Area 0.41 m2
Volume 1.17 m3
MATERIALS
Cement 10.54 bags
Gravel 1.17 m3
Sand 0.59 m3
Excavation 2.93 m3
INPUT VALUES
MANHOLE
L (Length) 1.5 m
H (Height) 1.3 m Slab Area 2.25
W (Width) 1.5 m Area 1 0.24
Thk (Thickness) 0.1 m Volume 0.849
No. of Manhole 1 pcs
X Spacing 0.25 m Length 53.3
Y Spacing 0.25 m Length 49.6
X steel dia 12 mm
Y steel dia 12 mm
COVER
No. of Cover 3 pcs
L (Length) 1.4 m
W (Width) 0.5 m Area 0.7
Thk (Thickness) 0.1 m
Volume 0.07
L Spacing 0.275 m
W Spacing 0.125 m length 13.23636
L steel dia 12 mm
W steel dia 12 mm
LEAN CONCRETE
Thickness 0.05 m
OUTPUT ILLUSTRATION
Area 0.20 m2
Volume - m3
W
MATERIALS
Cement - bags
Gravel - m3 H
Sand - m3
Excavation 0 m3
INPUT VALUES
Total Length m
H (Height) 0.6 m
W (Width) 0.8 m
Thk (Thickness) 0.1 m
X Spacing 0.25 m
Y Spacing 0.25 m
X steel dia 12 mm
Y steel dia 12 mm
OUTPUT ILLUSTRATION
Area 0.09 m2
Volume - m3
W
MATERIALS
Cement - bags
Gravel - m3 H
Sand - m3
Excavation 0 m3
INPUT VALUES
Total Length m
H (Height) 0.6 m
W (Width) 0.8 m
Thk (Thickness) 0.1 m
Total Length m
Diameter m