7 Days Strength 28 Days

S.No. Description of Work Date of Pouring REMARKS


Date Strength Date
1 Walls: BV-06 (1+650) 20-May-20 27-May-20 17-Jun-20 7 & 28 Days required
2 Concrete Encasement: 7+336.64 to 7+338.126, Thrust Block 45° (Step 02): 7+338.126 20-May-20 27-May-20 17-Jun-20 7 & 28 Days required
3 Base Slab: PRV-01 (2+900) 21-May-20 28-May-20 18-Jun-20 7 & 28 Days required
4 Base Slab: Double BV-09&10 (2+885), Cover Slab: BV-06 (1+650) 01-Jun-20 08-Jun-20 29-Jun-20 Already 7 Days submitted
5 Base Slab: BV-05 (0+950) 01-Jun-20 08-Jun-20 29-Jun-20 Already 7 Days submitted
6 Thrust Block, 45° (Step 01): 1+515.43 04-Jun-20 11-Jun-20 02-Jul-20 Already 7 Days submitted
7 Walls: BV-05 (0+950) 07-Jun-20 14-Jun-20 05-Jul-20 7 Days required
8 Thrust Block, 45° (Step 03, Final Step): 7+338.126 08-Jun-20 15-Jun-20 06-Jul-20 7 Days required
9 Thrust Block, 45° (Step 01): 1+368 11-Jun-20 18-Jun-20 09-Jul-20 7 Days required
10 Thrust Block, 45° (Step 02): 1+368 14-Jun-20 21-Jun-20 12-Jul-20 7 Days required
11 Thrust Block, 11.15° (Step 01): 1+368 17-Jun-20 24-Jun-20 15-Jul-20 7 Days required
12 Walls: PRV-01 (2+900) 18-Jun-20 25-Jun-20 16-Jul-20 7 Days required