EARTHWORK

TOTAL VOLUME FOR EXCAVATION: 34.53 m3


TOTAL LABOR COST:

FOR FOOTING:
No. of footing: 15
Depth of footing: 1.2 m
Size of footing: 1.0m x 1.0m

Volume of F1 (7 units) : V1-7


V1-7 = 1m x 1m x 1.2m x 7
V1-7 = 8.4 m3

Volume of F2 (8 units) : V8-15 Total volume: VFT


V8-15 = 1m x 1m x 1.2m x 8 VFT = 8.4 + 9.6
V8-15 = 9.6 m 3
VFT = 18 m3

FOR WALL FOOTING:


Depth of WF: 0.45 m Volume of WF: VWF
Width of WF: 0.3 m VWF = 0.45m x 0.3m x 34.3m
Total length of WF: 34.3 m VWF = 4.631 m3

FOR CARPORT:
Length: 5.85 m Volume of Carport exc. for S-o-G: VCP
Width: 4.1 m VCP = 5.85m x 4.1m x 0.1m
Depth: 0.1 m VCP = 2.399 m3

FOR SEPTIC TANK:


Length: 4m Volume of Septic tank: VST
Width: 1.2 m VST = 4m x 1.2m x 1.7m
Depth: 1.7 m VST = 8.16 m3

FOR STAIR FOOTING:


Length: 1m Volume of SF: VSF
Width: 0.6 m VSF = 1m x 0.6m x 0.8m
Depth: 0.8 m VSF = 0.48 m3
FOR DRAINAGE:
Length: 2.4 m Volume of DR: VDR
Width: 0.6 m VDR = 2.4m x 0.6m x 0.6m
Depth: 0.6 m VDR = 0.864 m3

TOTAL VOLUME FOR EXCAVATION:


VT = 18+4.6305+2.3985+8.16+0.48+0.864
VT = 34.53 m3