QUANTITY SURVEYING

NAME : Marc I. Ornido BSCE 4D

WORKSHEET 1 - Computation Sheet


Bill of Materials
ITEM - I EXCAVATION WORKS

Design Data:
Footing C2/F2 Tie Beam
Length : 1.2 m Total Length : 42.9562 m
Width : 1.2 m Width : 0.2 m
Thickness : 0.25 m Thickness : 0.3 m
No of Footing : 9m
Volume of Excavated Area
Footing = 3.24 cu.m
Tie Beam = 2.577372 cu.m
Total Excavation = 5.817372 cu.m
Design Data:
Footing C1/F1 Tie Beam
Length : 1.5 m Total Length : 34.8594 m
Width : 1.5 m Width : 0.2 m
Thickness : 0.3 m Thickness : 0.3 m
No of Footing : 9m
Volume of Excavated Area
Footing = 6.075 cu.m
Tie Beam = 2.091564 cu.m
Total Excavation = 8.166564 cu.m

Total Footing = 9.315 cu.m


Total Tie Beam = 4.668936 cu.m
Total Excavation = 13.98394 cu.m

ITEM - II CONCRETING WORKS

Design Data: I. For Footing Slab


Footing Slab C2/F2 ESTIMATED CEMENT, SAND AND
Length : 1.2 m GRAVEL
Width : 1.2 m MIXTURE: Class A
Thickness : 0.25 m TOTAL VOLUME : 9.315
No of Footing : 9m CEMENT 83.84 Bags
Footing Slab C1/F1 SAND 4.66 cu.m
Length : 1.5 m GRAVEL 9.32 cu.m
Width : 1.5 m
Thickness : 0.3 m
No of Footing : 9m
Column - C2/F2
Length : 0.35 m
Width : 0.3 m
Height : 1.4 m II. For Column
No of Column : 9m ESTIMATED CEMENT, SAND AND
Column - C1/F1 GRAVEL
Length : 1.4 m MIXTURE: Class A
Width : 0.35 m TOTAL VOLUME : 2.87
Height : 0.35 m CEMENT 25.80 Bags
No of Column : 9m SAND 1.43 cu.m
QUANTITY SURVEYING
Tie Beam - WF1
Total Length : 44.336 m
Width : 0.4 m III. Tie Beam
Thickness : 0.6 m ESTIMATED CEMENT, SAND AND
Tie Beam - FTB GRAVEL
Total Length : 34.8592 m MIXTURE: Class A
Width : 0.3 m TOTAL VOLUME : 74.38
Thickness : 0.2 m CEMENT 669.43 Bags
Tie Beam - RB2 SAND 37.19 cu.m
Total Length : 47.75 m GRAVEL 74.38 cu.m
Width : 0.3 m
Thickness : 0.15 m IV. Slab
Tie Beam - RB1
Total Length : 56 m
Width : 0.3 m
Thickness : 0.15 m
Tie Beam - B1
Total Length : 34.8594 m
Width : 0.25 m
Thickness : 0.35 m

Floor Slab ESTIMATED CEMENT, SAND AND


Length : 12 m GRAVEL
Width : 11.27 m MIXTURE: Class A
Thickness : 0.1 m TOTAL VOLUME : 17.55
2nd Floor Slab CEMENT 157.97 Bags
Length : 3.27 m SAND 8.78 cu.m
Width : 3.08 m GRAVEL 17.55 cu.m
Thickness : 0.4 m

ITEM - III NUMBER OF CONCRETE HOLLOW BLOCKS

Design Data:
Gross Area : 274.8
Opening Width Height Quantity Total Area Area for Opening :
Door - 1 0.9 2.15 1 1.935 24.7
Door - 2 0.9 2.15 1 1.935 Net Area :
Door - 3 0.8 2.15 2 3.44 250.1
Door - 4 0.6 2.15 3 3.87
Window -1 1.2 1.2 5 7.2 TOTAL NUMBER OF CHB
Window -2 0.8 1.2 4 3.84 = 3126.25
Window -3 0.8 1 1 0.8
Window -4 0.4 1.2 2 0.96
Window -5 0.6 0.6 2 0.72

MORTAR AND PLASTERING


Mortar
Cement 130.55 Bags
Sand 10.63 cu.m

Plastering (Both faces with 8mm Thickness)


