2.23
2.98
3.85
5.18
6.31
7.99
9.88
Kebutuhan Tulangan per meter Berat 1 Batang Tulangan Kebutuhan Tulangan Segmen
(Aktual) (Kg) (Buah)
7 1.04 206.500
7 1.04 133.000
4 1.04 118.000
4 1.04 76.000
3 1.04 88.500
3 1.04 57.000
7 1.04 96.600
7 1.04 133.000
4 1.04 55.200
4 1.04 76.000
3 1.04 41.400
3 1.04 57.000
7 1.04 144.900
7 1.04 133.000
4 1.04 82.800
4 1.04 76.000
3 1.04 62.100
3 1.04 57.000
ur Pelat Lantai
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KER
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Kolom
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Kolom Transversal 0.6 0.6 48 92 1.04
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Kolom Transversal 0.6 0.6 48 92 1.04
Rencana Anggaran Tulangan Longitudinal Kolom
ansversal Kolom
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
596 49.667 50 52
finement Kolom
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
1383 115.250 116 120.64
Rencana Anggaran Biaya
(Rp)
IDR 713,865,169
Rencana Anggaran Biaya
(Rp)
IDR 1,656,167,193
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LON
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
AHSP PEMBESIAN TULANGAN TRA
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
LIST TULANGAN STRUKTUR
Berat Berat 1 Batang HARGA SATUAN
Diameter Tulangan
(Kg/m) (Kg) per-12 Meter
D-22 2.98 35.76 IDR 338,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-19 2.23 26.76 IDR 253,000
D-10 0.617 7.404 IDR 100,000
D-13 1.04 12.48 IDR 118,000
D-25 3.85 46.2 IDR 439,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 1.04 12.48 IDR 118,000
D-13 1.58 18.96 IDR 118,000
D-13 2.23 26.76 IDR 118,000
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A (1-2) 2 0.5 0.8 1 0.617
as A (3-6) 11 0.5 0.8 1 0.617
as A (7-8) 2 0.5 0.8 1 0.617
as B 23 0.5 0.8 1 0.617
as C 23 0.5 0.8 1 0.617
as D 23 0.5 0.8 1 0.617
as E 23 0.5 0.8 1 0.617
as F 23 0.5 0.8 1 0.617
as G 23 0.5 0.8 1 0.617
as I to Core 1.95 0.5 0.8 1 0.617
as I (2-5) 11 0.5 0.8 1 0.617
as J (2-7) 19 0.5 0.8 1 0.617
Balok B1
as K (2-7) 19 0.5 0.8 1 0.617
as L (2-7) 19 0.5 0.8 1 0.617
as M 23 0.5 0.8 1 0.617
as N 23 0.5 0.8 1 0.617
as O 23 0.5 0.8 1 0.617
as P 23 0.5 0.8 1 0.617
as Q 23 0.5 0.8 1 0.617
as R (1-2) 2 0.5 0.8 1 0.617
as R (3-6) 11 0.5 0.8 1 0.617
as R (7-8) 2 0.5 0.8 1 0.617
SW X 4 0.5 0.8 1 0.617
CORE 5.5 0.5 0.8 1 0.617
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A (1-2) 2 0.5 0.8 1 1.04
as A (3-6) 11 0.5 0.8 1 1.04
as A (7-8) 2 0.5 0.8 1 1.04
as B 23 0.5 0.8 1 1.04
as C 23 0.5 0.8 1 1.04
as D 23 0.5 0.8 1 1.04
as E 23 0.5 0.8 1 1.04
as F 23 0.5 0.8 1 1.04
as G 23 0.5 0.8 1 1.04
as I to Core 1.95 0.5 0.8 1 1.04
as I (2-5) 11 0.5 0.8 1 1.04
