ITEM 405(1)a3 STRUCTURAL CONCRETE 20.

68 Mpa CLASS "A" 28 DAYS

COMPUTATION OF CROSS SECTION AREA:

AT STATION 0 + 000m DIAGONAL & TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 7.6 m
TOP: 3m
AREA: 1.59 sq. m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 033.78m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 7.35 m
TOP: 3m
AREA: 1.5525 sq.m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 049.70m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 7.5 m
TOP: 3m
AREA: 1.575 sq. m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 097.48m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 8m
TOP: 3m
AREA: 1.65 sq. m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 133.38m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 8.2 m
TOP: 3m
AREA: 1.68 sq. m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 166.66m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 7.6 m
TOP: 3m
AREA: 1.59 sq. m.
PILE CAP AREA: 0.25 sq. m.

AT STATION 0 + 175.87m DIAGONAL AND TOP DIKE


THICKNESS: 0.15 m
DIAGONAL: 5.9 m
TOP: 3m
AREA: 1.335 sq. m.
PILE CAP AREA: 0.25 sq. m.

COMPUTATION OF VOLUME PER STATION:

AT STATION 0 + 000m TO STATION 0 + 033.78m:


LENGTH: 33.78 m
AREA 1: 1.84 sq. m.
AREA 2: 1.8025 sq. m.
VOLUME 1: 61.52183 cu. m.

AT STATION 0 + 033.78m TO STATION 0 + 049.70m


LENGTH: 15.92 m
AREA 1: 1.8025 sq. m.
AREA 2: 1.825 sq. m.
VOLUME 2: 28.8749 cu. m.

AT STATION 0 + 049.70m TO STATION 0 + 097.48m


LENGTH: 47.78 m
AREA 1: 1.825 sq. m.
AREA 2: 1.9 sq. m.
VOLUME 3: 88.99025 cu. m.

AT STATION 0 + 097.48m TO STATION 0 + 133.38m


LENGTH: 35.9 m
AREA 1: 1.9 sq. m.
AREA 2: 1.93 sq. m.
VOLUME 4: 68.7485 cu. m.

AT STATION 0 + 133.38m TO STATION 0 + 166.66m


LENGTH: 33.28 m
AREA 1: 1.93 sq. m.
AREA 2: 1.84 sq. m.
VOLUME 5: 62.7328 cu. m.

AT STATION 0 + 166.66m TO STATION 0 + 175.87m


LENGTH: 9.21 m
AREA 1: 1.84 sq. m.
AREA 2: 1.585 sq. m.
VOLUME 6: 15.77213 cu. m.

TOTAL VOLUME: 326.6404 cu. m.


CONTRACT VOLUME: 305 cu. m.