CONCRETE
CONCRETE PROPORTIONS
CEMENT IN BAG
MIXTURE CLASS PROPORTION SAND GRAVEL
40 Kg 50 Kg
AA 1 : 1 1/2 : 3 12.00 9.50 0.50 1.00
A 0.04 9.00 7.00 0.50 1.00
B 1 : 2 1/2 : 5 7.50 6.00 0.50 1.00
C 0.04 6.00 5.00 0.50 1.00
FOOTING
FOOTING 1
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * t
Length,L(m) m CEMENT 0.00 Bags
Width,W(m) m SAND 0.00 cu.m
Thickness,t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
# of Footings
FOOTING 2
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * t
Length,L(m) m CEMENT 0.00 Bags
CONCRETE WORKS
Thickness,t(m) m GRAVEL 0.00 cu.m
COLUMN
*For Circular Columns, Enter the Cross-Sectional Area in Length and (1) at Width*
COLUMN 1
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * h
Length,L(m) m CEMENT 0.00 Bags
Width,W(m) m SAND 0.00 cu.m
Height,h(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
# of Columns
COLUMN 2
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * h
Length,L(m) m CEMENT 0.00 Bags
Width,W(m) m SAND 0.00 cu.m
Height,h(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
# of Columns
CONCRETE WORKS
BEAM
FLOOR BEAM
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * t
Length,L(m) m CEMENT 0.00 Bags
Width,W(m) m SAND 0.00 cu.m
Thickness,t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
ROOF BEAM
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = L * W * t
Length,L(m) m CEMENT 0.00 Bags
Width,W(m) m SAND 0.00 cu.m
Thickness,t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
SLAB
SLAB 1
CONCRETE MIX PROPORTION: B
FORMULA:VOLUME = L * W * t
CONCRETE WORKS
Total Area m
Thickness,t(m) m CEMENT 0.00 Bags
Volume,V 0.00 cu.m SAND 0.00 cu.m
GRAVEL 0.00 cu.m
SLAB 2
CONCRETE MIX PROPORTION: B
FORMULA:VOLUME = Total Area * thickness
CEMENT 0.00 Bags
Total Area m SAND 0.00 cu.m
Thickness,t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
STAIRS
CONCRETE
STAIR 1
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = [(RH * TR/2) * SW](n) + [(RH^2 + TR^2)^0.5](SW)(ts)
Riser Height,RH(m) m CEMENT 0 Bags
Thread Run,TR(m) m SAND 0 cu.m
Stair Width,SW(m) m GRAVEL 0 cu.m
# of Steps, n(step/s) step/s
Stringer Thickness,ts(m) m
Volume, V 0.00 cu.m
Quantity
LANDING 1
CONCRETE MIX PROPORTION: A
FORMULA:VOLUME = A * t
CONCRETE WORKS
Area, A(m^2) m^2 CEMENT 0 Bags
Thickness,t(m) m SAND 0 cu.m
Volume, V 0 cu.m GRAVEL 0 cu.m
Quantity
CONCRETE WORKS
ESTIMATED VALUES
TYPE CEMENT(BAGS) SAND(CU.M) GRAVEL(CU.M)
FOOTING 0 0 0
COLUMN 0 0 0
BEAM 0 0 0
STAIRS 0 0 0
SLAB 0 0 0
MATERIAL PRICES
MATERIAL MARKET PRICE UNIT
Cement ₱ 243.000 ₱ / bag (40 kg)
Sand ₱ 400.000 ₱ / cu. Meter
Gravel ₱ 700.00 ₱ / cu. Meter
GRAND TOTAL ₱ -
CONCRETE WORKS
Construction Estimate Calculator
(By: )
MASONRY
QUANTITY OF CEMENT AND SAND SAND FOR CHB MORTAR PER SQ. METER
EXTERIOR WALLS
FIRST FLOOR
SECOND FLOOR
TOTAL (EXTERIOR)
MASONRY WORKS
INTERIOR WALLS
FIRST FLOOR
SECOND FLOOR
TOTAL (INTERIOR)
MASONRY WORKS
QUANTITY OF CEMENT AND SAND SAND FOR CHB PLASTER PER SQ. METER
EXTERIOR WALLS
FIRST FLOOR
0.00 0.00
SECOND FLOOR