as J (2-7) 19 0.5 0.8 1 1.04
Balok B1
as K (2-7) 19 0.5 0.8 1 1.04
as L (2-7) 19 0.5 0.8 1 1.04
as M 23 0.5 0.8 1 1.04
as N 23 0.5 0.8 1 1.04
as O 23 0.5 0.8 1 1.04
as P 23 0.5 0.8 1 1.04
as Q 23 0.5 0.8 1 1.04
as R (1-2) 2 0.5 0.8 1 1.04
as R (3-6) 11 0.5 0.8 1 1.04
as R (7-8) 2 0.5 0.8 1 1.04
SW X 4 0.5 0.8 1 1.04
CORE 5.5 0.5 0.8 1 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok
ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
32 2.667 3 1.851
174 14.500 15 9.255
32 2.667 3 1.851
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
31 2.583 3 1.851
174 14.500 15 9.255
300 25.000 25 15.425
300 25.000 25 15.425
300 25.000 25 15.425
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
363 30.250 31 19.127
32 2.667 3 1.851
174 14.500 15 9.255
32 2.667 3 1.851
64 5.333 6 3.702
87 7.250 8 4.936
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as 7 (B-Q) 56 0.4 0.7 1 0.617
as 6 (B-G) 20 0.4 0.7 1 0.617
Balok B2
as 6 (J-Q) 28 0.4 0.7 1 0.617
as 5 (A-G) 24 0.4 0.7 1 0.617
Balok B2 as 5 (J-R) 32 0.4 0.7 1 0.617
as 4 64 0.4 0.7 1 0.617
as 3 (B-Q) 56 0.4 0.7 1 0.617
as 2 (B-I) 25.5 0.4 0.7 1 0.617
as 2 (M-Q) 16.7 0.4 0.7 1 0.617
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Balok B2 as 7 (B-Q) 56 0.4 0.7 1 1.04
as 6 (B-G) 20 0.4 0.7 1 1.04
as 6 (J-Q) 28 0.4 0.7 1 1.04
as 5 (A-G) 24 0.4 0.7 1 1.04
as 5 (J-R) 32 0.4 0.7 1 1.04
as 4 64 0.4 0.7 1 1.04
as 3 (B-Q) 56 0.4 0.7 1 1.04
as 2 (B-I) 25.5 0.4 0.7 1 1.04
as 2 (M-Q) 16.7 0.4 0.7 1 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok
ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
639 53.250 54 33.318
228 19.000 19 11.723
320 26.667 27 16.659
274 22.833 23 14.191
365 30.417 31 19.127
730 60.833 61 37.637
639 53.250 54 33.318
291 24.250 25 15.425
191 15.917 16 9.872
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Balok B1
Kebutuhan Tulangan Torsi Balok B1
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A-I 29.5 0.35 0.5 2 0.617
Balok B3
as M-R 20.7 0.35 0.5 2 0.617
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tu
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
as A-I 29.5 0.35 0.5 2 1.04
Balok B3
as M-R 20.7 0.35 0.5 2 1.04
Total 1 Lantai
Total Keseluruhan
Rencana Anggaran Tulangan Longitudinal Balok
ansversal Balok
Total Panjang Tulangan Kebutuhan Tulangan Total Kebutuhan Tulangan Total Berat Aktual
(Aktual) (Buah) (Aktual) (Kg)
263 21.917 22 13.574
185 15.417 16 9.872
Berat Aktual Rencana Anggaran Biaya
(Kg) (Rp)
6 IDR 3,746,782
4 IDR 2,497,854
IDR 6,244,636
IDR 74,935,634
Rencana Anggaran Biaya
(Rp)
IDR 3,460,944
IDR 2,517,050
IDR 5,977,994
IDR 71,735,930
Data LIST TULANGAN S
b 600 mm 0.6 m
Kolom K1 No Struktur Jenis Tulangan