Cement 360.14 Bags
Sand 3.00 cu.m

ITEM - IV NUMBER OF STEEL BARS


QUANTITY SURVEYING
Footing :
Design Data: Design Data:
FOOTING 1 FOOTING 2
Length : 1.5 m Length : 1.2 m
Width : 1.5 m Width : 1.2 m
Thickness : 0.3 m Thickness : 0.25 m
0.075 m 0.075 m
Con. Covering: Con. Covering:
75 mm 75 mm
Width of Column : 350 mm Width of Column : 250 mm
Dia. Bars : 16 mm Dia. Bars : 16 mm
No. of Bars along L : 8 pcs No. of Bars along L : 10 pcs
No. of Bars along W : 8 pcs No. of Bars along W : 10 pcs
No. of Footings : 9 units No. of Footings : 9 units

Required Developmental Length 397.44


Furnished development length 350
375 < 397.44 therefore hook is needed
but 47.44 is too short

Hook of Length :
Degree Length
90 deg 144
130 deg 256
must be divisible by 25, therefore use : 275 mm
0.275 m

Cutting List :
Net
LENGTH OF RSB FOR length of
Cutting Say Waste
16mm 1 RSB
6 3.157895 5 -3.5
7.5 3.947368 6 -3.9
9 1.9 4.736842 7 -4.3
10.5 5.526316 8 -4.7
12 6.315789 10 -7
Therefore use 6 m or 12m length of RSB for 16mm diameter bar

Net length of one reinforcing bar (m)


= 1.9
Number of Pcs
= 16

Bill of Quantities (6m of 16mm dia. RSB)


= 151.488 kg/m

Column :
Design Data:
COLUMN 1 COLUMN 2
No. of Column : 9 units No. of Column : 9 units
Length : 150 mm Length : 120 units
Width : 150 mm Width : 120 units

Design Data for C1-F1 Design Data for C1-F2


No. of vertical bars : 4 pcs No. of vertical bars : 6 pcs
Dia. of vertical bars : 16 mm Dia. of vertical bars : 16 mm
QUANTITY SURVEYING
Dia. of Ties : 10 mm Dia. of Ties : 10 mm
50 mm 50 mm
100 mm 100 mm
Spacing of Ties @ 4 : Spacing of Ties @ 4 :
150 mm 150 mm
200 mm 200 mm
Concrete Covering 0.075 mm Concrete Covering 0.075 mm
CC at top : 40 mm CC at top : 40 mm
0.016 m 0.016 m
Diameter of Bar : Diameter of Bar :
16 mm 16 mm
6m 3m
Height : Height :
6000 mm 3000 mm

Developmental Length = 800 mm


Length of 1 rod = 6800 mm
6.8 m
Total Length = 27.2 m bars of 16mm diameter

Colummn 1 (mm) Colummn 2 (mm)


Side A Side B Side A Side B
70 70 40 40

Placement Spacing Number of Ties Hook Longest Length


Top Zone 50 4 105
Top Zone 100 4 90
Top Zone 150 4 100
O.C 200 27 Bending
Bot. Zone 150 4 90 deg 60
Bot. Zone 100 4 135 deg 60
Bot. Zone 50 4
Total no. of stirrups = 51

Colummn 1 (mm) Colummn 2 (mm)


Cutting Length of Cutting Length of
370 mm 250 mm
Stirrups : Stirrups :
18870 mm 12750 mm
Total Length : Total Length :
19 m 10 dia. 13 m
Total number of
Total number of 10mm 3.15 pcs 2.13 pcs
10mm dia. RSD per
dia. RSD per column : 4.00 say 3 say
column :

Length (m) Diameter Pcs Bill of Quantities


7.5 16 72 479.52 kg/m
6 10 10.5 38.808 kg/m

Reinforcement Steel Bar for CHB :


Design Data: ground floor Design Data: second floor
Height : 6m Height : 3m
Length : 42.9562 m Length : 34.8594 m
QUANTITY SURVEYING
Opening : 7.7 m Opening : 17 m
Vertical Spacing Vertical Spacing
(60cm) : 2.13 m (60cm) : 2.13 m
Horizontal Spacing Horizontal Spacing
(3 Layers) : 2.15 m (3 Layers) : 2.15 m
Gross Area : 257.7372 Gross Area : 104.5782
Net Area : 250.0372 Net Area : 87.5782

Total Gross Area : 362.3154


Total Net Area : 337.6154

Number of Horizontal Bars (6m) : 120 pcs


Number of Vertical Bars (6m) : 121 pcs
241 pcs

Bill of Quantities (7.5m of 12mm dia. RSB)


= 1603.94 kg/m