0.00 0.00
TOTAL (EXTERIOR)
MASONRY WORKS
INTERIOR WALLS
FIRST FLOOR
0.00 0.00
SECOND FLOOR
0.00 0.00
TOTAL (INTERIOR)
WALL FOOTING
MASONRY WORKS
WALL FOOTING 1
CMP: A
FORMULA:VOLUME = L * W * t
L(m) m CEMENT 0.00 Bags
W(m) m SAND 0.00 cu.m
t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
WALL FOOTING 2
CMP: A
FORMULA:VOLUME = L * W * t
L(m) m CEMENT 0.00 Bags
W(m) m SAND 0.00 cu.m
t(m) m GRAVEL 0.00 cu.m
Volume,V 0.00 cu.m
TOTAL
ESTIMATED VALUES
MASONRY WORKS
CEMENT 0.00 BAGS
MATERIAL PRICES
MATERIAL MARKET PRICE UNIT
Cement ₱ 243.000 ₱ / bag (40 kg)
Sand ₱ 400.000 ₱ / cu. meter
Gravel ₱ 700.000 ₱ / cu. meter
CONCRETE HOLLOW BLOCKS ₱ 13.000 ₱ / piece
CONCRETE HOLLOW BLOCKS ₱ 11.000 ₱ / piece
CEMENT ₱ -
SAND ₱ -
GRAVEL ₱ -
GRAND TOTAL ₱ -
MASONRY WORKS
CONSTRUCTION ESTIMATE CALCULATOR
BY:
METAL
B. MAJOR FOOTING
Length Net Length: -0.15 m
METAL REINFORCEMENT
Commercial length of
6.00 No. of bars (12mm): 0.00 pcs
rebars
Total ties: 0.00 ties
Length of ties 0.30
Total length of ties: 0.00 meters
C. COLUMN
MAIN BAR
Bend @ Base Footing Total length 0.00 m
Length from footing to groundflo No. of main
#DIV/0! pcs
Height of backfill bars
Thickness of floor slab
Height of ground line to beam Total no. of
main bars #DIV/0! pcs
Depth of tie beam (12mm)
No. of bars
Commercial length of rebars
No. of column
LATERAL TIES
METAL REINFORCEMENT
TIE WIRE
Total ties: 0.00 ties
Length of ties
Total length of ties: 0.00 m
D. SLAB
Length No. of bars
Width Horizontal: #DIV/0! pcs
Spacing Vertical: #DIV/0! pcs
Total length: #DIV/0! m
Total no. of bars (10mm): #DIV/0! pcs
TIE WIRE
Total ties: #DIV/0! ties
Length of ties Total length
#DIV/0! m
of ties:
TOTAL NO. OF TIE WIRE (#16): #DIV/0! Kgs
E. WALL FOOTING
Length of wall Total length of continuous bars: 0.00 m
Bar space Total length temperature bars: #DIV/0! m
No. of continuous bars Total no. of bars (10mm): #DIV/0! pcs
TIE WIRE
Total ties: #DIV/0! ties
Length of ties
Total length
#DIV/0! m
of ties:
TOTAL NO. OF TIE WIRE (#16): #DIV/0! Kgs
F. BEAM
Total length of main
Total length of beam 0.00 m
bars:
Stirrups' spacing Length of stirrups: 0.00 m
Total no. of
No. of main bar #DIV/0! m
stirrups:
Effective cover
Total no. of main
0.00 pcs
bars (16mm):
METAL REINFORCEMENT
Total no. of main
0.00 pcs
bars (16mm):
Hook
Depth
Total no. of stirrups
#DIV/0! pcs
(10mm):
Width
TIE WIRE
Total ties: #DIV/0! ties
Length of ties
Total length
#DIV/0! m
of ties:
TOTAL NO. OF TIE WIRE (#16): #DIV/0! Kgs
G. ROOF BEAM
Total length of main
Total length of beam 0.00 m
bars:
Stirrups' spacing Length of stirrups: 0.00 m
Total no. of
No. of main bar #DIV/0! m
stirrups:
TIE WIRE
Total ties: #DIV/0! ties
Length of ties Total length
#DIV/0! m
of ties:
TOTAL NO. OF TIE WIRE (#16): #DIV/0! Kgs
METAL REINFORCEMENT
SUMMARY
QUANTITY UNIT COST AMOUNT
TOTAL NO. OF 10 mm Ø bars,pcs. #DIV/0! ₱120.00 #DIV/0!
TOTAL NO. OF 12 mm Ø bars,pcs. #DIV/0! ₱173.00 #DIV/0!
TOTAL NO. OF 16 mm Ø bars,pcs. 12 ₱307.00 ₱3,684.00
# OF 16 TIE WIRE USED, kgs. #DIV/0! ₱60.00 #DIV/0!