TITLE PAGE

fodkl [k.M c.Mk &tuin 'kkgtgkWiqjA


dk;Z dk uke %& xzke A

xzke iapk;r %&

;kstuk dk uke %& eujsxk

Plants 1000 No.

o"kZ %& 2020-21

vuqekfur ykxr :- :0 176904.20

S.No. Name of the Officer Designation Signature


1 M ANKIT SHUKLA
Er. Madhusudan Dixit T.A.
2 Sri UMASHANKAR SHARMA G.V.A./G.P.A.
3 Srimati MANJULATA PRADHAN
dk;Z dk uke %& xzke A
xzke iapk;r %&
;kstuk dk uke %& eujsxk

DETAILS OF MEASUREMENT
S.NO. Discription of Items No. L B H/D QTY. UNIT
1 Excavation of Trench Cum
2 Excavation of Pits(0.45x0.45x0.45) 1000 0.45 0.45 0.45 91.13 Cum
3 Plantation and Refiling of Pits 1000 No.
4 Earth work and Veeding 1000 No.
5 Cortage of Plants up to 20 km 1000 No.
6 Local cortage of Plants 1000 No.
7 Irrigation for 3 monts each 4th day 1000 No.
8 Accidental Planting 300 No.
9 Pashu Prahri(Watchman) 365 Mandays

T.A. G.P.V.A. Pradhan


dk;Z dk uke %& xzke A
xzke iapk;r %&
;kstuk dk uke %& eujsxk

ABSTRACT OF COST OF MATERIALS

S.No. MATERIAL QTY UNIT RATE PER AMOUNT

1 Photography 1.00 Job 200.00 Job 200.00


Add 12 % GST 24.00
TOTAL 224.00

T.A. G.V.A./G.P.A. PRADHAN


dk;Z dk uke %& xzke A
xzke iapk;r %&
;kstuk dk uke %& eujsxk

ABSTRACT OF COST OF LABOUR


S.No. Description of Item QTY. UNIT RATE AMOUNT

1 Excavation of Trench Cum 0.00


2 Excavation of Pits(0.45x0.45x0.45) 91.13 No 136.73 12460.20
3 Plantation and Refiling of Pits 1000 No 3.00 3000.00
4 Earth work and Veeding 1000 No 3.00 3000.00
5 Cortage of Plants up to 20 km 1000 No 40.20 40200.00
6 Local cortage of Plants 1000 No 40.20 40200.00
7 Irrigation for 3 monts each 4th day 1000 No 1.44 1440.00
8 Accidental Planting 300 No 10.05 3015.00
9 Pashu Prahri(Watchman) 365 Md 201.00 73365.00
T0tal 176680.20

T.A. G.V.A./G.P.A. PRADHAN


fodkl [k.M c.Mk &tuin 'kkgtgkWiqjA

dk;Z dk uke %& xzke A


xzke iapk;r %&
;kstuk dk uke %& eujsxk

FORM ( J )
S.No. PARTICULARS AMOUNT

1 Labour Cost 176680.20

2 Non Labour Cost 224.00

TOTAL 176904.20

Say 1.77
LACS

T.A. G.P.V.A. PRADHAN