h 600 mm 0.6 m
b 600 mm 0.6 m Longitudinal (Ulir)
Kolom K2
h 600 mm 0.6 m 1 Kolom Sengkang (Polos)
b 500 mm 0.5 m Confinenet (Polos)
Balok B50/80
h 800 mm 0.8 m Longitudinal (Ulir)
b 400 mm 0.4 m 2 Balok Sengkang (Polos)
Balok B40/70
h 700 mm 0.7 m Torsi (Ulir)
b 350 mm 0.35 m Longitudinal (Ulir)
Balok B35/50
h 500 mm 0.5 m 3 Shear Wall Sengkang (Polos)
Lantai h 150 mm 0.15 m Booundary Element (Polos)
Atap h 130 mm 0.13 m Tumpuan
b 400 mm 0.4 m 4 Pelat Lantai Lapangan
Shear Wall
h 400 mm 0.4 m Bagi
b 400 mm 0.4 m
Core Wall
h 400 mm 0.4 m
AHSP PEMBESIAN TULANGAN LONGI
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Shear Wall
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah Y SW Y 4 0.4 48 4 1.04
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah Y SW Y 4 0.4 48 4 1.04
ncana Anggaran Tulangan Longitudinal Shear Wall
NO URAIAN KODE
1 2 3
A Tenaga Kerja
1 Pekerja L.01
2 Tukang Besi L.02
3 Kepala Tukang L.03
4 Mandor L.04
JUMLAH HARGA TENAGA KE
B Bahan Campuran Beton
1 Besi Beton (Ulir) M.55.d
2 Kawat Ikat M.67
JUMLAH HARGA HARGA BAHAN
D Julah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)
E Overhead + Profit
F Harga Satuan Pekerjaan per-100 Kg (D+E)
Kebutuhan Tulangan Longitudinal Shear Wall
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah X SW X 8 0.4 48 1 1.04
R
Struktur
Panjang Lebar Tinggi Berat 1 Batang Tulangan
Komponen Struktur Ketengan Jumlah
(m) (m) (m) (Kg)
Shear Wall Arah X SW X 8 0.4 48 1 1.04
ncana Anggaran Tulangan Longitudinal Shear Wall
an(A+B)
15% x C
kisting Lantai (D+E)
Detail Pekerjaan Struktur Pelat Lantai
JUMLAH HARGA Struktur
Rp Panjang Luas
Komponen Struktur Ketengan Arah
7 (m) (m2)
29.5 X
Segmen 1 560.5
IDR 89,430 19 Y
IDR 51,414 13.8 X
Pelat Lantai Segmen 2 262.2
IDR 5,627 19 Y
IDR 6,046 20.7 X
Segmen 3 393.3
IDR 152,516 19 Y
Total
IDR 108,784 Total Keseluruhan
IDR 14,400
IDR 1,200
IDR 40,794
IDR 34,300
IDR 199,800
IDR 399,278
IDR 551,794
IDR 82,769
IDR 634,563
uktur Pelat Lantai
IDR 166,382,475
IDR 249,573,712
IDR 771,628,869
IDR 9,259,546,433
Data AHSP PEMASA
b 600 mm 0.6 m
Kolom K1 NO URAIAN
h 600 mm 0.6 m
b 600 mm 0.6 m 1 2
Kolom K2
h 600 mm 0.6 m A
b 500 mm 0.5 m 1 Pekerja
Balok B50/80
h 800 mm 0.8 m 2 Tukang Kayu
b 400 mm 0.4 m 3 Kepala Tukang
Balok B40/70
h 700 mm 0.7 m 4 Mandor
b 350 mm 0.35 m JUMLAH HARGA T
Balok B35/50
h 500 mm 0.5 m B
Lantai h 150 mm 0.15 m 1 Kayu Kelas III
Atap h 130 mm 0.13 m 2 Paku 5-12 Cm
b 400 mm 0.4 m 3 Minyak Bekisting
Shear Wall
h 400 mm 0.4 m 4 Balok Kayu Kelas II
b 400 mm 0.4 m 5 Plywood Tebal 9 mm
Core Wall
h 400 mm 0.4 m 6 Dolken Kayu Galam, 8-10 Cm Panjang 4 m
JUMLAH HARGA
C Julah Harga Tenaga
D Overhead + Profit
E Harga Satuan Pemasangan
AHSP PEMASANGAN 1 M2 BEKISTING BALOK
HARGA SATUAN
KODE SATUAN KOEFISIEN
Rp
3 4 5 6
Tenaga Kerja
L.01 OH 0.66 IDR 135,500
L.02 OH 0.33 IDR 155,800
L.03 OH 0.033 IDR 170,500
L.04 OH 0.033 IDR 183,200
JUMLAH HARGA TENAGA KERJA
Bahan
m3 0.04 IDR 2,719,600
Kg 0.4 IDR 36,000
Liter 0.2 IDR 6,000
m3 0.015 IDR 2,719,600
Lbr 0.35 IDR 98,000
Batang 6 IDR 33,300
JUMLAH HARGA HARGA BAHAN
Julah Harga Tenaga Kerja dan Bahan(A+B)
Overhead + Profit 15% x C
Harga Satuan Pemasangan 1m3 Bekisting Lantai (D+E)
Rencana Anggaran Tulangan Bekisting Balok B1
JUMLAH HARGA Struktur
Rp Panjang Lebar Tinggi Luas
Komponen Struktur Ketengan
7 (m) (m) (m) (m2)
as A (1-2) 2 0.5 0.8 1
IDR 89,430 as A (3-6) 11 0.5 0.8 5.5
IDR 51,414 as A (7-8) 2 0.5 0.8 1
IDR 5,627 as B 23 0.5 0.8 11.5
IDR 6,046 as C 23 0.5 0.8 11.5
IDR 152,516 as D 23 0.5 0.8 11.5
as E 23 0.5 0.8 11.5
IDR 108,784 as F 23 0.5 0.8 11.5
IDR 14,400 as G 23 0.5 0.8 11.5
IDR 1,200 as I to Core 1.95 0.5 0.8 0.98
IDR 40,794 as I (2-5) 11 0.5 0.8 5.5
IDR 34,300 as J (2-7) 19 0.5 0.8 9.5
Balok B1
IDR 199,800 as K (2-7) 19 0.5 0.8 9.5
IDR 399,278 as L (2-7) 19 0.5 0.8 9.5
IDR 551,794 as M 23 0.5 0.8 11.5
IDR 82,769 as N 23 0.5 0.8 11.5
IDR 634,563 as O 23 0.5 0.8 11.5
as P 23 0.5 0.8 11.5
as Q 23 0.5 0.8 11.5
as R (1-2) 2 0.5 0.8 1
as R (3-6) 11 0.5 0.8 5.5
as R (7-8) 2 0.5 0.8 1
SW X 4 0.5 0.8 2
CORE 5.5 0.5 0.8 2.75
Total
Total Keseluruhan
an Bekisting Balok B1 Rencana Anggaran Tulangan
ur Struktur
Rencana Anggaran Biaya
Komponen Struktur Ketengan
(Rp)
IDR 634,563 as 7 (B-Q)
IDR 3,490,098 as 6 (B-G)
IDR 634,563 as 6 (J-Q)
IDR 7,297,477 as 5 (A-G)
IDR 7,297,477 Balok B2 as 5 (J-R)
IDR 7,297,477 as 4
IDR 7,297,477 as 3 (B-Q)
IDR 7,297,477 as 2 (B-I)
IDR 7,297,477 as 2 (M-Q)
IDR 618,699 Total 1 Lantai
IDR 3,490,098 Total Keseluruhan
IDR 6,028,351
IDR 6,028,351 Rencana Anggaran
IDR 6,028,351
IDR 7,297,477
Komponen Struktur Ketengan
IDR 7,297,477
IDR 7,297,477 as A-I
Balok B3
IDR 7,297,477 as M-R
IDR 7,297,477 Total
IDR 634,563 Total Keseluruhan
IDR 3,490,098
IDR 634,563
IDR 1,269,126
IDR 1,745,049
IDR 114,998,719
IDR 1,379,984,624
Anggaran Tulangan Bekisting Balok B2
Struktur
Panjang Lebar Tinggi Luas Rencana Anggaran Biaya
(m) (m) (m) (m2) (Rp)
56 0.4 0.7 22.4 IDR 14,214,216
20 0.4 0.7 8 IDR 5,076,506
28 0.4 0.7 11.2 IDR 7,107,108
24 0.4 0.7 9.6 IDR 6,091,807
32 0.4 0.7 12.8 IDR 8,122,409
64 0.4 0.7 25.6 IDR 16,244,818
56 0.4 0.7 22.4 IDR 14,214,216
25.5 0.4 0.7 10.2 IDR 6,472,545
16.7 0.4 0.7 6.68 IDR 4,238,882
IDR 81,782,507
IDR 981,390,086
IDR 108,784
IDR 14,400
IDR 1,200
IDR 40,794
IDR 34,300
IDR 199,800
IDR 399,278
IDR 551,794
IDR 82,769
IDR 634,563
g Kolom K1